water resources plan

Upload: joverevocal

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Water Resources Plan

    1/39

    INTRODUCTION

    Irrigation is an artificial application of water to the soil. It is usually used to assist in

    growing crops in dry areas and during periods of inadequate rainfall. Additionally, it is

    very vital in crop production especially in rain-fed farming.

    The future of agriculture and food production lies much on irrigation. At the global

    scale 2,788,000 square kilometers of agricultural land is equipped with irrigation

    infrastructure. About 68% of the area equipped with irrigation is located in Asia, 17%

    in America, 9% in Europe, 5% in Africa and 1% in Oceania. A number of dams and

    irrigation infrastructure were built to increase the supply of water as well as to

    maximize the use of its availability.

    In the Philippines, agriculture is the lifeblood of the Filipino people. Various crops

    such as rice, corn, vegetables and others are widely cultivated to meet the

    increasing demand for food as the countrys population is in the boom. With this, to

    elevate food self-sufficiency of the country, the government together with private

    sectors joins hand in hand to provide adequate irrigation water for food production

    through implementing water resources infrastructure project throughout the country.

    While the Tucalan Communal Irrigation System has been in service for several

    cropping seasons, its efficiency has gradually deteriorated over the years. The

    increasing demand of water irrigation use has led into many constraints such as

    capacity problems, insufficient water quality and the technical deficiencies of existing

    irrigation infrastructures. It is in this view that the rehabilitation of the system had

    been included as a priority project in order to ensure efficient delivery of irrigation

    water to the farms of the existing irrigation system.

    Water Resource Plan Tucalan Communal Irrigation System 1 of 39

  • 7/28/2019 Water Resources Plan

    2/39

    PROBLEMS AND CONSTRAINTS

    The identified problems in the project area were related to production, technical and

    social problems.

    Production Problems:

    The unit yield of rice in the area prior to the project was considerably low at an

    average of 50 cavans per hectare. With no irrigation system, rice was grown

    under rain fed conditions. During some cropping seasons, the vegetative growth

    of rice was severely damaged due to lack of soil moisture. Harvest, therefore,

    during these periods were below the national average.

    Technical Problems:

    Agricultural activities were limited in the project area for lack of adequate

    irrigation water. Cultivation of rice as a major crop depended on rainfall which

    resulted to very low yields. The heavily silted reservoir has led to very low water

    head which was not sufficient to supply the irrigation water requirement of the

    farmlands. Additionally, deteriorating intake and canal structures resulted to

    inefficient water delivery and distribution to the service areas. Most of the lined

    canals were cracked and silted. On the other hand, the earth canals were eroded

    and required reshaping.

    Social and Institutional Problem:

    Non-existence of the Irrigators Association led to the insufficient knowledge of

    water users on proper water management which in turn resulted to the

    proliferation of illegal users, damage to canal structures and wastage of irrigation

    water. With no peoples organization supervising the operation of the system,

    collection rate of irrigation service fee was low and no sufficient maintenance

    resources were available during maintenance period. Damage structures and

    facilities were not restored and their conditions were aggravated with passing of

    each cropping season.

    Water Resource Plan Tucalan Communal Irrigation System 2 of 39

  • 7/28/2019 Water Resources Plan

    3/39

    OBJECTIVES OF THE PROJECTThe identification of long term and short term is hoped to guide public and private

    sector development decisions and activities direction. The results are expected to

    support the sustainability of the projected growth intensity for the 50-year period.

    The short-term and long-term objectives of the rehabilitation of the project are

    presented below:

    Short-Term Objectives

    1. To restore the intake structures and drainage facilities of the irrigation system

    in order to re-establish its functionality and operation.

    2. To strengthen the Irrigators Association capacity to undertake productive

    activities by providing institutional and agricultural support such as extension

    services, cooperative organization and social capability building.

    3. To improve the productive potentials of the agricultural farmlands in the area

    through increased cropping intensity and crop diversification.

    Long-Term Objectives

    1. To alleviate poverty and improve well-being of the farmer beneficiaries by

    giving them opportunities to increase their income.

    2. To transform the Irrigators Association into a self-sufficient organization

    capable of efficiently and effectively managing the operations of the system.

    At full development, production from the project area is expected to increase from

    2.50 tons/hectare to 5.00 tons/hectare for the first crop and 5.00 tons/ha for the

    second crop. However, production cost will increase considering the introduction of

    modern methods of farming with more inputs to be supplied. The target cropping

    intensity will be up to 148% in the whole service area. Palay production is also

    expected to reach 1,150 tons annually in the whole area from the present 387.50tons.

    Water Resource Plan Tucalan Communal Irrigation System 3 of 39

  • 7/28/2019 Water Resources Plan

    4/39

    EXISTING CHARACTERISTICS AND CONDITIONS OF THE STUDY AREA

    A Br ie f H is to ry o f Lasam

    History is by and large, the story in retrospect of a land and its people. The land, its

    name and occupancy, its location and wealth, the people , their idiosyncrasies and

    attributes, their tradition and culture, their faith and beliefs, their occupation andpursuits, their tribulations and ordeals, nay, their settlements and systems of

    government, are history's subject matter and reasons for being.

    The Land

    Barrio Macatabang was a place along the bank of the Cagayan River called so

    inhabited by Ybanag, Ilocano immigrant Filipino Chinese, and Malaweg.

    Macatabang was a part of Gattaran, but as the population increased, the people of

    the western part of Gattaran made a resolution that it be made a separate town.

    Congressman Paulino Alonso of the 2nd District of Cagayan introduced a bill in

    congress creating the municipality of Santo Tomas. Representative Cabarroguis of

    Nueva Vizcaya vigorously objected the suggested name on the first reading of the

    bill. Finally, Lasam was agreed upon in honor of the late Governor Honorio Lasam,

    the sixth governor of Cagayan (1915-1918)

    Water Resource Plan Tucalan Communal Irrigation System 4 of 39

  • 7/28/2019 Water Resources Plan

    5/39

    On June 13, 1950, the late President Elpidio C. Quirino signed R.A. 507 which made

    possible the creation of the municipality of Lasam.

    January 1951 was eventful for Lasam

    because it was her official inauguration as a

    town. However, another problem arose after

    the celebration of its inauguration. Although,

    it was stated in the bill that the site of Lasam

    would be the barrio be made the town site. In

    order to settle the dispute, an arrangement

    between the two political factions (the Jurado

    faction of Macatabang and the the Acre faction of Nabannagan) was made. They

    agreed that whoever was elected Mayor would have the privilege to situate the seat

    of government in his respective barrio. Fortunately, Jurado was elected Mayor by a

    margin of only two votes over Acre, thus, Macatabang became the town proper.

    The Immigrants

    In the early part of the 40s, immigrants

    from other provinces came to settle in

    Lasam and its nearby environs. They

    came from the central plains and the

    Ilocano provinces. Majority of them were

    Ilocanos who brought with them

    industriousness, thriftiness and sturdiness.

    Settling in the plains and meadows of the

    municipality, the Ilocanos with diligence who howed their lands into productive forms

    which boosted no less than the economic progress of Lasam.

    Eager and desirous to improve their lot, many of the immigrants have managed to

    send and continue to send their children to the schools, colleges, and universities

    enhancing on the process the literacy pasture of the municipality. From their ranks

    have emerged many of the municipality's teachers, artisans and professionals.

    Water Resource Plan Tucalan Communal Irrigation System 5 of 39

  • 7/28/2019 Water Resources Plan

    6/39

    It is important to note in this connection that a number of them have become Chief

    Executives of Lasam.

    Lasam is considered the largest municipality of the second district of the province of

    Cagayan in terms of population. It is also known as the rice bowl of Western

    Cagayan. It is the nucleus of the

    Zinundungan Valley and was

    endowed an abundant forest

    resources particularly hard umber

    and mangrove species. The

    municipality boosts excellent

    education system where one tertiary

    level, two vocational/agricultural

    secondary level, three academic

    high school, one TESDA institution

    and complete elementary and primary schools scattered all the barangays all over

    the area. The town is the second youngest town in the province.

    Location and Wealth

    Lasam town proper barely 13 kilometers, 20 degree south west of Magapit

    Suspension Bridge. It is 68 kilometers north of Tuguegarao, Cagayan by crossing

    the Cagayan River from the municipality of Gattaran, but following the Lasam-Logac-

    Magapit National Road, is 106 kilometers

    from Tuguegarao, Cagayan. It is bounded on

    the north east by the municipality of Lallo,

    Cagayan, on the north west by the

    municipality of Allacapan, Cagayan and

    Flora,Apayao, on the east by the Cagayan

    River, and Gattaran, Cagayan, on the south

    by Santo Nio, Cagayan and on the south

    west by the municipality of Rizal, Cagayan.

    Water Resource Plan Tucalan Communal Irrigation System 6 of 39

  • 7/28/2019 Water Resources Plan

    7/39

    It must have been for its location, its agricultural and commercial potentialities that

    prompted early immigrants to transfer to Lasam. Future events

    proved the wisdom of their choice for, with the Cagayan River and the Zinundungan

    River as the chief means of transportation at that time and for the long period, Lasam

    became the hub of trade and commerce for a wide area.

    The rivers were teeming with freshwater

    fish and shells and forests were

    everywhere abounding with raw building

    materials and wildlife. In fact, venison

    and meat of wild pigs were commodities

    which the traders from Aparri, with their

    roof-flat-bottomed rafts and boats, bough

    in quantity.

    Greed and ignorance soon took its toll. Forests were denuded without the thought of

    the future resulting in big floods and extensive soil erosion. Fingerlings, too, were

    trapped or caught for food or sale.

    The saving grace from all these senseless wastes came later when with advanced

    technology, a breakthrough in rice production was achieved. Farmers who would

    harvest only 15 to 25 cavans per hectare could now produce 70 to 100 cavans. Corn

    also became a prime crop augmenting the income of the farmers to a marked

    degree.

    Area and Population

    Lasam has a total land area of 234 square kilometers or 23,400 hectares.

    The total area of the municipality is divided among 30 barangays namely:

    Water Resource Plan Tucalan Communal Irrigation System 7 of 39

    PINSAL FALLS

  • 7/28/2019 Water Resources Plan

    8/39

    BARANGAY POPULATION

    Aggunetan 1,083

    Alannay 2,022

    Battalan 1,073

    Cabatacan East (Duldugan) 1,799

    Cabatacan West 1,606

    Calapangan Norte 825

    Calapangan Sur 749

    Callao Norte 828

    Callao Sur 840

    Cataliganan 323

    Centro I (Pob.) 2,259

    Centro II (Pob.) 2,078

    Centro III (Pob.) 1,817

    Finugo Norte 520

    Gabun 1,125

    Ignacio Jurado (Finugu Sur) 1,573

    Magsaysay 1,404

    Malinta 1,070

    Minanga Sur 713

    Minanga Norte 397

    Nicolas Agatep 884

    Peru 1,807

    San Pedro 1,644Sicalao 1,508

    Tagao 376

    Tucalan Passing 844

    Viga 712

    Nabannagan East 1,183

    Nabannagan West 2,519

    New Orlins 1,065

    TOTAL 36,646

    Water Resource Plan Tucalan Communal Irrigation System 8 of 39

  • 7/28/2019 Water Resources Plan

    9/39

    COVERAGE OF THE PROJECT

    The project will involve 141 farmers from Barangay Cabatacan East with a service

    area of 155 hectares of agricultural lands suitable to rice.

    VARIOUS TECHNICAL CONDITION OF THE STUDY AREA

    A. Topography and Slope Classification

    The service area is generally flat in terrain. According to the Bureau of Soils,

    the study area is among the 14,000 hectares or 60% of the total area of Lasam

    town that has a 0.30 slope which is level to nearly level. These land area are suitedfor agriculture.

    B. Meteorology and Hydrologic Investigation:

    The water source of the proposed service area is the Tucalan Creek and

    some tributaries.

    C. Climate:

    Under the climatic classification, the climate at the project area fall generally

    under Type III, i.e. rainfall is more or less evenly distributed throughout the year.

    Seasonal very pronounced, relatively dry from November to April and wet during the

    rest of the year.

    D. Rainfall:

    The project area is on the windward side during the northeast monsoon so

    that rainfall is generally heavy during this part of the year. Although the northeast

    monsoon season starts affecting the country by the later part of October and last in

    the month of April, rainfall generally declines significantly in the project area by

    February.

    The period March to April which covers the later part of the northeast

    monsoon season and the trade wind season has generally the lowest rain fall during

    the year.

    Water Resource Plan Tucalan Communal Irrigation System 9 of 39

  • 7/28/2019 Water Resources Plan

    10/39

    The project area is on the leeward side during the southeast monsoon from

    May to the later part of October, however, the area still receives substantial amount

    of rainfall during the period especially during the period from August to October.

    E. Flood Studies:

    Flood study to evaluate the occurrence of flood at the proposed damsite were

    not undertaken, however there were accurate information of flooding in the area.

    F. Sedimentation:

    There is no data on suspended bed load sediments for Tucalan Creek, hence,

    the sedimentation rate of this creek was based on the studies for various watershed

    in northern luzon. In the sedimentation studies at Magat River Reservoir, erosion

    rates are from 0.75 mm/year to 1.55 mm/year. As far as the sedimentation study is

    concerned wherein denudation or deforestation is extensive at the drainage area it

    can be presumed that there are erosions considering the present situation of the

    upper section of the damsite which is actually silted.

    G. Water Quality:

    The water flowing at the Tucalan Creek is 100% suitable for irrigation.

    Tucalan CIS had been diverting water from Tucalan Creek for some years ago. It

    was found out that there is no harmful effect that have been noted and recorded.

    Water Resource Plan Tucalan Communal Irrigation System 10 of39

  • 7/28/2019 Water Resources Plan

    11/39

    GENERAL LAYOUT OF TUCALAN COMMUNAL IRRIGATION SYSTEM

    Water Resource Plan Tucalan Communal Irrigation System 11 of39

  • 7/28/2019 Water Resources Plan

    12/39

    Pictorials of the Existing Condition of the Study Area

    Canal Structures

    Some canal structures are heavily

    silted and clogged with debris. Steel

    gate of gated structure as shown

    above were already out of place and

    others were damaged with passing ofeach cropping season.

    Water Resource Plan Tucalan Communal Irrigation System 12 of39

  • 7/28/2019 Water Resources Plan

    13/39

    Canalization

    The condition of main canals and laterals needs rehabilitation. Lined canals werecracked that results to seepage loses. Most of the stretch of canal are heavily siltedwhich lessen the capacity to carry the flow of water, thus, decrease in the efficiency.

    Water Resource Plan Tucalan Communal Irrigation System 13 of39

  • 7/28/2019 Water Resources Plan

    14/39

    Service Road

    This is the portion of service road that needs rehabilitation like surface stabilizationand gravelling. This will ensure convenience in the mobility of crop production andeasy access to different farm site.

    Diversion Dam

    Washout portion of the overflow damgreatly affects the efficiency andfunctionality of the irrigation systemespecially to quantity of water beingdiverted to canal networks.

    Water Resource Plan Tucalan Communal Irrigation System 14 of39

  • 7/28/2019 Water Resources Plan

    15/39

    Institutional Development

    The situation shows that there is no management plan for cropping schedule of

    farming. This results to the inefficient use of irrigation water.

    Water Resource Plan Tucalan Communal Irrigation System 15 of39

  • 7/28/2019 Water Resources Plan

    16/39

    AGRICULTURE CONDITION OFTHE STUDY AREA

    Rice is the principal crop of the project area. Depth of water needed during

    land preparation is 150 mm, maximum. Reduce water depth from 20-50 mm during

    transplanting and 5 days after the end of transplanting, increase and maintain the

    depth of water from 25-75 mm with maximum of 150 mm until 14 days before

    harvesting.

    Provision for water losses includes seepage, leakage and consumptive use of

    vegetation on the slope and/or along the stretch of the canal, the operational losses

    on account of some damaged structures, excess delivery and waste water incurred

    during transplanting and poor maintenance of paddy field dikes.

    A. Vegetative Cover

    The Tucalan Creek water shed area as estimated from the 1:50,000 m scale

    military map is 13.20 square kms. The drainage area is heavily forested despite the

    presence of selective logging operation. The low lying hills portions show baldness

    for no big forest trees is present. Tall grasses like bamboos, bohos, shrubs, cogons

    and those belonging to gramineae family are found.

    Some of the low land rice areas are found at the foot of the hills. On

    established paddy fields, the dominant grasses are cogon, and talahib. Other

    common grasses are echinochloa glabrescens, echinochloa coloma, cyperius iria,

    fimbristylis littoralis, ipomoea aquatica and monochoria vaginalis.

    B. Soil Type

    The general soil type of the service area is clayey and loamy types. These

    soil types crack easily upon drying; however it becomes soft within few hours after

    saturation. Along hillside in cultivated areas the soil dries to a depth from 50-70 cm

    or more.

    Water Resource Plan Tucalan Communal Irrigation System 16 of39

  • 7/28/2019 Water Resources Plan

    17/39

    C. Land Use

    The service area of 155 has is cultivated and planted to rice. Originally the

    area is irrigated. However, since the dam was washout the area became rain fed

    rice paddies.

    D. Land Ownership

    Approximately the distribution of land ownership is as follows:

    OWNERSHIP/CULTIVATORSHIP DISTRIBUTION BY PERCENTAGE

    AREA FARMERS

    Full Owner 73.90 84

    Share Tenants 11.00 22

    Lease Holder 14.20 15

    Amortizing Owner - -

    Full Owner & Lease Holder 39.50 10

    Full Owner & Share Tenants 11.80 7

    Share Tenant & Lease Holder 4.60 3

    Full Owner & Amortizing Owner - - _______

    T O T A L 155 141

    AGRO-ECONOMIC DATA

    A. General:

    To ascertain the economic viability of

    the project an agro-economic survey

    was conducted. The method and

    approach was through interview of

    randomly picked farmer beneficiaries.

    Information was also obtained from

    other government entities national

    and local who are involved with the

    different data. These pieces of

    information and data were compiled,Water Resource Plan Tucalan Communal Irrigation System 17 of39

  • 7/28/2019 Water Resources Plan

    18/39

    transcribed and consolidated and became the basis of projection and estimate of the

    project.

    B. Present Production

    The present average production per hectare for rainfed areas is 2.50 tons/ha. The

    present family net income of owner-operator for one (1) hectare rainfed rice is

    P17,104.00 annually. This meager farm net income cannot sustain the economic

    needs of the farmer, thus an irrigation system is vital to increase the rice production.

    Marketing of farm product in the area is not a problem. The farmers sell their

    palay to traders at the poblacion, others sell their products at NFA warehouse at

    Allacapan, Cagayan.

    IDENTIFIED UNCERTAINTIES

    1. Calamities and Weather Disturbances

    This Water Resource Plan aims at establishing a sustainable and functional

    irrigation system to improve the agricultural potentials of the study area. But

    because of calamities and weather disturbances such as typhoons, excessive

    flooding, El Nino, La Nina and others, risks that may lead to the destruction of

    irrigation infrastructures, access roads and casualty on crops are at stake.

    2. Production Cost

    In recent years, high prices of agricultural supplies such as hybrid seeds,

    fertilizers, insecticides and pesticides is one of the major burdens of farmers.

    It is also aggravated by the low market price of crop yields because trading is

    monopolized by private individuals. As an adverse effect, farmers might suffer

    indebtedness that will affect their quality of living.

    3. Fund Source

    In Philippine setting, realization of various infrastructure projects like this

    water resource plan depends on government funds. In most cases, there are

    limited available budget for the restoration and rehabilitation of existing

    irrigation infrastructures to sustain its functionality. This has been the scenarioWater Resource Plan Tucalan Communal Irrigation System 18 of39

  • 7/28/2019 Water Resources Plan

    19/39

    for Tucalan Communal Irrigation System. Funds may be available for certain

    year but uncertain of its next funding period.

    4. Political Will and Rapid Changing Priorities

    Because most of infrastructure projects are government funded, it takes a

    political will to ensure the potentials of the irrigation projects. These irrigation

    projects like the Tucalan CIS might be affected by the changing priorities of

    government officials as an effect of the transition of political administration.

    5. Accessibility/ Isolation of Production Area.

    The study area has 1.20 kilometers without proper access road which was

    included in this project plan to be developed. Problems in the future may

    include the maintenance for the serviceability of the access roads.

    6. Irrigation Association Capability

    The functionality and operation of the irrigation system depends on the

    effectiveness of Irrigator Association in carrying out irrigation management

    plan. Failure to establish its stability might hamper the optimum utilization of

    the system.

    ALTERNATIVES

    In determining the project irrigation requirements, all the above mentioned technical

    data and agricultural conditions were considered. For instance the cropping

    calendar shows that land preparation is set during the first week of May and

    September. Transplanting and vegetative or growth management follows until the

    start of harvesting which falls on the first week of October and February to complete

    a year-round cropping season. Another two and one half months (2) period is

    provided for repair and maintenance of the system before the on-set of the first

    cropping season of the following year.

    Three alternatives were identified for the project to suit the existing conditions: (1)

    Overflow-Type Weir, (2) Pump Irrigation Project (PIP) and (3) Shalow Tube Well.

    Water Resource Plan Tucalan Communal Irrigation System 19 of39

  • 7/28/2019 Water Resources Plan

    20/39

    Alternative 1: Overflow-Type Weir

    Scope

    This alternative involves the modification of the intake and earthfill dam across the

    Tucalan Creek to harness the potentials of the stream for irrigation. Major

    components of the project include the rehabilitation of irrigation and drainage

    network to ensure irrigation water will reach the whole service area. Other items of

    work will also include the provision of service road along the existing canal network

    and farm level facilities to guarantee efficient water delivery into the paddy level.

    Environmental Impact

    Results of field investigation conducted have revealed that there are no human

    settlements that could be affected in the diversion works location and with the stretch

    of the diversion canal to be undertaken.

    As far as the project is not within the environmentally critical areas, considering the

    works to be undertaken does not require massive excavation or quarrying, no big

    trees will be cut down nor reforestation areas will be traversed by canal, hence it is

    possible to ascertain within the project area, that there are no archeological sites,

    historical or native landmarks that will prejudice development of the project.

    Investment Cost

    Water Resource Plan Tucalan Communal Irrigation System 20 of39

    OVERFLOW-WEIR TYPE OF DAM

  • 7/28/2019 Water Resources Plan

    21/39

    The total investment cost of the project amounted to P18,382,002.56. This includes

    old loans amounted to P413,922.68. and this program for construction amounted to

    P18,600,000.00. Total Project Cost is P19,013,927.00 and the development cost is

    P122,670.47/ha.

    The estimated cost breakdown is as follows:

    Items of Work (Balance of Old Loan) This Investment Total Investment

    Diversion Works P 260,869.02 P1,439,660.00 P 1,700,529.02

    Canalization 153,053.66 10,356,850.00 10,509,903.66

    Canal Structure 3,286,100.00 3,286,100.00

    Terminal Facilities 303,505.00 303,505.00

    Drainage Facilities 100,000.00 100,000.00

    Project Facilities 75,000.00 75,000.00

    Service O & M Road 800,000.00 800,000.00

    Total Direct Cost P 413,922.68 P16,361,115.00 P16,775,037.68

    GESA 818,056.00 818,056.00

    Institutional 490,833.00 490,833.00

    Management Fee 930,000.00 930,000.00

    Total Indirect Cost 2,238,889.00 2,238,889.00

    Total Estimated Cost P 413,922.68 P18,600,004.00 P19,013,926.68

    To Estimate, Say P19,013,927.00

    Economic Internal Rate of return

    The final evaluation Economic Internal Rate of Return (EIRR) of the Overflow-Type

    Weir yielded 29.35% considering normal plan. However with the foresighted 20%

    increased in construction cost it yielded an IRR 23.85%. A 20% increase in

    construction cost and two years delay in attaining full project benefits resulted to an

    IRR of 22.34%.

    Water Resource Plan Tucalan Communal Irrigation System 21 of39

  • 7/28/2019 Water Resources Plan

    22/39

    Net Present Values and Benefit-Cost Ratios (NPV/BCR)

    At Normal Plan

    FUTURE NOMINAL VALUE PRESENT WORTH @ 10%

    INV. COST O & M BENEFIT 10% INV. COST O & M BENEFIT

    ( P'000) ( P'000) ( P'000) D.F. ( P'000) ( P'000) ( P'000)

    1 446.96 0.90912 10,042.44 0.8264

    3 10,042.44 0.7513

    4 779.50 5,792.50 0.6830 532.40 3,956.27

    5-50 779.50 5,792.50 6.7449 5,257.65 55,814.04

    Total 20,531.84 5,790.05 59,770.31

    Net Present Value ( NPV ) = 59,770.31 - ( 16,250.26 + 5,790.05 )

    = 37,730.00

    Benefit Cost Ratio ( BCR ) = 59,770.31

    ( 16,250.26 + 5,790.05 )

    = 2.71 > 1.00

    YEAR

    406.338,299.06

    7,544.87

    16,250.2600

    Advantage

    1. It can supply water to large irrigation areas.

    2. Reservoir form is a good storage of irrigation water that can be used

    especially during dry season.

    3. The service period efficiency is high compared to other irrigation option that is

    why it is the most adopted irrigation component in the Philippines.

    DisadvantageWater Resource Plan Tucalan Communal Irrigation System 22 of39

    t Normal Plan

    FUTURE NOMINAL VALUE ( P'000 ) AT PRESENT WORTH ( P'000 )

    Year Benefit on Increment At

    Investment Irrigation Benefit DF Value DF Value

    446.96 -446.96 0.7692 0.80 -357.5

    2 10,042.42 -10042.42 0.5917 0.64 -6427.1

    3 10,042.42 -10042.42 0.4552 0.512 -5141.7

    4 779.50 5,792.50 +5013.00 0.3501 0.4096 +2053.3

    5-50 779.50 8,275.00 +7495.50 1.1671 1.6353 +12257.

    T O T A L + 2384.2

    5 ( 30-25) ( 2384.27

    = 29.35

    - 354.15

    COST

    O & M

    At30% 25%

    +25INTERNAL RATE OF RETURN ( IRR ) =

    -343.80

    -5942.10

    -4571.30

    +1755.05

    +8748.00

    384.27 - 354.1

  • 7/28/2019 Water Resources Plan

    23/39

    1. Construction cost is quit high.

    Alternative 2: Pump Irrigation Project

    Scope

    The main component of this alternative will involve 2 units-250 watts diesel engines

    with a capacity of 3,200 cubic foot per minute. The water delivery component will

    include 36 diameter Reinforced Concrete pipe to augment the trapezoidal and

    square lined canals. Like the first alternative, other items of work will also include the

    rehabilitation of irrigation and drainage network to ensure irrigation water will reach

    the irrigable area.

    Economic Internal Rate of return

    Economic evaluation of this alternative shows that the increased investment cost and

    decreased irrigation benefits exert a considerable influence on the Economic Internal

    Rate of Return. The variations, however, are relatively slight. An increase of 25% in

    the investment cost corresponds to a reduction of 9.13% in the EIRR and a

    decreased of 20% in the irrigation benefits reduces the EIRR by about 10.77%

    points. The combined effect of the two cases on the EIRR is a reduction of

    approximately 18.72% points.

    Water Resource Plan Tucalan Communal Irrigation System 23 of39

    PUMP IRRIGATION PROJECT

  • 7/28/2019 Water Resources Plan

    24/39

    Based on the preceding assumptions and by discounting the cost and benefit

    streams over a 12 year period, the EIRR is estimated at 22.46%.

    Analysis of with and without project situations yielded to the annual financial gross

    value of production is P179,153.44 per average farm lot and the same value for

    future without project. For the future with project, annual financial gross value of

    production increased to P240,189.94 without costing labor. With the use of farm

    budgets, analysis of annual net farm incomes indicate that present net crop income

    of P62,474.12 would increased to P91,171.22 per average farm lot with the project.

    The difference in net crop incomes between the present and the future situations

    with project are substantial in determining adequate incentives to farmer

    beneficiaries.

    Benefit-Cost Ratio

    The project has a benefit-Cost Ratio of 1.51 considering incremental benefits for a

    15 year period at 15% discount rate of P8,591,680.00 and total Cost of

    P5,702,940.00.

    Investment Cost

    The total project cost was estimated at P9,842,025.30 with the following breakdown:

    Item of Work Amount

    I. Canalization

    3,000 PSI Reinforced Concrete 79,718.10

    Structure Excavation 59,361.10

    Installation of 36 diameter RCP 582,782.00

    Structure Backfill with Compaction 27,062.50

    II. Laterals (Lined Canal) 8,251,101.60

    III. Diesel Engines (2-250 watt) 842,000,00

    Total Project Cost 9,842,025.30

    Environmental Impact

    There is no significant environmental impact expected from the pump irrigation

    project. As with the first alternative, works to be undertaken does not requireWater Resource Plan Tucalan Communal Irrigation System 24 of39

  • 7/28/2019 Water Resources Plan

    25/39

    massive excavation or quarrying, no big trees will be cut down nor reforestation

    areas will be traversed by canalization.

    Advantage

    1. Pump is essential if irrigation by gravity is not possible.

    Disadvantage

    1. When pumps and other equipments break down, the resulting lack of water

    can be critical for plant growth.

    2. The cost of pumping water increases with the size of the service area.

    Therefore, its irrigated service area is limited.

    3. Functionality of the irrigation system declines as the efficiency of pump

    decreases.

    4. Cost of maintenance is expensive considering the continuous increase in the

    price of diesel and machine spare parts.

    Alternative 3: Shallow Tube Well

    Scope

    The Shallow Tube Well alternative will comprise 16 units of 2.5 Hp pump engines

    drilled on site and involves well boring and development. Suction pipes will be

    encased and will deliver water into the main canals.

    Water Resource Plan Tucalan Communal Irrigation System 25 of39

    SHALLOW TUBE WELL

  • 7/28/2019 Water Resources Plan

    26/39

    Investment Cost

    Total cost for the Shallow Tube Well is P6,528,977.20 and will have the following

    items of work:

    1. Pipe Casing2. Well Development3. Pumping Test4. Suction Pipe5. Pump & Engine6. Excavation7. Pump Chamber8. Stilling Basin

    Operation and Maintenance Cost

    Considerations in computing the operation and maintenance cost per hectare of rice

    is as follows:

    AssumptionsCost of Palay Per Cavan PhP 450.00Fuel Consumption Factor Per Pump Tear 0.6

    Crop Water Requirement for Rice Per Day 0.008Crop Maintenance 89

    (Number of Days Per Cropping)Irrigation Water Requirement Per Hectare (cu m/ha) 7,120Pumping Hours Required (hrs) 152.14Assumed Cost of Diesel (PhP/Liter) PhP 25.00

    Energy CostCost (Fuel Cost Per Hectare) PhP 2,282.05Consumption (Liters) 91.28

    Repair and maintenanceOil and Parts PhP 200.00Operator Php 216.00Well PhP 800.00

    Replacement Cost (Every 10 Years) PhP 680.00

    Total Estimated Operation and Maintenance Cost PhP952,595.70

    Advantage

    1. Good for small-scale irrigation projects

    Disadvantage

    1. The amount of water that can be abstracted from shallow well is limited, and,

    as a result, the areas which are irrigated from this water source will also be

    Water Resource Plan Tucalan Communal Irrigation System 26 of39

  • 7/28/2019 Water Resources Plan

    27/39

    limited.

    2. Excessive exploitation of the ground water by many users, however, will bring

    about a decline in the water table.

    3. Source of shallow tube well are likely to be very thin with a limited storage

    capacity for ground water..

    MULTI-CRITERIA ANALYSIS

    The three alternatives were subjected to a multi-criteria analysis in order todetermine which option is most responsive in terms of achieving the short-term andlong-term objectives of the project. Three criteria were selected: Impact onProduction, Social Equity and Sustainability.

    Criteria 1: Impact on ProductionThe provision of the irrigation system and the transfer of appropriate farmingtechnologies to the beneficiaries directly translate to the extension of areas forcultivation, crop intensification and adoption of modern crop varieties.Adequate irrigation water supply also results to higher agricultural outputswithin the projects influence area. Consequently, higher production yieldsignificantly contributes to the increase in the average household income ofthe farmers. The element to be rated in this criteria is the Yieldof Productionrepresented as the ratio of the average annual volume of production (in ton)and the area of production (in hectare).

    Alternative 1

    The Overflow-Type Weir is expected to irrigate the whole service area of 155

    hectares during the first cropping and 75 hectares during the second

    cropping. This will increase cropping intensity by 148% and will improve palay

    production from 387.50 tons to 1,150 tons annually. Production yield of 6.2

    tons per hectare will result to an increase in average annual on-farm income

    from P17,104.00 to P53,379.87.

    Alternative 2

    The Pump Irrigation Project will increase cropping intensity by 130% and is

    expected to irrigate 155 hectares during the first cropping and 47 hectares

    during the succeeding cropping season. While the whole irrigable area will be

    serviceable during the main cropping period, the projected low water level of

    the stream during the dry season which coincides with the second cropping

    will drastically affect the volume of source water. The annual volume of

    production is projected at 700 tons and yield is computed at 4.5 tons per

    hectare.

    Water Resource Plan Tucalan Communal Irrigation System 27 of39

  • 7/28/2019 Water Resources Plan

    28/39

    Alternative 3

    The Shallow Tube Well is expected to irrigate the whole service area of 155

    hectares during the main cropping. However, based on available aquifer data

    in the area available water source will serve only 39 hectares during the

    second cropping which will achieve a cropping intensity of 125%. Over theyears this is projected to decrease as aquifer levels will be critically depleted

    especially during pronounced dry seasons. Volume of production is estimated

    at 670 tons and a yield of 4.3 tons per hectare.

    The Overflow-Type Weir best satisfies the Criteria on Impact of Production as

    presented above. It posted the highest relative weight of 36%.

    Criteria 2: Social Equity

    A demand-driven and equity-based approach is adopted in the

    implementation of the project. Social equity refers to the involvement of the

    project beneficiaries in whole process of project development from planning,

    design, construction and operation. This will encourage them to actively

    participate in the implementation of the project. The provision of equity or

    counterpart from the beneficiaries is crucial and significant in ensuring the

    achievement of the projects purpose. Social equity also requires the

    establishment of a stable Peoples Organization to manage and supervise the

    operation and maintenance of the project. The element to be rated in this

    criteria is the relative participation and involvement of the beneficiaries in

    terms of labor provided (jobs generated) and the amount of counterpart fund

    contributed (pesos). The alternative with the most jobs generated in theconstruction of the project and with the highest counterpart fund provided will

    best satisfy the social equity criteria.

    Water Resource Plan Tucalan Communal Irrigation System 28 of39

    Alternative

    1 6.29 tons/ha 35.86%

    2 4.51 tons/ha 32.61%

    3 4.36 tons/ha 31.53%

    Production Yield Weight

    Impact on Production Criteria

    Alternative Weight

    1 53.73%

    2 27.81%

    18.45

    oc a qu ty r ter

    984,202.53

    652,897.72

    128

    66

    44

    Counterpart

    Fund (PhP)

    Jobs

    Generated

    1,901,392.70

  • 7/28/2019 Water Resources Plan

    29/39

    In terms of the Social Equity Criteria, Alternative 1 (Overflow-Type Weir)

    posted the highest relative weight of 54%.

    Criteria 3: Sustainability

    The project must be sustainable so that local mechanisms will be in place to

    ensure that the community shall continue to benefit long after the project is

    completed. The sustainability criteria will look into the optimum usable lifespan

    of the project including the level of investment required for the maintenance of

    the structures and facilities. An outright observation of the three alternatives is

    that the project cost is inversely proportional to the cost of maintenance. On

    the other hand, the total project cost is in direct proportion to the projected

    usable lifespan of the project.

    The alternative with the highest incidence of sustainability is the Overflow-

    Type Weir with a relative weight of 61%.

    COMPARATIVE ANALYSIS

    1. Summary of Alternatives

    2. A comparative evaluation of the three alternatives shows that the Overflow-Type

    Weir (Alternative 1) provides the best option in terms of higher Economic Internal

    Rate of Return and Benefit-Cost Ratio.

    Water Resource Plan Tucalan Communal Irrigation System 29 of39

    Alternative Weight

    1 60.98%

    2 24.39%

    3 14.63%952,595.70 8-12

    175,537.50 25-50

    1,054,000.00 15-20

    Sustainability Criteri

    Maintenance

    Cost (PhP)Lifespan (Yrs)

    1 Overflow-Type Weir 19,013,927.00 29.35 2.71 175,537.50

    2 Pump Irrigation System 9,842,025.30 22.46 1.51 1,054,000.00

    3 Shallow Tube Well 6,528,977.20 - - 952,595.70

    Alternative EIRR (%) BCR O&M Cost (PhP)Total Project

    Cost

  • 7/28/2019 Water Resources Plan

    30/39

    3. The EIRR of Alternative 1 is 7% percent higher than Alternative 2 and 120%

    higher in terms of BCR. The Overflow-Type Weir is also most advantageous in terms

    of O&M cost with a 1% O&M Cost Project Cost ratio.

    4. Since the irrigable service area is large, over-flow weir is best suited for its

    capacity to supply water to larger areas.

    5. The source of irrigation water when the overflow-type weir is adopted (Tucalan

    Creek) would be sufficient to meet the diversion requirements for the service area

    based on the discharge capacity of Tucalan Creek and its nearby tributaries. The two

    other alternatives pose uncertainties on underground water source.

    Based on the comparative analysis of the three alternatives, the Overflow-Type weir

    was selected for implementation in the project area. Though more expensive than

    the other options, it is chosen for its high incidence of sustainability.

    IMPLEMENTATION

    Scheme of Development

    The design approach for all items of work shall conform to NIA standards and

    specifications for irrigation projects.

    1. Diversion Works

    This involves the repair of the earthfill type diversion dam across Tucalan

    Creek at approximately 180500 N latitude and 1212815.90 E longitude. Thedam will serve to divert the flow of water thru a gated intake structure, which will

    regulate the flow of irrigation water to the canal network. Although it is not of the

    impounding type, the dam was originally constructed as earthfill because of the very

    wide section of the diversion site. The height of the dam to command the highest

    portion of the area entails high cost if concrete-overflow type is adopted.

    2. Canalization:

    Water Resource Plan Tucalan Communal Irrigation System 30 of39

  • 7/28/2019 Water Resources Plan

    31/39

    This involves the rehabilitation of dilapidated canal system from the existing

    outlet of intake up to the tail end of both the main canal and lateral canals.

    3. Canal Structures:

    This involves the construction of additional canal structures along the stretch

    of canal system, repair of damaged structures and replacement of all siphon

    structures to flume.

    4. Terminal Facilities:

    This involves the construction of additional turn-out structures, construction of

    main farm ditches and supplementary farm ditches to efficiently deliver water to the

    farm level.

    5. Service / Access Road:

    It involves the repair of 1.20 kms existing dirt road from the barangay road to

    Cabalacan West leading to the diversion dam and construction of service roads

    along the canal system.

    6. Drainage Facilities

    It involves the construction of drainage culverts along waterways and

    depression areas being traversed by the system.

    7. Project Facilities:

    This involves the construction of bunkhouse in the project area to be used

    during construction period.

    Construction Scheme and Schedule

    The project will be under the supervision of the Provincial Irrigation Engineer

    of Cagayan-Batanes. The proposed works will be undertaken into two categories

    force account works and contract works, major item of work will be awarded to

    contractors requiring the utilization of heavy equipments, while minor work and other

    work requiring intensive labor will be done by force account works to promote

    participation of farmer-beneficiaries during construction. In this process the projectWater Resource Plan Tucalan Communal Irrigation System 31 of39

  • 7/28/2019 Water Resources Plan

    32/39

    could generate 10% equity thru labor. Another way to generate equity, the farmer-

    beneficiaries could give cash or construction materials. The project will be

    scheduled for construction for 2 years.

    OPERATION AND MAINTENANCE

    Technical:

    1. Dam & ReservoirFor dam and reservoir to function properly the following are somemaintenance works that should be undertaken:

    a. Clearing of the reservoir area of any debris or floating materials

    b. Regular de-silting of the reservoir

    c. Restoration of upstream and downstream slope of the embankment

    d. Repair of upstream slope riprap.

    e. Repair of water gauge or staff gauge in the reservoir.

    2. Spillway

    The spillway should always be capable of releasing probable excessfloodwaters from the reservoir.

    a. The approach channel of the spillway should always be free of any obstructionor temporary structures.

    b. Repair of riprap in the approach, discharge and terminal sections should be donewhen necessary.

    3. Irrigation Distribution System

    a. Checking of any leakage or malfunctioning of the outlet structure.

    b. Cleaning and cutting of grasses in irrigation canal & embankment

    c. Removal of debris that can obstruct the flow of water along canals & canalembankment.

    d. Removal of silt deposits on canal bottom w/c can lessen the capacity of irrigationcanals.

    3. Paddy Fields (farmer beneficiaries party)

    Water Resource Plan Tucalan Communal Irrigation System 32 of39

  • 7/28/2019 Water Resources Plan

    33/39

    a. Leveling of paddy fields for even distribution of applied water.

    b. Height of paddy dikes must be maintained to not less than 20 cm to prevent overtopping or spillage of water.

    c. Paddy dikes should be properly compacted & plastered to minimize seepage flow.

    d. Farm ditches should be properly constructed & maintained such that each farmcan receive its equitable share of water.

    e. Additional paddy spillways provided for upland irrigations should be properlyclosed during lowland irrigation.

    Agro-Economic/ Financial

    At full development, production from the project area is expected to increase from

    2.50 tons/hectare to 5 tons/hectare for the first crop and 5 tons/hectare for the

    second crop. The cropping intensity will increase up to 148 % in the whole service

    area. The production is expected to reach 1,150 tons annually in the whole area from

    the present 387.50 tons. Annual net income is expected to increase from P

    17,104.00 to P53,379.87. These benefits are successfully attained with the

    application of farming innovations and policies. Irrigation by itself cannot do much

    way of development, but combined with other factors may create a potentially

    favorable situation for agricultural development. Other program supports such as

    credit sources, extension services and creation of money-lending cooperative in the

    association which has been shown to be inadequate in the area will

    have to be established and strengthened.

    Social Requirements

    The project after completion and successful test run of its facilities will be turned over

    to the Irrigators Association (IA) for operation and maintenance. Training and

    seminars will be conducted in order to assist the Irrigators Association as regard to

    proper Irrigation System Operation, Maintenance and Management. In this aspect

    the IA will be able to acquire knowledge to formulate their own plans and strategies

    applicable to their needs.

    Water Resource Plan Tucalan Communal Irrigation System 33 of39

  • 7/28/2019 Water Resources Plan

    34/39

    Impact of the Water Resource Plan

    The water resource plan for Tucalan Communal Irrigation System is designed to

    make a sustainable management of water and re-establishment of the operation and

    functionality of its irrigation components. Its impact in the increase of crop production

    contributes to social transformation and economic development of the area including

    the municipality itself.

    1. Urban Center and Commercial Development

    Beneficiaries seek to attain higher educational learning to further

    improve quality of living.

    With the increase of income for every household, consumption of

    various commodities and services would also increase. This will lead to

    commercial development on the area as well as nearby business

    centers.

    2. Human Settlement areas

    In the fulfillment of quality living, beneficiaries choose to have quality

    construction materials for their houses. They also strive to achieve

    electrical services for household purposes.

    3. Additional Roads

    The well-planned operation and maintenance of the irrigation system

    will create a continuous improvement of farm-to-market roads. These

    includes clearing, surface stabilization and gravelling of road networks.

    Aside from the convenience it provides, the cost of transporting farm

    production will be minimized.

    Water Resource Plan Tucalan Communal Irrigation System 34 of39

  • 7/28/2019 Water Resources Plan

    35/39

    CLIMATE MAP

    Water Resource Plan Tucalan Communal Irrigation System 35 of39

    THIS SITE

  • 7/28/2019 Water Resources Plan

    36/39

    LAND CLASSIFICATION MAP

    Water Resource Plan Tucalan Communal Irrigation System 36 of39

  • 7/28/2019 Water Resources Plan

    37/39

    LAND USE MAP

    Water Resource Plan Tucalan Communal Irrigation System 37 of39

  • 7/28/2019 Water Resources Plan

    38/39

    SOIL MAP

    Water Resource Plan Tucalan Communal Irrigation System 38 of39

  • 7/28/2019 Water Resources Plan

    39/39

    ANNEXES