waste concern turning a problem into a resource

Upload: sol-eskenazi

Post on 19-Feb-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    1/22

    This case was prepared by Jordan Mitchell, Research Assistant, under the supervision of Professor

    Johanna Mair, and in collaboration with the Schwab Foundation for Social Entrepreneurship, asthe basis for class discussion rather than to illustrate either effective or ineffective handling of anadministrative situation. October 2006.This case study has been written with the financial support of EABIS.

    Copyright 2006, IESE. To order copies or request permission to reproduce materials, call IESEPUBLISHING 34 932 534 200, send a fax to 34 932 534 343, or write Juan de Als, 43 - 08034Barcelona, Spain, or [email protected] part of this publication may be reproduced, stored in a retrieval system, used in a spreadsheet,or transmitted in any form or by any means - electronic, mechanical, photocopying, recording, orotherwise - without the permission of IESE.

    Last edited: 7/31/071

    anagement

    SCHWAB FOUNDATION FOR SOCI LENTREPRENEURSHIP

    DG-1502-E

    0-306-064

    CASE STUDY SERIES ON SOCIAL ENTREPRENEURSHIP

    Waste Concern: Turning a Problem into aResource

    Waste is merely raw material in the wrong place,

    journalist Frederick A. Talbot, Millions from Waste, 1920.

    In late September 2005, co-founders of Waste Concern, Iftekhar Enayetullah

    and Abu Hasnat Md. Maqsood Sinha, were looking at a pile of waste at the

    Matuail landfill site on the outskirts of Dhaka, Bangladesh. For ten years,

    Waste Concern had followed a decentralized composting model whereby

    each composting site was a small-scale operation processing three tons of

    organic waste per day. However, the Matuail site was different from past

    models as it would be a dual-purpose operation consisting of a gas recovery

    site and a 700-ton per day composting plant. Under the United Nations

    Clean Development Mechanism (CDM), the project would be eligible to earn

    tradable certificates for US$11 per ton of reduced methane gas, making it

    the first in the world to garner credits through composting waste.1

    While Enayetullah and Sinha were elated at the recent approval from

    the United Nations to build the site, they still had to overcome one key

    hurdle getting approval from the Dhaka City Corporation (DCC) for access

    to the land and waste. Enayetullah and Sinha believed there were three

    alternatives: 1) follow through with the original plan whereby DCC would

    1MOU signed by Waste Concern and WWR, www.wasteconcern.org, September 2004, Accessed December 28, 2005.

    IES176

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:

    MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    2/22

    2 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    supply both the land and waste; 2) purchase the land for the composting site and rely

    on the DCC for a waste supply; or, 3) purchase the land and take on the responsibility

    of waste collection themselves. While each option had its benefits and drawbacks,

    Enayetullah and Sinha were weighing up the financial, social and environmental

    aspects. A number of questions were at the fore: How could they benefit fromtransferring the learning between small-scale and large-scale operations? How should

    they organize themselves to best support the new initiative? How could they manage

    the relationship with the DCC, their international partners, and the citizens of Dhaka?

    Bangladesh

    Located between India and Burma, Bangladesh had a land area of 144,000 square

    kilometers and a population of over 144 million people.2The country had the ninth

    largest population in the world with one of the highest population densities at

    1,000 people per square kilometer. Population in urban areas such as the nations

    capital, Dhaka, exceeded 18,000 people per square kilometer in some areas. The city

    was home to 11.3 million people, making it the eleventh largest city in the world.

    Dhaka was expected to grow to 21.1 million people by 2015.3 It was estimated that

    approximately 25 percent of the countrys population lived in an urban area. This was

    expected to increase to 40 percent within 20 years.

    Total GDP was estimated at U$299.9 billion and GDP per capita was ranked 175 thout

    of 232 countries.4Approximately half of the population lived below the poverty line.

    Observers cited the central impediments to growth as: extreme monsoons and cyclones

    creating climatic instability, poor transportation and communication infrastructure,

    insufficient energy sources and inefficient government. See Exhibit 1 for a map and

    more facts about the country.

    Agriculture in Bangladesh

    63 percent of the labor force was employed in the agricultural sector compared to

    11 percent in industry and 26 percent in services. The primary agricultural products

    were rice, jute, tea, wheat, sugarcane, potatoes, tobacco, spices and fruit.

    Only 17 percent of the countrys soil was suitable for growing crops. Soil fertility was

    not only affected by improper waste management, but also through the use of

    4 million tons of chemical fertilizer per year, which hardened the soil and dried the

    moisture from the earth. Soil fertility was critical to the governments plan to increasecrop output to ensure foodstuffs for the countrys growing population.

    2CIA World Factbook, Bangladesh, www.cia.gov/cia/publications/factbook/geos, Accessed February 1, 2006.

    3 Saarc Workshop on Solid Waste Management, Country Paper Bangladesh, Department of Environment, Waste Concern, October

    2004, p. 3.

    4CIA World Factbook, Bangladesh, www.cia.gov/cia/publications/factbook/geos, Accessed February 1, 2006.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    3/22

    3IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    Waste Management in Bangladeshs Capital Dhaka

    The government-run Dhaka City Corporation (DCC) was responsible for all local

    governmental policy and management within the Dhaka metropolitan area, which

    covered 360 square kilometers and included six million residents of Dhaka megacitys

    11.3 million. Each day, these six million residents generated about 3,500 tons of waste.5

    This compared to over 17,000 tons per day of waste generated throughout the country.6

    In Dhaka, approximately 70 to 80 percent of the waste was organic and the remainder

    was paper, plastic, glass and other man-made materials.

    Nationally, the country did not have a consistent waste recycling program and waste was

    disposed of in nearly any area on the streets, in pits, in front of peoples homes or in

    the best case, in large cement containers. Large deposits of waste exposed the population

    to over 40 diseases.7It created insufferable odor and seeped into the land affecting soil

    fertility and ground water. During the monsoon season, waste was carried by extreme

    floods into the city. Mosquitoes and flies reproduced in waste and carried diseases to

    humans and other animals. In addition to the extreme health hazards, the physical mass

    of waste caused traffic problems on roads. Large deposits of waste also emitted harmful

    greenhouse gases (GHG) 8 into the atmosphere. It was estimated that Dhaka had an

    emission potential of 0.76 million tons of CO2 gas per year.9See Exhibit 2for photos of

    Dhakas waste challenges.

    Waste Collection

    The DCC was responsible for collecting all solid waste. However, due to its human,

    technological and financial resources, the DCC collected only 37 percent of all solid

    waste, even though it spent 50 percent of its operating budget on solid waste

    management. All waste collected by the DCC was piled into trucks and disposed of in

    low-lying areas outside of the city district. Observers believed that the collection

    process was inefficient given that the waste was handled four to five times before

    being disposed of. The cost of collecting one ton of waste by the DCC was estimated at

    670 BDT (US$11.26). The cost of the entire waste management process (from collection

    through to landfill operation) by the DCC was estimated at 2,045 BDT (US$38) per ton.

    The price of collecting waste was exacerbated by many dwellers habits of leaving their

    waste in front of their homes instead of taking it to designated concrete containers for

    pickup.

    In addition to the DCC, individuals known as Tokais or informal waste collectors,

    sought plastic, glass or paper and attempted to sell the waste to recycling factories for

    cash. Approximately 120,000 people were involved in informal waste collection and

    5Community based decentralized composting in Dhaka, Presentation by Waste Concern, Dhaka, September 13-17, 2004, slide 6.

    6Ibid., slide 5.

    7Ibid.

    8Greenhouse gases included carbon dioxide, methane, nitrous oxide, hydroflurocarbons, perfluorocarbons and sulfur hexafluoride. They

    prevented heat from escaping from the atmosphere and thus contributed to a greenhouse effect by warming the earths surface.

    9Enayetullah et al, 2004.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    4/22

    4 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    collected about 15 percent of the inorganic waste. Also, small companies had begun

    offering services for house-to-house collection in exchange for money, which was

    more prevalent in affluent areas of the city.

    Waste Disposal

    The Matuail landfill was the only official dumping site in the DCC district, which

    would be completely exhausted by the end of 2006. With strains on the land due to

    overpopulation, it was unlikely that another official dumping site would be opened.

    This led the DCC and other waste collectors to dump residuals in any available area.

    History of Waste Concern

    While conducting postgraduate research in early 1994, A. H. Md. Maqsood Sinha and

    Iftekhar Enayetullah had the idea of launching a non-governmental (NGO) researchorganization aimed at improving the environment by encouraging waste recycling in

    Bangladesh. Sinha, an architect and urban planner, met Enayetullah, a professional

    civil engineer and urban planner, while both were postgraduate students. As part of

    their postgraduate research, Enayetullah and Sinha set up a model of waste

    management whereby solid waste was collected and composted. The compost would

    then be used as a substitute for chemical fertilizer. The pair believed that the concept

    could be put into practice and sought support from different governmental agencies

    offering consultancy services for free. However, governmental officials did not support

    the project and Enayetullah and Sinha decided to establish their own NGO in 1995 in

    order to launch the first pilot project. The aim of the organization was to promote the

    idea of converting waste into a resource. The first project was directed at: developinga low-cost technique for [the] composting of municipal solid waste. 10 Enayetullah

    commented:

    In 1994, we tried hard to convince different government agencies to initiate the

    project by offering free consultancy services but they were all skeptical We believe

    that waste should be considered as a resource, rather than just a problem and it can

    be managed in a decentralized manner with public-private-community partnership.

    Thats why in 1995, we took the alternative course of demonstration of our model

    to convince different social groups.11

    Besides the skepticism in the government, Sinha and Enayetullah faced other barriers.

    They did not have access to appropriate waste treatment technology nor did they haveany land to launch their pilot project. The lack of knowledge of waste recycling

    combined with no official policy or framework further complicated their attempts to

    get the project off the ground. The pair sought seed money and financing, but were

    unsuccessful for one year in garnering support. Eventually, they convinced the Lions

    10Christian Zurbrgg; Drescher, Silke; Rytz, Isabelle; Sinha, A.H.Md. Maqsood; and Enayetullah, Iftekhar, Decentralised composting in

    Bangladesh, a win-win situation for all stakeholders, El Sevier, June 16, 2004.

    11Presentation by Waste Concern, Dhaka, September 13-17, 2004, slides 13-14.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    5/22

    5IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    Club Dhaka North to donate 1,000 square meters of land in the area of Mirpur for a

    three-month period. Sinha reflected, The Lions Club was very hesitant to give us land,

    because they were very afraid of creating a lot of odor.

    After getting the project operational in less than three months, Sinha and Enayetullah

    demonstrated that the odor from the site was not problematic. The Lions Club gave

    them permission to continue housing the project on Lions Club land. They used

    the project as a demonstration site and showed it extensively to individuals from

    government, private companies and the community. Sinha and Enayetullah estimated

    that the Mirpur project alone reduced the cost of the DCC by $15,085 annually.12This

    represented an 80 percent reduction in per ton management costs for waste for the

    DCC in the project area of Waste Concern.

    In 2000, Sinha and Enayetullah set up a for-profit consultancy arm of Waste Concern,

    allowing them to generate revenues to fund Waste Concerns not-for-profit research

    and development division. As of the fall of 2005, this dual structure was still in place.

    See Exhibit 3for the pairs CVs.

    The Waste Concern Model of Decentralized Composting

    Waste Concerns model integrated house-to-house waste collection, composting and

    marketing the compost as a fertilizer. The operation revolved around a small-scale,

    decentralized composting plant each plant was set up to process three tons of waste

    per day.

    Depending on the income level, households paid BDT 10 to 20 (US$0.17 to US$0.34) to

    Waste Concern per month. Waste was collected by one to three Waste Concernemployees who rode on rickshaws with 1.18 cubic meter capacity. Each rickshaw

    served between 300 and 400 households and the revenue from households paid for the

    salaries of the collectors. For each three-ton plant, there were 20 workers: nine workers

    for house-to-house collection and eleven people at the plant, including the plant

    manager.

    After the waste was collected, the rickshaw driver and collectors took the waste to the

    composting site. All waste was sorted and all recyclable products like glass, plastic and

    metals were separated and stored in a separate area. Three tons of organic waste

    yielded 750 kg of compost per day. The process of converting organic waste to saleable

    compost took 55 days: 40 days to produce the compost and 15 days for the compost to

    mature.

    Waste Concern used the Indonesian Composting Method all waste was piled in large

    heaps on top of a wooden structure and was turned every four to five days. The waste

    piles were under a covered shed, which protected the compost workers from the sun

    and rain. In order to turn solid waste to compost a temperature of between 55 and

    65 degrees Celsius was optimum. Workers used long bamboo sticks to turn over the

    12Christian Zurbrgg; Drescher, Silke; Rytz, Isabelle; Sinha, A.H.Md. Maqsood; and Enayetullah, Iftekhar, Decentralised composting in

    Bangladesh, a win-win situation for all stakeholders, El Sevier, June 16, 2004.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    6/22

    6 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    waste. Workers also watered the waste heaps, which gave the bacteria a new food

    source.13Exhibit 4shows the process and pictures of the operation.

    Once the compost had matured, it was sold to MAP Agro for BDT 2.5 (US$0.04) per kg.

    MAP Agro then enriched the compost and sold it through its parent companys

    (ALPHA Agro) extensive distribution network at prices from BDT 6 (US$0.10) to BDT

    12 (US$0.20).

    Revenues were split at 30 percent from house-to-house collection and 70 percent

    through the saleof composted materials.14Waste Concerns operating costs comprised

    raw materials used in composting, the salaries of the workers (both the waste collectors

    and the plant staff) and utilities. Each three-ton plant brought in total revenues of

    approximately BDT 741,000 (US$12,449) and spent approximately BDT 551,200

    (US$9,260) per year. All surpluses were used to fund compost testing at the

    governments laboratory (US$2,500 per year). The remainder was invested back into

    the site to maintain the building and supply uniforms for the workers.

    The fixed costs for establishing a new three-ton plant were BDT 1,008,000 (US$16,934).

    This included: the construction costs of the sorting platform, the composting shed with

    drainage, an office, a toilet and a storage area for the recovered recyclable products.

    Waste Concern relied solely on the donation of land from third parties and did not

    include the value of land in its fixed costs. Each plant offered a payback in 23 months.

    Exhibit 5shows the key revenues and costs of a three-ton plant.

    The Replication of the Decentralized Small-Scale Model

    In 1997, the Regional Urban Development Office-South Asia agreed to offer support

    and further test the model by scaling up the activity of Waste Concern in Dhaka.Ayear later, the Ministry of Environment and Forest of the Government of Bangladesh

    under the Sustainable Environmental Management Program supported by the United

    Nations Development Program (UNDP) requested that Waste Concern roll out the

    model to five communities within Dhaka. The DCC and Public Works Department

    however did not come forth with land, which led Sinha and Enayetullah to more

    demonstrations. Finally, the DCC and Public Works provided suitable land plots. Sinha

    talked about the obstacles:

    The single biggest obstacle for the model of community based decentralized

    composting project was availability of land in the city for such facilities. Public-

    private-community partnership and the concept of the 4 Rs (reduce, reuse, recycleand recovery of waste) were absent in Bangladesh before our intervention.15

    In 1999, Waste Concern began talking to the countrys pre-eminent fertilizer supplier,

    MAP Agro (a sister concern of ALPHA Agro), to purchase the organic fertilizer being

    13A.H.Md. Maqsood Sinha and Enayetullah, Iftekhar, Community Based Decentralized Composting, Urban Management Programme

    for Asia and the Pacific, 1999, pp. 8-9.

    14Lisa Hiller, Cash for Trash in Bangladesh, Choices, August 2002, p. 12.

    15A.H.Md. Maqsood Sinha and Enayetullah, Iftekhar, Teams Entry to the Fast 50 Social Entrepreneurs, Fast Company, 2002.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    7/22

    7IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    produced at Waste Concerns composting plants. Initially, MAP Agro was uncertain

    that local farmers would adopt organic fertilizer as part of their growing techniques.

    Waste Concern convinced MAP Agro by comparing the superior quality of crops grown

    with organic fertilizer in place of chemical fertilizer. Eventually, MAP Agro agreed to

    purchase all of Waste Concerns organic compost output and was the first in thecountry to begin marketing organic compost.

    In 2000, Waste Concern successfully rolled out the decentralized model to five

    communities in Dhaka city. With greater visibility, representatives from other

    Bangladeshi cities approached Waste Concern to see if the same concept could be

    rolled out to more sites. Enayetullah stated:

    We thought originally that we would be able to roll out the decentralized model

    and replicate it ourselves to other sites. But, it was not possible to do from a

    manpower perspective. If we had tried to do it all ourselves, it would have resulted

    in major delays in implementing it. With these types of projects the major barrier is

    the financing. We realized that if we could get the financing then we could supplythe technology.

    In looking for financing, Waste Concern approached several international banks and

    other international organizations. However, Waste Concern was unable to secure funds.

    International banks were concerned that the organization in its not-for-profit structure

    would not be able to pay back the bank loan. Development organizations supported

    similar projects but for piloting purposes only. This led Waste Concern to look for other

    sources of funding. After several presentations from Waste Concern and multiple levels

    of approval, the Department of Public Health Engineering of the Government of

    Bangladesh secured funding from UNICEF and replicated the Waste Concern model

    in

    14

    locations in 2002.16 In 2004, another 20 sites were approved to be implementedthroughout Bangladesh. All projects were organized as a three-way partnership: Waste

    Concern supplied the technology and know-how; the Bangladeshi government, UNICEF,

    CIDA (Canadian International Development Agency), and SDC (Sustainable Development

    Commission) funded the initiative; and, the private sector marketed the final composted

    fertilizer.

    Sinha and Enayetullah dedicated 50 percent of their time to research and development

    activities under the not-for-profit arm of Waste Concern. The other 50 percent was

    directed at the for-profit waste consultancy. Enayetullah stated: We use the

    consultancy to generate revenues to fund the not-for-profit research and development

    arm.

    By 2005, the government of Bangladesh actively encouraged farmers to increase their

    utilization of organic compost. Compost was cheaper than chemical fertilizer and most

    agreed that it produced superior crops. The acceptance of organic fertilizer encouraged

    three other companies to include organic fertilizers as part of their product portfolios.

    As of 2005, MAP Agro was the market leader followed by Northern Agro, Faruk

    Fertilizer and Fuvid Agro Ltd. Enayetullah stated: The demand for organic fertilizer is

    16Community based decentralized composting in Dhaka, Presentation by Waste Concern, Dhaka, September 13-17, 2004, slide 70.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    8/22

    8 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    growing and theres currently a problem with supply. Now, with four companies all

    offering organic fertilizers, this is good for fair competition.

    Waste Concerns model was recognized internationally as an efficient and cost-

    effective way of using waste. The model was being replicated in Vietnam and Sri

    Lanka. It was also lauded for providing employment for unskilled laborers. Sinha and

    Enayetullah were honored by becoming Ashoka Fellows in 2000, and won numerous

    awards such as the United Nations Poverty Eradication Award in 2002, the Fast

    Company Champions of Innovation in 2002, the Technology for Humanity from the

    U.S. Tech Museum in 2003, and Outstanding Social Entrepreneurs from the Schwab

    Foundation of Switzerland in 2003.

    CDM Proposal for Landfill Gas Extraction Site at Matuail, Dhaka

    Throughout 2003, Sinha and Enayetullah had the idea of increasing the scale of the

    three-ton composting plant. As Enayetullah stated:

    Small is beautiful, but you need to have scale. The small-scale decentralized three-

    ton composting plant is great for small and medium sized cities. However, in Dhaka,

    its probably best to have a larger centralized composting site. And, with a larger

    site, you have a real opportunity with tradable certificates. Without trading

    certificates, the opportunity of creating a centralized 700-ton per day composting

    site would not be feasible. Also, with large centralized sites, you can transfer the

    learning to smaller decentralized locations.

    Waste Concern submitted a proposal to the United Nations, which would allow the

    organization to earn tradable certificates called Certified Emission Reductions (CERs).Under the program known as the Clean Development Mechanism (CDM), nations were

    able to buy and sell CERs to hit their specific Kyoto Protocol emission reduction targets. 17

    Sinha and Enayetullahs idea was to use the existing landfill site in Matuail an area

    seven kilometers from Dhaka to recover methane gas from the 5-metre high landfill

    pile. They also wanted to use the land to build a large-scale centralized composting

    plant.

    In 2004, the Waste Concern team began conversations with the Dutch company World

    Wide Recycling BV (WWR) to jointly develop the landfill gas recovery site. WWR was

    a for-profit company that acted as an investor and operator by partnering with private

    and public enterprises in the creation of decentralized recycling centers. (See Exhibit 6

    for more information). In September 2004, WWR and Waste Concern signed a

    memorandum of understanding to form a special purpose company and put forward

    aproposal for consideration by the United Nations CDM Executive Board. WWR would

    provide all of the financing and Waste Concern would supply the local knowledge and

    technology and seek Bangladeshi government approval. Both parties would engineer

    17The Kyoto Protocol is an international agreement that called for 39 developed countries to reduce greenhouse gases by 5.2 percent

    over 1990 levels. CERs were one mechanism developed by the Kyoto Protocol.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    9/22

    9IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    the site and make the landfill site operational. The organizations would be able to sell

    the CERs for US$11 per ton of reduced methane gas.

    During 2005, both organizations met extensively with United Nations representatives,

    foreign and local government officials, academics, engineers, waste experts, electricity

    operators and local residents. In making their presentations to various stakeholders, the

    team presented the following benefits:

    Environmental capture 50 percent of the landfill gas emitted from the

    Matuail waste disposal site, which would reduce greenhouse gases and reduce

    the risk of onsite fires;

    Economic foreign capital inflow from WWR and potentially other sources;

    and,

    Social improved health conditions due to the reduction of gases and the

    creation of jobs for local residents.18

    On September 17, 2005, the landfill gas recovery project and the composting plant

    were accepted by the United Nations CDM initiative.

    Operations

    The site would have two main areas: the landfill gas recovery area and the composting

    area.

    Landfill Gas Recovery In the landfill recovery zone, methane gas emitted naturally

    from the decomposing landfill, would be captured and turned into electricity through a

    gas-powered engine. The electricity would then be used by local power utilities. Theteams planned to reshape the current landfill and introduce proper land filling

    techniques with daily cover of waste as well as leachate collection and treatment

    facility to reduce ground water pollution. These actions were aimed at extending the

    sites lifetime to 2021. The site would require extraction equipment including vertical

    wells, piping, a condensate separator and compressors. The gas utilization equipment

    included a flare, dedicated gas-engines, an electric generator and an electric grid

    connection.19

    In the first seven-year crediting period, WWR and Waste Concern predicted that the

    project would recover 50 percent of the methane gas. This would allow them to convert

    566,000 tons of CO2 equivalents (methane gas) from the landfill gas recovery projectalone). 20 The site would have an electricity production capacity of three to six

    megawatts (MW). In the first year, the site would produce 6,625 MW hours increasing

    to over 16,000 MW hours by 2010. Exhibit 7 shows a diagram and more details of

    theproject.

    18Clean Development Mechanism Project Design Document Form, UNFCCC, unfccc.org, Version 2, July 1, 2004, Accessed January 22,

    2006, pp. 2-3.

    19Ibid., pp. 5-6.

    20Ibid., p. 2.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    10/22

    10 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    Composting The composting plant would also be designed to reduce methane gas by

    avoiding waste landfilling and performing aerobic composting. Waste Concern and

    WWR developed a new methodology to calculate the reduction of methane emission by

    composting which was approved by the UNFCCC (United Nations Framework

    Convention on Climate Change). The compost would be turned into organic fertilizerand made available for sale to the countrys four fertilizer companies. The composting

    plant was significantly different to Waste Concerns small-scale plants. Whereas Waste

    Concerns smaller plants processed three tons of solid waste per day, the proposed site

    at Matuail would process 700 tons of solid waste per day. It was estimated that

    624,813 tons of CO2 equivalents would be reduced by composting 700 tons/day of

    solid waste in the composting plant.

    Finances

    The total investment to get the project operational was US$10 million. Approximately

    US$4.9 million was for the establishment of the composting area and US $3.5 millionfor the gas extraction and electricity generation portion of the project. Using a

    12percent discount rate to reflect commercial lending fees in Bangladesh, the team

    had calculated that the gas extraction portion of the site would create a negative net

    present value of US$-4.2 million over 15 years without CERs. However, with CERs, the

    project would produce a positive net present value. Under this scenario, revenues

    would be generated from the sale of electricity only.

    WWR would contribute the financing for both projects. Both sides were seeking

    additional funding in the form of a grant or long-term loan from the Netherlands

    Development Finance Company (FMO), which was a special bank set up in 1970 by the

    Dutch government for the purpose of assisting developing countries. FMO carefullyscrutinized projects to ensure they fell under strict guidelines such as public-private

    involvement, corporate governance, environmental details and social policies. The FMO

    offered a grant to a maximum of 45 percent of the project on a maximum project cost

    of 45million (US$54 million).21

    Seeking Approval from the DCC and Potential Options

    Even though Waste Concern had been given the green light by the CDM Board of the

    Government of Bangladesh in 2004 (see Exhibit 8 for a copy of the approval letter),

    they were still waiting for approval from the municipal DCC. The DCC owned and

    operated the Matuail landfill site. Enayetullah commented:

    We were authorized to go ahead with the project from the national government,

    but then the municipality did not give their authorization. They were a little

    concerned that they were handing over control of the landfill site to us. That was

    the point where we said, maybe we can separate the landfill site from the

    21Clean Development Mechanism Project Design Document Form, UNFCCC, unfccc.org, Version 2, July 1, 2004, Accessed January 22,

    2006, p. 6.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    11/22

    11IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    composting activity and change our approach. Its not necessary to keep the

    landfill and composting site together. We would just have to think of another plan.

    Enayetullah and Sinha had made the decision to continue seeking approval from the

    DCC for the landfill recovery site since they needed an established landfill site with a

    minimum of five to eight meters of waste in order to capture sufficient gas.

    The major question was what should be done with the composting site. Enayetullah

    and Sinha believed there were three central options:

    1. Continue with the original plan whereby DCC would supply the land and the

    waste for the composting site;

    2. Waste Concern would purchase the land for the composting site and the DCC

    would supply the waste; or,

    3. Waste Concern would purchase the land for the composting site and look after

    the collection of waste.

    Option 1: DCC to Supply the Land and Waste

    Under this option, the DCC would supply both the land and waste for the composting

    site. WWR and Waste Concern would be responsible for designing, constructing and

    operating the site. The fixed cost of constructing the composting site was estimated at

    US$4.9 million and annual operating costs were projected to be US$1.22 million.

    Revenues from the sale of compost were predicted to be US$3.11 million per year and

    the sale of tradable certificates would bring in US$560,000 per year. In exchange for

    using the DCCs land and waste, Waste Concern would pay a 20 percent royalty fee on

    the overall revenues of the composting site per year.

    Enayetullah and Sinha predicted a delay to the project of seven to twelve months

    before receiving approval from the DCC. In addition, Enayetullah and Sinha were

    uncertain of changes to the contract in the future.

    Option 2: Purchase the Land for Composting and DCC to Supply the Waste

    The second option was to purchase a plot of land for the composting site but use the

    waste collected by the DCC. Enayetullah and Sinha estimated that the cost of a suitable

    piece of land would be US$514,000. The fixed cost of constructing the site, the annual

    operating costs and all revenues would be the same as in the first option. WasteConcern would pay 10 percent of all the revenues to the DCC in exchange for

    supplying thewaste.

    Option 3: Purchase the Land and Collect the Waste

    Under the third option, Waste Concern would collect the waste directly from

    individuals at pre-determined quantities, qualities and in accordance with a pick-up

    schedule. Owning the land and collecting the waste would alleviate any royalty

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    12/22

    12 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    payments to the DCC. Enayetullah and Sinha estimated waste collection would cost an

    additional US$780,000 per year beyond the annual operating costs of $1.22 million for

    the site. All other fixed costs and revenues would be the same as the other options.

    The Decision

    Enayetullah and Sinha thought about what had been achieved in ten years. Their list of

    achievements was long through their efforts of setting up numerous decentralized

    composting sites, they had successfully achieved one of their key goals of turning

    waste into a resource. This, in turn, had improved soil quality, created employment,

    enhanced social standards, reduced sickness and disease, attracted international

    acclaim, spurred foreign investment and saved money for government bodies like the

    DCC and the Bangladesh Ministry of Environment.

    Now they were embarking on a major project that involved several international

    stakeholders and millions of U.S. dollars of investment. They had severalconsiderations: Which option for the centralized composting site would be the best for

    the future of Waste Concern? How could learning be exchanged between the

    centralized and decentralized composting models? What structure would be the most

    appropriate for Waste Concern? How should Waste Concern include all of the

    stakeholders in the impending change?

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    13/22

    13IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    Exhibit 1 Information About Bangladesh

    People Industry

    Population 144,319,628 Agricultural products Rice, jute, tea, wheat, sugarcane, potatoes, tobaccoAge structure Industries Cotton textiles, jute, garments, tea processing, newsprint,

    0-14 years old 33.1% cement, chemical fertilizer, light engineering, sugar 15-64 years old 63.5%+65 years old 3.4% Industrial product growth rate 6.7%

    Median age 21.87 Electricity production 17.42 billion kWhPopulation growth % 2.1% Oil production 6,825 bbl/day

    Oil consumption 84,000 bbl/dayEconomic Natural gas - p roduction 9.9 billion cu mGDP 299.9 billionGDP growth rate 5.2% Current account balance -591 millionGDP/capita 2100 Exports $9.372 billionGDP by sector Exports partners US 22.4%, Germany 14.5%, UK 11.2%, France 6.9%,

    Agriculture 20.5% Imports partners Italy 4%, India 15.1%, China 12.5%, Singapore 7.5%,Industry 26.7% Kuwait 5.5%, Japan 5.3%, Hong Kong 4.5%Services 52.8% Currency Taka (BDT)

    Inflation 6.7% F/X rate to US$ 64.26Unemployment 2.5% F/X rate to euroPublic debt as % of GDP 46.1%

    in US$ except where otherwise noted.

    Source: CIA World Fact Book, www.cia.gov, Accessed 1 February 2006.

    People Industry

    Population 144,319,628 Agricultural products Rice, jute, tea, wheat, sugarcane, potatoes, tobaccoAge structure Industries Cotton textiles, jute, garments, tea processing, newsprint,

    0-14 years old 33.1% cement, chemical fertilizer, light engineering, sugar 15-64 years old 63.5%+65 years old 3.4% Industrial product growth rate 6.7%

    Median age 21.87 Electricity production 17.42 billion kWhPopulation growth % 2.1% Oil production 6,825 bbl/day

    Oil consumption 84,000 bbl/dayEconomic Natural gas - p roduction 9.9 billion cu mGDP 299.9 billionGDP growth rate 5.2% Current account balance -591 millionGDP/capita 2100 Exports $9.372 billionGDP by sector Exports partners US 22.4%, Germany 14.5%, UK 11.2%, France 6.9%,

    Agriculture 20.5% Imports partners Italy 4%, India 15.1%, China 12.5%, Singapore 7.5%,Industry 26.7% Kuwait 5.5%, Japan 5.3%, Hong Kong 4.5%Services 52.8% Currency Taka (BDT)

    Inflation 6.7% F/X rate to US$ 64.26Unemployment 2.5% F/X rate to euroPublic debt as % of GDP 46.1%

    in US$ except where otherwise noted.

    Source: CIA World Fact Book, www.cia.gov, Accessed 1 February 2006.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    14/22

    14 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    Exhibit 2 Photos of Dhakas Waste Problem

    Source: Company documents.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    15/22

    15IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    Exhibit 3 CVs of Co-Founders

    IFTEKHAR ENAYETULLAH

    Date of Birth: August 18, 1967

    Education

    Masters Degree in Urban and Regional Planning with specialization in urban waste and

    environmental management from Bangladesh University of Engineering and Technology

    (BUET), Dhaka.

    Experience

    Co-founder and Director of Waste Concern conceptualized, designed andimplemented the community-based decentralized composting model, using public-

    private-community partnerships approach

    Member of the Institution of Engineers Bangladesh (IEB), Bangladesh Institute of

    Planners (BIP) and Building Partnership Development for Water and Sanitation

    of

    United Kingdom

    Founding member of WasteNet in Bangladesh

    Editor of a quarterly newsletter on waste management and recycling in Bangladesh

    Served as a Member of the Expert Committee on Clinical Waste Management

    constituted by the Government of Bangladesh

    More than forty publications to his credit, including scientific papers, articles, factsheets, manuals, reports, recycling and urban environmental management

    A professional civil engineer and urban planner by training

    Awards and Recognition

    Outstanding Social Entrepreneur by the Schwab Foundation of Switzerland for the

    year

    2003

    Tech Museum Awards 2003. Selected as Tech Laureate by the Tech Museum of USA for

    developing technology benefiting humanity

    Outstanding Engineers Award 2003 from the Institution of Engineers, Bangladesh

    (IEB). Professional Excellence Award 2003 as an engineer from the Daily Star a prominent

    newspaper of Bangladesh

    United Nations Poverty Eradication Award 2002 from entire Asia and the Pacific region

    Fast Company magazines first ever Fast 50 fifty champions of innovation for the

    year 2002

    Elected as an Ashoka Fellow in Ashoka Innovators for the Public of USA in 2000

    Source: Company documents.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    16/22

    16 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    Exhibit 3 (continued)

    ABU HASNAT MD. MAQSOOD SINHA

    Date of Birth: April 4, 1963

    Education

    Masters Degree in Urban and Regional Planning with specialization in environment, urban

    waste management and recycling from Asian Institute of Technology (AIT), Bangkok, Thailand

    Experience

    Co-founder and Director of Waste Concern conceptualized, designed and

    implemented the community-based decentralized composting model, using public-

    private-community partnerships approach

    Member of the Institution of Engineers Bangladesh (IEB), Bangladesh Institute of

    Planners (BIP) and Building Partnership Development for Water and Sanitation of

    United Kingdom

    Founding member of WasteNet in Bangladesh

    Editor of a quarterly newsletter on waste management and recycling in Bangladesh

    Member of the Local Consultative Group (LCG), an environmental subgroup in the field

    of waste and solid waste management and environment

    Served as a Member of the Expert Committee on Clinical Waste Management

    constituted by the Government of Bangladesh

    More than forty publications to his credit, including scientific papers, articles, fact

    sheets, manuals, reports, recycling and urban environmental management

    An urban planner and architect by profession

    Awards and Recognition

    Outstanding Social Entrepreneur by the Schwab Foundation of Switzerland for the

    year2003

    Tech Museum Awards 2003. Selected as Tech Laureate by the Tech Museum of USA for

    developing technology benefiting humanity.

    Outstanding Engineers Award 2003 from the Institution of Engineers, Bangladesh (IEB). Professional Excellence Award 2003 as an engineer from the Daily Star a prominent

    newspaper of Bangladesh

    United Nations Poverty Eradication Award 2002 from entire Asia and the Pacific region

    Fast Company magazines first ever Fast 50 fifty champions of innovation for the

    year 2002

    Elected as an Ashoka Fellow in Ashoka Innovators for the Public of USA in 2000

    Source: Company documents.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    17/22

    17IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    Exhibit 4 Composting Process

    Source: Company documents.

    Waste Collection

    Composting

    Sawdust / Bokashi

    Water

    ScreeningResidue

    Recyclables 6%

    Rejects 14%

    Local

    Market

    Transport

    to

    Dumpsite

    Private Sectordistributes

    compost to the

    farmers

    Sorting

    Piling

    Composting

    Maturing

    Screening

    Bagging

    Selling

    Composting

    Additives

    Marketing

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    18/22

    18 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    Exhibit 4 (continued)

    Digital Representation of Decentralized Composting Site

    Collection Sorting Piling

    Composting Composting (Turning) Bagging

    Source: Company documents.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    19/22

    19IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    Exhibit 5 Revenues and Costs of a Composting Plant

    Source: Company documents.

    Annual Financials of a Typical 3-ton Plant

    BDT US$F/X Rate 59.524

    Revenue from House-to-House Collection 141,000 2,369Revenue from Sale of Compost 600,000 10,080

    Total Revenue 741,000 12,449

    Total CostsRaw Materials 96,000 1,613

    SalariesWaste Collectors Salaries 141,000 2,369

    Composting Plant Workers Salaries 132,000 2,218Plant Manager 78,000 1,310

    Total Salaries 351,000 5,897

    Electricity, Water and Maintenance 104,220 1,751

    Total Costs 551,220 9,260

    Total Surplus/(Deficit) 189,780 3,188

    Major Assumptions for 3 ton/Day Plant

    Land Required / Plant (Katha) 7

    Fixed Cost / Plant * 1,008,000 16,934Operating Cost / Plant ** 300,000 5,040Total Laborers for Composting Only/ Plant *** 4Total Labourers (Including Collectors) 20Compost Produced (Daily) (kg) 750Expected Revenue from Sale of Compost **** 600,000 10,080Pay Back Period (Months) 23

    * Without Land Cost/Rent.** Operating Cost Excludes Cost-Neutral Collectors and Raw Material Costs.*** Laborers Required for Composting Purpose Only.**** From 1 Ton of Organic Waste 250 kg of Fine Compost Can Be Produced.

    Annual Financials of a Typical 3-ton Plant

    BDT US$F/X Rate 59.524

    Revenue from House-to-House Collection 141,000 2,369Revenue from Sale of Compost 600,000 10,080

    Total Revenue 741,000 12,449

    Total CostsRaw Materials 96,000 1,613

    SalariesWaste Collectors Salaries 141,000 2,369

    Composting Plant Workers Salaries 132,000 2,218Plant Manager 78,000 1,310

    Total Salaries 351,000 5,897

    Electricity, Water and Maintenance 104,220 1,751

    Total Costs 551,220 9,260

    Total Surplus/(Deficit) 189,780 3,188

    Major Assumptions for 3 ton/Day Plant

    Land Required / Plant (Katha) 7

    Fixed Cost / Plant * 1,008,000 16,934Operating Cost / Plant ** 300,000 5,040Total Laborers for Composting Only/ Plant *** 4Total Labourers (Including Collectors) 20Compost Produced (Daily) (kg) 750Expected Revenue from Sale of Compost **** 600,000 10,080Pay Back Period (Months) 23

    * Without Land Cost/Rent.** Operating Cost Excludes Cost-Neutral Collectors and Raw Material Costs.*** Laborers Required for Composting Purpose Only.**** From 1 Ton of Organic Waste 250 kg of Fine Compost Can Be Produced.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    20/22

    20 IESE Business School-University of Navarra

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    Exhibit 6 Information on World Wide Recycling BV (WWR) - Excerpts from Brochure

    World Wide Recycling BV (WWR) is a company that aims to introduce the Recycling CentreConcept worldwide, with an emphasis on Latin America, South-east Asia and former Eastern

    Europe. The company is owned by Mr. Jan Boone, founder and main shareholder of VAR BV.

    Conditions for Success

    WWR is convinced that a Public Private Partnership is the most suitable model for operating a

    recycling centre. After all, waste treatment is a public task that can executed more efficiently

    and at lower cost in cooperation with private entities. There are many definitions of a PPP. The

    one that fits the WWR concept best is:

    an institutional relationship between the public sector and members of the private-for-profit

    and/or the private-not-for-profit sector, in which the various public and private actorsparticipate in defining the objectives, the methods and the implementation of an agreement of

    cooperation.

    Investor and Operator

    WWRs objective is to participate as an investor as well as an operator. Through the use of its

    resources, WWR can financially engineer projects, thus underlining its commitment. At the

    same time, WWR can warrant the performance of the operation by acting as an operator in

    theproject.

    The Recycling Centre Concept

    The Principle

    A recycling centre is a landfill in combination with several recycling installations, each tuned

    to recover a specific fraction of the incoming waste. Various separate installations can be

    applied, depending on specific needs and circumstances. In developing a recycling centre, a

    modular approach is obvious: with reference to local circumstances the recycling centre may

    start with a single installation, after which the concept may be developed in full over a period

    of years.

    The Set-up: Decentralized

    WWR strongly advocates a decentralized set-up, with recycling centres located close to waste

    producing sources. In this set-up transportation of waste is being minimized. The Recycling

    Centre Concept warrants a working method that keeps the inconvenience of smell, visual

    distraction and attracted animals to a minimum. For the implementation of new projects, high

    standards will be applied. A new recycling centre can easily be built near an existing landfill,

    extending its lifetime and improving the environmental and social situation.

    Source: World Wide Recycling, www.wwrgroup.com, PDF Brochure, Accessed. February 6, 2006.

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    21/22

    21IESE Business School-University of Navarra

    DG-1502-EWaste Concern: Turning a Problem into a Resource

    Exhibit 7 Diagram of Landfill Area

    Source: Project Design Document Form, Proposal to CDM, p. 14.

    Details of CDM Project

    Emission reductions in first crediting period

    Year

    2006 6625 4185

    2007 13976 8829

    2008 14723 9301

    2009 15492 9787

    2010 16284 10287

    Proposal to CDM, p. 31.

    Net electricity delivered to

    grid by combusting

    extracted methane in gasengines

    CERs (net) related to

    prevented electricity

    generation in the grid(elsewhere)

    MWh tons (1000 kg)

    Waste production(households,Industry, etc.)

    Waste collection,sorting,transportation

    Landfill

    Landfill gasproduction

    Flaring

    Electricityproduction

    On site useof electricity

    Electricityfrom grid

    ElectricityTo grid

    End useBoundary limit

    Waste production(households,Industry, etc.)

    Waste collection,sorting,transportation

    Landfill

    Landfill gasproduction

    Flaring

    Electricityproduction

    On site useof electricity

    Electricityfrom grid

    ElectricityTo grid

    End useBoundary limit

    This document is authorized for use byTim Chai, from 8/27/2013 to 12/20/2013, in the course:MGMT 209: 001 Political and Social Environment of Management - Markovits (Fall 2013), University of Pennsylvania.

    Any unauthorized use or reproduction of this document is strictly prohibited.

  • 7/24/2019 Waste Concern Turning a Problem Into a Resource

    22/22

    DG-1502-E Waste Concern: Turning a Problem into a Resource

    Exhibit 8 Letter of Approval from the Government of Bangladesh

    Source: Company documents.