Walt Whitman High School

Addition & Renovation

Board of Education PresentationFebruary 12, 2019

Scope of Work

• Demolish Whittier Woods Pre-School and Whittier Woods Annex

• Construct Addition –75,000 GSF

• Renovate classrooms into Dance studio

• Renovate portions of the existing school, like the science labs on the 3rd floor, to facilitate phasing

• Create a commons space for students

• Increase number of parking spaces for staff and students

• Plan for future 22,000 GSF addition

• Incorporate sustainable design principles

• School to remain in operation during construction

Pre-School

Annex

School CharacterCircular drop off & Entrance at Whittier Woods Annex

Whittier Woods Pre-School from Whittier Blvd

Main entrance to Walt Whitman High School

Existing Site Plan

Expansion Area

EL.+350

1st floor EL.+3352nd floor EL.+3503rd floor EL.+365

EL.+335

EL.+335

Proposed Site Plan

Conceptual Building Section

Proposed 1st floor

Proposed 2nd floor

Proposed 3rd floor

Proposed 4th floor

Proposed Elevations