vision word macro for deltek vision 5.1 - feapc.com web viewcreate design drawings andspecifications...

2
One Cherry Parking Garage Evaluation Denver, Colorado One Cherry Center is an 11-story office building located in Denver, Colorado. The property included a five-story, 90,000-SF, concrete parking garage that was originally constructed in 1985. The garage extended under a portion of the office building’s main entrance plaza area, and also provided entrances to the building at multiple levels. Since original construction, the garage had problems with drainage and water ponding throughout several floor areas, which had led to accelerated deterioration of some structural concrete. The garage had isolated concrete repairs completed at various times in the past, but several issues related to drainage and general deterioration still existed. Facility Engineering Associates, P.C. (FEA) was retained by the property management in 2012 to assess the garage and provide recommendations for needed repairs in a phased approach over the following five years. After observing the garage and performing limited mechanical sounding, FEA created recommendations for repairs which included structural concrete patches, installation of new drains to alleviate existing drainage issues, installation of a new traffic bearing membrane to increase durability and aesthetics of the slab, and repairs to PRIMARY CLIENT REFERENCE Brett Sanders Asset Manager 501 S. Cherry Street Suite 610 Denver, CO 80246 (303) 770-6870 START DATE: April 23, 2012 COMPLETION DATE: On going VALUE OF CONTRACT: $49,100 CLIENT BENEFITS Received a holistic approach to fix previously on-going issues and increase overall appearance of the garage Provided prioritized multi- year work plan to address the most critical repairs first while meeting yearly project funding Minimized loss of use by effectively coordinating repair areas Repaired and new traffic coating reduced future maintenance costs Upgraded appearance of garage will meet demands of higher class tenants SCOPE ITEMS Assessment of garage to identify needed structural repairs and aesthetic updates

Upload: donguyet

Post on 06-Feb-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

One CherryParking Garage EvaluationDenver, Colorado

One Cherry Center is an 11-story office building located in Denver, Colorado. The property included a five-story, 90,000-SF, concrete parking garage that was originally constructed in 1985. The garage extended under a portion of the office building’s main entrance plaza area, and also provided entrances to the building at multiple levels.

Since original construction, the garage had problems with drainage and water ponding throughout several floor areas, which had led to accelerated deterioration of some structural concrete. The garage had isolated concrete repairs completed at various times in the past, but several issues related to drainage and general deterioration still existed.

Facility Engineering Associates, P.C. (FEA) was retained by the property management in 2012 to assess the garage and provide recommendations for needed repairs in a phased approach over the following five years. After observing the garage and performing limited mechanical sounding, FEA created recommendations for repairs which included structural concrete patches, installation of new drains to alleviate existing drainage issues, installation of a new traffic bearing membrane to increase durability and aesthetics of the slab, and repairs to other non-structural components to provide a consistent and upgraded appearance.

Following FEA’s recommendations, the property management was able to acquire the necessary funds to start the repair process. FEA is set to complete the first year’s design documents in early 2013.

PRIMARY CLIENT REFERENCEBrett SandersAsset Manager501 S. Cherry StreetSuite 610Denver, CO 80246(303) 770-6870 START DATE: April 23, 2012COMPLETION DATE: On going

VALUE OF CONTRACT: $49,100

CLIENT BENEFITS Received a holistic approach to fix

previously on-going issues and increase overall appearance of the garage

Provided prioritized multi-year work plan to address the most critical repairs first while meeting yearly project funding

Minimized loss of use by effectively coordinating repair areas

Repaired and new traffic coating reduced future maintenance costs

Upgraded appearance of garage will meet demands of higher class tenants

SCOPE ITEMS Assessment of garage to identify

needed structural repairs and aesthetic updates

Prioritize repairs to be completed over a 5-year duration

Produce opinions of costs for recommended repairs

Create design drawings andspecifications for construction