virginia greiman bigdig
TRANSCRIPT
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 1/42
Virginia A. Greiman
Professor of Megaprojects and Planning
Boston University
Lessons on Risk Managementfrom the Big Dig and other
Complex Megaprojects
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 2/42
Founded in 1986 the Tunnel was Completed in 1994. Thecost was double the forecast and in 1995 Eurotunnelstopped interest payment on its loans resulting in a decadelong process of restructuring. Debt service will not be fully
repaid for decades.
EuroTunnel | Manages the Channel Tunnel between Britain andFrance
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 3/42
“While I am glad that the toll payers are finally able to cross the new eastern spanof the Bay Bridge, it is important that we examine the problems that caused the
construction of the new span to be 10 years late and $5 billion over budget,”Senator DeSaulnier, California Housing and Transportation Committee Chair,October 30, 2013
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 4/42
California $68 Billion High Speed Rail
California high-speed rail will connect the mega-regions of thestate, contribute to economic development and a cleanerenvironment, create jobs and preserve agricultural andprotected lands. By 2029, the system will run from SanFrancisco to the Los Angeles basin in under three hours atspeeds capable of over 200 miles per hour.
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 5/42
Canary Wharf Terminal One of the five £10m tunneling machines
5½ of 26 miles of tunnels now built
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 6/42
• 54 Designs• 132 Construction Packages
• 161 Lane Miles
• 5 Major Interchanges
• Landmark Cable-stay Bridge
• Jacked Tunnels
• Immersed Tubes
• Soil Freezing
• Deep Soil Mixing• 8 miles of Slurry Wall
• Jet Grouting
• Excavation and Parks
Boston’s Big Dig
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 7/42
EIS - Environmental Impact Statement ICE - Interstate Cost Estimate CSU – Cost and Schedule Update
Cost of Boston’s Big Dig
Copyright © 2013 by Virginia A. GreimanCopyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 8/42
Boston’s Big Dig
Copyright © 2013 by Virginia A. GreimanCopyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 9/42
Boston’s Big Dig
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 10/42Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 11/42
Megaprojects and Mega Risk
Understanding Program RiskManagement
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 12/42
Copyright © 2013 by Virginia A. Greiman
Risk Program Structure
Project Company
OrganizationalStructure
(Project)
ContractualStructure
(Risk)
GovernanceStructure
(Finance/Authority)
Risk ManagementExecutive Team
Dedicated Staff
Decision Making
Dedicated BudgetDirect ReportCore ManagementSupport
Key takeaway - Structure Matters
Risk Allocation, Risk
Mitigation, RiskControland Risk Incentives
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 13/42
Seven Cost Centers
• Construction
• Program Management
• Design
• Force Accounts
• Right of Way
• Risk Management
• Geotechnical
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 14/42
Copyright © 2013 by Virginia A. Greiman
Role:• Technology• Design• Construction• Expert Advice
Management
Consultant
Preliminary
DesignerContract
Administ rator
Construction
Manager
Integrated Project
Organization
May include both
public and private
sector employees
Private Entity Public EntityProject Company
State and Federal
Government
Advocate for thePublic
Commitment of
Funding, Services or
Both
Role:• Plan Project• Execute Project• Control Project• Close Project
Role:• Financing• Governing Board• Project Management and
oversight• Interface with Stakeholders
• Regulator
Is your PPP a Partnership or a Risk?
Copyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 15/42
Central Artery/Tunnel Project Risk Management Organization
Project Director
Risk Manager
WC/GL Loss Control
Claims Adjusting
Workers
Compensation& General Liability
Airport Contracts
Claims Adjusting
Airport Contractor
Liability
Builder’s Risk Claims
AdjustingBuilders’ Risk
Claims AdjustingRailroad Surety
Loss Prevention
Claims Adjusting
Professional
Liability
Employer’s Liability
Legal
Technical
Services
ProgramManager
Insurance
Brokerage
/Consultants
Safety & Health
Integrated Team
Risk Finance
OCIP Trust
Audits
Regulatory/
Utility
Claims
Services
Environmental
Consultant
Non-Wrap-Up
Broker/Insurance
Critical
Infrastructure
Risk MgtConsultant DBE Broker LondonBroker
Professional Liability
Claims Adjusting
ContractorSafety Rep.
Safety PartnerManagement
Automobile
LiabilityLondon Airport
Contractors/Excess
Prof. Liability/GL Excess
Insurance
Carriers
Claims Handling
ServicesCore
Managers
Support
Copyright © 2013 by Virginia A. GreimanCopyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 16/42
Copyright © 2013 by Virginia A. Greiman
CA/T Project Insurance Wrap-up
Coverage’s ($609M) (2006 CA/T Project Finance Report)
262
215
48
11
8
5
60
0 100 200 300
Administrative Costs andSafety Mitigation
Railroad Protective Liability
Airport Contractors’ Liability
Professional Liability
Builders’ Risk
General Liability/ExcessLiability
Worker's Compensation
Copyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 17/42
What is Project Success?
• Being on Time and Budget?
• Meeting Goals?
• Achieving Sustainability?
Key takeaway - Know what success means on your project
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 18/42
Scope
TimeCost
Design, Risk, Safety and Quality Decisions
Traditional Iron Triangle
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 19/42
merging: Sustainability of economisocial and institutional benefits
Open space, parks and islands
Re-knitting neighbourhoods and entry points
Expansion of shellfish populationVentilation/air quality
Smart highway system
Economic opportunity/trained workforce/minority/women
business development
Utility corridor
Increased property values
Intermodal
Copyright © 2013 by Virginia A. GreimanCopyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 20/42
The Importance of Context
Context awareness and sensitivity to context on the part of
project decision makers is vital for both the successful
planning, appraisal and delivery of MTPs and suitable
treatment of contextual risks, uncertainties and
complexities.Omega Centre, Mega Projects, 2012
Key takeaway – Environmental factors, values, mega events andpolitical influence/support remains as critical contextual factors over theentire life cycle
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 21/42
The Big Dig’s Risk ManagementMission Zero Accident Philosophy
Operating an integrated world-class Risk Management Program for:
• Engineering and Construction
• Loss Control• Safety and Health
To protect the Commonwealth of Massachusetts, Big Dig contractors,
consultants, workers and the general public against catastrophic loss
by:
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 22/42
Copyright © 2013 by Virginia A. Greiman
Big Dig Safety and HealthPrograms and Practices
Substance Abuseand Prevention
Program
Shared
Responsibility
Continuous
Improvement
PracticesTraining and
BestPractices
Safety Incentive
Program (SHARE) Mitigation
Program
Emergency
Response
Public
Image
Threat
Assessment
Community
Involvement
Program
Abutter
Program
Zero Accident
Tolerance
And many more…
Owner Controlled Insurance
Program
1,344
Environmental
Commitments
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 23/42
Classification of Catastrophic Loss
• Mining Operations
• Ground Freezing
• Deep WaterTunneling
• Funding
• Revenue Risk
• Depression,Recession,Inflation
• Political/RegulatorRisk
• Cave-in, Collapse,Landslide
• Earthquake, Water, Wind
• Fire, Flood, Tidal Waves
• Human Error
• Terrorism
• Pollution
• Chemical Leakage
• Utility Disruption
Human Perils Natural Perils
Technological
Perils
Economic
Perils
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 24/42
The Role of Improvization andIntuition in Risk Management
U.S. Airways Flight 1549, Hudson River, January 15, 2009
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 25/42
How do you know when yourproject is in trouble?
• Costs Rising and Schedule Delays?
• Safety Violations and Lost Time Increases?
• Near Misses and Substantial Rework?
• Exposures Increasing and Claims growing?
• Ethical Problems?
• Critical long-term safety failure?
Key takeaway - All of the above are warning signs your program is at risk
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 26/42
Key Checkpoints for RiskManagement
• Assumptions – Do you review assumptions regularly?
• Perceptions – Are they correct?
• Constraints – Are they realistic?
• Root Causes – Have you identified the root cause of every event or just thesymptoms?
• Cultural Adaptation – Has change occurred?
Key takeaway - Risk assessments should incorporate the above checkpoints
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 27/42
Managing Risk and Change throughIntegration and Collaboration
“ We can’t solve problems by usingthe same kind of thinking we used
when we created them.”
- Albert Einstein
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 28/42
Integration on large and complexprojects: Managing the four Ps
T
The People
The
Programs
The
Processes
The
Project
Methodologies
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 29/42
Partnering
StakeholderParticipation
Claims & Changes
Audi t and
Oversight (OCC)
DisputeResolution
KnowledgeTransfer and
Innovation
Utility
Protection
Safety and
Health
Quality Assurance
RiskManagement
Technology
Advancement
The Programs
Central Artery/Tunnel
Project Integrated
Programs
Copyright © 2013 by Virginia A. GreimanCopyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 30/42
Questions
Are you successfully integrating
• Your People?
• Your Processes?
• Your Programs?
• Your Project Methodologies?
Where can you improve?
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 31/42
Expectancy:
(Quantitative)
• Experts
• Experience
• Tunnel or
building collapse
• Fire in tunnel• traffic
Congestion
• Snowstorm
• Worker injuries
Risk Reality and Impact of Unknowns
• Floods
• Tunnel Leaks• Utility
Disruptions
Known risk UnknownRealized
R
• Flood Gates
Broken?
• Archivelocations?
• Subsurface
Conditions?
Realized:• Actual Losses
Incurred
• Known and
Unknown Risk
• Lessons Learned
• Best Practices
Uncertainty:• Intuitive
• Processes and
Procedures
• Controls
Copyright © 2013 by Virginia A. GreimanCopyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 32/42
0
24
6
8
1012
14
16
18
RatePeople
50004500
4000
3500
3000
2500
2000
1500500
0
Peak Manpower/Year
Actuals per year
National Average
Recordable Rate
Copyright © 2013 by Virginia A. GreimanCopyright © 2013 Megaproject Management by John A. Wiley, Hoboken, NJ
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 33/42
Big Dig’s Worst Disaster
2006 Ted Williams Tunnel Roof CollapseSource: NTSB Report
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 34/42
NTSB Findings1. Lack of understanding and knowledge in the construction community about
creep in adhesive anchoring systems.
2. Prior Incident - Failure of Powers Fasteners, Inc., to determine that the
anchor displacement that was found in the high-occupancy vehicle tunnel in
1999 was a result of anchor creep.
3. Failure of the owner to implement a timely tunnel inspection program that
would likely have revealed the ongoing anchor creep.
Key takeaway - Are we assuming ourcontractors have the requisite knowledge or do we verify experience?
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 35/42
Collapse of I-5 BridgeWashington State
“ The collapse of the I-5 Bridge is a wakeup call
for the entire Nation. This is a really significant
event and we need to learn from it, not just in
Washington but around the country."
Chairman, Debbie Hersman, National Transportation Safety Board
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 36/42
Key Questions in Quality Management
• Are cost and schedule pressures detracting from safety critical designand/or design verification?
• Is there an effective pathway to express your concerns?
• Are safety critical maintenance activities being identified and conveyed toothers by the proper authorities?
• Are inspections implemented in a timely manner?
• Have all stakeholders worked to understand root causes associated with
any unexpected results or off-nominal behaviors in development, testing orintegration?
• Are you assuming engineering accountability or are you delegating?
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 37/42
Challenges for Risk Managementin Megaprojects
• Weak governance
• Low bid contracts
• Schedule driven projects
• Subjectivity in risk analysis/optimism bias
• Lack of knowledge and technical competence
• Strategic misrepresentations
• Wrong perceptions
• Immature risk culture
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 38/42
More challenges…
• Sub-Optimal risk mitigation
• Indecision and ambiguous procedures
• Incomplete root cause analysis
• Inadequate change control and contingency management
• Absence of conflict management
• Weak stakeholder management
• Failure to focus on long term critical safety
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 39/42
Risk Reduction Recommendations
• Establish the highest level of commitment and create a strong riskmanagement culture!
• Develop a zero accident strategy and empower safety managers and teams!
• Integrate risk across projects and share best practices!
• Incentivize risk management from the bottom up!
• Watch out for secondary risks!
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 40/42
What have we learned?
Competency in decision making requires:
• adequate assessment of risk, uncertainty and complexity
• Sensitivity to context
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 41/42
More lessons…..
• Megaprojects require “Open Systems” due to their complex, interrelationshipswith the communities and the citizens it serves.
• Projects should focus on Sustainability and not just the iron triangle!
• Sustainability is multidimensional and extends to economic, social, institutionaland environmental benefits!
Copyright © 2013 by Virginia A. Greiman
7/23/2019 Virginia Greiman BigDig
http://slidepdf.com/reader/full/virginia-greiman-bigdig 42/42
Virginia A. Greiman
Professor of Megaprojects and PlanningBoston University
617-353-6860
Thank You!
Questions???