vacuum system design impact on cryomodulesthis presentation will focus on a few specific vacuum...
TRANSCRIPT
This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.
Michigan State University designs and establishes FRIB as a DOE Office of Science National User Facility in support of the mission of the Office of Nuclear Physics.
Paul GibsonVacuum & Installation Group Leader
Vacuum System Design Impact on Cryomodules
This presentation will focus on a few specific vacuum areas which are potential sources of gas loading on cryomodules• (1) The MEBT connection to the first cryomodule
• (2) The standard Diagnostic Box used adjacent to every cryomodule
• (3) The Charge Stripper system and its impact on adjacent matching cryomodules
• (4 – overall) The Fast Valve layout
Outline
QWR 0.041QWR 0.085
HWR 0.29 HWR 0.53
HWR 0.53
RFQ
ECR
Charge stripper 13
2
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 2
Requirements for vacuum systems connecting to cryomodules are defined» FRIB Driver Linac Vacuum Requirements (T31201-SP-000031)
• Warm section (between cryomodule) ready for beam: From a vacuum requirement point of view, a cryomodule and its adjacent warm section(s) are ready for beam when under cold conditions:» 1. Warm section pressure < 5.E-9 Torr with gate valves open and all cavities conditioned.
» 2. If warm section pressure > 1.E-7 Torr, gate valve should be closed
• Cold-warm transition (between cryomodule and other section) vacuum: Pressure < 1 E-8 Torr
Vacuum calculations have been done with cryomodule gate valves CLOSED• Assure there is no pumping REQUIRED from the cryomodule to meet the
requirements (highly conservative)
“SRF Standard” processing will be applied to all vacuum boxes adjacent to cryomodules (minimize particulates)• Same cleaning processes applied to all vacuum components in the accelerator
Beamline components should be capable of 125 degree C minimum bakeout• Baking done as pre-processing or in situ as needed to meet requirements
Vacuum Requirements for Cryomodules Defined
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 3
Medium Energy Beam Transport (MEBT) couples directly to first cryomodule• Ion Sources are ~ 43 m away
from the first cryomodule
MEBT Requirement: < 1E-8 Torr
Requirements met using:• Conservative outgassing value
for Radio Frequency Quadrupole (RFQ) source term; 5E-8 Torr» RFQ valve open to the MEBT
• Unbaked desorption value
• Cryomodule valve closed
• Pumps sized for MEBT bunchergas loads
MEBT Does Not Impose a Gas Load on the first Cryomodule [1]
~ 7.25 m
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 4
MEBT Does Not Impose a Gas Load on the first Cryomodule [2]
MEBT reaches required vacuum with cryomodule valve closed
RFQ Cryomodule
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 5
Cryomodule requirements dictate ultra-high vacuum handling and “particulate free” methodology (SRF Standard) on installations adjacent to cryomodules
» Cleanroom techniques for assembly / installation
» Pump down / venting using clean pump carts
Diagnostic Box used throughout accelerator» 3 3/8” Conflat flanges and 40 mm I.D. (@ cryomodules - 57)
• SRF Standard applied to these installations
» Similar box in transport regions, 47.5 mm I.D.
Diagnostic Box installations have:» 75 l/s diode ion pump
» Cold cathode gauge
» Metal sealed right angle valve
» Beam Position Monitor (BPM)
» Halo Monitor Ring
.
Diagnostic Box Does Not Impose a Gas Load on the Cryomodules [1]
Diagnostic Port(Shown for reference)
BPM
A mock-up is planned for this
system to study the accessibility
and the installation processes
required
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 6
Diagnostic Box Does Not Impose a Gas Load on the Cryomodules [2]
Diagnostic box reaches required vacuum with cryomodule valves closed
CryomoduleCryomodule
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 7
Lattice drawing layout of Charge Stripper area (upstream section)• “Optical dog-leg” prior to nearest matching cryomodules (4 – 50 magnets)
• Fast valves prior to nearest matching cryomodules
• Diagnostic box with ion pump at exit of charge stripper
• Large crosses allow substantial differential pumping capacity
Charge Stripper Does Not Impose a Gas Load on the Matching Modules [1]
~6.8 m from Charge Stripper Valves to Matching CM Valves
(similar downstream configuration)
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 8
Vacuum model• Matching Cryomodules (CMs) upstream and downstream from Charge Stripper
• Boundary conditions: CM valves closed
Outgassing sources:• Thermal desorption from walls
• Lithium vapor» Liquid lithium in vacuum chamber
» Lithium sticks to walls at room temperature
Requirements:• < 1E-8 Torr near matching CMs
• < 1E-6 Torr near Lithium (Li) stripper
Lithium diffusion model:• Li vapor pressure at the Charge Stripper cylinder set to 1E-5 Torr
» Provided by F. Marti
• Two cases considered:1. Simulation assuming Li sticks to walls outside of charge stripper module (realistic)
2. Simulation assuming Li is non-sticking, relying on pumps only (pessimistic)
Charge Stripper Does Not Impose a Gas Load on the Matching Modules [2]
Model provided by P. Guetschow
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 9
Charge Stripper Does Not Impose a Gas Load on the Matching Modules [3]
Matching CM Matching CM
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 10
Charge Stripper Does Not Impose a Gas Load on the Matching Modules [4]
Requirements
Matching CM Matching CM
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 11
Charge Stripper Does Not Impose a Gas Load on the Matching Modules [5]
Requirements
Matching CM Matching CM
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 12
Fast Valves Protect Cryomodules
8 fast valves located in the accelerator to protect cryomodule vacuum» Baseline design is using VAT model 75 Fast Valves; 40 mm I.D.
• Fast valve can sense and close in < 10 ms (per VAT)
» Fast valve trigger will pull the fast MPS which inhibits the beam in ~ 35 us
» Multiple valves will trigger based upon a single sensor reading• Sensors in folding segments 1 and 2 will trip both entry and exit fast valves
• Sensors upstream and downstream of the charge stripper will trip both fast valves
• A fast valve trigger will close isolation valves on cryomodules in the vicinity as well as nearby beamline isolation valves via the control system
• Sensor threshold is programmable and for FRIB is planned to be 1x10-7 Torr
• Fast valve trigger is planned to be disabled via the control system when beam is off to avoid inadvertent trips
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 13
Calculations show that cryomodules do not experience gas loads from the warm / transport sections
Fast valve systems are located throughout the accelerator to protect cryomodules
Summary
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 14
Backup
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 15
Front End Vacuum Calculation Results [1]
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 16
Split into 3 vacuum models:• Pre-RFQ = Extraction Region (ER) + CSS + LEBT
• RFQ
• MEBT (from RFQ exit to first cryomodule in LS1)
RFQ
VENUS
Source
ARTEMIS
SourceCSS
LEBT
MEBT
Front End Vacuum Calculation Results [2]
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 17
Vacuum covers the entire FRIB facility but this talk focuses on ASD and vacuum in relation to cryomodule interfaces
Accelerator Vacuum Layout and Preliminary Design Complete [1]
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 18
Accelerator Vacuum Layout and Preliminary Design Complete [2]
Lattice Model
Requirements
Vacuum Model
Folding Segment 2• SC dipoles
• RT optical elements
• 1 matching module
• 1 beam dump
Molflow+ Results
Establish
Basis of
Estimate
(BOE)
Similar models provided for
vacuum calculations by:
B. Durickovic – FRIB
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 19
ASDRequirements specified
• FRIB Driver Linac Vacuum Requirements (T31201-SP-000031)» Prepared by the FRIB Accelerator Physics Group,
» Includes all systems from ion sources to the gate valve prior to the ESD target chamber
• Requirements basis• Vacuum estimates for the FRIB driver linac (T31201-TD-000157)
» Prepared by F. Marti and Y. Zhang
• Layout• Expanded Lattice File
(T31201-CM-00022)
• Design• ASD Vacuum System Design
(T31210-TD-000240)
Vacuum Requirements Defined
*Table from FRIB Driver Linac Vacuum Requirements
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 20
Cold cathode – Inverted magnetron vacuum gauge• 1x10-11 torr capability
• 2 ¾” CF connection
• At least 125o C bakeout with magnets and connectors attached• Depending upon mfg
• MKS 422 and Agilent IMG-300
Metal sealed right angle valve• UHV metal to metal seal closing, leak rate < 2x10-10 cc/sec
• Bakeable to > 250o C• Depending upon mfg
• 2 ¾” CF connection
• MDC, Agilent, VAT, Nor-Cal
Extra 2 ¾” CF port for fast valve sensor or additional gauge• Convection enhanced pirani considered
» Not installed since available on pump cart during pumpdown and qualification
Diagnostic Box Design Complete [1]
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 21
65 l/s diode ion pump initially selected• 75 l/s for diode – 65 l/s for triode
• Rated 50,000 hours at 1x10-6 torr• Equals ~ 5,000,000 hours at 1x10-8 FRIB
operating pressure > 570 yrs
• Lifetime is proportional to pump treatment
• Residuals are H2, CO, and N2
• 6” CF connection; SHV connector
• Mfgs: Gamma, Agilent, Duniway
Diagnostic Box Design Complete [2]
For Agilent
VacIon Plus
75 Diode
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 22
The plot is for an “average section” of beam transport line ~ 5.5 m long and 47.5 mm I.D. with diagnostic boxes at each end• The average pressure changes minimally with pumping speed
• Indicates that the system is heavily conductance limited
Ion Pump Pumping Speed vs. Average Pressure Analyzed
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 23
Accelerator System• Protect the superconducting accelerating and matching modules from a
beam induced vacuum event (failure)» Worst case assumption is a sonic pressure wave; 340 m/s
» Fast valve can sense and close in < 10 ms (per VAT)
» Therefore sensors must be place at least 3.4 m from fast valve or as far as possible based upon layout• This is accomplished in most areas
» Multiple valves will trigger based upon a single sensor reading• Additional sensor in the middle of the folding segments will trip both entry and exit fast valve
• Sensors upstream and downstream of stripper area will trip both fast valves to isolate system
» A fast valve trip will pull the fast MPS which inhibits the beam in < 35 us
» A fast valve trip will close slow valves on cryomodules in the vicinity as well as any nearby beamline isolation valves through the controls system
» Sensor threshold is programmable and for FRIB is 1x10-7 torr
» Fast valve trigger is disabled via the control system when beam is off
Fast Valve Requirements
P. Gibson, March 2014 Workshop on Cryomodule Maintenance - 15, Slide 24