using benefit-cost analysis to understand the costs and ...p3-value demonstrates value for money...

28
Using Benefit-Cost Analysis to Understand the Costs and Benefits of Public-Private Partnership Projects Presentation at the International Transportation Economic Development Conference April 9-11, 2014 Dallas, Texas Patrick DeCorla-Souza, P3 Program Manager Federal Highway Adminstration

Upload: others

Post on 23-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

Using Benefit-Cost Analysis to Understand the Costs and Benefits of

Public-Private Partnership Projects

Presentation at the International Transportation Economic Development Conference

April 9-11, 2014 Dallas, Texas

Patrick DeCorla-Souza, P3 Program Manager

Federal Highway Adminstration

Page 2: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

2

Outline

Study background Findings from literature review Proposed BCA methodology Example application of methodology Next steps

Page 3: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

3

Study Background

FHWA has developed a P3 evaluation toolkit, including an analytical tool – P3-VALUE

P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s balance sheet

FHWA is developing a Benefit-Cost Analysis (BCA) approach to address: • Non-financial impacts (e.g., user benefits) • Take a broader perspective

Page 4: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

4

Findings from Literature Review

A true BCA approach has not been used by public agencies to evaluate P3s

Key impacts of P3 to be assessed relate to: • Cost efficiencies • Risk transfer • Earlier delivery • Service quality

Page 5: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

5

Proposed BCA Framework

1.Define Procurement Alternatives

2. Identify and Value Risks

3. Estimate Financial Costs

4. Estimate Benefits and Net Benefits

5. Evaluate Impact of Risks/ Uncertainty on Net Benefits

Ass

umpt

ions

Preferred Alternative

Page 6: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

6

Illustrative Example

Existing 10-mile 4-lane highway segment Add one lane per direction Toll all lanes 50-year analysis period

We will now go through the five BCA steps using the example

Page 7: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

Step 1

Define Alternatives

Page 8: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

8

1a. Define Procurement Alternatives

Conventional Design-Bid-Build, with

O&M by public agency

Toll revenues (and revenue risk) retained by public agency

P3 Design-Build-Finance-

Operate-Maintain Toll revenues retained by

P3 concession, with transfer of revenue risk to the concessionaire

Page 9: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

9

1b. Define Costs and Benefits of P3

Impact Category

Public Sector and User Cost Impact Impacts on Benefits Decreased Increased

Cost Some costs decrease because of greater private-sector innovation and efficiency.

Some costs increase because of greater transaction costs and additional skill and effort required to reach an agreement – not addressed.

Reduced social cost of project

Risk Transfer Risk costs reduced because of better risk management.

Public sector risk could increase if contract terms are not adequately designed – not addressed.

Expected cost of risks reduced because of risk transfers to concessionaire.

Page 10: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

10

1b. Costs and Benefits of P3 (contd.)

Impact Category

Public Sector and User Cost Impact Impact on Benefits Decreased Increased

Schedule Costs reduced due to shorter construction duration because of better schedule management and earlier financing.

Earlier delivery shortens the time in initiating benefits from service.

Service Quality User costs reduced because of better pavement quality and better tolling and active traffic management service.

Benefits greater because of improved service.

Page 11: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

Step 2

Identify and Value Risks

Page 12: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

Identify and Value Risks for Each Alternative

Risk Type Design/ Const. Phase

Operations Phase

“Pure” risks (i.e. event risks)

Estimate contingency

Estimate contingency

Parameter uncertainties

Estimate allowance

Estimate allowance

Systematic, long-term performance and project coordination risks

Estimate virtual risk premium

Page 13: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

Step 3

Estimate Costs

Page 14: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

14

3a. Real Risk-Adjusted Costs for Base Case

Total cost = $699 M (real dollars)

Page 15: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

15

3b. Real Risk-Adjusted Costs for P3

Total cost = $629 M (real dollars)

Page 16: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

16

3c. PV of Risk-Adjusted Costs for Base Case

Total cost = $334 M (discounted dollars)

Page 17: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

17

3d. PV of Risk-Adjusted Costs for P3

Total cost = $356 M (discounted dollars)

Page 18: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

Step 4

Estimate Benefits and Net Benefits

Page 19: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

19

4a. Real Base Case Benefits

Total benefits = $1,091 M (real dollars, not adjusted for risk)

Page 20: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

20

4b. Real P3 Benefits

Total benefits = $1,337 M (real dollars, not adjusted for risk or earlier economic development)

Page 21: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

21

4c. PV of Base Case Benefits

Total benefits = $404 M (real dollars, not adjusted for risk)

Page 22: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

22

4d. PV of P3 Benefits

Total benefits = $553 M (real dollars, not adjusted for risk or earlier economic development)

Page 23: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

23

4e. NPV of Difference Between Options

PV of Net Benefits of P3 option = $126 M (not adjusted for risk)

Base Case (million $)

P3 Option (million $)

Difference (million $)

Real Costs $699 $629 Benefits $1,091 $1,337 Net Benefits $392 $708 $416

Present Value Costs $334 $356 Benefits $404 $553 Net Benefits $70 $197 $126

Page 24: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

Step 5

Evaluate Impacts of Risk on Estimated Net Benefits

Page 25: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

5. Identify and Assess Impact of Risks on Benefits for Each Alternative

Risk Type Design/ Const. Phase

Operations Phase

“Pure” risks (i.e. event risks)

Sensitivity of NPV difference

to delivery schedule risk

Sensitivity of NPV difference

to long-term performance

risk

Parameter uncertainties N.A.

Sensitivity of NPV difference to parameter assumptions

Page 26: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

26

Example of Sensitivity Analysis

Fuel price assumption has very small impact on difference in NPV of net benefits

Page 27: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

27

Next Steps

Refine BCA methodology in response to review comments

Develop primer on P3 evaluation using BCA Develop Guidebook for practitioners Enhance P3-VALUE tool to include a BCA option

Page 28: Using Benefit-Cost Analysis to Understand the Costs and ...P3-VALUE demonstrates Value for Money analysis • Evaluates only financial impacts • From perspective of procuring agency’s

28

Contact Information

Patrick DeCorla-Souza P3 Program Manager Office of Innovative Program Delivery Federal Highway Administration (202) 366-4076 [email protected]

P3 Website: http://www.fhwa.dot.gov/ipd/p3/