use of pert and cpm model in projects

Upload: sheeba-shankari

Post on 07-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    1/26

    USE OF PERT AND CPM MODEL IN

    PROJECTS

    Presented by,

    Sathya.S (10UTB18), Sheeba Shankari.M.C (10UTB19)

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    2/26

    CONTENT OF THE PRESENTATION Introduction to Network techniques (PERT and CPM Model in

    Projects)

    Projects and its characteristics that make them amenable to be analyzed

    by PERT and CPM

    Development of Project Network

    Time estimation

    Determination of Critical Path

    Scheduling of the activities when resources are limited

    Crashing of the Project

    Network Cost controlling

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    3/26

    INTRODUCTION TO NETWORK TECHNIQUES

    Focus to Implement the project

    Completion of numerous activities - Resources

    Purpose of network technique

    Two network techniques:

    PERT Model

    - Planning and Scheduling

    - Risky and Uncertain Projects

    - Probabilistic

    CPM Model

    - Scheduling and Cost controlling in industrial projects

    - Risk free Projects

    - Deterministic

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    4/26

    PROJECTS THAT ARE AMENABLE TO

    ANALYSIS BY PERT AND CPM

    Launching a spaceship

    Research and Development Program

    Construction of a plant

    Building of a river valley project

    Training of a manpower

    Starting a new venture

    Characteristics of the above projects that make them amenable to

    analysis by PERT and CPM:

    - Project broke down into set of jobs

    - Jobs must be performed into certain sequence

    - Jobs can be start or stop in an independent manner

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    5/26

    TERMINOLOGY USED IN NETWORKS

    Activity

    Event

    Network

    Path

    Critical

    Forward method

    Backward method

    2

    43

    1 ReceiveGuests

    TakeDinner

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    6/26

    RULES FOR NETWORK CONNECTION

    Each activity should have a preceding and

    a succeeding event.

    Denoted numerically by a pair of

    preceding and succeeding event.

    Each event should have a unique number.

    No loops in the project network

    Not more than one activity can have the

    same preceding and succeeding event.

    1

    2 3

    1 2

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    7/26

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    8/26

    DETERMINATION OF CRITICAL PATH

    Calculate the Earliest occurrence time (EOT) for each event- Earliest Starting time

    EST(i, j) = EOT(i)

    - Earliest Finishing time

    EFT(i, j) = EOT(i) + d(i, j)

    Calculate the Latest occurrence time (LOT) for each event

    - Latest Starting time

    LST(i, j) = LOT(j) - d(i, j)

    - Latest Finishing time

    LFT(i, j) = LOT(j)

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    9/26

    CONT.

    Calculate the Slack for each event

    Slack = LOT - EOT

    Obtain the Critical and Slack paths

    Compute the Activity floats

    Total float (i, j) = LOT(j) - EOT(i) - d(i, j)

    Free Float (i, j) = EOT(j) - EOT(i) - d(i, j)

    Independent Float (i, j) = EOT(j) - LOT(i) - d(i, j)

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    10/26

    SCHEDULING WHEN RESOURCES ARE

    LIMITED

    Critical activities Vs Non critical activitiesTwo Schedules:

    Early Start Schedule

    All Events occur at their earliest time (EST & EFT)

    May have Time lags in completion of certain activities

    All activities emanating from an event begin at the same time

    Late Start Schedule

    All Events occur at their Latest time (LST & LFT)

    Certain activities may start after a time lag

    All activities leading to an event complete at the same time

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    11/26

    Problem1

    Scheduling to match availability of Manpower

    Resource Constraint - only 12 men available for the project

    1

    4

    53

    2

    2 days (b) 1 day (e)

    2 days (c)

    2

    8

    6

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    12/26

    Event EOT LOT Activity Duration EST EFT

    1 0 0 a(1-2) 10 0 1

    2 1 3 b(1-3) 2 0 2

    3 2 2 c (1-5) 8 0 2

    4 5 5 d(2-5) 4 1 3

    5 5 5 e(3-5) 6 2 3

    f(3-4) 5 2 5

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    13/26

    Problem- 2

    Scheduling to match the release of funds

    Total Cost = 15,600,000

    Resource Constraint:

    Release of funds 1st year - 6,900,000

    2nd year - 6,800,000

    3rd year - 1,900,000

    Activity Duration in

    months

    Cost per Month Cost Rs.

    (1-2) 13 200,000 2,600,000

    (1-3) 12 500,000 6,000,000

    (2-4) 2 1,000,000 2,000,000

    (3-4) 8 250,000 2,000,000

    (2-5) 15 100,000 1,500.000

    (4-5) 2 750,000 1,500,000

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    14/26

    Release of funds:

    1st year - 6,900,000 2nd year - 6,800,000 3rd year - 1,900,000

    Activity( i, j )

    Duration(Months)

    Early StartTime

    EarlyFinishTime

    LatestStart Time

    LatestFinishTime

    (1 - 2) 13 0 13 0 13

    (1 - 3) 12 0 12 6 18

    (2 - 4) 2 13 15 24 26

    (3 - 4) 8 12 20 18 26

    (2 - 5) 15 13 28 13 28

    (4 - 5) 2 20 22 26 28

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    15/26

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    16/26

    CONT..

    Variance = 2

    Variance = Sum of variances of activity durations on critical

    path.

    Simple Example:

    Variance for X is 2 = ((5-3)/6)2 = 0.11 Variance for X is 2 = ((7-1)/6)2 = 1

    Y is less certain than X, so accept the contract with X

    Optimistictime(weeks)

    Most likelytime

    Pessimistictime

    Duration

    Accountant X 3 4 5 4

    Accountant Y 1 4 7 4

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    17/26

    CONT Probability of completion by a specified date:

    Z Probability distribution of completing a project onthe specified date job

    D Specified date to complete a job

    T Mean Standard deviation for critical path duration

    Simple Problem:

    If the project has a critical duration of 28 weeks and its standarddeviation is 3.07, then what is the probability of completing a project in 20days.

    Probability of completing project in 20 days is Z=(20-28)/3.07

    Z = -2.6

    From cumulative probability distribution table Z(-2.6) = 0.005

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    18/26

    CPM MODEL

    Focus of CPM analysis is on variations in activity times as a result of changes in

    resource assignments.

    Main thrust of CPM is on time-cost relationships

    CPM find the project schedule which have minimum total cost.

    Assumptions in CPM analysis:

    Cost associated with the project is of two components, Direct costs and

    Indirect costs.

    Crashing Project can be expedited which involves employing more

    resources.

    Time and Direct Cost of the project are inversely proportional

    Indirect cost and time are directly proportional

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    19/26

    COST - TIME LINE

    Activity time

    Crashing activity

    Crashtime

    Crash

    cost

    Normal Activity

    Normal

    time

    Normal

    cost

    Slope = crash cost per unit time

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    20/26

    INDIRECT COSTS

    Ind

    irectCostof

    Project

    Project Duration

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    21/26

    PROCEDURE

    Obtain the critical path in the normal network. Determine the

    project duration and direct cost.

    Examine the cost-time slope of activities on the critical path

    obtained and crash the activity which has the least slope.

    Identify the new critical path after crashing, now determine the

    project duration and cost.

    Repeat steps 2 and 3 till activities on the critical path are

    crashed.

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    22/26

    PROBLEM ON CRASHING

    Indirect cost Rs 2000 per week

    ActivityNormal

    timeCrash time

    NormalCost

    CrashCost

    Cost toexpediteper week

    1-2 8 4 3000 6000 750

    1-3 5 3 4000 8000 2000

    2-4 9 6 4000 5500 500

    3-5 7 5 2000 3200 600

    2-5 5 1 8000 12000 1000

    4-6 3 2 1/2 10000 11200 24005-6 6 2 4000 6800 700

    6-7 10 7 6000 8700 900

    5-7 9 5 4200 9000 1200

    45200 70400

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    23/26

    PROJECT DURATION AND TOTAL COST

    Exhibit Activities CrashedProject

    durationin weeks

    Totaldirectcosts

    TotalIndirectcosts

    Total Cost

    A None 30 45,200 60,000 1,05,200

    B (2-4) 29 46,700 58,000 1,04,700

    C (2-4) and (5-6) 27 49,500 54,000 1,03,500

    D (1-2),(2-4) and (5-6) 24 52,500 48,000 1,00,500

    E

    (1-2),(2-4),(5-6) and

    (6-7) 21 55,200 42,000 97,200

    F(1-2),(2-4),(3-5),(5-6)and (6-7)

    20 56,400 40,000 96,400

    G(1-2),(2-4),(3-5),(5-6), (4-6) and (6-7)

    19 1/2 57,600 39,000 96,600

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    24/26

    COST CONTROLLING

    Basic Principle of NCS:

    Costs are planned, measured, analyzed and controlled in terms of

    project activities.

    Network Cost System

    Cost Projection

    Analysis and Control of costs

    Monitoring and Control of cost:

    Costs incurred to date

    Budgeted Costs to date

    Value of work done to date

    Cost over-run(under-run) to date

    Time over-run(under-run) to date

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    25/26

    EXAMPLES

    TIME & COST, BUDGET & ACTUAL

    EG 1:

    If a budgeted cost for the particular activity is Rs.1,000

    and it should be completed in 1day. The actual cost incurred is

    Rs.800 for completing the 2/3rd of work in 1day. What is the

    cost variance?

  • 8/4/2019 Use of Pert and Cpm Model in Projects

    26/26

    Thank You