use of pert and cpm model in projects
TRANSCRIPT
-
8/4/2019 Use of Pert and Cpm Model in Projects
1/26
USE OF PERT AND CPM MODEL IN
PROJECTS
Presented by,
Sathya.S (10UTB18), Sheeba Shankari.M.C (10UTB19)
-
8/4/2019 Use of Pert and Cpm Model in Projects
2/26
CONTENT OF THE PRESENTATION Introduction to Network techniques (PERT and CPM Model in
Projects)
Projects and its characteristics that make them amenable to be analyzed
by PERT and CPM
Development of Project Network
Time estimation
Determination of Critical Path
Scheduling of the activities when resources are limited
Crashing of the Project
Network Cost controlling
-
8/4/2019 Use of Pert and Cpm Model in Projects
3/26
INTRODUCTION TO NETWORK TECHNIQUES
Focus to Implement the project
Completion of numerous activities - Resources
Purpose of network technique
Two network techniques:
PERT Model
- Planning and Scheduling
- Risky and Uncertain Projects
- Probabilistic
CPM Model
- Scheduling and Cost controlling in industrial projects
- Risk free Projects
- Deterministic
-
8/4/2019 Use of Pert and Cpm Model in Projects
4/26
PROJECTS THAT ARE AMENABLE TO
ANALYSIS BY PERT AND CPM
Launching a spaceship
Research and Development Program
Construction of a plant
Building of a river valley project
Training of a manpower
Starting a new venture
Characteristics of the above projects that make them amenable to
analysis by PERT and CPM:
- Project broke down into set of jobs
- Jobs must be performed into certain sequence
- Jobs can be start or stop in an independent manner
-
8/4/2019 Use of Pert and Cpm Model in Projects
5/26
TERMINOLOGY USED IN NETWORKS
Activity
Event
Network
Path
Critical
Forward method
Backward method
2
43
1 ReceiveGuests
TakeDinner
-
8/4/2019 Use of Pert and Cpm Model in Projects
6/26
RULES FOR NETWORK CONNECTION
Each activity should have a preceding and
a succeeding event.
Denoted numerically by a pair of
preceding and succeeding event.
Each event should have a unique number.
No loops in the project network
Not more than one activity can have the
same preceding and succeeding event.
1
2 3
1 2
-
8/4/2019 Use of Pert and Cpm Model in Projects
7/26
-
8/4/2019 Use of Pert and Cpm Model in Projects
8/26
DETERMINATION OF CRITICAL PATH
Calculate the Earliest occurrence time (EOT) for each event- Earliest Starting time
EST(i, j) = EOT(i)
- Earliest Finishing time
EFT(i, j) = EOT(i) + d(i, j)
Calculate the Latest occurrence time (LOT) for each event
- Latest Starting time
LST(i, j) = LOT(j) - d(i, j)
- Latest Finishing time
LFT(i, j) = LOT(j)
-
8/4/2019 Use of Pert and Cpm Model in Projects
9/26
CONT.
Calculate the Slack for each event
Slack = LOT - EOT
Obtain the Critical and Slack paths
Compute the Activity floats
Total float (i, j) = LOT(j) - EOT(i) - d(i, j)
Free Float (i, j) = EOT(j) - EOT(i) - d(i, j)
Independent Float (i, j) = EOT(j) - LOT(i) - d(i, j)
-
8/4/2019 Use of Pert and Cpm Model in Projects
10/26
SCHEDULING WHEN RESOURCES ARE
LIMITED
Critical activities Vs Non critical activitiesTwo Schedules:
Early Start Schedule
All Events occur at their earliest time (EST & EFT)
May have Time lags in completion of certain activities
All activities emanating from an event begin at the same time
Late Start Schedule
All Events occur at their Latest time (LST & LFT)
Certain activities may start after a time lag
All activities leading to an event complete at the same time
-
8/4/2019 Use of Pert and Cpm Model in Projects
11/26
Problem1
Scheduling to match availability of Manpower
Resource Constraint - only 12 men available for the project
1
4
53
2
2 days (b) 1 day (e)
2 days (c)
2
8
6
-
8/4/2019 Use of Pert and Cpm Model in Projects
12/26
Event EOT LOT Activity Duration EST EFT
1 0 0 a(1-2) 10 0 1
2 1 3 b(1-3) 2 0 2
3 2 2 c (1-5) 8 0 2
4 5 5 d(2-5) 4 1 3
5 5 5 e(3-5) 6 2 3
f(3-4) 5 2 5
-
8/4/2019 Use of Pert and Cpm Model in Projects
13/26
Problem- 2
Scheduling to match the release of funds
Total Cost = 15,600,000
Resource Constraint:
Release of funds 1st year - 6,900,000
2nd year - 6,800,000
3rd year - 1,900,000
Activity Duration in
months
Cost per Month Cost Rs.
(1-2) 13 200,000 2,600,000
(1-3) 12 500,000 6,000,000
(2-4) 2 1,000,000 2,000,000
(3-4) 8 250,000 2,000,000
(2-5) 15 100,000 1,500.000
(4-5) 2 750,000 1,500,000
-
8/4/2019 Use of Pert and Cpm Model in Projects
14/26
Release of funds:
1st year - 6,900,000 2nd year - 6,800,000 3rd year - 1,900,000
Activity( i, j )
Duration(Months)
Early StartTime
EarlyFinishTime
LatestStart Time
LatestFinishTime
(1 - 2) 13 0 13 0 13
(1 - 3) 12 0 12 6 18
(2 - 4) 2 13 15 24 26
(3 - 4) 8 12 20 18 26
(2 - 5) 15 13 28 13 28
(4 - 5) 2 20 22 26 28
-
8/4/2019 Use of Pert and Cpm Model in Projects
15/26
-
8/4/2019 Use of Pert and Cpm Model in Projects
16/26
CONT..
Variance = 2
Variance = Sum of variances of activity durations on critical
path.
Simple Example:
Variance for X is 2 = ((5-3)/6)2 = 0.11 Variance for X is 2 = ((7-1)/6)2 = 1
Y is less certain than X, so accept the contract with X
Optimistictime(weeks)
Most likelytime
Pessimistictime
Duration
Accountant X 3 4 5 4
Accountant Y 1 4 7 4
-
8/4/2019 Use of Pert and Cpm Model in Projects
17/26
CONT Probability of completion by a specified date:
Z Probability distribution of completing a project onthe specified date job
D Specified date to complete a job
T Mean Standard deviation for critical path duration
Simple Problem:
If the project has a critical duration of 28 weeks and its standarddeviation is 3.07, then what is the probability of completing a project in 20days.
Probability of completing project in 20 days is Z=(20-28)/3.07
Z = -2.6
From cumulative probability distribution table Z(-2.6) = 0.005
-
8/4/2019 Use of Pert and Cpm Model in Projects
18/26
CPM MODEL
Focus of CPM analysis is on variations in activity times as a result of changes in
resource assignments.
Main thrust of CPM is on time-cost relationships
CPM find the project schedule which have minimum total cost.
Assumptions in CPM analysis:
Cost associated with the project is of two components, Direct costs and
Indirect costs.
Crashing Project can be expedited which involves employing more
resources.
Time and Direct Cost of the project are inversely proportional
Indirect cost and time are directly proportional
-
8/4/2019 Use of Pert and Cpm Model in Projects
19/26
COST - TIME LINE
Activity time
Crashing activity
Crashtime
Crash
cost
Normal Activity
Normal
time
Normal
cost
Slope = crash cost per unit time
-
8/4/2019 Use of Pert and Cpm Model in Projects
20/26
INDIRECT COSTS
Ind
irectCostof
Project
Project Duration
-
8/4/2019 Use of Pert and Cpm Model in Projects
21/26
PROCEDURE
Obtain the critical path in the normal network. Determine the
project duration and direct cost.
Examine the cost-time slope of activities on the critical path
obtained and crash the activity which has the least slope.
Identify the new critical path after crashing, now determine the
project duration and cost.
Repeat steps 2 and 3 till activities on the critical path are
crashed.
-
8/4/2019 Use of Pert and Cpm Model in Projects
22/26
PROBLEM ON CRASHING
Indirect cost Rs 2000 per week
ActivityNormal
timeCrash time
NormalCost
CrashCost
Cost toexpediteper week
1-2 8 4 3000 6000 750
1-3 5 3 4000 8000 2000
2-4 9 6 4000 5500 500
3-5 7 5 2000 3200 600
2-5 5 1 8000 12000 1000
4-6 3 2 1/2 10000 11200 24005-6 6 2 4000 6800 700
6-7 10 7 6000 8700 900
5-7 9 5 4200 9000 1200
45200 70400
-
8/4/2019 Use of Pert and Cpm Model in Projects
23/26
PROJECT DURATION AND TOTAL COST
Exhibit Activities CrashedProject
durationin weeks
Totaldirectcosts
TotalIndirectcosts
Total Cost
A None 30 45,200 60,000 1,05,200
B (2-4) 29 46,700 58,000 1,04,700
C (2-4) and (5-6) 27 49,500 54,000 1,03,500
D (1-2),(2-4) and (5-6) 24 52,500 48,000 1,00,500
E
(1-2),(2-4),(5-6) and
(6-7) 21 55,200 42,000 97,200
F(1-2),(2-4),(3-5),(5-6)and (6-7)
20 56,400 40,000 96,400
G(1-2),(2-4),(3-5),(5-6), (4-6) and (6-7)
19 1/2 57,600 39,000 96,600
-
8/4/2019 Use of Pert and Cpm Model in Projects
24/26
COST CONTROLLING
Basic Principle of NCS:
Costs are planned, measured, analyzed and controlled in terms of
project activities.
Network Cost System
Cost Projection
Analysis and Control of costs
Monitoring and Control of cost:
Costs incurred to date
Budgeted Costs to date
Value of work done to date
Cost over-run(under-run) to date
Time over-run(under-run) to date
-
8/4/2019 Use of Pert and Cpm Model in Projects
25/26
EXAMPLES
TIME & COST, BUDGET & ACTUAL
EG 1:
If a budgeted cost for the particular activity is Rs.1,000
and it should be completed in 1day. The actual cost incurred is
Rs.800 for completing the 2/3rd of work in 1day. What is the
cost variance?
-
8/4/2019 Use of Pert and Cpm Model in Projects
26/26
Thank You