USC Installation. Commissioning Task Force 1st Run Meeting, June 3rd, 2004. USC Layout /1. Shaft Gas room Laser room Counting rooms (2 floors) Service area (2 floors) TS/CV zone. USC Layout /2. USC Layout /3. Planning overview. SCX - Jan 05 to July 05 SDX - June 04 to Dec 05 - PowerPoint PPT PresentationTRANSCRIPT
June 2004 Andrea Gaddi, PH-CMI
USC InstallationUSC Installation
Commissioning Task Force
1st Run Meeting, June 3rd, 2004
June 2004 Andrea Gaddi, PH-CMI
USC Layout /1USC Layout /1
ShaftGas roomLaser roomCounting rooms (2 floors)Service area (2 floors)TS/CV zone
June 2004 Andrea Gaddi, PH-CMI
USC Layout /2USC Layout /2
June 2004 Andrea Gaddi, PH-CMI
USC Layout /3USC Layout /3
June 2004 Andrea Gaddi, PH-CMI
Planning overviewPlanning overview
SCX - Jan 05 to July 05SDX - June 04 to Dec 05USC - June 04 to Feb 06UXC - Nov 04 to April 07
2004 2005 2006 2007
SCX
SDX
USC
UXC
June 2004 Andrea Gaddi, PH-CMI
USC planningUSC planning
Planning of activities related to USC and PM shaft
(from today to Magnet test)
June 2004 Andrea Gaddi, PH-CMI
First activities in PM shaft and US cavern:Concrete blocks into elevator basementClosing of shaft basement Temporary ventilationTemporary electricityProtection plug on top of shaft
4 weeks - from June 04
June 2004 Andrea Gaddi, PH-CMI
First components to be lowered trough PM shaft to US cavern:(lowering done during night time)
Auxiliary mobile crane10-t gantry crane for USC service areaLHe transfer linesUSC metallic structures (*)
10 weeks - from July 04
June 2004 Andrea Gaddi, PH-CMI
PM shaftMaterial lowering (night time)
Ventilation units and ductsTS/EL transformersCoil bus-barsVacuum transfer line rails
Activities (daytime)Permanent ventilation ductsLift modules and machinery (*)Metallic staircase modules (*)
10 weeks “window” - from Sept 04
June 2004 Andrea Gaddi, PH-CMI
US cavernUSC Shaft area
Elevator installation (*)Coil discharge linesCooling and fire fighting pipesGas piping
55 weeks (14 weeks idle) - from Oct 04
June 2004 Andrea Gaddi, PH-CMI
US cavernUSC Service Area
10-t crane assemblyMetallic structures (*)Coil bus-bars into US - UX tunnel/1
Vacuum transfer line rails into US - UX tunnel/2LHe transfer line into US - UX tunnel/2Electric safe roomVentilation ducts and units (*)Cooling and gas piping (*)Cable trays (*)TS/EL switchboards
55 weeks - from July 04
June 2004 Andrea Gaddi, PH-CMI
US cavernUSC Control area
Metallic structures (*)Ventilation ducts (*)Cable trays (*)Cooling pipes (*)
Ready for racks (March 05)Rack installationPower distribution to racks
Ready for crates (June 05)Crates installation
55 weeks - from July 04
June 2004 Andrea Gaddi, PH-CMI
ConclusionsConclusions
Components to be installed in USC Service area andrelated activities are well defined. For the time being,nothing has showed to be critical, unless a minor probleminvolving the LHe transfer line that needs some worksin UXC to be completed before being put in place.
Racks and related services to be installed in USC countingrooms are clearly on the critical path. Many sub-system haveto be integrated (cooling pipes, ventilation ducts, powerlines, cable trays) into a relatively confined space. It is reallyimportant to have the final layout of racks and cable routingvalidated asap.
Some services from surface wouldn’t be available before Sept 05