![Page 1: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/1.jpg)
US20/O.B. Riley – Cook Roundabout Alternative 1
![Page 2: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/2.jpg)
US20/O.B. Riley – Cook Roundabout Alternative 1
![Page 3: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/3.jpg)
US20/O.B. Riley – Cook Roundabout Alternative 1
![Page 4: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/4.jpg)
US20/O.B. Riley – Cook Roundabout Alternative 2
![Page 5: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/5.jpg)
US20/O.B. Riley – Cook Roundabout Alternative 2
![Page 6: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/6.jpg)
US20/O.B. Riley – Cook Roundabout Alternative 2
![Page 7: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/7.jpg)
US20/O.B. Riley-Cook Half Diamond Single Point Interchange Hybrid
![Page 8: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/8.jpg)
US20/O.B. Riley-Cook Half Diamond Single Point Interchange Hybrid
![Page 9: US20/O.B. Riley – Cook Roundabout Alternative 1 Documents/Tumalo Concepts Map.pdfRiley-Cook for lowering roadways Possible ROW needed for conversions at US20/8th 8th St. ROW needs/retaining](https://reader033.vdocuments.us/reader033/viewer/2022042018/5e760c966d2c5a77575fdbe5/html5/thumbnails/9.jpg)
Preliminary ConstructionCost Estimates
Alternative Construction Cost Only
Right-of-Way Costs
Total Costs
Roundabout $9,600,000 $1,000,000 $10,600,000
Ped/Bike Undercrossing $2,600,000 TBD TBD
SPI Hybrid (Raise US20 & Partially lower O.B. Riley-
Cook$22,800,000 $6,000,000 $28,800,000