urvey at optimal quality whether it is road or river,...

25

Upload: others

Post on 15-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

~ 1 ~

Com

pa

ny P

rofile

urvey at optimal quality whether it is Road or river, Rail or

Canal, Mines or Plant we are ahead of others. Deserve the

best position in view of employees and client not by paper

but by successful completion of commitments to client. Drive

innovative processes and systems, aided by technology to provide

overall clarity in both survey systems and construction Systems

including maintenance of plant.

S

OOUURR VVIISSIIOONN

~ 2 ~

Com

pa

ny P

rofile

recision Survey Consultancy a journey to find the new horizon in the

system of survey since 2004. A few employees and with a few

instruments. After 4 years it is going to become a milestone in the

way of survey, whether it is the Road or River, Rail or Canal, Mines or Plants

with the 60 family members and utilization of modern technologies. As the

Quality of work is mature day by day, affects the growing list of prideful

clients.

Our group is committed to delivering specialized services, intelligent

solutions and logical approaches to effectively assist employer /client in the

areas of operational compliance and services reliability as well as support the

optimal use of investment across their project.

The combined team consists of building services Engineers , Company

Directors, Facilities Managers and Construction Project Managers.

The group can expand and contract to meet customer and project demands via

our own internal establishment of dedicated staff.

P

OOVVEERRVVIIEEWW

~ 3 ~

Com

pa

ny P

rofile

Precision Survey Consultancy operates multiple types of survey successfully such as:

LAND SURVEY.

TOPOGRAPHY SURVEY

HYDROGRAPHIC SURVEY

TRANSMISSION LINE

ROAD SURVEY

RAIL SURVEY

ENGINEER SURVEY

SURFACE AND VOLUME MEASUREMENT AND DETAIL DESIGN

MINING PROJECT

WATER SUPPLY AND SEWERAGE PROJECTS

CONSTITUTION WORK AND BUILDING

CANAL SURVEY

SSEERRVVIICCEESS

~ 4 ~

Com

pa

ny P

rofile

A sufficient numbers of effective engineers with other dedicated staffs as along with

modern machineries and updated soft ware:

Man Power:

Sl. No. Particulars Quantity

1) Civil Engineer 04Nos.

2) Surveyor 20Nos.

3) Asst. Surveyor 25Nos.

4) Survey Boy 25Nos.

5) Accountant 02Nos.

6) Purchaser 02Nos.

7) Office Assistance 02Nos.

8) Sales Officer 02Nos.

9) Auto CAD Draftsman 03Nos.

Machineries:

Sl. No. Particulars Quantity

1) Total Station 30 Nos.

2) Digital Thedolite 08 Nos.

3) Auto Level 65 Nos.

4) Digital Level 02 Nos.

5) Hand GPS 08 Nos.

6) Water Current Meter 01 No.

7) DGPS & RTK 02 Nos.

8) ECO – Sounder 01 No.

OOUURR RREESSOOUURRCCEESS

~ 5 ~

Com

pa

ny P

rofile

Soft Ware: 1) Auto CAD Civil 3D – 2010, 2011 & 2012

2) Land Development Desktop

3) C-Soft Wiseimage Pro ver12.x (AutoCAD & Window version)

4) E – Survey CAD

5) Civil Design

~ 6 ~

Com

pa

ny P

rofile

BUIDL

OOUURR CCLLIIEENNTTSS::

~ 7 ~

Com

pa

ny P

rofile

Others Clients:

Jain Infra Projects

Orissa Stevedores Ltd.

Ahluwalia Group Coal Mines Association

Makino Modern India Concast Godavari Group

Haldia Steel

Balaji Road System Ltd

MSPL Limited

~ 8 ~

Com

pa

ny P

rofile

*Topographical Survey:

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

1 Survey work in CMERI Colony Campus

Durgapur Central Mechanical

Engineering Research Institute (CMERI)

2013 Topographical

Survey On Going

2 Total Station Survey of Alipore Zoo

Alipore Zoological Garden 2013 Topographical

Survey On Going

3

Preparation of survey drawings for Pilot Project under RAY in Siliguri MC, Darjeeling District in West Bengal

Siliguri IL&FS Infrastructure

Development Corporation LTd

2013 Topographical

Survey On Going

4

Topographical Survey Drawing by using Automatic Total Station (ATS) & Auto Level for Campus of High Court, Calcutta and its surrounding area.

Culcutta Public Works Department

2013 Topographical

Survey Completed

5

Topographical Survey work at 75 acre Sabujdweep island on the river Hooghly near Balagarh in Hooghly District

Hooghly Knight Frank 2013 Topographical

Survey On Going

6 Topographical Survey Work in CMERI Campus, Durgapur

Durgapur Central Mechanical

Engineering Research Institute (CMERI)

2012 Topographical

Survey Completed

7 Survey Work at Diamond Harbour Road Area

Kolkata Kolkata Environmental

Improvement Project (KEIP)

2012 Topographical

Survey Completed

8

Topographical Survey works of HRT for Suntaley H.E. Project, East Sikkim

Sikkim

Govt. of India Central Water Commission

Sikkim Investigation Division

2012 Topographical

Survey Completed

9 Topographical Survey for 100 acres land at Kalyani

Kalyani

West Bengal Electronics Industry

Development Corporation Limited

(WEBEL)

2012 Topographical

Survey Completed

10

Topographical Survey of the site for proposed shifting of the South 24 Parganas District Headquartert at Baruipur

Baruipur

Bengal Urban Infrastructure

Development Limited (BUIDL)

2012 Topographical

Survey Completed

~ 9 ~

Com

pa

ny P

rofile

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

11

Preparation of Topographical Survey plan of Hajrat Data Mahabub Oli (RA) Shaah Mazar Sharif Premises at Patharchapuri,Suri in the district of Birbhum using Total Station & installation / Construction of RCC control pillar along property line of the premises in connection with its development for

providing brtter amenities to the pilgrims.

Birbhum West Bengal Minorities

Development & Finance Corporation

2012 Topographical

Survey Completed

12

Topographical Surveys in Connection with Basis Services For Urban Poor (BSUP) Projects under RAY Scheme with a view to interalia identify the beneficiaries and their housing and infrastructure requirments.

Baruipur

Bengal Urban Infrastructure

Development Private Limited (BUIDPL)

2012 Topographical

Survey Completed

13

Survey work in operational area in connection with New Hangars adjacent to Air India Steel Hanger at NSCBI Airport,Kolkata

Kolkata Airports Authority of

India (AAI) 2012

Topographical Survey

Completed

14

Survey of total Land using Total Station and Installation/Construction of RCC Permanent Pillars along the boundary of the land for Proposed ESI Hospital at Haldia

Haldia ENGINEERING

PROJECTS (INDIA) LTD.

2012 Topographical

Survey Completed

15

Topographical Survey work at proposed Industrial Prak of HCCI of 1000 acres at Jagatballavpur

Jagatballavpur Bengal HCCI

Infrastructure Ltd 2011

Topographical Survey

Completed

16

Topographical Survey for Preparation of Comprehensive Pollution Abatement Scheme for Howrah Municipal

Corporation

Howrah Infrastructure Professionals

Enterprises (P) Ltd

2011 Topographical

Survey Completed

17 Topographical Survey at Behala Site, Kolkata

Kolkata Jain Infrastructure

Limited. 2011

Topographical Survey

Completed

18

Strengthening of main runway 19L-01R at NSCBI Airport, Kolkata

Kolkata Airports Authority of

India (AAI) 2011

Topographical Survey

Completed

19

Topographical Survey at Naginimora, Village Lower Tiru, Dist. - Mon, Nagaland

Nagaland Black Glod Excavators

(P) Ltd. 2011

Topographical Survey

Completed

~ 10 ~

Com

pa

ny P

rofile

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

20 Topography Survey of Land at Jangipara, Dist. Hooghly

Jangipara Howrah Mills Co Ltd. 2011 Topographical

Survey Completed

21 Surveying work at site, Baidyabati,Kolkata

Kolkata SMS Infrastructure

Limited. 2011

Topographical Survey

Completed

22

Basic Services for the Urban Poor in Five numbers Urban Local Bodies in Kolkata Metropolitan Area under JNNURM

Kolkata IL&FS Infrastructure

Development Corporation LTd

2011 Topographical

Survey Completed

23

Completion of Topographical

Survey of Siliguri Municipal Corporation Area(Part) and adjoining Area details of GAP Work of Siliguri Municipal Corporation

Siliguri Infrastructure Professionals

Enterprises (P) Ltd

2011 Topographical

Survey Completed

24

Complete Contour Survey for identified area adjoining to IT Township at Uttarpara

Uttarpara, Howrah

IL&FS Infrastructure Development

Corporation LTd

2010 Topographical

Survey Completed

25

Preparation of RL contour map of entire VMH premises at an interval of 10 M.

Kolkata Victoria Memorial Hall 2010 Topographical

Survey Completed

26

Topographical Survry of Proposed Road Connecting J.L. Nehru Road

Durgapur SPS Mani

Infrastructure Pvt. Ltd. 2010

Topographical Survey

Completed

27

Topographical Road Survey works in different location under HDRP with Howrah District

Howrah Howrah Improvement

Trust (HIT) 2010

Topographical Survey

Completed

28

Topographical Survey of Canal Adjacent to ther Boundary of IQ City Project at Sovapur, Durgapur

Durgapur SPS Mani

Infrastructure Pvt. Ltd. 2010

Topographical Survey

Completed

29

Topographical Survey

Showing Existing Infrastructure Features.

Garia IL&FS Infrastructure

Development Corporation LTd

2010 Topographical

Survey Completed

30

Detailed Topographical Survey for Sewerage Project at Baruipur Municipal Area under JNNURM

Baruipur IL&FS Infrastructure

Development Corporation LTd

2009 Topographical

Survey Completed

31

Topographical Survey of 21

Wards of Ranigunj Municipality Area covering

24.99 Sq.Km., for preparation of Detaild Project report of Raniganj Drainage Project under JNNURM Scheme.

Raniganj

Bengal Urban

Infrastructure Development Private

Limited (BUIDPL)

2009 Topographical

Survey Completed

32

Detail Topographical Survey work for Nalanda Class Room Complex at IIT, Kharagpur, B-Block

Kharagpur Simplex Infrastructures

Limited 2009

Topographical Survey

Completed

~ 11 ~

Com

pa

ny P

rofile

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

33

Survey & Demarcation of Land area of Martin Railway with Howrah District

Howrah Howrah Zilla Parishad 2007 Topographical

Survey Completed

34

Topographical and Contour Survey for Drainage and Under Ground Sewerage system within DMC under JNNURM Project

Durgapur Durgapur Municipal Corporation (DMC)

2007 Topographical

Survey Completed

35

Topographical Survey work for Surface water scheme for added area of HMC

Howrah Kolkata Metropolitan Water & Sanitation

Authority (KMW&SA)

2007 Topographical

Survey Completed

36

Topographical Survey and Contour for Drainage Plan for Raturia Angadpur area.

Raturia Angadpur

Asansol Durgapur Development Authority

(ADDA)

2007 Topographical

Survey Completed

37 Topographical Survey of our plant at Kandra Site

Kandra Adhunik Alloys &

Power Ltd. 2006

Topographical Survey

Completed

~ 12 ~

Com

pa

ny P

rofile

* Hydrographic Survey Record:- Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of Work Remarks

1

Conducting Survey work for improvement of Entrence Channel of Minor Fishing Harbour at Harwood point.

Kakdwip. South 24

Pgs.

WEST BENGAL FISHERIES

CORPORATION LTD.

2013 Hydrographical

Survey On Going

2 Hydrographic Survey at different location within West Bengal

Howrah Howrah Irrigation

Division (HID) 2012

Hydrographical Survey

On Going

3 Hydrographic Survey of RANGANADI Reservoir

Arunachal Pradesh

North Eastern Electric Power Corporation

Limited (NEEPCO)

2013 Hydrographical

Survey Completed

4

Cross Section Survey for River Senger and Korondia Nala at Kanpur

Kanpur DHI (India) Water

& Environment Pvt. Ltd.

2012 Hydrographical

Survey Completed

5

Conducting Bathymetric survey within within the area LTC jetty and passenger jetty at lot no 8 up to the deepest point towards mod river along with the shore line at Hardwood Point,Kakdwip.South 24 Pargananas

Kakdwip

WEST BENGAL FISHERIES

CORPORATION LTD.

2012 Hydrographical

Survey On Going

6

Bathymetric Survey within area outfall of Dubda Canal where it is falling at Bay of Bengal

Kakdwip

WEST BENGAL FISHERIES

CORPORATION LTD.

2012 Hydrographical

Survey Completed

7

Hydrographic survey at Kalyani Ganga river (Hooghly river) and Budge Budge Ganga (Hooghly

river) and provision of Hydrological data

Kolkata SECON PRIVATE

LIMITED. 2012

Hydrographical

Survey Completed

8

Cross Section Survey Project for Vansadhara River Project from Gunupur to Kashinagar

Orissa DHI (India) Water

& Environment Pvt. Ltd.

2011 Hydrographical

Survey Completed

9

Survey work for assessing Scour at River bed by Echo sounding

method of Main Bridge Piers of SVB Project.

Kolkata

Second Vivekananda

Bridge Tollway Companhy Private

Ltd

2011 Hydrographical

Survey Completed

10 Hydrographic Survey at Mandermani River Site

Purba Medinipur

Dredging & Desiltation Co. Pvt.

Ltd.

2010 Hydrographical

Survey Completed

11

Survey works for our Canal rehabilitation works at Churial Main Canal, Package - 8 (In between Ch: 6400 to Ch: 14695)

Mahestala, Kolkata

Dredging & Desiltation Co. Pvt.

Ltd.

2008 Hydrographical

Survey Completed

~ 13 ~

Com

pa

ny P

rofile

* Road Survey:-

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

1

Preparation of Detailed Project Report (DPR) of roads under 250+New Connectivity in respect of normal PMGSY road works in different Blocks in the District of Bankura.

Bankura WBSRDA 2013 Road

Survey & DPR

On Going

2

Topographical, hydraulic and Land Acquisition survey for a stretch of NH-

117 (from Ch.1.000 Km. to Ch. 5.500

Km) Kona Expressway

Kolkata PWD

(NH SURVEY DIV. NO - II)

2012 Road

Survey On Going

3

Topographical, hydraulic and Land Acquisition survey for a stretch of NH-31C (from Ch.224.500 Km. to Ch. 226.500 Km), around the existing bridge over river Gadadhar at Alipurduar, in the district of Jalpaiguri,W.B

Alipurduar PWD

(NH SURVEY DIV. NO - II)

2012 Road

Survey On Going

4

Topographical, hydraulic and Land Acquisition survey for preparation of Land Schedule, Land Acquisition Cost Estimate along with L.A.Drawing as per the format prescribed by the MORT&H regarding Improvement of the length of NH-80, Falling in the district of Murshidabad W.B.

Murshidabad PWD

(NH SURVEY DIV. NO - II)

2012 Road

Survey On Going

5 Topographical Survey of Rural Road under PMGSY Scheme of Govt of India.

Malda

IL&FS Infrastructure Development

Corporation LTd

2012 Road

Survey Completed

6 Topographical Survey of Rural Road under PMGSY Scheme of Govt of India.

Siliguri & Paschim

Midnapur

IL&FS Infrastructure Development

Corporation LTd

2012 Road

Survey Completed

7 Gantak Road Project Sikkim Brahmaputra Infrastructure

Ltd.

2011 Road

Survey Completed

8

Topographical Survey for the stretch of Farraka to Raiganj Section Ch+295.00 Kms to 398.00 Kms. For NH-34 Project

in all respect in the state of West Bengal.

NH-34 Hindustan

Construction Co Ltd (HCC)

2010 Road

Survey Completed

9

Topographical Survey along identified road corridors in Durgapur City for development of a Bus Rapid Transit System in Asansol Urban Area under JNNURM.

Durgapur

Bengal Urban Infrastructure Development

Private Limited (BUIDPL)

2009 Road

Survey Completed

~ 14 ~

Com

pa

ny P

rofile

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

10

Proposed Trafffic Easing / Management Measures for de-congestion of Benachetty Nachan Road from Bhiringi More (on NH-2) to Prantika in Durgapur and enhancing of urban mobility within Durgapur City in Asansol Urban Area under JNNURM

Durgapur

Bengal Urban Infrastructure Development

Private Limited (BUIDPL)

2009 Road

Survey Completed

11 Survey & Demarcation of Land area of Martin Railway with Howrah District

Howrah Howrah Zilla

Parishad 2009

Road Survey

Completed

12

Traffic Easing / Management Measures

for de-congestion of OLD G.T. Road and enhancing of Urban mobility within Asansol City in Asansol Urban Area in Asansol Urban Area under JNNURM

Asansol

Bengal Urban Infrastructure Development

Private Limited (BUIDPL)

2009 Road

Survey Completed

13

Proposed widening of EM Bypass from Ultadanga to Kamal Gazi for development of a Bus Rapid Transit System (BRTS) under JNNURM Scheme

Kolkata

Bengal Urban Infrastructure Development

Private Limited (BUIDPL)

2008 Road

Survey Completed

14

Proposed Elevated road on Budge Budge Trunk Road from Zhinjira Bazar

to Batanagar More in South 24 Parganas District in KMA area of PPP Basis

Budge Budge

Bengal Urban Infrastructure

Development Private Limited

(BUIDPL)

2008 Road

Survey Completed

~ 15 ~

Com

pa

ny P

rofile

* Engineering Consultancy Survey: Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

1 Ratle Hydro Eletric Power Project Kistwar, Jammu

& Kashmir Larsen &

Toubro Limited 2013

Engineering Survey

On Going

2

Topographical Survey work using Total Station Theodolite along with necessary Skilled/ Unskilled personnel, Tools & Plants & Machinery all complete for providing PHE Services at Action

Area - II of New Town Kolkata Project.

Kolkata

Govt. of W.B. North 24 Pgns. W/S Division -

II, P.H.E.D.

2013 Engineering Consultancy

Survey On Going

3 Koradi Thermal Power Station Nagpur Larsen &

Toubro Limited 2012

Engineering Survey

On Going

4 Deployment of survey CHP Phase 2,Sagardighi site.

Sagardighi,WB McNally Bharat

Engineering Compaly Ltd.

2012 Engineering

Survey On Going

5

Deployment of survey team with necessary machinary & tools at pltcm-BOKARO

Jharkand,Bokaro McNally Bharat

Engineering Compaly Ltd.

2012 Engineering

Survey On Going

6 3X660 MW Power Project , Talwandi Saboo,

Saboo Larsen &

Toubro Limited 2012

Engineering Survey

On Going

7 GIS Power Station Kolkata Larsen &

Toubro Limited 2012

Engineering Survey

On Going

8

Topographical Survey work using

Total Station Theodolite along with necessary Skilled/ Unskilled personnel, Tools & Plants & Machinery all complete for providing PHE Services at Action Area - II of New Town Kolkata Project.

Kolkata

Govt. of W.B. North 24 Pgns. W/S Division -

II, P.H.E.D.

2012 Engineering Consultancy

Survey Completed

9

LE110063-IDCT & CHIMNEY FOR 2X600 MW VISA POWER AT RANIGARH

Raigarh Larsen &

Toubro Limited 2011

Engineering Survey

On Going

10 Rajpura Thermal Power Rajpura Larsen &

Toubro Limited 2011

Engineering Survey

On Going

11 INDIAN OIL, CORPORATION LTD.

Paradeep Refinery Paradeep

Larsen & Toubro Limited

2011 Engineering

Survey On Going

12

Survey work at site on hire basis to check the co-ordinate points, levels and make layouts for areas like CW and ACW water line, BTG, lay down areas, Fabrication yards and other necessary required areas.

LANCO always

inspiring 2011

Engineering Survey

Completed

13 Deployment of Survey Team with machinery .

Durgapur Jain

Infraproject Limited.

2011 Engineering

Survey Completed

~ 16 ~

Com

pa

ny P

rofile

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

14 Survey Work at Box drain & different pipe line stretches

Kolkata Jain

Infraproject Limited.

2011 Engineering

Survey Completed

15

Topographical Survey work using Total Station Theodolite along with necessary Skilled/ Unskilled personnel, Tools & Plants & Machinery all complete for providing PHE Services at Action Area - II of New Town Kolkata Project.

Kolkata

Govt. of W.B.North 24

Pgns.W/S Division -II,

P.H.E.D.

2011 Engineering Consultancy

Survey Completed

16 Topography Survey at Coke Oven

JSL Stainless LTd.

2011 Engineering Consultancy

Survey Completed

17 Jaypee Nigrie Super Thermal Power Plant

Singrauli Larsen &

Toubro Limited 2010

Engineering Survey

On Going

18 Survey at 2x700MW Rajpura Thermal Power Project ,

Patiala, Punjab Larsen &

Toubro Limited 2010

Engineering Consultancy

Survey Completed

19

Survey Works for 6X150 MW structural steel works and chimney works at Mahan Singrauli,MP

MP Larsen &

Toubro Limited 2010

Engineering Survey

Completed

20

Topographical Survey work using Total Station Theodolite along with necessary Skilled/ Unskilled personnel, Tools & Plants & Machinery all complete for providing PHE Services at Action Area - II of New Town Kolkata Project.

WB

Govt. of W.B. North 24 Pgns. W/S Division -

II, P.H.E.D.

2010 Engineering Consultancy

Survey Completed

21

Erection work for construction of 400KV D/C Tower Packages - A3 under Transmission system associated with pallatana GBPP and Bangaigaon TPS in North Eastern Region

IVRCL Infrastructures & Project Ltd.

2010 Engineering

Survey Completed

22

Deployment of survey Team with Machinaries & Tools on monthly rental basis at 2X700 MW rajpura Thermal Power Project,

Rajpura, Dist Patiala, Punjab

Punjab Larsen &

Toubro Limited 2010

Engineering Survey

Completed

23

Construction of Integrated Passenger Terminal Building at NSCBI Airport,Kolkata

Kolkata ITD-ITD CEM

JV. 2010

Engineering Survey

Completed

24

Geodetic and precision survey for construction of Phase - II facilities and other areas of Coke Oven Battery No.4 complex of Visakhapatnam Steel Plant.

Andrapradesh Rashtiya Ispat Nigam Limited

2010 Engineering Consultancy

Survey Completed

~ 17 ~

Com

pa

ny P

rofile

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

25

Survey work for installing ROW pillars along ROW line of SVB Project

Kolkata

Second Vivekananda

Bridge Tollway Companhy Private Ltd

2010 Engineering Consultancy

Survey Completed

26

Survey Work for 6X150 MW structural steel work and chimney work at Mahan Singrauli, MP

MP Larsen &

Toubro Limited 2010

Engineering Consultancy

Survey Completed

27 Survey work for DHAMRA Rail

link Project Larsen &

Toubro Limited 2009

Engineering

Survey Completed

28

Construction of Integrated Passenger Terminal Building at NSCBI Airport,Kolkata

Kolkata ITD-ITD CEM

JV. 2009

Engineering Survey

Completed

29 Survey work at COBP Project at Orissa

Orissa JSL Limited. 2009 Engineering

Survey Completed

30 Survey team with total station for SMS area.

Jajpur, Orissa JINDAL

STAINLESS 2009

Engineering Survey

Completed

31

Survey at Nalanda Class Room

Complex at IIT Kharagpur.B-Block .

Kharagpur,WB Simplex

Infrastructures Limited.

2009 Engineering

Survey Completed

32

Topographical Survey work using Total Station Theodolite along with necessary Skilled/ Unskilled personnel, Tools & Plants & Machinery all complete for providing PHE Services at Action Area - II of New Town Kolkata Project.

New Town Kolkata

Govt. of W.B. North 24 Pgns. W/S Division -

II, P.H.E.D.

2009 Engineering Consultancy

Survey Completed

33

Topographical Survey work using Total Station Theodolite along with necessary Skilled/ Unskilled personnel, Tools & Plants & Machinery all complete for providing PHE Services at Action Area - II of New Town Kolkata Project.

New Town Kolkata

Govt. of W.B. North 24 Pgns. W/S Division -

II, P.H.E.D.

2008 Engineering Consultancy

Survey Completed

34

Topographical Survey work using Total Station Theodolite along

with necessary Skilled/ Unskilled personnel, Tools & Plants & Machinery all complete for providing PHE Services at Action Area - II of New Town Kolkata Project.

New Town Kolkata

Govt. of W.B. North 24 Pgns. W/S Division -

II, P.H.E.D.

2007 Engineering Consultancy

Survey Completed

35

Survey work for Second Vivekananda Bridge Project site at Dakhineshwar - Kolkata

Kolkata Larsen &

Toubro Limited 2005

Engineering Consultancy

Survey Completed

~ 18 ~

Com

pa

ny P

rofile

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

36

Construction of Integrated Passenger Terminal Building at NSCBI Airport,Kolkata

Kolkata ITD-ITD CEM

JV. 2004

Engineering Consultancy

Survey Completed

37 Survey Work at Kol Dam Project in Himachal Pradesh

Himachal Pradesh

Col Mines Associated

Traders

2004 Engineering Consultancy

Survey Completed

38

Survey at SAIL Durgapur Steel Plant for the Project of Debottlenecking of RAW Material Handling Plant

Durgapur Tecpro Systems

Limited.

Engineering Consultancy

Survey Completed

* Pipe Line Survey: Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

1

GPS survey work by RTK instrument for our pipe line job of 8000.00mts. Approx from GOKULPUR to HIJLI station at KHARAGPUR division Sourh Eastern Railway

Kahragpur McNally Bharat

engineering Company Limited.

2013 Pipe Line Survey

On Going

2

Route alignment suggestion best possible route from Chandil Dam to Ranchi

Ranchi HINDALCO

Industries Limited 2012

Pipe Line Survey

Completed

3

Pipeline Route Survey for 8.625" ODX28Km., IOCL ATF - Kolkata Pipeline work from Mourigram

Terminal to AFS Gouripur

Kolkata Harisons Industries

2011 Pipe Line Survey

Completed

4

Reconnaissance and pipeline route survey work for the section from Dankuni Coal Complex to Receiving terminal (NH2/NH6 Junction).

Howrah Greater Calcutta

Gas Supply Corporation Ltd.

2007 Pipe Line Survey

Completed

~ 19 ~

Com

pa

ny P

rofile

* Mining Survey: Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

1

Preparation of plans for Oting coal Mine of Black Gold Excavators Pvt.Ltd

Nagaland Black Gold Excavators

Pvt.Ltd

2012 Mining Survey

Completed

2 Contour / Grid Survey at Sharda OC Mine, Sohagpur area SECL

MP Cuprum Bagrodia

Limited 2010

Mining Survey

Completed

3 Topographical Survey work Nagaland Tirucoal Project 2008 Mining Survey

Completed

4

Topographical Survey of about 3.83 Sq.Km. (383 Hectors) in respect of Dumri Coal Block, Dist. - Hazaribagh, Jharkhand State.

Jharkhand Mahacol Trexim Private Limited

2008 Mining Survey

Completed

5 Topographical Survey of Tiru Area (Upper and Lower) in Nagaland

Nagaland NCP Oting (JV) 2007 Mining Survey

Completed

* Railway Survey:

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

1

Topographical Survey in connecting with preparation of Feasibility Report for JSPL.

GUA Balaji Rail Road Systems Limited

(BARSYL)

2012 Railway Survey

Completed

2

Execution of Survey Work for our joka BBD Bag Metro Railway Project Site.

Kolkata McNally Bharat

Engineering Company Limited

2012 Metro

Railway Survey

Completed

3 Survey of platforms in between Bandel-Katwa Station

Katwa Mesa Narula-

GCC(JV) (MNG)

2011 Railway Survey

Completed

4

Traversing & Traversing Calculation from Phoolbagan to Central Metro Station (Total Legnth of 6Km. Approx) including Drawing Submission for

KMRC:UG2

Kolkata ITD - ITD

Cementation India Limited

2010 Railway Survey

Completed

5

Detailed survey with the help of Total Station between Tamluk (Junction cabin) and Rajgoda Railway Station in Kharagpur Division of South Eastern Railway for a Total length of 13.5Km.

Tamluk KEC International

Limited 2010

Railway Survey

Completed

~ 20 ~

Com

pa

ny P

rofile

Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

6

Topographical Survey for preparing Engineering Plan of the proposed Private siding of M/s Raigarh Coal Benification Pvt. Ltd. near Robertson Railway Station, S.E.C. Railway

Raigarh, Chattrishgar

MBB Consultancy Services Pvt. Ltd.

2009 Railway Survey

Completed

7 Detailed Survey at Patratu by Total Station

Balaji Rail Road Systems Limited

2009 Railway Survey

Completed

8 Railway siding Survey Balaghat,MP Sova Ispat Limited 2008 Railway Survey

Completed

9 Detail Survey of Railway Siding by total Station at Gamharia site

Tatanagar, Jharkand

Balaji Rail Road Systems Limited

2008 Railway Survey

Completed

10

Detailed Survey for Chattibariatu & Kerandari Coal Mines Railway siding project of NTPC Ltd.

Dehri On Sone,Bihar

Balaji Rail Road Systems Limited

2008 Railway Survey

Completed

11

Layout Survey and taking x-section of a pvt. Railwar siding taking off from Tapsi-Barbani line of Asansol Division of ER by Total Station.

Asansol Balaji Rail Road Systems Limited

2008 Railway Survey

Completed

12 Detailed Survey at GUA Railway station yard by Total Station

GUA Balaji Rail Road Systems Limited

2008 Railway Survey

Completed

13

Detailed Survey at ACC, Madhukunda Plant by Total Station

Madhukunda Balaji Rail Road Systems Limited

2008 Railway Survey

Completed

14 Detailed Survey at Borojamda Site Borojamda Balaji Rail Road Systems Limited

2007 Railway Survey

Completed

15 Deatiled Survey at Barada Railway

Yard by Total Station Barada

Balaji Rail Road

Systems Limited 2007

Railway

Survey Completed

16 Deatiled Survey at Bolani Railway Yard by Total Station

Bolani Balaji Rail Road Systems Limited

2007 Railway Survey

Completed

17 Railway siding by Total Station Purulia,WB Haldia Steels Ltd. 2006 Railway Survey

Completed

18

Layout of Proposed Railway Track from take off point to Buffer end of Shri Ramrupai Balaji Steel Ltd. At Banskopa Durgapur

Durgapur Jai Balaji Group 2006 Railway Survey

Completed

~ 21 ~

Com

pa

ny P

rofile

* HT Line Project:

Sl. No.

Description of Work Location Area/

Length Principal Client

Year of Starting

Pattern of Work

Remarks

1

Detail Survey of existing 132kv D/C Transmission Line of DVC from Kalipahari to BALCO including submission of Route Alignment Drawing,Profile Drawing & Tower Scheduling.

Durgapur 6.5 km. DPSC Limited. 2013 Transmission Line Survey

On Going

2 Route Alignment Survey Ranchi 20.863

km.

Hindalco Industries

Limited

2012 Transmission Line Survey

Completed

3

Survey and soil investigation for 400kV D/C transmission line for 2x660MW STPP at Banka ,Bihar

Bihar 29 km L&T

Construction 2012

Transmission Line Survey

Completed

4

400 KV D/C Tower Packages-A3 under Transmission System associated with Pallatana GBPP and Bongaigaon TPS in North Eastern Region.

Bonga 15 km IVRCL

Infrastructures & Projects Ltd.

2010 Transmission Line Survey

Completed

* GPS Survey: Sl. No.

Description of Work Location Principal Client Year of

Starting Pattern of

Work Remarks

1 20 nos of DGPS points fixing. Nagaland Zymax Technologies 2012 DGPS Survey

Completed

2 DGPS Control Point survry work Salt Lake (Kolkata)

Consulting Engineering Services

(INDIA) Private Limited

2012 GPS Survey Completed

3 DGPS Point Process Howrah Geosmart Technology 2011 DGPS Survey

Completed

4

GPS Point & Control Point fixing at entire area of Kolkata Metro Railway Project (East - West)

between subhas sarovar and Central Station Based for KMRC:UG2

Kolkata ITD - ITD Cementation

India Limited 2010 GPS Survey Completed

5 GPS Survey of Slum in Uttarpara - Kotrang Municipality Area

Uttarpara IL&FS Infrastructure

Development Corporation LTd

2006 GPS Survey Completed

6 Gps Survey of Slum in Kalyani Municipality area

Kalyani IL&FS Infrastructure

Development Corporation LTd

2006 GPS Survey Completed

~ 22 ~

Com

pa

ny P

rofile

Others Completed Project List:

1) Development of HINDALCO Factory at Muri.

2) Kandra Steel Plant Development.

3) Kol Dam Project in Himachal Pradesh.

4) Chakdah-Bongan Road Project.

5) South City at Kolkata.

6) Railway siding development at Dadhapara Station.

7) Railway siding development at Rupond Station.

8) D.S.P. Township Road development Project.

9) Tata Iron mines at Noamundi.

10) Monarchak Transmission Line Survey.

11) Railway siding development of ESL MINING LTD at Barbil.

12) DRDO Project at Nayagaon, Assam

13) NTPC 225 Flood Control Project at Farakka.

14) Existing Railway line development for HINDALCO at Hirakundh.

15) NEPAZE Steel Plant Development.

16) LAFARGE Cement Plant Development at Bhatapara.

17) OCL Railway siding development at Bayree.

18) HCL Railway siding development at Ghatsila.

19) Railway siding development at Durgapur.

20) BCCL out Sourcing Project at Dhanbad.

21) Railway siding development at Sri Ramrupai Balaji Steel Plant .

22) Railway siding development at Dadhapara Station.

23) Canal survey at chilka and RatnaJira river at Puri (Phase -I).

24) Rail Survey at different Private siding in CKP division under South Eastern Railway.

25) Proposed Water Treatment Plant survey at Nagpur, Jharsuguda, Koderma, Maithon, Bhuj,

Mejia for L&T.

26) Survey for proposed railway siding for NTPC at Hazaribag under BARSYL.

27) Plant survey of material handling system for Birla Cement at Durgapur.

28) Survey for fabrication and Batching plant of airport authority at Netaji Subhas Chandra

Bose Internationa Airport (NSCBIA), Kolkata under ITD Cementation Ltd.

29) Completion Bally Water Line Project.

30) Completion Topography survey for Kolkata Metro Railway from Central to Howrah

Maidan.

~ 23 ~

Com

pa

ny P

rofile

31) Topography survey of two stations one is SEALDAH & another one is Central Metro

Station under ITD.

32) Pillar Installation at metro related area under ITD.

33) Survey for new airport complex and runway at Netaji Subhas Chandra Bose International

Airport in Kolkata under ITD CEM JV.

34) Survey of canal at chilka and survey of Ratnajira River at Puri (Phase-II).

35) Survey at Thermal Power Plant of L&T Ltd. at Nagpur, Jharsuguda, Koderma, Maithon,

Bhuj, Mejia site.

36) Canal Survey at Mandermuni in Digha.

37) BRTS Road survey at Durgapur under BUIDL.

38) Detail Topography layout survey under HINDALCO Industries Limited.

39) Topographical survey at Bhadrakh Site under Larsen & Toubro.

40) Survey Project within Zone Command area including preparation data base and drawing

under Surface Water Based Water Supply Scheme in the arsenic affected areas of S outh 24

Parganas District.

41) Collecting Horizontal Reference Point from i) cut & cover (subhas sarobar); ii) Phool Bagan;

iii) cross over; iv) Sealdah; v) Central station under ITD - ITD CEM JOINT VENTUE.

42) Survey work under L&T at Rajmundrai Site.

43) Details survey at EM-Bypass relevant area

44) Rail survey work at Shantipur under Mesa Narula JV.

45) Kachrapara Municipality survey.

46) Sewerage Network survey work for the Kanchrapara, Kalyani, Champdani, Rishra,

Nabadeep, Krishnanagar municipalities under National Ganga River Basin Authority

(NGRBA).

47) Survey work at Barbil, Jharkhand under Global Industries.

~ 24 ~

Com

pa

ny P

rofile

The list of client along with the work volume is increasing day to day.

Simultaneously the quality of work reflects by the satisfaction of client.

Precision Survey consultancy commit to the client to provide the

best service at all time.

CCOONNCCLLUUSSIIOONN