upper mississippi river 9-foot navigation system st. paul district 13 locks and dams
DESCRIPTION
U.S. Army Corps of Engineers St. Paul District Channels & Harbors Project Presentation for 2012 WEDA Midwest Chapter By Steve Tapp April 27 th , 2012. Upper Mississippi River 9-Foot Navigation System St. Paul District 13 Locks and Dams 284 Miles of 9-Foot Channel Mississippi River - PowerPoint PPT PresentationTRANSCRIPT
US Army Corps of Engineers
BUILDING STRONG®
U.S. Army Corps of EngineersSt. Paul DistrictChannels & Harbors Project
Presentation for2012 WEDA Midwest Chapter
BySteve Tapp
April 27th, 2012
BUILDING STRONG®17 April 2009 2
Upper Mississippi River9-Foot Navigation System
St. Paul District
• 13 Locks and Dams• 284 Miles of 9-Foot Channel
• Mississippi River • Minnesota River • St. Croix River • Black River
• 11 Shallow Draft Recreation Harbors • 3 Shallow Draft Commercial Harbors
BUILDING STRONG®
• Average 850,000 CY/YR
• Season is May-November
• Government & Contract Dredges Used
St. Paul District Dredging
3
BUILDING STRONG®
Government Equipment
Dredge GOETZ
• Replaced THOMPSON in
2005
• 20-inch cutterhead pipeline
dredge
St. Paul District Dredging
4
BUILDING STRONG®
Government Equipment
Dredge DUBUQUE
• 12 inch cutterhead pipeline dredge
Excavators
&
Cranes
St. Paul District Dredging
5
BUILDING STRONG®
Contract Equipment
Hydraulic
• Mostly site excavations
• Some channel dredging
Mechanical
• Mostly channel dredging
• 3 year contract with LS Marine in 2011
St. Paul District Dredging
6
BUILDING STRONG®
2011 Dredging Summary
Total Dredged = 1,478,989 CY Jobs = 54
62% Government 38% Contract
Contractor: LS Marine
Dredging Season 2011:April 27th – November 16th
(Last year May 24th – October 13th)
Dredge GOETZ
St. Paul District Dredging
7
BUILDING STRONG®
2013: Pool 2 Channel Modification?500,000 CY
2014: Lost Island Site Unloading (Pool 5)750,000 CY
2015: McMillan Island Site Unloading (Pool 10)200,000 CY
2016: Lower Pool 2 Multiple Site Unloading1,000,000 CY
Upcoming Dredging Jobs
8
BUILDING STRONG®
Capoli Slough
9
Environmental Management ProgramProtect 10 IslandsConstruct 9 New IslandsQty Estimates
250K CY Sand Fill 35K CY Fines 30K CY Rock
Award Late 2011
BUILDING STRONG®
Pool 2 Channel Study
Complete Plan in 2012 Award Contract in 2013 Remove .5 Mile of
Channel ? Reduce Dredging Improve Safety
10
BUILDING STRONG®11
Thanks!Thanks!