Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Technical Coordination Session
Technical Coordination for Upgrade (Austin Ball) 20 mins
ResponsibilitiesOrganisation Host Lab and Common projects progress & issuesSchedule, Milestones, Reviews, Change ControlCost estimates and concerns
Preliminary detailed planning for LS1 (Martin Gastal) 20 mins
Endcap muon region coordination issues (Dick Loveless) 15mins
Tracking region coordination issues (Nicola Bacchetta) 15 mins
Electrical and electronic systems projects (Magnus Hansen) 15 mins
Magnet and service infrastructure projects (Paola Tropea) 15 mins
Beam radiation monitoring projects (Anne Dabrowski) 10 mins
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Technical Coordination
- assure the provision of host lab technical support to the experiment (≥ provisions guaranteed under “General Conditions for Experiments”)
surface assembly buildings and underground caverns primary infrastructure and services (eg power, water, parking)core expertise (eg safety advice and oversight)
-manage the provision and operation of common elements of the technical project and identify and coordinate additional common programmes. eg solenoid, shielding, cooling system, detector power, BRM, common cabling teams.....
-assure safe design, fitness for purpose, timely and cost-effective delivery and coherent, safe, installation + operation of detector systems including compatibility with:
existing detectors and detector infrastructureCERN host infrastructure,
accelerator complexCERN rules & host state regulations.
3-fold mandate
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
TC and upgrade
“maintenancc”
“consolidation”“upgrade”
“technical operation
“construction”
Technical Coordination
Common TC structure and reporting lines cover all types of activity
TC defined “consolidation & upgrade” as: ALL changes of configuration after Sept 2008 (ES, UPS, farm cooling, Gazprom, mag shields, BRM, ZDC, etc etc)
Boundaries are blurry:
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
TC essentials for upgrade
-Consolidation & Upgrade common fund (additional to M & O A and CERN as host funding).
-Safety team (+ subsystem links)
-Engineering + technical teams for infra & common systems, plus general elec & mech support
-Mechanical, Electrical and Electronic Integration Team (homogeneous)
-Planning and logistics teams (includes full ALARA dose planning)
-Recognised review process, including external referees, as applied to CMS so far.
(TP-TDR) -PRR-EDR/ESR(several)-MPR(several)-ECR-POR-TIP etc
- As-built engineering model and the Equipment Management Database, (the essential starting points of any intervention on the detector).
-Subsystem “field coordinators”
-Collaboration teams with detector expertise as common resource for subsystems
(from May 08 upgrade workshop)
Technical Coordination
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination & Upgrade
Endcap MuonRegion
Trackingregion
HCAL r/o > 3 region
YE4
Bpix Fpix PLT
CSC4
HOHB/HE
CAST HF
RPC4
CAL TRAK BSC TAS/ SHIELD
BP VFWD
BP
Mech IntegrationElec Integration
Infrastructure &Engineering Support
Technical ReviewTechnical Support
PlanningInstallation support
Installation oversight
Link structure for detector consolidation & upgrade
Magnet & Common Services
TK cold
Safety,RP shielding & radioprotection
Assembly & support facilities
Workshops
Cryo Cooling
MovingElec
BRMMachine interface
ME1/1 r/o
Inertion & Humidity Control
R. Loveless
H. GerwigW.ZeunerM. Hansen
A.Surkov A. Lanaro S.Buontempo
W.Erdmann
tbd tbd –urgent!
G. Bolla M.Gastal C.Schaefer A. Onnela
D.Wood
A.Gaddi
P.Tropea S. Lusin H.Gerwig
P.Tropea
Barrel Mu r/o
C. Bedoya
MB1 TRB
SC move
C. SchaeferW. Zeuner
A. DabrowskiP. Siegrist
M. GastalD. HayP.Petiot
A. Ball
N. Bacchetta
B. Cure
Gas
G. Fetchenhauer
M.Giunta S. Popescu
K.Borras
CO2
H.Postema
T
hese ar
e links to
TC
NOT managem
ent reportin
g lines
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Technical Reviews
Principle defined in Constitution of the CMS experiment, Section 6.7:
"Before launching the construction (or modification) of major parts of any CMS sub-detector or sub-system, or engaging in major related expenditures, the Technical Coordinator, with the agreement of the relevant sub-project manager, organizes reviews to confirm the soundness and completeness of the chosen design including the coherence of all interfaces with respect to neighbouring sub-detectors or other parts of CMS; the aim being to minimize risks in cost and schedule". review types: PRR, ECR, ESR, EDR : (follow-ups usually needed)In addition:“Each subdetector will undergo one or more MPRs (Manufacturing Progress Reviews) at strategic moment(s) of the production process. The Technical Coordinator will decide which production processes merit MPR's. The MPR committee will ascertain whether the manufacture is going as planned, whether the quality requirements and milestones are likely to be met and whether the resources (financial and human) required to complete the production are available.”
And in practice we also introduced “installation EDR’s”, prior to installation of items in CMS.
The same review process is being applied to consolidation and upgrade
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Consolidation & Upgrade
Done and reports complete or in final editing:
PLT MPR 17 Jun 2011
CASTOR ECR 30 Jun 2011
ME1/1 ECR/ESR 08 Jul 2011
BSC upgrade workshop 22 Jul 2011
YE4 assembly & installation 15 Sept 2011
ZDC crane 28 Sept 2011 (Inst rev still reqd)
Imminent:
PLT MPR follow-up 17 Nov 2011
RPC4 EDR 24 Nov 2011
CASTOR “ show & tell EDR” 14 Dec 2012
Shielding Dec 2012 ??
Reviews and workshops 2011
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Common facilities (Surface buildings 678,904,892,SX5)
Common systems (Magnet, RP shielding)
Endcap Muon (YE4)
Tracking (45mm o/d beampipe)
Host lab & Common Project progress
Brief update on some selected projects:
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Surface facilities: 678 : 500m2 storage “tent”Critical to the logistics sequence of liberating ISR and re-equipping SX5
Nov 2011: another tent will be needed to clear tooling in ISR
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Surface Facilities: 904 zoneA.Sharma, D. Hay
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Surface Facilities: 892
Cryo equipment removed.
Floor pits filled.
Platform refurbished.
867 released for LHC radiation w/shops
Outer shell/door still requires work.
Duplicate workshop & ECAL labs displaced from 867 by LHC machine
ECAL test stations
+ETHZ workshop
available again.
867 released for LHC radiation w/shops
Party imminent!
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Surface Facilities, Pt 5: SHL
16/03/[email protected]
1’st floor nearing completion
Delivery of pixel cold/clean(ish) lab not possiblein time for YETS 2011-12.Contingency plan in case of BCM/pix removal was to transport to TIF.Blockages due to RP shielding & quake tolerance issuesWill be ready for LS1 for 18 deg operation.
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
14
Common Systems, Infra & Facilities: Magnet
Magnetic field off: ~ no useful physicsMagnet on-off-on: limited number of such cycles in lifetime (200-300?)
Highest priority:
Redundant Helium compressor pair
- critical single point failure : 7 mo recovery!
- replacements now only built to order, but provision for redundant pair foreseen
- identified pre-purchases (effectively compressor spares: rotors, bearings etc) to reduce downtime to 1 mo.
- Order placed (CERN funds: contribution or loan)
Benoit Cure
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Common Systems, Infra & Facilities: RP shieldsA.Surkov, Wolfram Zeuner
Finalising design of RP shielding from Tracker Bulkhead to 11m . Single set of tooling, supporting shield from below, compatible with all activities.
-Aim to complete design by early autumn.
-EDR this year if possible.-Start manufacture 2011.
-Full test in LS1 (before needed for ALARA)
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
New CMS central beampipe
Be
supportBe or AlBe??
oldnew
1630
14501948
=4.9
SS or AlBe?? SS or AlBe??Be
supportBe or AlBe??
oldnew
1630
14501948
=4.9
SS or AlBe?? SS or AlBe??
Issues:
Impedance, HOM etc: shape OKVacuum impedance: OK .Support collar on cone at 1630 mm: OKAperture OK : approved by LEB, LMCMaterials and Construction:Cones 1450 -->1948 machined from AlBeConsidering replacing SS conical section (up to bellowsjunction with Endcap pipe at 3.12m) with AlBe. AlBe to Be braise to be studiedLighter pipe, as strong, reduces sag, activation and backgrounds, eliminates transition piece.
3120
CMS E & I, for C. Schaefer
support
Ball, Bacchetta, Schaefer, Zeuner, EIC, TE-VSC
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Beampipe upgrade: simulation
• New geometry implemented in FLUKA Changes:
– Radius of cylindrical part smaller– Conical part changed from stainless steel to AlBeMet.– Pixel layer 1 at smaller radius
• Simulations use beam background simulated by N.Mokhov
Moritz Guthoff – Staus: CMS BRM
Moritz Guthoff - Staus CMS BRM
PIXEL
Conical BP & flangeSt.steel->AlBeMetCylindical BP
(Smaller)
OLD
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
6.10.2011 Moritz Guthoff - Staus CMS BRM6.10.2011 Moritz Guthoff - Staus CMS BRM 18
Chargedhadrons
neutralhadrons
electrons
OLD NEWPIXEL
BEAM
Prelim
inary
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Endcap Muon Upgrade
YE4 shielding disk: material qualified, first steel sector cases being assembled Complex assembly tooling designed and in purchase procedure. “push-back” system nearing completion. Assembly EDR held in Sept
CSC4, RPC4, ME1/1 front end: Review process ongoing .
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
YE4 shielding disk: milestones
NB
Date format
!!!!!
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Tracking (Pixel/beampipe) upgrade timing
Milestones for new beampipe
Mechanical params for aperture calc Jun 2011 CompleteMaterial (!) and integration studies July 2011 CompleteLEB approval Aug 2011 CompleteLMC approval Aug 2011 CompleteCall for tender Sept-Nov 2011 CompleteFC approval Dec 2011Finalise design Jan 2012EDR Jan 2012Place order: Feb 2012Delivery at CERN: mid 2013Testing complete Nov 2013 leaves time for 1 weld re-work.Ready for installation Dec 2013 milestone in common with LHC
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
LHCC Milestone Level definitions
Level 1 milestones: are derived from the overall planning for CMS assembly & usually represent changes of dominant activity on the critical path
towards readiness for beam operation.
Level 2 milestones: are defined by sub-system managers and represent keybenchmarks in sub-detector progress towards the relevant level 1 milestones.Level 3 milestones: are defined by sub-system managers to complement the level 1 and 2 milestones by providing a more detailed breakdown of objectives and a mechanism for intermediate monitoring of major tasks in progress.
L2 “ready for installation” milestones and “schedule float”- L2 “ready for installation” milestones mark the date from which a major section of the detector is intended to be ready be used in the master assembly sequence.- They allow flexibility in tuning the master assembly sequence without impacting subdetector planning.
- The target float from the critical path is 3 months (usable as contingency during last year of construction, by agreement with Technical Coordination).
from LHCC meeting, 15 June 2004, updating 15 Mar 1999
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Example: v34.2 UX schedule overview
Level 1 milestones mark major activity changes on CPLevel 2 RFI milestones show the latest date where anitem is "on the shelf " ready to use on CP.
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
YETS 2011-12: Focus now P-spikes 18.3m R5
Suspects: physical aperture problem desorption instability due to adsorbed gas
TC CONSIDERS THIS THE DOMINANT KNOWN RISK TO 2012 OPERATION
YETS 2011-12 planning is therefore being re-designed to give priority to:
• Radiography of both ends around this region and survey check from 13m to 50m.
• Bakeout –z end beampipe for 18 3 m ( same for +z end if radiography reveals no fault)
• Activate a so far unused NEG cartridge to double the pumping speed (increased threshold for desorption instability)• Install additional instrumentation in the 18 3 m region.
THIS ACTIVITY IS INCOMPATIBLE WITH OPENING THE YOKEbut the planned programme with yoke closed can still be done – with added difficulty
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
YETS 2011-12 main activities
Survey, radiography and bakeout of 18 3 m region
Installation of the much-delayed ZDC crane (last chance - activation) Validate CASTOR calorimeter insertion with beampipe at vacuum. Install PLT demonstrator on CASTOR table at +z end (subject to MPR 17 Nov) Remove BSC to preserve for heavy ion programme
provide for tests of BSC 2 technology (focussed on beam-halo) Replace components in one HF RBX’s Install CSC4/RPC4 posts and RE4 demonstrators Re-work Muon Barrel DT system LV connectors New crane in CV room
Obligatory & advisory annual maintenance of services Tests of AUG, Diesel backup, Evacuation etc Re-verification of alarm action matrix (minimising collateral damage risks)
Input from Divonne TC workshop: 17 weeks needed to justify opening detector.Including vac work, 20 weeks would now be needed. Little prospect of getting a head start on LS1 work (such as Tracker humidity seal)
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Draft LHC baseline planning LS124 months physics to physics, 20 months beam to beam
Input from CMS: need 20 months, starting no earlier than Dec 2012
Sequencing &Co-activity beingunderstood.
Timeframes less convincing
LHC preferred startdate 17 Nov.
Many resources from Institutes-Interference with-expt resources?
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
CMS draft planning LS1Martin Gastal: for detail see his talk
Tracker cold operation is given priority : leads to complex logisticsCMS need 24 months beam to beam to be comfortable: working on alternative sequences
Nominal BP RFI
Beampipe installed
Await tender discussions to see if it could work
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
LHC plan post-LS1 & phase 1 pixel insertion
Case made to LMC for beampipe approval Aug 2011:
Unless we think there is a possibility of phase1 pixel being ready in late 2014, we should stick with this message: synergy with LINAC4 connection is likely.
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Concerns: there are many!
-Cash needed in 2011- 2014
-Likelihood of a chaotic year for finances in 2012
-Maintaining the base of technically competent personnel eg common systems experts field coordinators
-Draft LS1 plan: beampipe rfi is lateHO HPD —> SiPM on YB0 is high risk and lengthycontingency for re-opening after CRAFT has started insufficient24 months beam-to-beam needed to be comfortable
-YE4 delivery: assembly pushes RP area completion in SX5 into LS1
-SX5 (OSC+ SL53) facility progress slow/blocked
-Completing retreat from ISR
Upgrade workshop FNAL Nov 2011 AB
Technical Coordination
Host Lab & Common Project 2012-14
Facilities: 904, SX5 (OSC) completion, additional buildings to house remaining ISR equipment.
Magnet & Common SystemsRP shielding, Opening system consolidation. Cryo compressor redundancy.UPS system extension in USC.
Endcap MuonYE4, YE4 pushbackYE3 manifold mods for RE4, (YE1 cooling manifold accessibility?)
TrackerBeampipe, Humidity Control (seal), N2 high capacity, CO2 cooling integration.
>3CASTOR insertion with bp at vacuum, beampipe support consolidation
As in other projects, will need to decide what’s essential?