Upgrade workshop FNAL Nov 2011 AB Technical Coordinat ion Technical Coordination Session hnical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities Organisation Host Lab and Common projects progress & issues Schedule, Milestones, Reviews, Change Control Cost estimates and concerns liminary detailed planning for LS1 (Martin Gastal) 20 mins cap muon region coordination issues (Dick Loveless) 15mins cking region coordination issues (Nicola Bacchetta) 15 mins ctrical and electronic systems projects (Magnus Hansen) 15 mins net and service infrastructure projects (Paola Tropea) 15 mins m radiation monitoring projects (Anne Dabrowski) 10 mins

Upload: cori-shepherd

Post on 18-Jan-2016

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Technical Coordination Session

Technical Coordination for Upgrade (Austin Ball) 20 mins

ResponsibilitiesOrganisation Host Lab and Common projects progress & issuesSchedule, Milestones, Reviews, Change ControlCost estimates and concerns

Preliminary detailed planning for LS1 (Martin Gastal) 20 mins

Endcap muon region coordination issues (Dick Loveless) 15mins

Tracking region coordination issues (Nicola Bacchetta) 15 mins

Electrical and electronic systems projects (Magnus Hansen) 15 mins

Magnet and service infrastructure projects (Paola Tropea) 15 mins

Beam radiation monitoring projects (Anne Dabrowski) 10 mins

Page 2: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Technical Coordination

- assure the provision of host lab technical support to the experiment (≥ provisions guaranteed under “General Conditions for Experiments”)

surface assembly buildings and underground caverns primary infrastructure and services (eg power, water, parking)core expertise (eg safety advice and oversight)

-manage the provision and operation of common elements of the technical project and identify and coordinate additional common programmes. eg solenoid, shielding, cooling system, detector power, BRM, common cabling teams.....

-assure safe design, fitness for purpose, timely and cost-effective delivery and coherent, safe, installation + operation of detector systems including compatibility with:

existing detectors and detector infrastructureCERN host infrastructure,

accelerator complexCERN rules & host state regulations.

3-fold mandate

Page 3: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Page 4: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

TC and upgrade

“maintenancc”

“consolidation”“upgrade”

“technical operation

“construction”

Technical Coordination

Common TC structure and reporting lines cover all types of activity

TC defined “consolidation & upgrade” as: ALL changes of configuration after Sept 2008 (ES, UPS, farm cooling, Gazprom, mag shields, BRM, ZDC, etc etc)

Boundaries are blurry:

Page 5: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

TC essentials for upgrade

-Consolidation & Upgrade common fund (additional to M & O A and CERN as host funding).

-Safety team (+ subsystem links)

-Engineering + technical teams for infra & common systems, plus general elec & mech support

-Mechanical, Electrical and Electronic Integration Team (homogeneous)

-Planning and logistics teams (includes full ALARA dose planning)

-Recognised review process, including external referees, as applied to CMS so far.

(TP-TDR) -PRR-EDR/ESR(several)-MPR(several)-ECR-POR-TIP etc

- As-built engineering model and the Equipment Management Database, (the essential starting points of any intervention on the detector).

-Subsystem “field coordinators”

-Collaboration teams with detector expertise as common resource for subsystems

(from May 08 upgrade workshop)

Page 6: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Technical Coordination

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination & Upgrade

Endcap MuonRegion

Trackingregion

HCAL r/o > 3 region

YE4

Bpix Fpix PLT

CSC4

HOHB/HE

CAST HF

RPC4

CAL TRAK BSC TAS/ SHIELD

BP VFWD

BP

Mech IntegrationElec Integration

Infrastructure &Engineering Support

Technical ReviewTechnical Support

PlanningInstallation support

Installation oversight

Link structure for detector consolidation & upgrade

Magnet & Common Services

TK cold

Safety,RP shielding & radioprotection

Assembly & support facilities

Workshops

Cryo Cooling

MovingElec

BRMMachine interface

ME1/1 r/o

Inertion & Humidity Control

R. Loveless

H. GerwigW.ZeunerM. Hansen

A.Surkov A. Lanaro S.Buontempo

W.Erdmann

tbd tbd –urgent!

G. Bolla M.Gastal C.Schaefer A. Onnela

D.Wood

A.Gaddi

P.Tropea S. Lusin H.Gerwig

P.Tropea

Barrel Mu r/o

C. Bedoya

MB1 TRB

SC move

C. SchaeferW. Zeuner

A. DabrowskiP. Siegrist

M. GastalD. HayP.Petiot

A. Ball

N. Bacchetta

B. Cure

Gas

G. Fetchenhauer

M.Giunta S. Popescu

K.Borras

CO2

H.Postema

T

hese ar

e links to

TC

NOT managem

ent reportin

g lines

Page 7: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Technical Reviews

Principle defined in Constitution of the CMS experiment, Section 6.7:

"Before launching the construction (or modification) of major parts of any CMS sub-detector or sub-system, or engaging in major related expenditures, the Technical Coordinator, with the agreement of the relevant sub-project manager, organizes reviews to confirm the soundness and completeness of the chosen design including the coherence of all interfaces with respect to neighbouring sub-detectors or other parts of CMS; the aim being to minimize risks in cost and schedule". review types: PRR, ECR, ESR, EDR : (follow-ups usually needed)In addition:“Each subdetector will undergo one or more MPRs (Manufacturing Progress Reviews) at strategic moment(s) of the production process. The Technical Coordinator will decide which production processes merit MPR's. The MPR committee will ascertain whether the manufacture is going as planned, whether the quality requirements and milestones are likely to be met and whether the resources (financial and human) required to complete the production are available.”

And in practice we also introduced “installation EDR’s”, prior to installation of items in CMS.

The same review process is being applied to consolidation and upgrade

Page 8: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Consolidation & Upgrade

Done and reports complete or in final editing:

PLT MPR 17 Jun 2011

CASTOR ECR 30 Jun 2011

ME1/1 ECR/ESR 08 Jul 2011

BSC upgrade workshop 22 Jul 2011

YE4 assembly & installation 15 Sept 2011

ZDC crane 28 Sept 2011 (Inst rev still reqd)

Imminent:

PLT MPR follow-up 17 Nov 2011

RPC4 EDR 24 Nov 2011

CASTOR “ show & tell EDR” 14 Dec 2012

Shielding Dec 2012 ??

Reviews and workshops 2011

Page 9: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Common facilities (Surface buildings 678,904,892,SX5)

Common systems (Magnet, RP shielding)

Endcap Muon (YE4)

Tracking (45mm o/d beampipe)

Host lab & Common Project progress

Brief update on some selected projects:

Page 10: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Surface facilities: 678 : 500m2 storage “tent”Critical to the logistics sequence of liberating ISR and re-equipping SX5

Nov 2011: another tent will be needed to clear tooling in ISR

Page 11: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Surface Facilities: 904 zoneA.Sharma, D. Hay

Page 12: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Surface Facilities: 892

Cryo equipment removed.

Floor pits filled.

Platform refurbished.

867 released for LHC radiation w/shops

Outer shell/door still requires work.

Duplicate workshop & ECAL labs displaced from 867 by LHC machine

ECAL test stations

+ETHZ workshop

available again.

867 released for LHC radiation w/shops

Party imminent!

Page 13: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Surface Facilities, Pt 5: SHL

16/03/[email protected]

[email protected]

1’st floor nearing completion

Delivery of pixel cold/clean(ish) lab not possiblein time for YETS 2011-12.Contingency plan in case of BCM/pix removal was to transport to TIF.Blockages due to RP shielding & quake tolerance issuesWill be ready for LS1 for 18 deg operation.

Page 14: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

14

Common Systems, Infra & Facilities: Magnet

Magnetic field off: ~ no useful physicsMagnet on-off-on: limited number of such cycles in lifetime (200-300?)

Highest priority:

Redundant Helium compressor pair

- critical single point failure : 7 mo recovery!

- replacements now only built to order, but provision for redundant pair foreseen

- identified pre-purchases (effectively compressor spares: rotors, bearings etc) to reduce downtime to 1 mo.

- Order placed (CERN funds: contribution or loan)

Benoit Cure

Page 15: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Common Systems, Infra & Facilities: RP shieldsA.Surkov, Wolfram Zeuner

Finalising design of RP shielding from Tracker Bulkhead to 11m . Single set of tooling, supporting shield from below, compatible with all activities.

-Aim to complete design by early autumn.

-EDR this year if possible.-Start manufacture 2011.

-Full test in LS1 (before needed for ALARA)

Page 16: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

New CMS central beampipe

Be

supportBe or AlBe??

oldnew

1630

14501948

=4.9

SS or AlBe?? SS or AlBe??Be

supportBe or AlBe??

oldnew

1630

14501948

=4.9

SS or AlBe?? SS or AlBe??

Issues:

Impedance, HOM etc: shape OKVacuum impedance: OK .Support collar on cone at 1630 mm: OKAperture OK : approved by LEB, LMCMaterials and Construction:Cones 1450 -->1948 machined from AlBeConsidering replacing SS conical section (up to bellowsjunction with Endcap pipe at 3.12m) with AlBe. AlBe to Be braise to be studiedLighter pipe, as strong, reduces sag, activation and backgrounds, eliminates transition piece.

3120

CMS E & I, for C. Schaefer

support

Ball, Bacchetta, Schaefer, Zeuner, EIC, TE-VSC

Page 17: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Beampipe upgrade: simulation

• New geometry implemented in FLUKA Changes:

– Radius of cylindrical part smaller– Conical part changed from stainless steel to AlBeMet.– Pixel layer 1 at smaller radius

• Simulations use beam background simulated by N.Mokhov

Moritz Guthoff – Staus: CMS BRM

Moritz Guthoff - Staus CMS BRM

PIXEL

Conical BP & flangeSt.steel->AlBeMetCylindical BP

(Smaller)

OLD

Page 18: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

6.10.2011 Moritz Guthoff - Staus CMS BRM6.10.2011 Moritz Guthoff - Staus CMS BRM 18

Chargedhadrons

neutralhadrons

electrons

OLD NEWPIXEL

BEAM

Prelim

inary

Page 19: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Endcap Muon Upgrade

YE4 shielding disk: material qualified, first steel sector cases being assembled Complex assembly tooling designed and in purchase procedure. “push-back” system nearing completion. Assembly EDR held in Sept

CSC4, RPC4, ME1/1 front end: Review process ongoing .

Page 20: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

YE4 shielding disk: milestones

NB

Date format

!!!!!

Page 21: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Tracking (Pixel/beampipe) upgrade timing

Milestones for new beampipe

Mechanical params for aperture calc Jun 2011 CompleteMaterial (!) and integration studies July 2011 CompleteLEB approval Aug 2011 CompleteLMC approval Aug 2011 CompleteCall for tender Sept-Nov 2011 CompleteFC approval Dec 2011Finalise design Jan 2012EDR Jan 2012Place order: Feb 2012Delivery at CERN: mid 2013Testing complete Nov 2013 leaves time for 1 weld re-work.Ready for installation Dec 2013 milestone in common with LHC

Page 22: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

LHCC Milestone Level definitions

Level 1 milestones: are derived from the overall planning for CMS assembly & usually represent changes of dominant activity on the critical path

towards readiness for beam operation.

Level 2 milestones: are defined by sub-system managers and represent keybenchmarks in sub-detector progress towards the relevant level 1 milestones.Level 3 milestones: are defined by sub-system managers to complement the level 1 and 2 milestones by providing a more detailed breakdown of objectives and a mechanism for intermediate monitoring of major tasks in progress.

L2 “ready for installation” milestones and “schedule float”- L2 “ready for installation” milestones mark the date from which a major section of the detector is intended to be ready be used in the master assembly sequence.- They allow flexibility in tuning the master assembly sequence without impacting subdetector planning.

- The target float from the critical path is 3 months (usable as contingency during last year of construction, by agreement with Technical Coordination).

from LHCC meeting, 15 June 2004, updating 15 Mar 1999

Page 23: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Example: v34.2 UX schedule overview

Level 1 milestones mark major activity changes on CPLevel 2 RFI milestones show the latest date where anitem is "on the shelf " ready to use on CP.

Page 24: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

YETS 2011-12: Focus now P-spikes 18.3m R5

Suspects: physical aperture problem desorption instability due to adsorbed gas

TC CONSIDERS THIS THE DOMINANT KNOWN RISK TO 2012 OPERATION

YETS 2011-12 planning is therefore being re-designed to give priority to:

• Radiography of both ends around this region and survey check from 13m to 50m.

• Bakeout –z end beampipe for 18 3 m ( same for +z end if radiography reveals no fault)

• Activate a so far unused NEG cartridge to double the pumping speed (increased threshold for desorption instability)• Install additional instrumentation in the 18 3 m region.

THIS ACTIVITY IS INCOMPATIBLE WITH OPENING THE YOKEbut the planned programme with yoke closed can still be done – with added difficulty

Page 25: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

YETS 2011-12 main activities

Survey, radiography and bakeout of 18 3 m region

Installation of the much-delayed ZDC crane (last chance - activation) Validate CASTOR calorimeter insertion with beampipe at vacuum. Install PLT demonstrator on CASTOR table at +z end (subject to MPR 17 Nov) Remove BSC to preserve for heavy ion programme

provide for tests of BSC 2 technology (focussed on beam-halo) Replace components in one HF RBX’s Install CSC4/RPC4 posts and RE4 demonstrators Re-work Muon Barrel DT system LV connectors New crane in CV room

Obligatory & advisory annual maintenance of services Tests of AUG, Diesel backup, Evacuation etc Re-verification of alarm action matrix (minimising collateral damage risks)

Input from Divonne TC workshop: 17 weeks needed to justify opening detector.Including vac work, 20 weeks would now be needed. Little prospect of getting a head start on LS1 work (such as Tracker humidity seal)

Page 26: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Draft LHC baseline planning LS124 months physics to physics, 20 months beam to beam

Input from CMS: need 20 months, starting no earlier than Dec 2012

Sequencing &Co-activity beingunderstood.

Timeframes less convincing

LHC preferred startdate 17 Nov.

Many resources from Institutes-Interference with-expt resources?

Page 27: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

CMS draft planning LS1Martin Gastal: for detail see his talk

Tracker cold operation is given priority : leads to complex logisticsCMS need 24 months beam to beam to be comfortable: working on alternative sequences

Nominal BP RFI

Beampipe installed

Await tender discussions to see if it could work

Page 28: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

LHC plan post-LS1 & phase 1 pixel insertion

Case made to LMC for beampipe approval Aug 2011:

Unless we think there is a possibility of phase1 pixel being ready in late 2014, we should stick with this message: synergy with LINAC4 connection is likely.

Page 29: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Concerns: there are many!

-Cash needed in 2011- 2014

-Likelihood of a chaotic year for finances in 2012

-Maintaining the base of technically competent personnel eg common systems experts field coordinators

-Draft LS1 plan: beampipe rfi is lateHO HPD —> SiPM on YB0 is high risk and lengthycontingency for re-opening after CRAFT has started insufficient24 months beam-to-beam needed to be comfortable

-YE4 delivery: assembly pushes RP area completion in SX5 into LS1

-SX5 (OSC+ SL53) facility progress slow/blocked

-Completing retreat from ISR

Page 30: Upgrade workshop FNAL Nov 2011 AB Technical Coordination Technical Coordination Session Technical Coordination for Upgrade (Austin Ball) 20 mins Responsibilities

Upgrade workshop FNAL Nov 2011 AB

Technical Coordination

Host Lab & Common Project 2012-14

Facilities: 904, SX5 (OSC) completion, additional buildings to house remaining ISR equipment.

Magnet & Common SystemsRP shielding, Opening system consolidation. Cryo compressor redundancy.UPS system extension in USC.

Endcap MuonYE4, YE4 pushbackYE3 manifold mods for RE4, (YE1 cooling manifold accessibility?)

TrackerBeampipe, Humidity Control (seal), N2 high capacity, CO2 cooling integration.

>3CASTOR insertion with bp at vacuum, beampipe support consolidation

As in other projects, will need to decide what’s essential?