  • Upgrade to SAP NetWeaver ProcessIntegration 7.3

    Sujit HemachandranProduct ManagementSAP NetWeaver Process IntegrationSAP Labs India

    December 2010

  • 2010 SAP AG. All rights reserved. / Page 2

    Upon completion of this presentation, you will be able describe :? The upgrade paths to SAP NetWeaver PI 7.3? The Configuration Templates provided for easy upgrade and PI Robustness

    Objectives

  • 2010 SAP AG. All rights reserved. / Page 3

    Agenda

    SAP NetWeaver PI 7.3 Value Proposition and TimelinesUpgrade to SAP NetWeaver PI 7.3

    PI Robustness Configuration Template

  • 2010 SAP AG. All rights reserved. / Page 4

    SAP NetWeaver Process Integration 7.3Value Proposition

    Reliable Messaging and Queuing

    Software LifecycleSecurity

    User Management

    ScalabilityHigh Availability

    Archiving

    ConfigurationMonitoring

    Administration

    Dynamic Routing Transformation Connectivity

    Infrastructure Services Java EE5 / ABAP

    EventsProcess

    Automation

    Repository and Governance? Improved design governance? Eclipse-based design time for service

    provisioning? Unified WS-RM compliant event provisioning

    and subscription

    Service Bus? Single stack ESB capabilities via AAE? Increased productivity & richer connectivity

    on AAE? Processing of very large files? Support of pub / sub scenarios? Adoption of standards (SOAP 1.2, WS

    Policy 1.2, WS Trust 1.3, Java SE 6 )

    Unified Lifecycle Management? Central monitoring via SAP Solution

    Manager? Search for payload attribute values? Improved upgrade and fault tolerance

    Process Integration

    Service Bus

    User Interaction (for example, Business Task Management)

    B2B Partner3rd Party

    Middleware3rd Party

    ApplicationSAP

    Services Registry

  • 2010 SAP AG. All rights reserved. / Page 5

    Planned Timeline*

    2010 2011

    SAP NetWeaver 7.3

    Ramp-up start started onNov 29*.

    ** Ramp ups are scheduled up to 6 months might beclosed earlier depending on fulfillment of KPIs.

    *Future dates are subject to change.This presentation and SAP's strategy and possible future developments are subject to change and may bechanged by SAP at any time for any reason without notice. This document is provided without a warrantyof any kind, either express or implied, including but not limited to, the implied warranties of merchantability,fitness for a particular purpose, or non-infringement.

    SAP Solution Manager 7.1Ramp-up start scheduled for Q2 / 2011**

    End of maintenance? SAP XI 3.0: Mar. 2010 (+ 3 years ext. maint.)? SAP NetWeaver PI 7.0x, 7.1x: Dec. 2015 (+ 2 years ext. maint.)? SAP NetWeaver 7.3: Dec. 2015 (+ 2 years ext. maint.)Further information at http://service.sap.com/pam

  • 2010 SAP AG. All rights reserved. / Page 6

    Agenda

    SAP NetWeaver PI 7.3 Value Proposition and TimelinesUpgrade to SAP NetWeaver PI 7.3

    PI Robustness Configuration Template

  • 2010 SAP AG. All rights reserved. / Page 7

    Upgrade or New Installation?

    New Installation of SAP NetWeaver PI

    ?Transport of software components into the Enterprise Services Repository

    ? Transport of configuration objects into the Integration Directory

    ? Move systems from your XI 3.0/SAP NetWeaver 7.0 system to newSAP NetWeaver PI system

    ? Use new SAP NetWeaver PI for new integration scenarios

    Support

    ? SAP NetWeaver RIG How-To Guide(http://www.sdn.sap.com/irj/sdn/howtoguides)

    ? SAP Consulting Services

  • 2010 SAP AG. All rights reserved. / Page 8

    Direct Upgrade Paths

    SAP NetWeaver 04SAP XI 3.0

    SAP NetWeaver 7.0

    SAP NetWeaver 7.0,EHP 1

    SAP NetWeaver 7.0,EHP 2 (planned)

    SAP NetWeaver PI 7.1

    SAP NetWeaver PI 7.1,EHP 1

    SPS 15

    SPS 05

    Highestposs. SPS

    SAP NetWeaver Process Integration 7.3

    Release Upgrade Update EHP

    SAP SPS *

    * Refer to PAM

  • 2010 SAP AG. All rights reserved. / Page 9

    Syte

    Upgrade Phases

    Planning

    TechnicalDowntime

    UpgradePreparation

    BusinessDowntime

    Upgrade Roadmap Steps

    Post-Upgrade Tests

    System Downtime

    Reduce system downtimeduring Post-Upgrade

  • 2010 SAP AG. All rights reserved. / Page 10

    Upgrade PhasesPost Upgrade (Follow Up Acitvities)

    ?Upgrade procedure contains up to 43 manual follow up activities?depending on OS/ database?29 done at system downtime

    ? Step automation with Central Technical Configuration (CTC) Templates

    ? Steps chosen because ofhigh impact onbusiness downtime? Eight steps automated? Five steps no longer needed? Two partially automated? Leaves 14 manual activites

    during downtime

    Before

    Now

  • 2010 SAP AG. All rights reserved. / Page 11

    Improved Post- Upgrade ProcedureAutomated Steps

    As of SAP NetWeaver PI 7.1, EHP 1, SPS 4

    ? Performing Follow-Up Activities for Service Users?Switch some users from type Service to System?Assign new composite roles to technical users

    ? Performing Queue Registration?Enhanced functions of qRFC inbound queues as of PI 7.1?Register further qRFC inbound queues

    ? Adjusting the Exchange Profile?Adjust property com.sap.aii.connect.integrationbuilder.startpage.url

    ? Activating the ICM Service? For security reasons upgrade program disables Internet Communication

    Framework (ICF) services during upgrade?Activate required services after the upgrade

  • 2010 SAP AG. All rights reserved. / Page 12

    Improved Post- Upgrade ProcedureAutomated Steps

    ? Performing Follow-Up Activities for System Landscape Directory?Depend on former setup

    ? Importing ESR Content for Software Component SAP_BASIS?Content is part of the SCA? Import it into system

  • 2010 SAP AG. All rights reserved. / Page 13

    Improved Post- Upgrade ProcedureAutomated Steps

    As of SAP Netweaver 7.30

    ? Creating Java RFC Destination BusinessProcessEngine_RFC? Description for the ccBPM monitoring

    ? Creating ABAP Background Jobs?

    Details in SAP Note 1321868

  • 2010 SAP AG. All rights reserved. / Page 14

    Upgrade Guide SAP NetWeaver PI 7.1, EHP 1

    SAP Service Marketplace

    service.sap.com/instguides

  • DemoDEMO

  • 2010 SAP AG. All rights reserved. / Page 16

    CTC Templates/Wizards for SAP NetWeaver PIRelease Upgrade, Upgrade EHP, SPS

    ? PI Upgrade - SAP Note 1321868?7.11: SPS4 Patch 0?7.30: SPS0 Patch 0

    ? PI Upgrade EHP - SAP Note 1450419?7.30: SPS0 Patch 0

    ? PI / ESR Support Package Update - SAP Note 1444305?7.30: SPS0 Patch 0

  • 2010 SAP AG. All rights reserved. / Page 17

    Ramp UP Knowledge TransferUpgrade Workshop

    ?With RTC (Release to Customer) planned for next year, 2011

    ? Two days upgrade workshop?Participants upgrade a SAP NetWeaver 7.0 to a SAP NetWeaver 7.3 system

    ?Currenty planned agenda?Overview of Upgrade/Update?Phases of the technical upgrade (sync points between ABAP and Java)?PI Specific points?Migration Controller?Preparation Steps?References and Further Information

  • 2010 SAP AG. All rights reserved. / Page 18

    Agenda

    SAP NetWeaver PI 7.3 Value Proposition and TimelinesUpgrade to SAP NetWeaver PI 7.3PI Robustness Configuration Template

  • 2010 SAP AG. All rights reserved. / Page 19

    CTC Template/Wizards for SAP NetWeaver PIFunctional Wizards

    ? PI SLD Self Registration - SAP Note 1439558? 7.10 SP5 Patch 8, 7.11 SP1 Patch 0, 7.30 SP0 Patch 0

    ? PI Demo Client - SAP Note 1304208? 7.11 SP0 Patch 0, 7.30 SP0 Patch 0

    ? PI Full Qualified Host Name - SAP Note 1320707? 7.11 SP1 Patch 0, 7.30 SP0 Patch 0

    ? PI Adapter Engine in Java Proxy Runtime Mode - SAP Note 1346933? 7.11 SP4 Patch 0, 7.30 SP0 Patch 0

    ? PI Robustness Configuration - SAP Note 1400543? 7.30 SP0 Patch 0

    ? PI Single Sign-On Configuration - SAP Note 1473556? 7.30 SP1 Patch 0

    ?PI Self Test for SAP NetWeaver - SAP Note 1286149PI Wizards Overview SAP Note 1286428

  • 2010 SAP AG. All rights reserved. / Page 20

    PI Robustness Configuration

    ?Wizard reads all PI-relevant AS ABAP and ASJava system parameters

    ? Makes suggestions for a consistent overall configuration

    ? Test and productive execution mode available

    ? Configuration Wizard: SAP Note 1400543

    ? Parameter description SAP Note 1375656

  • 2010 SAP AG. All rights reserved. / Page 21

    CTC Template/Wizards for SAP NetWeaver PISystem Copy Wizard and Initial Setup

    ? Performing a PI system copy SAP Note 1299373

    ? As of SAP Netweaver PI 7.3

    ? Automated steps for Integration Server, SLD and Exchange Profile

    ? Improved and extended templates for initial setup

    ? More detailed options to define passwords

    ? Destinguish between local and central SLD setup

    ? SSO for AS Java Stack

  • 2010 SAP AG. All rights reserved. / Page 22