UPDATES ON THE IMPLEMENTATION OF SHS
SHS SLOTS OF DEPED AND NON-DEPED SCHOOLS PER PROGRAM
PROGRAM DEPED NON-DEPEDACADEMIC 3040
STEM 420ABM 720HUMS 480GAS 1440
TECH VOC 2240ARTS & DESIGN 160SPORTSTOTAL 5440
TVIs that DepEd can Partner
TESDA Accredited Training and Assessment Centers- Extendicare, Dagupan City- UNICARE, Dagupan City- MAXIMA Tech Skills, Dagupan City- TESDA, Binmaley, Pang.- ScribeFast Transcription Training Center, Dagupan
City- TechSkills Phils., Dagupan City
INITIATIVES ON TEACHER HIRING
Conduct preliminary steps:– Identify the Needed Teachers per
specialization/track offering per school.– Publish the Teacher Needs in the conspicuous place
in the division office.Request for the Teacher NeedsFollow up the NOSCA for the new teacher itemsPublish allocated teaching items for the SHSAccept applications for screening
INITIATIVES ON SECURING EQUIPMENT
• Provide a list of equipment needed specialization and track offerings
• Coordinate with the LGU and provide them the listing for possible funding.
• Include in the APP for the LSB• Present the list to potential stakeholders during
the stakeholders meeting• Provide TA to schools on how to secure
equipment to possible stakeholders.
GEOGRAPHIC MAP OF SHSDagupan City Division
7. Federico Ceralde Integrated School
2. Bonuan Boquig National High School
8. Pugaro Integrated School
3. Judge Jose de Venecia Sr. MNHS
6. East Central Integrated
School1. Dagupan City National High School
4. Carael National High
School
5. Salapingao NHS
Blue balloons – Public SHS
UPDATED TIMELINEActivities TimelineOn Teachers Hiring October 2015-May 2016
Classrooms
Start of bidding process for new classroom bldg construction
October – December 2015
Construction of new classroom bldg October 2015 May 2016
Ocular inspection for the readiness of classrooms May 2016
Seats Ready
Account for the needed seats for the SHS October – December 2015
Procure the needed seats. January – March 2016
Deliver the needed seats to the schools April – May 2016
Instructional Materials Ready
Determine the needed Instructional Materials per area. Oct – Nov 2014Start of the procurement process October – Nov. 2015Procure the needed Instructional materials following the procurement process
December 2015 –March 2016Distribute/Deliver the IMs to the schools. April 2016
Activities TimelineScience Laboratories Ready
Determine the number of Science Laboratories to be constructed
Oct – Nov 2014Start of bidding process for the construction of new science laboratories
Nov. – December 2015Construction of the science laboratories December 2015 –March 2016Inspection and turnover of the said laboratories April 2016
Computer Laboratories Ready
Determine the number of Computer Laboratories to be constructed
Oct – Nov 2014Start of bidding process for the construction of new computer laboratories
Nov. – December 2015
Construction of the computer laboratories December 2015 –March 2016Inspection and turnover of the said laboratories April 2016
Water and Sanitation Facilities Ready
Determine the needed WATSAN facilities Oct – Nov 2014Start of the procurement process Nov. – December 2015Installation/construction of the needed WATSAN facilities December 2015 –March 2016Inspection of the readiness of the WATSAN facilities April 2016
Activities Timeline
Tracks/Strands Specific Materials, Facilities, and Equipment ReadyConduct inventory of the materials, facilities and equipment needed per track/strandsCoordinate with partners for the provision of the needed materials
Jan 2015 – May 2016
Forge a MOA/MOU with the identified partners
Libraries Ready
Start of procurement process Oct – Nov 2014Constructiion of new libraries and Library Hub for the Division
Nov. – December 2015Installation of needed facilities and equipment inside the library
December 2015 –March 2016Acquisition/procurement of books/reference materilas needed for the particular track/strand
April 2016
Agreements finalized formally (e.g. MOA or MOU)
Conduct meetings/conferences/SHS Summit with partnerts/ stakeholders
Jan 2015 – May 2016
Forge a MOA/MOU with the partners/stakeholders