updated resettlement plan subproject of guihua bridge ... · number parameter unit...

80
Resettlement Planning Document The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff and may be preliminary in nature. Document Stage: Final Project Number: 42012 July 2014 Updated Resettlement Plan Subproject of Guihua Bridge-Shilongping Road of Wushan County Under PRC: Chongqing Urban–Rural Infrastructure Development Demonstration Project Prepared by Chongqing Duojie Investment Consulting Co., Ltd. Chongqing Municipality, PRC

Upload: others

Post on 02-Nov-2019

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

Resettlement Planning Document

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those

of ADB’s Board of Directors, Management, or staff and may be preliminary in nature.

Document Stage: Final Project Number: 42012 July 2014

Updated Resettlement Plan Subproject of Guihua Bridge-Shilongping Road of Wushan County Under PRC: Chongqing Urban–Rural Infrastructure Development Demonstration Project

Prepared by Chongqing Duojie Investment Consulting Co., Ltd.

Chongqing Municipality, PRC

Page 2: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework
Page 3: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

ADB-funded Chongqing Urban–Rural Infrastructure Development

Demonstration Project

Guihua Bridge-Shilongping Road of Wushan County

Final Resettlement Plan

People’s Government of Wushan County

Chongqing Duojie Investment Consulting Co., Ltd.

China·Chongqing

July 2014

Page 4: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 - 1 -

Content

EXECUTIVE SUMMARY .............................................................................................................................................. 1

A. Project Background Information .................................................................................................................................... 1

B. Scope of Land Acquisition ............................................................................................................................................. 1

C. Information Disclosure,Participation and Grievance .................................................................................................. 2

D. Legal Framework and Compensation rate ..................................................................................................................... 2

E. Relocation and Income Restoration ................................................................................................................................ 3

F. Resettlement Cost Estimation and Management ............................................................................................................. 3

G. Organizations and Implementation Plan ........................................................................................................................ 3

H. Monitoring and Evaluation ............................................................................................................................................ 3

1 PROJECT DESCRIPTION .......................................................................................................................................... 4

1.1 Introduction .................................................................................................................................................................. 4

1.2 Project Profile ............................................................................................................................................................... 4

1.3 Project Impacts ............................................................................................................................................................. 5

2 SCOPE OF LAND ACQUISITION, DEMOLITION AND RELOCATION ........................................................... 1

2.1 Permanent Land Acquisition ......................................................................................................................................... 1

2.1.1 Statistics of Permanent Land Acquisition .................................................................................................................. 1

2.1.2 Impacts Analysis of Farmland Land Acquisition ....................................................................................................... 2

2.2 Temporary Land Occupation ........................................................................................................................................ 3

2.3 House Demolition and Impacts Analysis ...................................................................................................................... 3

2.4 Attachments and Fruit Trees ......................................................................................................................................... 4

3 SOCIO-ECONOMIC SURVEYS ................................................................................................................................. 2

3.2 Social and Economic Status Quo of the Rural Towns Involved ................................................................................... 2

3.3 Social and Economic Status Quo of the Villages Involved ........................................................................................... 3

3.4 Social and Economic Status Quo of the Households Affected by the Project .............................................................. 4

3.4.1 Demographics of Affected Persons ............................................................................................................................ 5

3.4.2 Landownership Condition.......................................................................................................................................... 6

3.4.4 Income Condition ....................................................................................................................................................... 7

3.4.5 Expenditure Status Quo ............................................................................................................................................. 8

3.4.6 Income and Expenses Analysis .................................................................................................................................. 9

3.5 Impacts on the Vulnerable Groups ................................................................................................................................ 9

3.6 Survey on Aspiration of Relocations of Persons Affected ............................................................................................ 9

4 PUBLIC PARTICIPATION AND APPEAL MECHANISM .................................................................................... 11

4.1 Public Participation Program ...................................................................................................................................... 11

4.1.1 Public Participation in Progress ............................................................................................................................. 11

4.1.2 Public Participation Plan of the Next Stage ............................................................................................................ 12

4.2 Appeal Mechanism ..................................................................................................................................................... 13

5 LEGAL FRAMEWORK AND RESETTLEMENT POLICY ................................................................................. 15

5.1 ADB Resettlement Principles ..................................................................................................................................... 15

Page 5: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 - 2 -

5.2 ADB Resettlement Laws and Policy Basis ................................................................................................................. 18

5.2.1 Relevant Laws and Regulations of Chinese and Local Governments ...................................................................... 18

5.2.2 Relevant Policies of ADB ......................................................................................................................................... 19

5.3 Compensation Rate ..................................................................................................................................................... 19

5.3.1 Compensation Principles ......................................................................................................................................... 19

5.3.2 Compensation Rate .................................................................................................................................................. 19

5.4 Eligibility and Entitlement Matrix .............................................................................................................................. 22

6 RESETTLEMENT AND RESTORATION OF INCOMES SCHEME .................................................................. 25

6.1 Demolition and Relocation ......................................................................................................................................... 25

6.1.1 Demolition and Relocation Objectives .................................................................................................................... 25

6.1.2 Demolition and Relocation Scheme ......................................................................................................................... 25

6.1.3 Demolition and Relocation of the Affected Persons................................................................................................. 26

6.1.4 Compatibility Analysis of the Relocation Sites ........................................................................................................ 27

6.1.5 Concerns for the Vulnerable Groups ....................................................................................................................... 27

6.2 Restoration of Incomes ............................................................................................................................................... 27

6.2.1 Income Objectives and Content ............................................................................................................................... 27

6.2.2 Income Loss Assessment .......................................................................................................................................... 27

6.2.3 Income Restoration Plan ......................................................................................................................................... 28

6.3 Special Concerns ........................................................................................................................................................ 33

6.3.1Concerns for Women ................................................................................................................................................. 33

6.3.2 Income Restoration Support of the Vulnerable Groups ........................................................................................... 33

6.4 Restoration of the Temporary Land Occupation ......................................................................................................... 33

7 RESETTLEMENT COST ESTIMATION AND MANAGEMENT ........................................................................ 34

7.1 Resettlement Cost Estimation ..................................................................................................................................... 34

7.2 Source of Fund ............................................................................................................................................................ 36

7.3 Resettlement Cost Management ................................................................................................................................. 36

8 ORGANIZATIONS ..................................................................................................................................................... 38

8.1 Organizations Involved in the Resettlement ............................................................................................................... 38

8.2 Responsibilities of the Organizations ......................................................................................................................... 38

8.3 Organizational Capability ........................................................................................................................................... 42

9 IMPLEMENTATION PLAN ...................................................................................................................................... 44

10 MONITORING, EVALUATION AND REPORTING SYSTEM ....................................................................... 46

10.1 Internal Monitoring and Evaluation .......................................................................................................................... 46

10.1.1 The Internal Monitoring Institution ....................................................................................................................... 46

10.1.2 Internal Monitoring Objective ............................................................................................................................... 46

10.1.3 The Main Content of the Internal Monitoring ....................................................................................................... 47

10.1.4 Internal Monitoring Report ................................................................................................................................... 47

10.2 External Monitoring and Evaluation ........................................................................................................................ 47

10.2.1 External Monitoring Institution ............................................................................................................................. 47

10.2.2 External Monitoring Objectives ............................................................................................................................. 47

10.2.3 External Monitoring and Evaluation Method ........................................................................................................ 48

10.2.4 Main Tasks ............................................................................................................................................................. 49

10.2.5 External Monitoring and Evaluation Report ......................................................................................................... 49

Page 6: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 - 3 -

Appendix 1 Resettlement Information Brochure (RIB) .............................................................................................. 50

附件 2 巫山县补偿文件 ............................................................................................................................................... 55

Page 7: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 1

Page 8: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 1

EXECUTIVE SUMMARY

A. Project Background Information

Guihua Bridge-Shilongping Road in Wushan County, Chongqing is in construction design

phase now, of which the compilation work of The Feasibility Study Report has been finished in

December 2013.

According to the requirements of ADB, The Resettlement Plan of this project is

required prior to approval of contract awards and start of land acquisition.

Chongqing Duojie Investment Consulting Co., Ltd. has been entrusted by the owner to

launch a socio-economic survey on the relevant villages and groups as well as the affected

persons alongside the Guihua Bridge-Shilongping Road with the cooperation of the related

departments of local villages and towns. DMS was conducted in June 2014 by the county land

resource bureau and the relevant townships and villages.

The compilation of The Resettlement Plan aims to guarantee that the living standard of

persons affected by the land acquisition will be improved or at least equivalent to that which they

had without the project.

B. Scope of Land Acquisition

Land acquisition in this project will affect 5 groups of 3 villages in 2 towns. The permanent

acquisition of 551.37mu collective land, among which there is 54.03mu farmland, 392.03mu

woodland and 105.31mu wasteland, will affect 278 households with 1198 persons. 185.41mu

temporary land occupation, including 18.19mu farmland, 131.78mu woodland and 35.45mu

wasteland, will affect 99 households with 414 persons. Demolition area amounts to 2889.30m2,

all of which are rural houses, including 1453.51m2 masonry-concrete structured houses,

437.66m2 masonry-timber structured houses, 914.01m

2 cob wall houses and 83.85m

2 simple

structured houses, affecting 14 households with 73 persons in total.

Page 9: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 2

C. Information Disclosure,Participation and Grievance

During the socio-economic survey in Feb. 2014, all of the affected households, villages,

village cadres and governments of towns and county have participated in it mainly by means of

taking part in the conferences, interviews, key group interviews, public participation activities,

community consultations and so on. Now the county government, the implementing organization

and village cadres are consulting and discussing with the representatives of the affected persons

about the impacts and compensation scheme to protect the benefits of affected persons and

provide income restoration program for them. The resettlement plan will be published on the

ADB’s website. Land acquisition and The Resettlement Information Brochure, which contains

land acquisition condition, resettlement progress and procedure, compensation rate, resettlement

allowance, livelihood restoration measures and so on, will be provided to the affected households

as soon as possible before the RP disclosure by ADB.

D. Legal Framework and Compensation rate

Land acquisition and resettlement compensation rate will adhere to the Wushan Government

Document 28 (2013) and ADB’s Policy on Involuntary Resettlement. Rural farmers who will

suffer partial land loss but will not become urban residents will be offered cash compensation

based on the quantity of land loss, compensation for crops and cash or in-kind support based on

the willingness of affected persons for livelihood restoration. The restoration measures include:

encouraging them to buy the urban endowment insurance; providing them with employment

opportunities during the project construction and operational phases; developing economic crops

with higher economic value; promoting and developing new enterprises and secondary and

tertiary businesses; and providing technical training to the affected persons to increase their skills

and promote employment.

Page 10: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 3

E. Relocation and Income Restoration

The per capita income loss for the affected village is as follow: Lizao village is 61 RMB; Guihua

village is 52 RMB, Qixing village is 45 RMB. Income loss of the affected persons in consequence of

the acquisition of farmland will be restored by compensation allowance, benefits for changing

from “agricultural to non-agricultural” status, technical training, recommended employment,

provision of micro credits and some other ways to make sure that the standard of living for

affected persons is at least equivalent to that which they had “without the project”.

F. Resettlement Cost Estimation and Management

The resettlement cost road project of the Guihua Bridge-Shilongping in Wushan County

totals to RMB37,612,200 yuan, accounting for 27% of the total investment of the Project. The

cost of LAR includes RMB22,795,600 yuan of basic charge, RMB2,735,500 yuan of management

and monitoring cost, RMB9,801,600 yuan of land acquisition taxes and dues and RMB2,279,600

yuan of contingencies. The resettlement cost is all from counterpart funds. The compensation will

be firstly allocated to the land acquisition agencies. Then the land acquisition agencies will

compensate the affected persons according to the land acquisition area.

G. Organizations and Implementation Plan

The organizations of the road project include the leading unit and the implementing unit. The

leading unit includes the Wushan County project leading groups and Wushan County project

management office. The implementing unit includes Wushan County Transportation Development

Co., Ltd(IA)., resettlement management office and cadres groups from towns and villages and so

on.

H. Monitoring and Evaluation

According to the ADB, internal and external monitoring of resettlement plan

implementation will be conducted in this project. Each project implementing unit will conduct

internal supervision and monitoring to ensure compliance with the provisions of the resettlement

Page 11: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 4

plan. An independent agency will be organized by Halcrow Union Consulting Company) by

means of bidding to conduct external monitoring and evaluation. Semi-annual external

resettlement monitoring reports will be forwarded directly to both the Chongqing Municipal

PMO (CPMO) and ADB.

1 PROJECT DESCRIPTION

1.1 Introduction

This resettlement plan is made according to the Asian Development Bank (ADB)’s Policy on

Involuntary Resettlement (SPS 2009), other social security and social principles, the laws and

regulations of the People's Republic of China (PRC), the relevant land acquisition policies of

governments of Chongqing and Wushan County. This plan has summarized those policies

mentioned above and come up with effective measures to reduce the negative impacts caused by

the project by means of a series of public participation activities and sufficient consultations.

The Resettlement Plan is based on: (i) The detailed design (prepred on May 2014) and

design unit’s discussions; (ii) field investigation in the relevant area; (iii) consultations and

discussions with the representatives of the affected households, government officers of the

affected municipality and towns, cadres of the affected villages and societies and affected

persons; (iv) the socio-economic survey on the affected households conducted in December 2013

and February 2014.

1.2 Project Profile

With the overall length of 12.2km, the road project of the Guihua Bridge-Shilongping

section of Wushan County starts from the east side of Guihua Bridge in Guihua Village and ends

in Shilongping of the Provincial Highway S103, whose former name is National Highway G348.

Guihua Bridge-Zaoyang Tourism District section is four-lane sub-arterial road. Zaoyang Tourism

District-Shilongping section is a tertiary highway.

Map 1-1 shows the road alignment and geographical location.

Page 12: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 5

Figure 1 – Road Location

Table 1-1Main Technical Parameters

Number Parameter Unit Quantities/indicator

1 Road Length km 12.2

Width m 8.5m

2

Class m3 III

Earthwork m3 141460

Stonework m3 330074

3 Protection and Drainage m3 102324

4 Surface m2 116190

5 Culvert path 40

6 Bridge 3

7 Occupation of Land (Permanent) mu 451

8 Construction Safety Cost Estimation ten thousand 9792

9 Average Cost of Per Kilometer ten thousand 802.6

1.3 Project Impacts

Land acquisition in this project will affect 5 groups of 3 villages in 2 towns. The permanent

acquisition of 551.37mu collective land, among which there is 54.03mu farmland, will affect 278

households with 1198 persons. 185.41mu temporary land occupation, including 18.19mu

farmland, will affect 99 households with 414 persons. Demolition area amounts to 2889.30m2,

Page 13: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 6

including 1453.51m2 masonry-concrete structured houses, 437.66m2 masonry-timber structured

houses, 914.01m2 earthen-wall houses and 83.85m

2 simple structured houses.

To reduce the negative impacts of the project on the local social and economic aspects, the

design unit and the project owner : (1) optimized the plan in the design phase on the basis of

reducing the amount of permanent land acquisition and temporary land occupation as far as

possible; (2) will take remedial actions to reduce the negative impacts of the project on the

livelihood of the affected persons as far as possible when the land acquisition and demolition are

unavoidable.

According to the design, there are 2 schemes of the project. The final design is the best one

chosen in consideration of land acquisition. See Table1-2 for a comparison of the impact of land

acquisition and resettlement between the design before and after optimization.

Table1-2 Comparison of Design Alternatives

Proposal 1 (for comparison) Proposal 2 (recommended)

Impact

comparison

1. The collective land to be permanently

acquired is over 618.2mu.

2. Residential houses of 24 households

have to be demolished.

3. About 1527 persons are affected by the

land acquisition.

3. The budget for land acquisition,

demolition and resettlement is about

41.4526million yuan.

1. The collective land to be permanently

acquired is over 551.37mu.

2. Residential houses of 14 households have

to be demolished.

3. About 1198 persons are affected by the

land acquisition.

3. The budget for land acquisition,

demolition and resettlement is about

37.6122million yuan.

The optimization of the RP reduces about 66.83mu land to be permanently acquired and

decreases 10 households to be demolished, persons affected by the land acquisition decreases

329 persons and the cost of land acquisition and resettlement decreases by approximate 3.8404

million yuan.

Page 14: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 1

2 SCOPE OF LAND ACQUISITION, DEMOLITION AND

RELOCATION

2.1 Permanent Land Acquisition

2.1.1 Statistics of Permanent Land Acquisition

The project will acquire 551.37mu collective land, among which there is 54.03mu farmland,

392.03mu woodland and 105.31mu wasteland. It will affect 5 groups of 3 villages in 2 towns,

which include 278 households with 1198 persons.

The specific amount of the land acquisition is available in Table 2-1 and the land types

acquired can be seen in Picture 2-1.

The land types being acquired in this project mainly include farmland, woodland and

wasteland.

1, According to the survey, all of the farmland being acquired are dry land. Crops involved

include wheat, corn, sweet potatoes, potatoes, vegetables and so on;

2, Land area acquired by this project suffers from soil depletion and the soil is thin. The

woodland area mainly grows small shrubs and herbaceous plants. There are a few shrubwoods

around the residential area, most of which are cypresses and deciduous shrubs, no rare tree

species;

3, The acquired area by this project is full of high mountains and steep slopes, with the soil

thin and vegetation sparse. In addition, people living there also contribute to the water loss and

soil erosion of the area and the relatively serious stony desertification of the soil. As a result of

this, there exists large scale of wasteland.

Table 2-1 Permanent Land Acquisition

Subitem Administrative Division Affected

Household

Affected

Persons Subtotal

Land Types

Town Village Group Farmland Wasteland Woodland

the Guihua

Bridge-Shil

Longmen

Office

Lizao

Village

6 71 302 134.82 13.21 25.75 95.86

3 13 56 50.12 4.91 9.57 35.64

Page 15: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 2

ongping

Section WuxiaTown

Guihua

Village

4 57 244 96.22 9.43 18.38 68.41

5 125 545 250.62 24.56 47.87 178.19

Qixing

Village 4 12 51 19.59 1.92 3.74 13.93

Total 278 1198 551.37 54.03 105.31 392.03

Note: The numbers source from the detailed construction design and field investigation.

2.1.2 Impacts Analysis of Farmland Land Acquisition

According to the survey, 115 of the 278 affected households will be affected by the

farmland acquisition. 163 of the 278 affected households will only be affected by the woodland

and wasteland acquisition. The Farmland Acquisition impact analysis can be found in Table 2-2.

Table 2-2 Affected Households Farmland Loss Condition

Subitem

Administrative

Division

The Proportional Distribution of Affected Households Farmland

Loss(household)

Town Village Subtotal <10

% 10%~20% 20%~30% 30%~50% >50%

the Guihua

Bridge-Shilon

gping Section

of Wushan

County Ring

Beltway

Longmen Office Lizao

Village 45 28 13 4

WuxiaTown

Guihua

Village 65 40 20 5 0 0

Qixing

Village 5 3 2 0 0 0

Total 115 71 35 9 0 0

Based on the above table, the impact of land loss for household is minor. 71 households’

farmland loss is less than 10%. 35 households’ land loss is between 10% and 20%. Only 9

households’ farmland loss is between 20% and 30%,and none of the affected households lose

more than 30% farmland.

Farmland Woodland Wasteland

Picture 2-1 Land Types Acquired Pictures

Page 16: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 3

2.2 Temporary Land Occupation

Temporary land occupation mainly refers to the makeshift road for construction,

construction material area, construction camps, and waste slag area and so on. Temporary land

occupation area totals to 184.41mu, among which 18.19mu farmland, 131.78mu woodland and

35.45mu wasteland, affecting 99 households with 414 persons. The specific information is

available in Table 2-3.

Table 2-3 Temporary Land Occupation Area

Subitem Town Village

Temporary Collective Land

Occupation(mu) Affected Persons

Town Village Group Total Farmland Woodland Wasteland Households Persons

the Guihua

Bridge-Shil

ongping

Section of

Wushan

County

Ring

Beltway

Longmen

Office

Lizao

Village

6 45.34 4.45 32.22 8.67 21 88

3 16.86 1.65 11.98 3.22 12 50

WuxiaTown

Guihua

Village

4 32.36 3.17 23.00 6.19 23 96

5 84.28 8.27 59.90 16.11 35 145

Qixing

Village 4 6.59 0.65 4.68 1.26 8 35

Total 185.41 18.19 131.78 35.45 99 414

2.3 House Demolition and Impacts Analysis

According to the survey, the reconstruction and extension project of this project will

demolish 2889.30m2 houses, including 1453.51m

2 masonry-concrete structured houses, 437.66m

2

masonry-timber structured houses, 914.01m2 earthen-wall houses and 83.85m

2 simple structured

houses, affecting 14 households with 73 persons in total. Among the 14 affected households, 11 of

them will be suffered by the residential house demolition; anther 3 will only be suffered by shed

demolition. The demolition information and the affected houses types are respectively available in

Table 2-4 and Picture 2-2.

In the light of the field investigation, the affected housed types mainly include

masonry-concrete structured houses, masonry-timber structured houses, earthen-wall houses and

simple structured houses. All of the masonry-concrete structured houses have been built after

2000. Most of the masonry-timber structured houses and earthen-wall houses have been built in

Page 17: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 4

the 1970s or 1980s. The simple structured houses are mainly pens and woodsheds.

Table 2-4 House Demolition Area

Villag

e Group Name

Family

Member

s

Total

Construction Classification Classification

Masonry- Masonry- Earth

Wall

House

Simple

Structure

d House

Main

House

Attache

d Room

Concrete

Structure

d House

timber

Structure

d House

Lizao

Village

6th

Villag

e

Group

Xiaohai

Peng 4 360.92 319.52 41.4 319.52 41.4

Zekang

Peng 5 269.9 0 216.9 53 216.9 53

Zelin Peng 5 109.29 109.2

9 0 109.29

Guihua

Village

5th

Villag

e

Group

Bingkun

Xiao 7 27.88 27.88 0 27.88

Shuming

Huang 4 34.5 24.5 10 24.5 10

4th

Villag

e

Group

Gongzhi

Zhou 8 189.19

189.1

9 0 189.19

Gongan

Zhou 3 142.01 38.7 90.66 12.65 129.36 12.65

Xianyi Xu 6 260.9 202.7 58.2 260.9 0

Bingtao

Chen 6 233.07 106.35 96.15 30.57 106.35 126.72

Ruqing Li 5 148.56 112.63 30.5 5.43 143.13 5.43

Zhongquan

Huang 8 571.58 107.88 428.5 35.2 107.88 463.7

Zhongzhi

Huang 5 166.82 166.82 166.82 0

Qianchun

Zhang 3 205.76 205.76 205.76 0

Hongchun

Liu 4 168.65 168.65 168.65 0

Total

14

Household

s

73 2889.0

3 1453.51 437.66

914.0

1 83.85

1849.7

7 1039.26

2.4 Attachments and Fruit Trees

Attachments usually refer to the adjacent accommodations, ground attachments and special

Page 18: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 5

public facilities. In this project, the affected attachments mainly refer to roads, enclosures, dams,

tombs, wells, fruit trees and weed trees etc. Table 2-5 shows the specific information.

Table 2-5 Attachments and Fruit Trees

Attachments Type Unit

Amount

Total

the Guihua Bridge-Shilongping Section of Wushan

County Ring Beltway

Longmen

Office WuxiaTown

0

adjacent

accommodations

farm track macadam m2 75 60 15 0

mud-gravel m2 290 120 50 120

retaining wall rubble m3 45 10 20 15

sunning field

concrete m2 10 10

slab stone m2 55 25 30

earth m2 35 35

tombs earth grave each 3 1 2

with tombstone each 2 1 1

wells

stone m3 3 1 2

concrete m3 1 1

simple m3 3 2 1

cesspools m3 10 2 8

Trees

fruit trees

transplant grafted

seedling plant 60 20

40

d=2-4cm plant 31 11 20

d=4-7cm plant 42 12 30

d=7-10cm plant 17 12 5

d=10-13cm plant 6 5 1

weed trees

lower than3cm plant 133 33 100

d=3-5cm plant 54 14 40

d=5-10cm plant 52 27 25

d=10-15cm plant 30 3 5 22

d=15-20cm plant 27 5 10 12

sinocalamu

affinis and

miscellaneous

bamboo

small bundle less than

20 plants bundle 3 1 1

1

big bundle 21~40

plants bundle 19 12 5

2

4th Group of Guihua Village, 4th Group of Guihua Village, 4th Group of Guihua Village, 4th Group of Guihua Village,

Page 19: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 6

Hongchun Liu, 1 brick house Qianchun Zhang, 2 brick houses Zhongzhi Huang, Zhongquan Huang, 1brick

1 brick house house,1 earthen-wall

househouse

4th Group of Guihua Village, 4th Group of Guihua Village, Ruqing Li, 1 brick house 4th Group of Guihua Village,

Xianyi Xu, 2 brick houses Bingtao Chen, 1 brick house 1 earthen-wall househouse

Page 20: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 1

4th Group of Guihua Village 4th Group of Guihua Village, 5th Group of Guihua Village, 6th Group of Lizao Village,

Gongan Zhou, 1 brick house, Gongzhi Zhou, 1 keekwilee house Bingshen Xiao, Xiaohai Peng, 2 brick houses

1 earthen-wall house house 1 earthen-wall househouse

6th Group of Lizao Village, 6th Group of Lizao Village,

Zelin Peng, cob wall Zekang Peng, masonry-timber wall

Picture 2-2 Houses to Be Demolished in the Road Project of the Guihua Bridge-Shilongping

Section

Page 21: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

3 SOCIO-ECONOMIC SURVEYS

Lying in the east end of Chongqing Municipality, Wushan is the center of the Three Gorges

Reservoir Region, with the Padang County of Hubei in the east, Jianshi County of Hubei in the

south, Fengjie County in the west and Wuxi County in the north. It covers 2,958 square

kilometers, governing 26 towns, 315 villages and 30 neighborhood committees, with the total

population of 624,000, of which there are 20 ethnic minority groups with 6,839 people, who live

in the towns and villages near the boundary of Wushan county and Hubei Province the ADB

project doesn’t impact any ethnic minority people .The maximum distances from the east to the

west and from the south to the north are respectively 61.2 Km and 80.3Km. The lowest elevation

and the highest elevation (Taiping Mountain) are respectively 156m and 2,680m. Mountainous

region and the hills respectively cover 96% and 4% of the whole county.

In 2013 →ushan’s GDP totals to3.5 billion yuan, 13.1% higher than last year, among which

1.89 billion yuan has been achieved by the primary industry with the growth rate of 7.8% and an

increment of 1.025 billion yuan. The secondary industry has achieved an increment of 0.867

billion yuan with the year-on-year growth rate of 14.2%. The tertiary industry has achieved an

increment of 1.753 billion yuan with the year-on-year growth rate of 17.1%. The three main

industries structure ratio has updated to 25.5: 28: 46.5 from the original 27: 26: 47. Fixed-asset

investment, local financial revenue and the rural per capita net income have respectively

increased28.7%, 38.5% and 14.1%.

Table 3-1 Economic Indexes Contrast 2013

The Rural Per Capita Net Income Per Capita GDP

Rural Per

Capita Net

Income

Wushan County Proportion % Per Capita GDP

(yuan)

Wushan County

Proportion %

China 5140 72.4 18934 35.9

Chongqing 4509 85.4 14660 46.4

Wushan County 3996 100.0 7802 100.0

3.2 Social and Economic Status Quo of the Rural Towns Involved

Wuxia Town is the economic and culture center of Wushan County. Longmen Office, sitting

beside Wuxia Town, is the rural-urban junction of Wushan County, having relatively better social

and economic conditions. Table 3-2 is the main economic indexes of affected towns.

Table 3-2 Main Economic Indexes of Affected Towns

Town

Year-end

Populatio

n

Farmland

Area mu

Grain

Yield

(ton)

Total Income

of Rural

Economy ten

thousand

Rural Per Capita

Net Income (yuan

Industrial Structure Ratio

Primary

Industry

Secondary

Industry

Tertiary

Industry

Page 22: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 3

Wuxia Town 68045 57486 26434 28930 4252 37% 20% 43%

Longmen Office 51758 48782 24385 42145 4315 42% 18% 40%

According to the GDP data, it can be found that the GDPs of Wuxia Town and Longmen

Office are derived from secondary industry and tertiary industry. The tertiary industrial output

value accounts for more than 40% of the total GDP and the service industry becomes the main

strength of the GDP.

3.3 Social and Economic Status Quo of the Villages Involved

This project will affect 3,323 households with 13,768 persons in 3 villages, of which

agricultural population is 13,750, accounting for 99.87% of the total population; the poverty

population accounts for 2.24% of the total population. The basic population information of the

affected villages is available in Table 3-3.

Table 3-3 Basic Population Information of the Affected Villages

Project Administrat

ive Division Village

Total Number

of Household

household

Total

Population

person

Agricultural

Population

(person)

Poor

Household

(household)

Poverty

Population(

person)

Rural Per

Capita Net

Income(yuan

the Guihua

Bridge-Shilongp

ing Section of

Wushan County

Ring Beltway

Longmen

Office Lizao 1215 5015 5012 21 96 4298

WuxiaTown

Guihua 998 4128 4120 18 80 4165

Qixing 1110 4625 4618 30 132 4395

Total 3323 13768 13750 69 308

It can be seen from the table above that the rural per capita net income of 3 affected villages

all exceed 4,000 yuan, higher than the rural per capita net income of Wushan County in 2012.

Lizao Village is governed by Longmen Office (i.e. Longmen Town in the map). Guihua Village

and Qixing Village are governed by WuxiaTown. Geographically, the latter two villages are nearer

to Wushan County. Due to the better regional advantage, their economic conditions are a little

better than other remote towns and villages in Wushan County.

Page 23: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 4

3.4 Social and Economic Status Quo of the Households Affected by the

Project

In February 2014, with the help of Wushan County Transportation Development Co., Ltd., the

compilation unit has investigated the basic information and aspirations of relocation of the

affected households. The main purpose of the survey is to: (1) get the latest socio-economic

information of the affected persons who might lose their lands or properties because of the project;

(2) know the affected persons’ aspirations of the land acquisition and income restoration

measures.

This survey is conducted by sampling survey method, combining with consulting the village

and group cadres, questionnaires and interviews. The respondents are 60 households from 6

groups of 3 villages in 2 towns who have been affected by the permanent land acquisition,

accounting for 21.58% of the total affected households.

Picture 3-1 Location Map of the Affected Towns and Villages

Page 24: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 5

Table 3-4 Sampling Survey Proportions

Subitem Town Viilage Households Sampling Survey Households Sampling Survey Proportion

the Guihua

Bridge-Shilongping

Section of Wushan

County Ring

Beltway

Longmen

Office

Lizao

Village 84 20 23.81%

WuxiaTo

wn

Guihua

Village 182 37 20.33%

Qixing

Village 12 3 25.00%

Total 278 60 21.58%

3.4.1 Demographics of Affected Persons

The demographics of affected persons include gender, age, family composition, education

background and occupation etc. This survey has investigated 60 households with 247 persons.

The demographics information is available in Table 3-4.

Table 3-5 Demographics of Investigated Households

the Guihua Bridge-Shilongping Section Total

Town Longmen Office WuxiaTown

Village Lizao Village Guihua Village Qixing Village

Gender Man Woman Man Woman Man Woman Man Woman Subtotal %

Households 20 37 3 60 60

Total Number

of People

83 151 13 247 247

Average

Population

4.15 4.08 4.33 4.1 4.1

1, Age Structure

<16 7 8 13 14 1 0 21 22 43 17.41%

16-60岁 25 24 47 44 5 4 77 72 149 60.32%

>60 9 10 16 17 1 2 26 29 55 22.27%

Total 41 42 76 75 7 6 124 123 247 100%

2, Education Background

Illiteracy 1 3 1 2 0 2 5 7 2.83%

Elementary

School

10 11 20 22 3 2 33 35 68 27.53%

Junior High

School

23 23 43 42 4 4 70 69 139 56.28%

Senior High

School

7 5 12 9 19 14 33 13.36%

Total 41 42 76 75 7 6 124 123 247 100%

3, Labor Force Composition

Child 4 5 8 7 1 0 13 12 25 10.12%

Student 8 7 12 12 1 1 21 20 41 16.60%

Page 25: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 6

Labor Force 20 20 40 39 4 3 64 62 126 51.01%

Aging Population 9 10 16 17 1 2 26 29 55 22.27%

Total 41 42 76 75 7 6 124 123 247 100%

4, Occupation of the Labor Force

Farmer 7 11 15 19 1 1 23 31 54 42.86%

Migrant Workers 13 9 25 20 3 2 41 31 72 57.14%

Total 20 20 40 39 4 3 64 62 126 100.00%

(1) Gender Structure——there are 123 women and 124 men in the 60 households with 247

persons, the proportions is respectively 49.8% and 50.2%.

(2) Age Structure——43 persons are 0~16 years old, accounting for 17.41% of the total

population; 149 people are 16~60 years old, accounting for 60.32% of the total population; 55

people are above 60 years old, accounting for 22.27% of the total population.

(3) Education Background——7 people are illiterate among the investigated people,

accounting for 2.83% of the total population; 68 people have only received primary school

education, accounting for 27.53% of the total population; 139 people’s highest degree is junior

high school, accounting for 56.28% of the total population; 33 persons’ highest degree is senior

high school, accounting for 13.36% of the total population. Illiteracies are mainly above 60 years

old.

(4) Labor Force Composition——there are 25 children, 41 students, 126 laborers and 55

aging people, respectively accounting for 10.12%, 16.60%, 51.01% and 22.27% of the total

population.

(5) Occupation of the Labor Force——there are 54 farmers among the labor force

population of 126, accounting for 42.86% of the total population. There are 72 migrant workers

(21 temporary migrant workers working at home in the slack seasons, 20 migrant workers

working at home perennially, 31 migrant workers working outside perennially), accounting for

57.14% of the total population.

3.4.2 Landownership Condition

According to the survey, the per capita farmland area of 1.01mu of the 3rd

Group of Lizao

Village is the largest one of the affected groups, and the smallest one is 0.94mu of 4th

Group of

Page 26: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 7

Qixing Village. The specific information is available in the Table 3-6.

Table 3-6 Per Capita Farmland Areas of the Affected Groups

Subitem Administrative Division

Per Capita Farmland Areas(mu) Town Village Group

the Guihua Bridge-Shilongping

Section

Longmen Office Lizao Village 6 0.98

3 1.01

WuxiaTown Guihua Village

4 0.94

5 0.95

Qixing Village 4 0.94

3.4.4 Income Condition

3.4.4.1 Income Composition Analysis

According to the income composition of 60 investigated households, agricultural income

accounts for only about 10% of the household economic income and the non-agricultural income

accounts for 90%. Therefore, earnings from migrant workers are the main source of the household

economic income. See Table 3-7.

Table 3-7 Household Income Composition

Subitem Town Village

Sampling

Survey

Household

s

Household Average Income Type

Household

Average

Household

Cost

Expenditure

Househol

Net IncoPlanting Cultivating

Working

for

Others

Other

Ways

the Guihua

Bridge-Shil

ongping

Section

Longmen

Office

Lizao

Village 20 1725 1838 18000 2500 24063 4400 19633

WuxiaTown

Guihua

Village 37 1650 1700 17000 3500 23850 4250 19600

Qixing

Village 3 1620 2000 19000 23620 4200 19420

3.4.4.2 Household Income Level Distribution

Annual per capita net income of 12 sampling households is more than 5,000~8,000 yuan,

accounting for 20% of the 60 sampling households. Annual per capita net income of 48 sampling

households (80%) is between 3,000 yuan and 5,000 yuan, equal to the town’s average level. See

Table 3-8.

Table 3-8 Per Capita Net Income Level Distribution of the Sampling Households

Page 27: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 8

Net Income

(yuan/person·year)

Less than

1500 1501-3000 3001-5000 5000-8000

More than

8000 Total

Households(household) 0 0 48 12 0 60

Proportion % 0.00% 0.00% 80.00% 20.00% 0.00% 100.00%

3.4.4.3 Women's Income Analysis

→omen’s income is part of the total household income. According to the survey, among the

60 investigated households, there is 1 household in which women’s income accounts for 50% of

the total household income. In 25 households, women’s income accounts for 40~50%. In 22

households, women’s income accounts for 30~40%. In 12 households, women’s income accounts

for less than 30%. The specific analysis is available in Table 3-9.

Table 3-9 Women's Income Distribution in the Household Total Income Proportion of the Women’s

Income % <30% 30%~40% 40%~50% >50% Total

Households household 12 22 25 1 60

Proportion % 20% 37% 42% 2% 0

The fact that the proportion of women’s income is less than that of man’s is closely related to

the working hours of female migrant workers. In accordance with the survey, female migrant

workers of the affected persons are mainly engaged in non-manual and unskilled jobs for which

the payments are relatively low, such as restaurant waiter, baby-sitters, cleaners, clothing making

or shoemaking and so on. Some women work outside discontinuously instead of perennially

because they have to spare some time to look after their children and aging parents.

3.4.5 Expenditure Status Quo

The expenditure of the affected households mainly includes production cost, food and drink,

clothing, education, medical treatment, entertainment, transportation and communication. The

average expenditure of the affected households is in Table 3-10.

Table 3-10 Expenditure of the Affected Persons

Subitem Town Village Sampling

Households

Household Average Expenditure Type Total

Expenditure

per household

Production

Cost

Food

and

Drink

Cloth

ing

Educ

ation

Medical

Treatme

nt

Entertain-

ment

Transportation and

Communication Others

the

Guihua

Longmen

Office

Lizao

Village 20 1900 9000 2500 800 600 1300 2900 2500 21500

Page 28: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 9

Bridge-Sh

ilongping

Section

WuxiaTo

wn

Guihua

Village 37 1750 8500 1800 500 800 1400 2800 2500 20050

Qixing

Village 3 1800 9000 1700 200 800 1300 3600 2400 20800

According to the analysis, the affected person’s food and drink expenditure accounts for

about 50% of the total expenditure and the production cost only accounts for about 8% of the total

expenditure. This keeps in line with the fact that the affected persons’ economic income is mainly

derived from working outside the hometown.

3.4.6 Income and Expenses Analysis

The total household average income of 60 sampling households can meet the expenditure.

See Table 3-11.

Table 3-11 Affected Persons’ Surplus Condition Unit: CNY

Subitem Town Village Total Income

Per Household

Total

Expenditure

Per Household

Surplus Per

Household

Proportion of

Surplus

the Guihua

Bridge-Shilongping

Section

Longmen Office Lizao Village 24063 21500 2563 10.65%

WuxiaTown Guihua Village 23850 20050 3800 15.93%

Qixing Village 23620 20800 2820 11.94%

During the investigation, when asked about the use of surplus money, most of the

investigated people have said that they will deposit the surplus in a bank, and some households

have said that they are saving money for doing business in the town like running a restaurant or a

small shop.

3.5 Impacts on the Vulnerable Groups

According to the socio-economic survey, this project will not affect the vulnerable groups.

3.6 Survey on Aspiration of Relocations of Persons Affected

115 of the 278 households affected by the land acquisition will be affected by the farmland

acquisition. 60 households in the survey are all affected by the farmland acquisition. About 60%

labor forces are working outside their hometown. The main household income is derived from the

migrant workers. The APs have the right to select the resettlement methods such as cash

compensation or land exchange with same quality and quantity. However, almost children and

Page 29: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 10

aged people stayed in Villageswho have no enough ability to plant crops, therefore, all the APs

tend to select cash compensation. See Table 3-12.

Table 3-12 Affected Persons’ Aspirations of Relocation

Aspirations of Farmland

Acquisition

Land

Loss<10%

Land

Loss10%-20%

Land Loss

20%-30%

Land Loss

30%-50%

Land

Loss >50%

cash compensation 61 35 9 0 0

There are 27 men and 33 women (The sampling proportion of women is 52.56 %.) in the 60

respondents. Aspirations differ between men and women. See Table 3-13.

Table 3-13 Different Aspirations of Men and Women

Item Man n=27 Woman n=33

reasonable compensation 100% 100%

compensation in time 100% 100%

employment training 33% 45%

f future jobs 33% 42%

employment information 30% 55%

recommended employment 30% 58%

child’s education 100% 100%

help during the relocation 30% 55%

others (government’s help) 100% 100%

According to the survey, aspirations differ between men and women. It can be found that

men and women reach a 100% agreement on the reasonable compensation, compensation in time,

child’s education and other government’s help. However, women pay more attention to the

employment training, recommended employment and the rest aspects than men.

Page 30: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

4 PUBLIC PARTICIPATION AND APPEAL MECHANISM

4.1 Public Participation Program

Both the compiling process of The Resettlement Plan and the resettlement implementation

phase attach great importance to the participation and consultation of the affected persons. RP was

prepared on the basis of the full negotiation with affected persons on the related compensation

rates and schemes in June-July 2014.

In consideration of the practical situation of this project, the public participation is divided

into three phases:

Phase Main Content Current

Situation

Phase 1

During the project construction design phase and The draft Resettlement

Plan preparation process, people responsible for the organization

consult the interest-related units, introduce the project information to

the affected masses and discuss the compensation rate and policies as

well as the resettlement plan and measures.

Dec.

2013-Feb.201

4

Phase 2

Distribute The Resettlement Information Brochure to the households who will

be affected by the land acquisition during the meeting. The basic information,

impacts, compensation policies, resettlement scheme and the appeal channels

etc. will also be disclosed to the relevant masses.

Late July.

2014

Phase 3

Before the implementation of the land acquisition, people in charge should

convene affected persons to attend meetings to gather advice and suggestions

on compensation and resettlement.

Aug.-Sept.

2014

Phase 4

During the construction and operation process, regular research and interviews

will be conducted in the affected areas to know the compensation payment

condition and the livelihood restoration condition. The monitoring institution

will check the release condition of The Resettlement Information Brochure and

evaluate its effects.

2014-2016

4.1.1 Public Participation in Progress

In accordance with the ADB’ requirements, the project owner and design unit have organized

special socio-economic investigation team to conduct a specific survey on the affected households

and the rural collective economic organization, in order to get the information of the project

impact and the socio-economic situation of the affected persons. So far, two public participation

activities have been organized during the feasible design phase and the present construction

design phase. See Table 4-1.

Page 31: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 12

Table 4-1 Public Participation Condition

Initiator Time Participant Number Objective Main Concern and Suggestions

The Feasibility

Study Report

Compilation

Unit

2013.9

staff of the governments

of the towns and

county, villagers and

affected persons

14 collecting project

design information

necessary investigation for the project design;

acquaintance of the affected persons’ opinions

on the project

The Resettlement

Report

Compilation

Unit

2013.12

village cadres, affected

persons, women and

vulnerable groups

80

investigating the

socio-economic

condition for the land

acquisition and

relocation

sufficient compensation for the land

acquisition;

possible ways put forward by the affected

persons to restore their livelihood;

discussion of the compensation mode

Construction

Design Unit 2014.1

Transportation Bureau,

project owner, directors

of the villages and towns

20 collecting project

design information necessary investigation for the project design;

The

Resettlement

Report

Compilation

Unit

2014.2

village cadres, affected

persons, women and

vulnerable groups

125

investigating the

socio-economic

condition for the land

acquisition and

relocation;

Prepare the RP.

land acquisition and demolition area

investigation;

economic investigation of the affected

persons ;

affected persons’ aspirations of the relocation

(14 HHs choose self-built option);

Wushan county

land and

resources bureau

2014.5-

6

Leaders in Affected

towns, villages, and Aps 130 DMS

Detailed measurement for land acquisition and

house demolish

4.1.2 Public Participation Plan of the Next Stage

According to the schedule, the relevant compensation has been settled in June 2014 by

means of consultations and discussions with the affected persons. The notice of the specific land

acquisition area was also been issued in July 2014. From August to September2014, the

compensations of the land acquisition and demolition are going to give out: 1) giving out The

Resettlement Brochure which includes the relevant land acquisition compensation policies, laws

and regulations, compensation rate, appeal mechanisms and land acquisition plan; 2) convening

the official villager assembly to illustrate the payment and application method of the

compensation and distributing the resettlement compensation. The public participation program of

the next stage is in Table 4-2.

Table 4-2 The Consultation Program of the Next Stage

Objective Task Time Implementation

Institution Participants Note

Page 32: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 13

1. Update of the RP

after DMS

DMS; taking the affected

persons’ opinions into full consideration and

working out a feasible

compensation scheme

2014.7 owner, villages and

towns

all affected

persons

Decide final compensation

scheme.

2. Notice of The

Resettlement Plan

distributing the Chinese

version of The

Resettlement Plan

2014.7-8

the implementation

institution,

governments of the

villages and towns

all affected

persons

Distribute the renewed The

Resettlement Plan which has

been approved by the ADB to

the affected households.

3. Distribution of the

resettlement

compensation

signing The Land

Acquisition Agreement

with the affected persons

and distributing the

resettlement

compensation

2014.8-9

the implementation

institution, the Land

and Resources Bureau,

land requisition

personnel and the

cadres of the villages

and towns

all affected

persons

1) Distribute the

compensation;

2) Find out people who want

to change their agricultural

status to non-agricultural"

status and determine the

application methods of

investing the compensation.

4.2 Appeal Mechanism

To ensure that opinions of the APs on such issues as land occupancy, compensation and

personnel resettlement can be solved in an open and fast way to avoid APs of the project to be

forced to resort to adopt complex formal channels to express their dissatisfaction or complaint, IA

has established handling procedures involved with appeal of the project, with specific steps as

follows:

Step 1: In case the APs or village committees have any objection to the land compensation

RP, they can propose an oral or written appeal to the township government. If they file their

appeal orally, it is required to be addressed by the township government with a written record.

The township government shall make a disposition within one week;

Step 2: In case the APs are still unsatisfied with the disposition in Step 1, they can still

appeal to Wushan County Land Resources Bureau or the Resettlement Office in accordance with

relevant laws and regulations of Chongqing, the Land Resources Bureau or the Resettlement

Office shall make a disposition within 10 days;

Step 3: In case the APs remain unsatisfactory with the disposition in Step 2, they can lodge

an appeal to WushanCounty PMO after receiving the disposition, and the County PMO shall

make a disposition within one week;

APs can decide to go through the legal system directly and may decide not to use

the project level grievance channels.

APs can file a lawsuit aiming at any aspect of the resettlement, including

compensation rates etc. The above channel of appeal will be notified to APs by way of meeting

and RIB so that the APs can get a full awareness of their right to appeal. At the same time, the

media will be utilized to strengthen publicity, and the opinions and proposals of various aspects

on the work of resettlemen will be solidified into information provisions, which shall be studied

timely and solved by the resettlement agencies at all levels. All these agencies shall receive

complaints and appeals from the affected people free of charge, and reasonable expenses arising

therefrom will be paid out from unforeseeable fee of migration resettlement. For channel of

appeal, see Table 4-1 .

APs can also submit complaints to ADB which will be handled by the Project Team. If an

AP is still not satisfied and believes they have been harmed due to non-compliance with ADB

Page 33: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 14

policy, they may submit a complaint to ADB’s Office of Special Project Facility or Office of Compliance Review in accordance with ADB’s Accountability Mechanism1.

Table 4-3 Persons in Charge of Each Appeal Phase

Phase Accepting

Institution Contact Office Tel Address

Phase 1 Longmen Office Zhang Gong 023-57623190 Government

WuxiaTown Chen Rongbin 13594465656 No. 56, Middle Rd., Guangdong

Phase 2 Wushan County

Project Office Zhou Bin 13983538190 Development and Reform Commission

Phase 3

Land and

Resources Bureau

of Wushan

County

Wu Qiang 023-63651411

Phase 4 Government of

Wushan County He Shaofeng 02357651010

1 For further information see: http://www.adb.org/Accountability-Mechanism/default.asp.

Phase 1: If the affected persons are dissatisfied with the compensation of land acquisition, demolition and resettlement,

they can submit written or oral complaint to the committee village. If it is an oral complaint, the village committee shall

keep a written record and deal with it in 2 weeks.

Phase 2: If the affected persons are dissatisfied with the result of the Phase 1, they can submit written complaint to the

town government after receiving the result. The town government shall determine how to deal with it and send a written

notice to the claimant.

Phase 3: If the affected persons are dissatisfied with the result of the Phase 2, they can submit written complaint to the

Land and Resources Bureau according to the relevant laws and regulations after receiving the result. The Land and

Resources Bureau shall determine how to deal with it in 2 weeks and send a notice to the claimant.

Phase 4: If the affected persons are dissatisfied with the result of the Phase 3, they can submit an administrative review to

the county people’s government after receiving the result. They can also submit an administrative litigation to the local

People’s Court in 3 months according to the Civil Procedure Law.

Picture 4-1 the Appeal Procedure

Page 34: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 15

5 LEGAL FRAMEWORK AND RESETTLEMENT

POLICY

5.1 ADB Resettlement Principles

Resettlement Principles:1. Screen the project early on to identify past, present, and future

involuntary resettlement impacts and risks. Determine the scope of resettlement planning through

a survey and/or census of displaced persons, including a gender analysis, specifically related to

resettlement impacts and risks.

2. Carry out meaningful consultations with affected persons, host communities, and

concerned nongovernment organizations. Inform all displaced persons of their entitlements and

resettlement options. Ensure their participation in planning, implementation, and monitoring and

evaluation of resettlement programs. Establish a grievance redress mechanism to receive and

facilitate resolution of the affected persons’ concerns. Support the social and cultural institutions

of displaced persons and their host population. Where involuntary resettlement impacts and risks

are highly complex and sensitive, compensation and resettlement decisions should be preceded by

a social preparation phase.

3. Improve, or at least restore, the livelihoods of all displaced persons through (i) land-based

resettlement strategies when affected livelihoods are land based where possible or cash

compensation at replacement value for land when the loss of land does not undermine livelihoods,

(ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt

compensation at full replacement cost for assets that cannot be restored, and (iv) additional

revenues and services through benefit sharing schemes where possible.

4. Provide physically and economically displaced persons with needed assistance, including

the following: (i) if there is relocation, secured tenure to relocation land, better housing at

resettlement sites with comparable access to employment and production opportunities,

integration of resettled persons economically and socially into their host communities, and

extension of project benefits to host communities; (ii) transitional support and development

Page 35: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 16

assistance, such as land development, credit facilities, training, or employment opportunities; and

(iii) civic infrastructure and community services, as required.

5. Improve the standards of living of the displaced poor and other vulnerable groups,

including women, to at least national minimum standards. In rural areas provide them with legal

and affordable access to land and resources, and in urban areas provide them with appropriate

income sources and legal and affordable access to adequate housing.

6. Develop procedures in a transparent, consistent, and equitable manner if land acquisition

is through negotiated settlement to ensure that those people who enter into negotiated settlements

will maintain the same or better income and livelihood status.

7. Ensure that displaced persons without titles to land or any recognizable legal rights to land

are eligible for resettlement assistance and compensation for loss of nonland assets.

8. Prepare a resettlement plan elaborating on displaced persons’ entitlements, the income and

livelihood restoration strategy, institutional arrangements, monitoring and reporting framework,

budget, and time-bound implementation schedule.

9. Disclose the final resettlement plan and its updates to affected persons and other

stakeholders.

10. Conceive and execute involuntary resettlement as part of a development project or

program. Include the full costs of resettlement in the presentation of project’s costs and benefits.

For a project with significant involuntary resettlement impacts, consider implementing the

involuntary resettlement component of the project as a stand-alone operation.

11. Pay compensation and provide other resettlement entitlements before physical or

economic displacement. Implement the resettlement plan under close supervision throughout

project implementation.

12. Monitor and assess resettlement outcomes, their impacts on the standards of living of

displaced persons, and whether the objectives of the resettlement plan have been achieved by

taking into account the baseline conditions and the results of resettlement monitoring. Disclose

monitoring reports.

Page 36: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 17

5.2 Comparison of ADB’s Involuntary Resettlement Policies with the

PRC’s LAR Policies

Generally speaking, there are many similarities between the ADB’s involuntary resettlement policies and the PRC’s LAR policies, which include:

(1) Both of them attach an importance to avoiding or reducing resettlement during the

planning and design stage of a project;

(2) Both of them attach an importance to the restoration and improvement of the

livelihood of APs;

(3)Both of them attach an importance to the openness and transparency of the

resettlement policies;

(4) Both of them attach an importance to the participation and awareness of the public

during resettlement;

(5) Both of them require that the formulation and implementation of the resettlement

compensation standards must be based on the law and according to the law.

However, there are still some differences in some aspects between ADB’s involuntary resettlement policies and the PRC’s LAR policies, which include:

(1) ADB attaches more importance to the planning prior to the implementation of

resettlement, and it requires that a feasible RP must be compiled;

(2) The ADB’s resettlement policies require that during resettlement, all losses of all APs must be compensated according to replacement costs, including those people having no

legal land ownership. However, the LAR policies of the PRC provide a different compensation

policy to unlicensed buildings.

(3)ADB attaches more importance to the special care extended to the vulnerable people

during resettlement; and

(4) ADB attaches more importance to monitoring and checking during resettlement.

Based on the above analysis, during the preparation for resettlement, this Project takes

Page 37: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 18

full account of the relevant policies of ADB and takes the following measures to meet the

demands of ADB:

(1)The preparation of the Project must be based on concrete socio-economic survey

and physical survey, and the RP must be prepared in details;

(2) Special care must be given to vulnerable people during resettlement

implementation;

(3) Make compensation to non-registered buildings constructed before the cut-off time,

based on replacement value of structures;

(4) Establish internal and external monitoring systems for resettlement.

With the above measures, the ADB’s resettlement policies and the PRC’s LAR policies will be seamlessly bridged and the smooth implementation of resettlement of the Project will be

guaranteed.

5.3 ADB Resettlement Laws and Policy Basis

5.3.1 Relevant Laws and Regulations of Chinese and Local Governments

(1) Urban Real Estate Administration Law of the People’s Republic of China (1994);

(2) Enforcement Regulations of Land Administration Law of the People’s Republic of China;

December 1998;

(3) State Council Decision to Deepen Reform and Strictly Enforce Land Administration (GF

[2004] 28) (October, 2004);

(4) Land Administration Law of PRC (2004);

(5) Notice of Ministry of Finance, Ministry of Land and Resources on Issues Regarding

Adjusting Charging standard of Paid Use of Newly-added Construction Land (CZ [2002] 93);

(6) Cultivated Land Acquisition Provisional Tax Law of the People’s Republic of China

(2008);

(7) Rural Highway Construction Administrative Methods of Chongqing Municipality;

(8) Chongqing Municipality Administrative Measures on Charging and Using of Cultivated

Page 38: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 19

Land Reclamation Fee, Cultivated Land Idling Fee and Land Reclamation Fee;

(9) Notice of People’s Government of Chongqing Municipality on Issues Regarding Adjusting

the Policy of Land Acquisition, Compensation and Resettlement (YFF [2013] 58);

(10) Notice of Ministry of Finance, State Forestry Bureau on Issuing “Interim

Administrative Measures of the Usage of the Forest Vegetation Recovery Fee” (CZ [2002] 73);

(11) Notice of People’s Government of Wushan County on Issuing Interim Methods of Land

Acquisition and Resettlement Compensation (Wushan County [2008] 39);

(12) Notice of People’s Government of Wushan County on Issues Regarding Adjusting the

Compensation rate of Land Acquisition, Demolition and Resettlement (Wushan FF [2013] 28).

5.3.2 Relevant Policies of ADB

(1) ADB’s Safeguard Policy Statement (Manila, June 2009).

(2) ADB’s Gender Checklist - Resettlement (Manila, February 2003).

5.4 Compensation Rate

5.4.1 Compensation Principles

All land and properties loss abide by the resettlement principles: (1) compensation will be

paid before the acquisition of the properties and land; (2) Provide technical training, help and

employment opportunities for the resettled agricultural labor force to guarantee that their living

standard will not decline because of the project; (3) Crops and attachments compensation will be

paid to the contractor or the property owner in full; (4) Enhance the management during the

construction period to minimize the timescale and the negative impacts of the project; (5)

Distribute the compensation to the affected labor force to help them continue their present job or

engage in individual business.

5.4.2 Compensation Rate

(1) Land compensation fee and Resettlement subsidy Standard

Page 39: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 20

In accordance with the compensation policies in Wushan FF [2013] 28, the compensation of

all kinds of land will be calculated on the basis of land acquisition area and the standard is 16,000

yuan/mu; the resettlement subsidy of all areas will be calculated on the basis of the “agricultural

to non-agricultural” status population and each person who changes from agricultural status to

non-agricultural status can get 36,000 yuan.

The project IA and contractors will put notices 1-2 months in advance of the project

implementation in order the farmers have enough time to harvest standing crops. The project IA

will provide relevant taxes and government fees.

(2) Crops Compensation rate

Crops compensation refers to farmland compensation. According to the survey, the woodland

affected by the project is timber forest with no commercial crop forest (e.g., orchards). The land

in the timber forest is mainly open forest land where grows shrubs and herbaceous plants. The

timber forest does not bring economic benefits to local people. Since the affected area of the

project is linear in shape, the remaining forest after the land acquisition can meet the affected

households’ needs of timber. Only very few arbors will be affected and compensated according to

the Wushan FF [2013] 28. The farmland compensation rate is 1,800 yuan/mu for grain crops and

2,600 yuan/mu for the vegetable crops.

According to the project timescale, the crops compensation caused by the temporary land

occupation will be paid for 2 years. The compensation rate is the negotiated agreement between

the IA and the affected persons on the basis of the resettlement cost. The annual net income of the

farmland is about 920 yuan/mu, which is lower than the compensation rate, so the compensation

rate is high enough. The project IA will pay a reclamation fee at the rate of 20/m2 and undertake the

reclamation of the temporarily occupied land. The fee will be returned to the IA if the reclaimed land has

passed inspection.

The project IA and contractors will put notices 1-2 months in advance of the project implementation

in order the farmers have enough time to harvest standing crops.

(3) Demolition Compensation

Page 40: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 21

The house demolition compensation rate is: 870 yuan/m2

for the masonry-concrete structured

houses, 720 yuan/m2 for the masonry-timber structured houses, 540 yuan/m

2 for the earthen wall

houses and 270 yuan/m2 for the simple structured houses;

The demolition compensations include moving subsidy, demolition and resettlement subsidy

and relocation subsidy. The moving subsidy is calculated by household. A one-off payment of 500

yuan will be given to the household with no more than 3 members. For households with more

than 3 members, each additional person will get 100 yuan increment. However, the maximum of

the moving subsidy is 1000 yuan. Every affected person can get 150 yuan of demolition and

resettlement subsidy each month (until the end of the resettlement, and the scheduled time of this

project is 6 months). Every affected person can also get a one-off payment of 500 yuan as a

relocation subsidy. The specific compensation rate is in Table 5-1.

All the house demolished farmers have the right to salvage material. There will be no charge

for house relocation and reconstruction.

(4) Attachments Compensation rate

The attachments mainly refer to roads, retaining wall, earth dike, tombs, wells, cesspools,

fruit trees, weed trees, etc. After consulting the Wushang County Forestry Bureau, the affected

land in Wushan County is open forest land, the acquisition of which needs to be put on records in

the Wushang County Forestry Bureau. The project owner has to pay the forest vegetation

restoration fee of 6 yuan/m2

to the Wushan County Finance Bureau. The weed trees compensation

will comply with the provisions of Wushan FF [2013] 28. The specific attachments compensation

rate is in Table 5-1.

Table 5-1 Compensation rate in Point

Serial Number Name and Structure Unit Compensation rate

I. Permanent Land Acquisition Compensation

rate

1 Land Acquisition Compensation yuan/mu 16,000

2 Farmland Resettlement Subsidy yuan/mu 36,000

5 Crops Compensation

Grain crops yuan/mu 1,800

Vegetable crops yuan/mu 2600

II. Temporary Land Occupation Standard

1 Garden Plots, Paddy Fields, Dry Land yuan/mu 1800

2 Woodland and Others yuan/mu 900

. Demolition Compensation

Page 41: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 22

1 Houses

Masonry-concrete Structured yuan/m2 870

Masonry-timber Structured yuan /m2 720

Cob Wall yuan/m2 540

Earthen-wall yuan/m2 270

2 Moving Subsidy

No More than 3 members yuan/household 500

4 Persons yuan/household 600

5 Persons yuan/household 700

6 Persons yuan/household 800

3 Demolition and Resettlement Subsidy yuan/month·person 150

4 Relocation Subsidy yuan/person 500

Attachments Compensation rate

Types Unit Unit Price

1 roads macadam yuan/m

2 55

mud-gravel yuan/m2 33

2 retaining wall rubble yuan/m3 50

3 Sunning field

concrete yuan/m2 30

slab stone yuan/m2 20

earth yuan/m2 10

4 tombs Earth grave yuan/each 2000

with tombstone yuan/each 3000

5 wells

stone yuan/m3 30

Concrete yuan/m3 30

simple yuan/m3 15

6 cesspools yuan/each 200

7 fruit trees

transplant grafted seedling yuan/plant 3

d=2-4cm yuan/plant 24

d=4-7cm yuan/plant 27

d=7-10cm yuan/plant 53

d=10-13cm yuan/plant 93

8 weed trees

lower than3cm yuan/plant 2

d=3-5cm yuan/plant 5

d=5-10cm yuan/plant 9

d=10-15cm yuan/plant 17

d=15-20cm yuan/plant 30

9

sinocalamu affinis

and miscellaneous

bamboo

small bundle less than 20

plants yuan/ bundle 15

big bundle 21~40 plants yuan/ bundle 24

5.5 Eligibility and Entitlement Matrix

The cut-off date of the project was 27 June 2014. Those people who reclaim wasteland or

build constructions and attachments in the occupation areas after above mentioned date will not

get the compensation, neither will those who rush to build constructions and attachments or plant

Page 42: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 23

crops in the occupation areas.

Table 5-2 is the Entitlement Matrix based on the mentioned compensation principles.

Table 5-2 Entitlement Matrix

Type

Scope of

Application Rights Holder Compensation Policy Implementation

Permanent

Land

Occupation

551.37mu

of 5 groups of 3

villages in 2 towns

1) 278

households

with 1198

persons of 3

villages in 2

towns;

The land compensation fee is 16,000

yuan/mu. The resettlement subsidy is

36,000 yuan/person. Both of them will

be directly distributed to the affected

persons.

(1). Compensation for

standing crops will be

paid to the AHs;

(2). The AHs will receive

free training;

(3). The village collective

will use the

compensation for

community facilities.

(4). Jobs during

construction and

maintenance will be

provided.

(5) Replacement land of

equivalent quantity and

quality will be provided to

Aps;

(6) Trainings will be

provided during

construction.

2) 318 affected

persons of

permanent land

acquisition who

will be

urbanized

The resettlement subsidy is 36,000

yuan/person which will be directly

distributed to the affected persons.on

the basis of the amount of land to be

acquired.

3) all affected

persons;

Grain corps compensation rate is

1,800yuan/mu. Vegetables corps

compensation rate is 2,600 yuan/mu.

Both of them will be directly distributed

to the owner by cash.

Temporary

Land

Occupation

185.41mu

temporary land

occupation, which

includes 18.19mu

farmland,

131.78mu

woodland and

35.4mu wasteland.

1) rural

collective

economic

organization

with land

ownership ;

Cash compensation will be distributed

to the collective or individuals who own

the land. Farmland like garden plots,

paddy fields, dry land compensation

rate is 1,800 yuan/mu/year. Woodland

and others compensation rate is 900

yuan/mu/year.

Measure the detailed land area

and negotiate with the land

owners;

During the restoration of

the temporary land

occupation, Wushan County

Land and Resources Bureau

will supervise the entire

process of restoration

according to the Land

Administrative Law until the

condition of the restored land

is acceptable.

2) Project IA

Temporary land occupation will be paid

for 2 years. The project IA will pay a

reclamation fee at the rate of 20/m2 and

undertake the reclamation of the

temporarily occupied land. The fee will

be returned to the IA if the reclaimed

land has passed inspection

Page 43: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 24

House

Demolition

House demolition

area is 2,889.03m2,

which includes

1453.51m2

masonry-concrete

structured houses,

437.66m2

masonry-timber

structured houses,

914.01m2

masonry-timber

structured houses

and 83.85m2

simple structured

houses.

73 persons (14

households)

affected by

demolition

Compensation rates of

masonry-concrete structured houses,

masonry-timber structured houses,

masonry-timber structured houses and

simple structured houses are

respectively870yuan/m2, the

masonry-concrete structured houses,

720 yuan/m2 for the masonry-timber

structured houses, 540 yuan/m2 for the

cob wall houses and 270 yuan/m2. 500

yuan moving subsidy will be given to

the household with no more than 3

members. For households with more

than 3 members, each additional person

will get 100 yuan increment. However,

the maximum of the moving subsidy is

1000 yuan. Every affected person can

get 150 yuan of demolition and

resettlement subsidy each month for 6

months. Every affected person can get a

one-off payment of 500 yuan.

Homesteads and related services will be

provided free of cost to AHs.

(1) Receiving house

compensation at

replacement cost, and

transition subsidy, moving

subsidy and relocation

subsidy;

(2) Providing housing plots

in the same community

provided by local village

freely;

(3) All the house

demolished farmers have

the right to salvage

material. There will be no

charge for house

relocation and

reconstruction.

Attachments roads, dams, tombs

etc. owners

Related organizations will remove the

telegraph poles.

The owners will remove the tombs by

themselves.

The notice on removing the

tombs should be issued on the

local newspaper or broadcast

one month before the land

acquisition. Mean While, the

local government and

monitoring agency should

monitor the progress and

procedure of the action.

Agricultural

Status to

Non-agricult

ural Status

people who want

to change their

status

all people who

want to change

their status

The population converted into urban

status will receive resettlement subsidy

of 36,000 yuan per person. The

resettlement subsidy of any

land-expropriated farmer aged under 16

years will be fully paid to the

individual; AP aged 16 years or above

will pay endowment insurance

premiums based on age group, where

the government and individual shall pay

50% each. People with different ages

pay different endowment insurance

premium. The 50% part which the

Governments of Wushan County

and towns are responsible for the

implementation. Land and

Resources Bureau and Labor and

Social Security Bureau are

responsible for the basic social

insurance.

Page 44: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 25

government pays for the insurance is

from the 80% of the land compensation

and land planning fee if not enough.

Vulnerable

Groups This project affects no vulnerable groups.

6 RESETTLEMENT AND RESTORATION OF INCOMES

SCHEME

6.1 Demolition and Relocation

This project is a reconstruction and extension project. The construction design has abided by

the principle of minimizing the demolition and land acquisition area. The total house demolition

area is 2,889.03m2, all of which are rural houses, affecting 14 households with 73 persons.

6.1.1 Demolition and Relocation Objectives

The specific demolition and relocation objectives of the project are as follow.

(1) Minimize the impacts of involuntary resettlement by optimizing the project design.

(2) Guarantee the interests of the affected persons by providing sufficient and immediate

funds for the demolition and resettlement, which is the important part of the project;

(3) Provide help, like vehicles and labor force, to the affected persons during the demolition

and resettlement process;

(4) The affected persons will integrate into new community both in economic and social

field;

(5) Encourage the affected persons to prepare and implement the demolition and

resettlement plan while respecting their resettlement aspirations;

(6) Affected persons’ life and livelihood must restore as soon as possible to the state before

the project.

6.1.2 Demolition and Relocation Scheme

According to the →ushan County FF [2013] 28 and the affected persons’ aspirations of

resettlement, all of the 14 households affected by the demolition choose self-built resettlement.

Page 45: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 26

They will apply for the self-built houses in accordance with The Rural Homestead Management

Regulations after receiving the compensation set by Wushan County FF [2013] 28.

6.1.3 Demolition and Relocation of the Affected Persons

The homesteads of self-built resettlement will be chosen from their own village group area

by the project owner and the village committee with consultation with AHs. New homesteads cost,

administration cost, land leveling cost, road construction cost, utilities installation cost and the

mapping cost will be paid by the project owner, to make sure that the affected persons’ new

housing conditions are not worse than the “non-project” ones.

The planned compensation rate will increase by 50% of the standard in Wushan County FF

[2013] 28: 870 yuan/m2 for masonry-concrete structured houses, 720 yuan/m

2 for masonry-timber

structured houses, 540 yuan/m2 for masonry-timber structured houses and 270 yuan/m

2 simple

structured houses. The resettlement prices in the affected area are 800 yuan/m2 for

masonry-concrete structured houses, 650 yuan/m2 for masonry-timber structured houses, 500

yuan/m2 for masonry-timber structured houses and 250 yuan/m

2 simple structured houses. Based

on the survey, the replacement cost for self-building masonry-concrete structured houses is

around 800 yuan/m2. Therefore, the compensation rate can meet the requirements of resettlement.

The moving subsidy for affected households who have chosen self-built resettlement will be

distributed by household. 500 yuan moving subsidy will be given to the household with no more

than 3 members. For households with more than 3 members, each additional person will get 100

yuan increment. However, the maximum of the moving subsidy is 1000 yuan. Every affected

person can get 150 yuan of demolition and resettlement subsidy each month for 6 months. Every

affected person can get a one-off payment of 500 yuan for relocation subsidy.

For households with no more than 3 members will get 90m2 homestead. For households with

more than 3 members, each additional person will get 30m2 increments. However, the maximum

area of the homestead is 150m2. According to the survey, all the affected persons plan to choose

homesteads near the highways in a scattered manner. The specific sites are not set yet. The

affected HHs will get the new homestead for free. Affected persons will apply to the Land

Page 46: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 27

Administration Department for the land use right of homestead. The approval procedure is free of

charge. In addition, the land acquisition institution will pay for the land leveling and facilities

preparation. All the house demolished farmers have the right to salvage material. There will be no

charge for house relocation and reconstruction.

6.1.4 Compatibility Analysis of the Relocation Sites

Self-built resettlement households all choose to live in their own village, so their social

customs, language and culture, religious beliefs and so on will stay the same. The consistency is

favorable.

6.1.5 Concerns for the Vulnerable Groups

The vulnerable groups include five-guarantee households (without income sources), households

covered by minimum living security (CNY195/month per person) and households with disability and

women-headed households

Based on the definition and consultation, there’s no vulnerable group under this

subcomponent.

6.2 Restoration of Incomes

6.2.1 Income Objectives and Content

The overall income restoration objectives are to make sure that the affected persons’ income

and living standard will at least restore to the state before the project.

6.2.2 Income Loss Assessment

Income losses caused by permanent land acquisition is evaluated on the basis of the income

from plant industry and land loss area of the affected households. See Table 6-1.

Table 6-1 Income Loss Assessment Caused by Permanent Land Acquisition

Subitem Town Village

Affected

Households

Affected

Persons

Farmland

Acquisition Area

(mu)

Income from

Planting

Industry

yuan/mu/y

ear

Per Capita

Income Loss

(yuan/person

/year) Total Per

Capita

the Guihua

Bridge-Shil

ongping

Longmen

Office Lizao Village 84 358

18.12 0.05

1200 61

Wuxia Guihua Village 182 789 33.99 0.04 1200 52

Page 47: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 28

Section Town QIxing Village 12 51 1.92 0.04 1200 45

It can be found that the income loss of Lizao Village the maximum income loss caused by

the project: per capita income loss is 61 yuan. However, the overall income loss caused by the

project is relatively small. The average income loss proportion is about 3% of the per capita

income. For the average household with 4 people, the income loss is around 200-250 yuan,

accounting for 1% of their average income.

6.2.3 Income Restoration Plan

The income restoration plan mainly includes cash compensation, social insurance for people

who have changed their agricultural status into non-agricultural status, technical training,

recommended employment and other measures.

80% of land compensation fees in land acquisition shall be used to cover basic endowment

insurance for urban enterprise employees for land-expropriated farmers, and transferred by the

county land and resources bureau to the county labor and social security bureau; the remaining 20%

shall be paid to the affected rural collective economic organization for collective economic

development, and the production and livelihood restoration of its members.

The resettlement subsidy is paid to persons based on the amount of land to be acquired and

becomes larger if the amount of land per capita is lower. E.g, if the land per capita of Subvillage A

is 1 mu and the project will acquire 1 mu in the subvillage, which means 1 person should be

urbanized. Thus in this situation the resettlement subsidy for one mu land will be CNY36,000; but

if the land per capita is 0.5 mu, then 2 persons will be urbanized. And accordingly the resettlement

subsidy for 1 mu land will be CNY72,000.

The population to be converted into urban status of each village will be determined at a

village meeting based on acquired land area. All households affected by HD may apply for

conversion into urban status voluntarily. Most of the AHs prefer to convert old or 40s-50s family

members into urban status. The resettlement subsidy of any land-expropriated farmer aged under

16 years will be fully paid to the individual; one aged 16 years or above will pay endowment

insurance premiums based on age group, where the government and individual shall pay 50%

Page 48: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 29

each.

If the sum of 80% of the land compensation fee and the insurance paid by the individual is

less than the pension, the gap shall be paid by the land acquisition department.

6.2.3.1 Endowment Insurance for People Who Have Changed Their Status

(1) Number of People Who Have Changed Their Agricultural Status into Non-agricultural

Status

People in affected collective economic organizations that have lost

all land they own will have to change their agricultural status into

non-agricultural status. The number of people in affected collective

economic organizations that have lost part of land they own will be the

calculated result of the sum of farmland acquisition area (areas of

orchards, grassplots will be treated as farmland, the same below) and

0.5 uncultivated land area divided by the per capita farmland area of the

collective economic organizations before the project. See Table 6-2. The

choice of the people who have to change their status is based on the

land acquisition area order. The order will be decided by the

representatives of towns and village committees. Affected person who

has more land to be acquired will have the priority to change status.

The final list has not been worked out till the land agreement will be

signed.Table 6-2 Computation of the Number of the

“Agricultural to Non-agricultural” Status Changing

People

Subitem Administrative Division

Farmland

Acquisition

Area (mu)

Non-cultivated

Land Acquisition

Area (mu)

Per Capita

Land Area

(mu) Number: =[ +

*0.5]/ Town Village Group

the Guihua

Bridge-Shilongpi

ng Section

Lizao

Village

Lizao

Village

6 13.21 121.61 0.98 76

3 4.91 45.21 1.01 28

Wuxia Guihua 4 9.43 86.79 0.94 57

Page 49: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 30

Town Village 5 24.56 226.06 0.95 145

Qixing

Village 4

1.92 17.67 0.94 12

Total 318

Note: Decimals in the numbers calculated in the table have been treated as 1 person more.

(2) Endowment Insurance for People Who Have Changed Their Status

According to the Wushan FF [2013] 28, the consultations from the local Labor and Social

Security Departments and the practical situation, the choice of the people who have to change

their status is based on the land acquisition area order. The order will be decided by the

representatives of towns and village committees. With the respect for their aspirations, people

who have to change their status will pay for the endowment insurance. The endowment insurance

of people who have changed their status will be paid by their land acquisition and resettlement

compensation. If the compensation is not enough to pay the endowment insurance, the project

acquisition institution will make up the balance. If the compensation is more than the endowment

insurance payment, the balance will go to the affected person.

The population to be converted into non-agricultural status of each village will be

determined at a village meeting based on acquired land area. All households affected by HD may

apply for conversion into non-agricultural status voluntarily. Most of the AHs prefer to convert

old or 40s-50s family members into urban status. The resettlement subsidy of any land-acquired

farmer aged under 16 years will be fully paid to the individual; one aged 16 years or above will

pay endowment insurance premiums based on age group, where the government and individual

shall pay 50% each. People with different ages pay different endowment insurance premium. See

Table 6-3. The population converted into non-agricultural status will receive resettlement subsidy

of 36,000 yuan per person, which will be enough for the payment of pension insurance. The 50%

part which the government pays for the insurance is from the 80% of the land compensation and

land planning fee if not enough.

Table 6-3 Endowment Insurance Premiums and Pensions by Age Group

Age group Population Endowment insurance premium paid at

a time (yuan)

Pension receivable

(yuan)

Old people

80 years or

more 2 7500 750

75-79 10 7500 650

Page 50: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 31

70-74 13 8150-10750 550

Male 60-69

Female 55-69 43 11400-20500 500

40s-50s people Male 50-59

Female 40-54 82 20500 500

Middle- aged or young

people

Male 40-49

Female 30-39 37 11532 500

Male 20-39

Female 20-29 31 5766 500

16-19 7 1153.2-4612.8 500

Note: The resettlement subsidy of any land-expropriated farmer aged under 16 years shall be fully paid to the

individual.

Old people having attained retiring age will receive pensions from the month following the

approval of the compensation and resettlement program after paying endowment insurance

premiums at a time (According to 2013 standards, the basic pension is 500 yuan/month, and

starting from January 1, 2013, increase the monthly pension benefit per person 35 yuan, on the

basis, and in line with personnel pay period excluding converted seniority per year plus three

yuan. For December 31, 2012 and before the age of 75 years old people, will increase the monthly

pension benefit per person 50 yuan. After January 1, 2013 the age of 75 years old people, from the

age of 75 years old of month, will improve the original standards from 50 yuan to 100yuan per

person per month for elderly people.), so that each person converted into urban status will receive

an annual pension of at least 6,420 yuan.

6.2.3.2 Compensation for People Who Will Not Change Their Status

The compensation for people who will not change their status includes land compensation

fee and resettlement subsidy.They can develop investment projects like planting and breeding

industries with the help of the local government. According to the survey, suitable investment

projects for the place are in Table 6-3.

Table 6-4 Economic Investment Project Cost and Average Annual Income yuan

Project Unit

Investment yuan

Total Cost

Income yuan

Initial Cost

Annual

Operating

Cost

Labor Cost Gross Income Net Income

Pig Raising head 300 1000 1000 2300 4000 1700

Fruit Planting mu 800 700 1000 2500 5000 2500

Page 51: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 32

Small Shop

a village-

level 3000 20000 8000 31000 40000 9000

a town- level 6000 30000 10000 46000 75000 29000

Note: the initial cost includes sties, fruit seedlings and so on. The annual operating cost includes fertilizer, fodder

and so on.

6.2.3.3 Technical Training and Recommended Employment for the Affected Persons

Affected persons have the priorities to acquire the technical training and recommended

employment. The technical trainings arranged by the local government every year are available in

Table 6-4.

Table 6-5 Technical Trainings Arranged by the Local Government

Agency Training content Cost Training populations

Animal

Husbandry

Bureau

Black goats, pigs, rabbits

breeding

The government provides living

allowance at the rate of 30 yuan each

time (or day); the training usually lasts

a week each time, the government

grants 550 yuan for accommodation

subsidies.

All the farmers with

breeding animals more than

50

Forestry

Bureau Sericulture skills

living allowance at the rate of 100

yuan/person

All the farmers having the

willingness and the Aps

have the priorities.

Human

Resource

Bureau

Vocational training centers

provide technical training,

include: clothing, electronics and

electrical, process industries,

construction, drive repair,

machinery and so on.

Affected people can participate in free

training 5000 persons in 2012

Human

Resource

Bureau and

Poverty

Alleviation

Bureau

Pre-job skills training: Training

County Vocational Education

Center conducts a six-month

training program (including five

months’ training, a month

internship, and will recommend

jobs after training.

Poverty and resettlement people may

dispense with tuition

In 2012, cumulative

transfer of labor 180,000

people; Wushan Vocational

Industrial Park absorbs

about 3,000 people, and

150,000 people to

Guangdong, Shanghai and

other cities.

Women’s

Federation Tailoring

Affected people can participate in free

training

In 2012 a total of more than

8,000 people got trained,

and more than 1,500 people

got the jobs in Wushan

County Vocational

Industrial Park garment

factories.

6.2.3.4 Generate Income Involved in the Project

During the implementing process of the project, the recruitment of migrant labor should give

priority to the affected persons to help increase their income. The IA will give more chance to

APs for project engagement, especially for those unskilled position such as cleaner, cook, and

concierge. During the operation and maintenance stage, some jobs such as road cleaning, tree

Page 52: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 33

plant could be provided to the local Aps. Besides, employing women as workers during

construction will be considered as an important contract items. The road construction income is

2,640 yuan/month if calculated by 120 yuan/day and 22 days a month. The income of the affected

persons can be more than 50,000 yuan in 2 project years if they work 10 months a year.

6.3 Special Concerns

6.3.1Concerns for Women

Both men and women have the equal rights of being employed and trained. And during the

construction stage and the operation & maintenance stage of the project, some unskilled jobs as

road clean, road greening,cooking can be provided for the local women. →omen’s Federation

shall take part in the entire process of the technical training (such as opening small business along

the new road, e.g. ) and employment recommendation of women and pay close attention to

women’s income restoration, so as to guarantee that women enjoy the equal employment rights

with men during the land acquisition and income restoration.

6.3.2 Income Restoration Support of the Vulnerable Groups

This project affects no vulnerable groups.

6.4 Restoration of the Temporary Land Occupation

Temporary land occupation mainly refers to the construction site, construction material area,

borrow area mud disposal area and so on. According to Wushan FF [2013] 38, temporary land

occupation should sign Land Use Agreement with the affected households. The Land Use

Agreement must be sealed by the village committee and reported to the county Land and

Resources Bureau to be recorded. The land occupation institute can use the land only after the

approval and the distribution of the compensation. The longest temporary land occupation period

is no more than 2 years and the temporary land occupation is within 2 years.

The IA has to pay the compensation to the affected persons. Meanwhile, the IA will pay a

reclamation fee at the rate of 20/m2 to the county Land and Resources Bureau, and undertake the

Page 53: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 34

reclamation of the temporarily occupied land. The fee will be returned to the IA if the reclaimed

land has passed the inspection. If the affected land cannot be restored because of the external

factors, the cash deposit will be paid to the affected persons by the permanent land acquisition

compensation rate. If the land occupation institution cannot restore the affected land in person, the

cash deposit can be treated as the entrust cost for the relevant units to restore the affected land.

During the restoration of the temporary land occupation, Wushan County Land and

Resources Bureau will supervise the entire process of restoration according to the Land

Administrative Law until the condition of the restored land is acceptable.

7 RESETTLEMENT COST ESTIMATION AND

MANAGEMENT

7.1 Resettlement Cost Estimation

The total resettlement cost of the project of the Guihua Bridge-Shilongping section is

37,612,200 yuan, including four parts: (1) 183,320 yuan temporary land occupation compensation,

2,207,000 yuan demolition and resettlement compensation, 38,200 yuan attachments

compensation; (2) 2,735,500 yuan management and monitoring cost; (3) 9,801,600 yuan land

acquisition tax; (4) 2,279,600 yuan contingencies. See Table 7-1.

Table 7-1 Resettlement Budget

Serial

Number Name and Structure

Compensation

rate Unit

the Guihua

Bridge-Shilongping

Section

Number Cost

A Basic Cost 22795646.36

I Permanent Land Acquisition 20367227.68

1 Land compensation fee 16,000 yuan/mu 551.37 8821965.51

2 Resettlement subsidy 36,000 yuan/person 318 11448000.00

4 Crops Compensation 1,800 yuan/mu 54.03 97262.17

II Temporary Land Occupation 183242.88

1 Farmland Compensation 1,800 yuan/mu· year 18.19 32739.84

2 Temporary Non-cultivated Land

Occupation Compensation 900 yuan/mu· year 167.23 150503.04

House Compensation 2206973.80

1 Houses Masonry-concrete 870 yuan/m2 1453.51 1264553.70

Page 54: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 35

Structured

Masonry-timber

Structured 720 yuan /m2 437.66 315115.20

Earthe-Wall 540 yuan/m2 914.01 493565.40

Simple Structured 270 yuan /m2 83.85 22639.50

2 Moving

Subsidy

No More than 3

members 500 yuan/household 2 1000.00

4 Persons 600 yuan/household 3 1800.00

5 Persons 700 yuan/household 4 2800.00

6 Persons 800 yuan/household 2 1600.00

7Persons 900 yuan/household 1 900.00

8Persons 400 yuan/household 2 800.00

3 Demolition and Resettlement

Subsidy 150 yuan/month·person 73 65700.00

4 Relocation Subsidy 500 yuan/person 73 36500.00

Attachments Compensation

rate 38202.00

1 roads macadam 55

yuan/m2 75 4125.00

mud-gravel 33 290 9570.00

2 retaining

wall rubble 50 yuan/m3 45 2250.00

3 dams

concrete 30

yuan/m2

10 300.00

slab stone 20 55 1100.00

earth 10 35 350.00

4 tombs stone 2000 yuan/each 3 6000.00

concrete 3000 yuan/each 2 6000.00

5 wells

stone 30

yuan/m3

3 90.00

concrete 30 1 30.00

simple 15 3 45.00

6 cesspools stone 200 yuan/m3 10 2000.00

7 fruit trees

transplant grafted

seedling 3 yuan/plant 60 180.00

d=2-4cm 24 yuan/plant 31 744.00

d=4-7cm 27 yuan/plant 42 1134.00

d=7-10cm 53 yuan/plant 17 901.00

d=10-13cm 93 yuan/plant 6 558.00

8 weed trees

3cm以下 2 yuan/plant 133 266.00

d=3-5cm 5 yuan/plant 54 270.00

d=5-10cm 9 yuan/plant 52 468.00

d=10-15cm 17 yuan/ bundle 30 510.00

d=15-20cm 30 yuan/ bundle 27 810.00

9

sinocalamu

affinis and

miscellaneous

bamboo

small bundle less

than 20 plants 15 yuan/plant 3 45.00

big bundle 21~

40 plants 24 yuan/plant 19 456.00

Page 55: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 36

B management and monitoring cost 2735477.56

1 Resettlement Plan Implementation

and Management Cost 6% of A 1367738.78

2 Resettlement Plan External

Monitoring Cost 6% of A 1367738.78

C Land Acquisition Taxes 9801550.67

1 Land Acquisition Management

Cost 4% of A 911825.85

2 Land Acquisition Planning Cost 5000 yuan/mu 551.37 2756864.22

3 Farmland Reclamation Cost 20 yuan/m2 36041.04 720820.75

4 Paid Use of Newly-added

Construction Land Cost 8 yuan/m2 367765.69 2942125.50

5 Farmland Occupation Cost 25 yuan/m2 36041.04 901025.93

6 Forest Vegetation Restoration Cost 6 yuan/m2 261481.40 1568888.42

D Contingencies 10% of A 2279564.64

E Total A+B+C+D 37612239.23

7.2 Source of Fund

All resettlement compensation is paid by the supporting funds of the local government of

Wushan County.

7.3 Resettlement Cost Management

Table 7-1 is the fund flow diagram and the supervisory process. The owner institute or the

Resettlement Administration Office will manage the fund. The ADB Office of Wushan County

will supervise and direct the use of the fund to prevent fund embezzlement.

Table 7-1 Fund Flow Diagram

Resettlement Subsidy

Wushan County

Transportation Development

Co., Ltd.

Resettlement

Administration

Office → Affected Persons

80% of Land compensation

fee

eau

20% of Land compensation

fee

Wushan County

Transportation Development

Co., Ltd.

Resettlement

Administration

Office

→ Village

Committee

Resettlement

Institution/

Affected

Persons

Attachments Wushan County Resettlement → Affected Persons

Page 56: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 37

Transportation Development

Co., Ltd.

Administration

Office

Infrastructure and Special

Facilities

Wushan County

Transportation Development

Co., Ltd.

Resettlement Administration Office Owners of the

Facilities

All Kinds of Tax

Wushan County

Transportation Development

Co., Ltd.

Tax Collection Institution

Management Cost

Wushan County

Transportation Development

Co., Ltd.

Resettlement Administration Office

Training Cost

Wushan County

Transportation Development

Co., Ltd.

Training Institution

Supervision and Assessment

Cost

Wushan County

Transportation Development

Co., Ltd.

Individual Supervisory Body

Page 57: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

8 ORGANIZATIONS

8.1 Organizations Involved in the Resettlement

In order to implement the resettlement plan effectively, a top-down agency network within

governments of different levels will be established, which will be in complete charge of the

planning, coordination, implementation and monitoring of the resettlement. The agency network

for the resettlement is framed as shown in Figure 8-1.

the Leading Group of the

Project Office of ADB in

Wushan County

The Project Management Office

of ADB of Wushan County

Wushan Transportation

Development Co., Ltd (The

unit of the property owners)

The Migrant Resettlement

Management Office External Monitoring

Institution

The Migrant Resettlement

Management Office

Persons in Charge in the

Villages and Groups and the

Representatives of the Affected

Persons

The Affected Persons

Figure 8-1 The Agency Network for Resettlement

8.2 Responsibilities of the Organizations

1. The Leading Group of the Project of ADB in Wushan County

This leading group consists of the Deputy County Chief and related persons from such

departments as the Development and Reform Committee, Bureau of Transportation, Bureau of

Land Management, Bureau of Finance, Bureau of Civil Affairs, Office of Poverty Relief, etc.

Their primary duty is to strengthen their leadership in this project and ensure the effective

The

Leading

Bodies

The

Agencies

for the

Implement

ation of

Resettle-

ment

Page 58: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 39

implementation of the resettlement. In addition, they are also in charge of making the policies

concerning the resettlement and coordinating organizations of different levels in the land

acquisition and demolition. The Project Management Office of ADB of Wushan County is

established under the leadership of this leading group.

2. The Project Management Office of ADB of Wushan County

The Project Management Office of ADB of Wushan County consists of the staff from the

Development and Reform Committee of Wushan County, Bureau of National Land and Resources,

Water Conservancy Bureau, the owners of the project and leaders of governments of different

levels. Its main responsibilities include:

(1) Entrusting the design institution with the task of delimiting the impact scope and with the

socio-economic research as well as researches into the impact;

(2) Training the staff in charge of the specific resettlement work;

(3) Organizing and coordinating the making and enacting of the resettlement plan;

(4) Holding the public negotiation and publishing the resettlement plan;

(5) Monitoring the management and usage of the funds for the resettlement, and signing

agreements with the Migrant Resettlement Management Office.

(6) Instructing, coordinating and monitoring the entire resettlement process in the charge of

the Migrant Resettlement Office;

(7) Holding internal monitoring activities, making internal monitoring reports and

participating in the financial payments and the annual audits.

3. Wushan Transportation Development Co., Ltd

Under the leadership of the Project Management Office of ADB of Wushan County, Wushan

Transportation Development Co., Ltd is in charge of the implementation of the ADB project, the

internal monitoring. Meanwhile, it also has the responsibility to raise compensation for the

resettlement and to entrust the Migrant Resettlement Management Office with the specific

resettlement work.

4. The Resettlement Management Office

Page 59: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 40

The Resettlement Management Office is in charge of the specific implementation of the

resettlement, and its main responsibilities include:

(1) Assisting the design institution in delimiting the impact scope, and conducting

socioeconomic researches;

(2) Assisting in making and enacting the Resettlement Plan;

(3) Holding public negotiations and publishing the resettlement policies;

(4) Dealing with all the formalities involved in the application for, examination and approval

of the land acquisition;

(5) Managing the funds for the land acquisition, and monitoring its appropriation and usage;

(6) Training the staff for the resettlement work in the villages and towns;

(7) Monitoring the resettlement work in the villages and towns;

(8) Assisting in handling any problem encountered in the resettlement;

(9) Assisting in the internal and external monitoring;

(10) Writing reports on the implementation progress of the project and submitting them to

the ADB Office for examination.

5. The Coordinators for the Resettlement in the Villages and Towns

The Coordinators for the resettlement of the migrants in the villages and towns are mainly

in charge of:

(1) Participating in the project investigation and assisting in the making of the resettlement

plan;

(2) Organizing the public to take part in the propagation of the resettlement policies;

negotiating with the village committee and the representatives of the affected persons and

then confirming the persons that are to be transformed from rural residents to non rural

residents;

(3) Implementing, checking, monitoring and recording the resettlement within the local

region;

(4) Dealing with the selection of the locations of the new houses and all the formalities

Page 60: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 41

involved in the examination and approval for the construction;

(5) Participating in the payment and management of the compensation;

(6) Monitoring the land acquisition;

(7) Reporting the process of the land acquisition and resettlement to the County Bureau of

Land and Resources, the Project Office of ADB and the resettlement office.

Solving problems in the process of the project implementation.

6. The Village Committee and the Villagers’ Group

The main cadres of the administrative village will participate in the resettlement. Their

major duties include:

Participating in the socio-economic research and researches into the impact;

Organizing the public to take part in the propagation of the resettlement policies;

negotiating with the village committee and the representatives of the affected persons and

then confirming the persons that are to be transformed from rural residents to non rural

residents;

Implementing the land adjustment and organizing the restoration;

Managing the funds and holding conferences attended by villagers to discuss the usage of

the compensation;

Reporting to the superior organizations the opinions and suggestions of the affected

persons;

Handling appeals, conducting re-researches and other work in the later stages;

Reporting the resettlement progress;

Helping to resettle the disadvantaged households.

7. The External Monitoring Institution

The Project Office will entrust experienced monitoring agencies as the external monitoring

institutions. Their main duties include:

(1) Monitoring all aspects of the resettlement and reporting to Asian Development Bank

through the ADB Office.

Page 61: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 42

(2) Offering technical support and advices to the Project Management Office of ADB and the

Migrant Resettlement Management Office during the research and the drafting of the resettlement

plan.

Configuration of personnel in different institutions as shown in Figure 8-1

Figure 8-1 Configuration of Personnel

Department Person in Charge Title Telephone

People’s Government of

Wushan County Zheng Ping Town Chief 02357612345

People’s Government of

Wushan County Shang Wei Deputy Town Chief 02357683359

Development and Reform

Committee Li Shangkun Director 02357682509

The Governmental Office of

Wushan County Gong Xili Deputy Director 02357682879

Bureau of Finance of

Wushan County Wang Xin Deputy Bureau Director 023 57683765

Bureau of Transportation of

Wushan County Huang De’an Deputy Bureau Director 02357684232

Bureau of Forestry of

Wushan County Section Chief Liang Section Chief 18996656768

Bureau of Audit of Wushan

County Liu Qianzhong Vice Director General 02357691680

Government of WuxiaTown Tu Xiaoping Town Chief 02357693366

Wushan Transportation

Development Co., Ltd. Fang Jian CEO 13896907111

Wushan Transportation

Development Co., Ltd. Cao Ming 13609441136

8.3 Organizational Capability

In order to ensure the smooth implementation of the resettlement, the staff for the

resettlement must be trained and related fieldwork be conducted before the start of the land

acquisition and the resettlement of the relevant persons.

The ADB Office in Chongqing will be in charge of training the staff for the resettlement,

whose contents include the related ADB policies, domestic laws and regulations concerning the

land acquisition, theories on the socio-economic researches and the corresponding methods as

Page 62: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 43

well as requirements, etc.

In order to get the staff more acquainted with the project, the project office of Wushan

County will be in charge of training the staff for the resettlement to a further extent, whose

contents include the related ADB safeguard policies, respective laws and regulations on the land

acquisition of Wushan County, Chongqing Municipality and China.

The Migrant Resettlement Management Office should establish a polished information

management system for the land acquisition and manages the data concerning the compensation

for the land acquisition by means of computers. It should also consolidate the information

feedback by making a report to the project offices of the cities and towns concerned as well as the

owners of the project regularly (usually once a month) so as to ensure an unblocked information

access in a both top-down and bottom-up manner.

Page 63: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 44

9 IMPLEMENTATION PLAN

The resettlement includes: information disclosure, The Resettlement Plan and budget, detailed

income restoration plan, the renewal of The Resettlement Plan, Compensation Agreement signing,

implementation capability construction and internal and external monitoring etc. The specific

implementation is in Table 9-1.

Table 9-1 The Resettlement Implementation Plan

No. Resettlement Task Objectives Responsible Institution Deadline

A. Information Disclosure

1 Information Brochure Distribution 278 household County Project Office 2014.7

2

Issuing The Resettlement Plan in all Affected

Villages 3 villages County Project Office 2014.7

3

Issuing The Resettlement Plan on ADB’s

Website The Resettlement Plan ADB 2014.8

B. The Resettlement Plan and budget

1 The Approval of the Implementation Plan Wushan Transportation Bureau 2014.6

2

The Approval of The Resettlement Plan and

budget 36, 732, 000 County Government 2014.7

3 The Approval of the Compensation rate County Government 2014.8

C. Detailed Income Restoration Plan

1

Representative Assembly of the Resettlement

and Income Restoration Plan 3 villages

County Project Office,

Governments of Towns and the

County, Villages 2014.7

2 Technical Training for the Affected Persons all affected people

County Project Office,

Governments of Towns and the

County 2014.7– 2014.12

D.

Detailed Design and the renewal of The

Resettlement Plan

1

Decision of the Cut-off Date and Detailed

Design

Design Unit; County Land and

Resources Bureau t2014.7

2 Detailed Measurement and Investigation

County Land and Resources

Bureau, Towns and Villages 2014.6-7

3 The Approval of the Land Use 551.37 mu Land and Resources Bureau 2014..8

E. Compensation Agreement

1 Agreement with the Villages 3 villages

County Land and Resources

Bureau 2014.8

2 Agreement with the Households 278 households

County Land and Resources

Bureau 2014.8-9

F. Implementation Capability Construction

1 Responsible Staff from Towns for Resettlement 3 villages

County Land and Resources

Bureau 2014.7

Page 64: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 45

2 Appointed Village Cadres 6 persons

County Land and Resources

Bureau 2014.8

3 Train the Employee all personnel

County Project Office, Land and

Resources Bureau 2014.6

4 Establish the Appeal Mechanism 12 persons

County Project Office, Land and

Resources Bureau 2014.6

G. Monitoring and Evaluation

1 Basic Information Investigation 25% affected persons External Monitoring Institute 2014.9

2 Establish the Internal Monitoring System

Municipality, County Project

Office, Towns and Villages 2014.8

3

Signing Contract with the External Monitoring

Institute 2014.8-2017

4 Internal Monitoring Report Semi-annual Project Office 2014-2017

5 External Monitoring Report twice a year External Monitoring Institute 2014-2016

6 Evaluation Report once a year External Monitoring Institute 2016 and 2017

H. Consultation Records Project Office 2014-2018

I. Record of grievances Related local government 2014.10

J. Commencement of Civil Works Related local government 2014.10-12

1. Transfer of land to Project

Related local government 2014.8

2. Demolition of housing

Related local government 2014.8

3. Relocation to new houses APs 2014.12

Page 65: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 46

10 MONITORING, EVALUATION AND REPORTING

SYSTEM

In order to ensure the smooth implantation of the land acquisition, housing demolition and

resettlement of the migrants concerned, this project will toughly abide by the policy of the

migrant resettlement of Asian Development Bank by regularly monitoring and evaluating the

work of land acquisition and the migrant resettlement. The monitoring system consists of two

independent parts, namely the internal monitoring and the external monitoring.

10.1 Internal Monitoring and Evaluation

The internal monitoring comprises a monitoring system, clearly articulated goals, definite

tasks, the exact work to be conducted and reports, etc.

10.1.1 The Internal Monitoring Institution

The internal monitoring will be in the charge of the leading Group of the Land Acquisition,

Demolition and Resettlement of Wushan County, but the detailed operative work will be

conducted by the Land and Resources Bureau of Wushan County and the group of the migrant

resettlement on the specific village and town levels. The fundamental purpose of the internal

monitoring is to ensure that all the agencies on different levels can function effectively in the

course of executing this resettlement plan, and to ensure the protection of the legal rights and

interests of those influenced by the project as well as the successful implementation of the entire

project.

10.1.2 Internal Monitoring Objective

(1). To check the progress and completion of the land acquisition and demolition.

(2). To ensure an unblocked channel of communication and negotiation between those in charge

of the project and the persons affected by this project.

(3). To ensure that the persons affected by the project are to receive their compensations at the

Page 66: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 47

time stipulated by the agreement without any corruption involved.

(4) To ensure that the appeals proposed by the persons affected by the project are to be handled

within the stipulated period of time.

10.1.3 The Main Content of the Internal Monitoring

(1). The payment of the compensations for the migrants

(2). The resettlement of the persons affected by the project.

(3). The specific schedule for the land acquisition, demolition and compensation.

(4).The conformity to the relevant policies concerning the land acquisition, demolition and

resettlement.

(5). The participation and negotiation of the migrants in the course of the implementation of the

entire project.

(6). The training for the resettled migrants, the work scheme and the working efficiency.

10.1.4 Internal Monitoring Report

In the course of the implementation of the project, the governments of towns and villages

concerned will, based on the monitoring samples, collect and record the resettlement

information of the persons affected by the project and convey this progress to the agency

responsible for the project in the county.

10.2 External Monitoring and Evaluation

10.2.1 External Monitoring Institution

The current external monitoring agency entrusted by Halcraw will conduct the external

monitoring for this project, and submit the related report to ADB through CPMO.

10.2.2 External Monitoring Objectives

(1). To ensure that the living standard of the persons affected by the project will be reinstated to

and remain at the original level after the completion of the land acquisition, demolition and

compensation work.

Page 67: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 48

(2). To find out the related causes if their living standard fails to be restored to the original level.

(3). To make an evaluation of the general efficiency, effects, impacts (including the behavioral

reactions of the persons affected by the project) and the sustainability of the resettlement policies.

(4). To make an evaluation as to whether the living standard, the means of livelihood and the

income of the persons affected by the project are completely restored.

(5) To monitor whether the AP’s livelihood status keep the same or better after the

construction.

10.2.3 External Monitoring and Evaluation Method

(1). The independent monitoring institution will make an exhaustive research into the persons

affected by the project in order to obtain information about their present standards of production

and living. The survey about their standards of production and living will be conducted once a

year in order to measure the changes in them. Such methods as the tracking surveys, random

interviews and fieldwork will be employed so as to gain the indispensable information for the

evaluation.

(2). Group discussions, negotiations and consultations with the parties concerned (the local

government, non-governmental organizations, the community leaders and the affected persons).

(3). Interviews with the key figures such as the local leaders and the village leaders for a detailed

knowledge of the specific implementation of the resettlement.

(4). To make some public conferences to learn more about all the aspects of the resettlement

work.

(5). Personal investigations of the implementation of the work of the land acquisition, demolition

and compensation, and interviews with individuals or organizations.

(6). Informal surveys or talks; to make an informal research into the affected villages and the staff

in charge of the resettlement work by means of non-sampling methods.

Page 68: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 49

10.2.4 Main Tasks

The independent monitoring institution will monitor and evaluate the land acquisition and

resettlement, and make an assessment report on the basis of the findings. The independent

monitoring institution must submit the assessment report to Asian Development Bank, the agency

in charge of the project and other related departments in order to assist them in making policies.

The affected persons and the non-governmental organizations will also participate in the

monitoring and evaluation of the project.

The monitoring and evaluation should include:

(1). The progress of the land acquisition, demolition and compensation work;

(2). The progress of the resettlement of the affected migrants;

(3). The specific usage of the compensation funds;

(4). The restoration of the living standard of the affected persons;

(5). The working efficiency of the resettlement institution;

10.2.5 External Monitoring and Evaluation Report

The external monitoring and evaluation institution will, based on the progress of the

resettlement, submit an external monitoring and evaluation report to Asian Development Bank

through its office. After the implementation of the resettlement, such a report will be submitted

once a year until the living standard of the affected farmers is restored to their original level.

Page 69: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 50

Appendix 1 Resettlement Information Brochure (RIB)

(The name of the affected person)

The Road Project of the Guihua Bridge—Shilong Ping Section of Wushan Coutny is a key

component of the ADB-financed Chongqing Urban-Rural Infrastructure Development

Demonstration Project, whose construction is to entail some impact for your family (or unit). This

brochure is aimed at acquainting you with some basic information about this project, the specific

impact, the resettlement policies, the compensation rates, the scheduled progress of the

resettlement work, the rights and interests of the persons affected by this project and the appeal

procedures.

1. A General Introduction to this Project

The Guihua Bridge—Shilong Ping Section of Wushan County , where the Guihua Village is

situated, starts from the eastern end of the Guihua Bridge and ends where it converges with the

Shilong Ping section of the provincial highway S103, and finally gets connected with the national

highway G348 (the present provincial highway S103), spanning 12.2km in total. The roads from

the Guihua Bridge to the Zaoyang New Zone of Tourism are 4-lane dual carriageways linking

cities and those from Zaoyang New Zone of Tourism are tertiary highways.

2. The Areas Affected by the Land Acquisition

The land acquisition will concern 5 groups in 3 villages of 2 towns with a permanent

acquisition of 551.37 mu of collective land consisting of 54.03 mu of farmland, 392.03 mu of

woodland and 105.31 mu of wasteland, involving 1,198 people from 278 households. The

temporary land occupation area totals 185.41 mu consisting of 18.19 mu of farmland, 131.78 mu

of woodland and 35.45 mu of wasteland, involving 414 people from 9 households. The area of the

Page 70: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 51

houses to be demolished totals 2889.30m2, all of which are located in the rural region. Among the

houses are 1,453.51m2 of masonry and concrete structured houses, 437.66m

2 of masonry and

timber structured houses, 914.01m2 of cob-wall structured houses and 83.85m

2 of simply

structured houses, involving 73 people from 14 households.

3. The Resettlement Policy

The resettlement policies concerned here are mainly based on such documents as Safeguard

Policy Statement (Manila, June 2009), The Notice about the Further Adjustments Made to the

Compensation and Resettlement Standards for the Land Acquisition and Demolition Issued by

Wushan County Government ( Wushan FF [2013] 28).

4. The Rights and Interests of the Affected Persons

The affected land, agriculture and income sources, whether they are affected permanently or

temporarily, privately owned or publicly owned, will be estimated and then get compensated or

restored according to their types and amounts of damage.

After 27, June 2014, the newly cultivated land, constructed buildings or residencies shall not

be compensated. In addition, any utilitarian construction and planting for the purpose of

compensation shall not be compensated.

The affected persons will be compensated in proportion to their replacement costs while the

depreciations shall not be taken into consideration. For the vulnerable, the compensation for their

land and property must be fully paid in time. The local governments and village committees

should pay special attention to them in the process of restoration. For example, those capable of

physical work should be provided with opportunities for a further development while the

widowed and handicapped without any work ability should be included in the local social welfare

system.

5. Compensation rates

Number Name and Structure Unit Compensation rate

I. Compensation rate for Permanent Land

Acquisition

1 Compensation for the Farmland yuan/mu 16,000

2 Compensation for the Farmland-based Farmers yuan/mu 36,000

5 Compensation for the Green Crops yuan/mu 1,800

Page 71: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 52

II. Compensation rate for Temporary Land

Occupation

1 Orchards, Paddy Fields, Dry Farmland, etc. yuan/mu 1800

2 Woodland and others yuan/mu 900

. Compensation for the Demolition

1 Houses

Masonry-concrete Structured yuan/m2 870

Masonry-timber Structured yuan/m2 720

Cob-wall yuan/m2 540

Simply-structured yuan/m2 270

2 Compensation for the

House Moving

no more than 3 family members yuan/household 500

4 family members yuan/household 600

5 family members yuan/household 700

6 family members yuan/household 800

3 Compensation for the Transitional Period of the

Resettlement yuan/month·person 150

4 Compensation for the Resettlement yuan/person 500

Attachments to the Ground

Attachments Type Unit Unit Price

1 road macadam yuan/ m2 55

mud-gravel yuan/ m2 33

2 enclosure rubble yuan/ m2 50

3 dam

concrete yuan/ m2 30

slab stone yuan/ m2 20

earth yuan/ m2 10

4 tomb earth grave yuan/each 2000

with tombstone yuan/each 3000

5 well

stone yuan/ m3 30

concrete yuan/ m2 30

simple yuan/ m2 15

6 cesspool yuan/each 200

7 fruit tree

transplanted grafted seedlings yuan/ plant 3

d=2-4cm yuan/ plant 24

d=4-7cm yuan/ plant 27

d=7-10cm yuan/ plant 53

d=10-13cm yuan/ plant 93

8 weed tree

lower than 3cm yuan/ plant 2

d=3-5cm yuan/ plant 5

d=5-10cm yuan/ plant 9

d=10-15cm yuan/ plant 17

d=15-20cm yuan/ plant 30

9

sinocalamu affinis

and miscellaneous

bamboos

small bundle less than 20

plants yuan/ plant 15

Big bundle 21~40 plants yuan/ bundle 24

6. Appeal Procedures

Page 72: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 53

In order to ensure that the opinions of the affected persons on such issues as the land

acquisition, the compensation and the resettlement can receive the feedback in a transparent, fair

and effective manner, and to avoid their being forced to resort to complicated formal channels to

express their dissatisfaction or dissents, those in charge of this project has set up the related

appeal procedures. The complainant can submit his or her complaint intention to Asian

Development Bank to seek some resolution. If the complainant is still unsatisfied with the

proposed resolution, or it violates the Safeguard Policy Statement, the complainant can lodge his

or her appeal directly through the No.1 responsibility system of Asian Development Bank.

Besides, the affected person can appeal to courts of any level. The appeal procedures and the

contact information of the corresponding person or organization in charge in each stage are as

follows:

申 各阶段负责人

Stage Case Accepting Contact Office Address

Stage 1: If the affected person is unsatisfied with or has any dissents on the land acquisition, demolition and

compensation, he or she can appeal to the local village committee in an oral or written form. If it is an oral

appeal, the village committee should record it in a written way and handle it within 2 weeks.

Stage 2: If the affected person is unsatisfied with the decision made in the first stage, he or

she can appeal to the local government in the town in a written form after receiving the

handling result in the previous stage. The government should handle it within 2 weeks and

inform the complainant in a written form.

Stage 3: If the affected person is unsatisfied with the decision made in the second stage, he or

she can appeal to the National Land and Resources Bureau according to the relevant law after

receiving the handling result in the previous stage. The National Land and Resources Bureau

should handle it within 2 weeks and inform the complainant.

Stage 4: If the affected person is unsatisfied with the decision made in the third stage, he or

she can apply to the people’s government of the town concerned for an administrative

reconsideration after receiving the handling result in Stage 3, or lodge an administrative

appeal to the local people’s court according to the civil procedure law within 3 months.

Figure 4-1 Appeal Procedures

Page 73: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 54

1. Before submitting the procedure intention through the ADB responsibility mechanism, the affected person

can have some negotiation with the related department of ADB to seek some resolution. If the affected person is

unsatisfied with the resolution proposed, he or she can then resort to the responsibility mechanism for an appeal.

and Hearing

Body

Telephone

1 Longmen Office Zhang Gong 023-57623190 Government

WuxiaTown Chen Rongbin 13594465656 No. 56, Middle Rd., Guangdong

2

the Project Office

of Wushan

County

Zhou Bing 13983538190 National Development and Reform

Committee

3

National Land and

Resource Bureau

of Wushan

County

Wu Qiang 023-63651411

4

The People’s Court of Wushan

County

He Shaofeng 02357651010

Page 74: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 55

附件 2 巫山县补偿文件

Page 75: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 56

Page 76: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 57

Page 77: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 58

按照 2008年

Page 78: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 59

Page 79: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 60

Page 80: Updated Resettlement Plan Subproject of Guihua Bridge ... · Number Parameter Unit Quantities/indicator 1 Road Length km 12.2 Width m 8.5m 2 Class m3 III Earthwork m3 141460 Stonework

亚洲银行贷款重庆市巫山县绕城路桂花大桥至石龙坪段道路工程移民安置报告

重庆巫山县人民政府 重庆多杰投资咨询有限公司 61