university of cincinnati€¦ · web viewramp metering systems are traffic devices used to...
TRANSCRIPT
Project Progress Report
Ramp Metering in Freeway System
Submitted To:
The 2014 Summer NSF REU Program
Sponsored By:
The National Science FoundationGrant ID No.: DUE – 0756921
College of Engineering and Applied ScienceUniversity of Cincinnati
Cincinnati, Ohio
Prepared By:
Emma Hand, Civil Engineering, University of CincinnatiJared Sagaga, Computer Science, University of Cincinnati
Isaac Quaye, Aerospace Engineering, University of Cincinnati
Report Reviewed By:
Heng Wei, PhD, PE, EITREU Faculty MentorAssociate Professor
Department of Civil and Architectural Engineering and Construction ManagementUniversity of Cincinnati
July 3, 2014
1
Abstract
In 2013, traffic congestion cost commuters in the U.S. approximately $101 billion in lost time
and wasted fuel. Local governments and transportation agencies have used a variety of
mitigation strategies to reduce the cost of traffic congestion. This report examines one such
strategy, ramp metering. Using a modelling approach to evaluate the various types of metering,
we will be taking into consideration various components such as operational characteristics, the
ramp meter system in effect, and the amount of lanes on the on-ramp. The key element of
deploying a ramp metering system is to control the traffic entering the freeway mainline, with the
intent to reduce congestion and in turn reduce travel times and ensure the safety of motorists.
Data collected during this project along with previously gathered data will be used to create
traffic simulations using the micro simulation software VISSIM, and to determine the
effectiveness of the placement of these meters.
2
Introduction
Ramp metering systems are traffic devices used to control traffic entering the freeway mainline.
Ramp meters are being used in states such as Arizona, Michigan, Minnesota and others, and have
been shown to successfully regulate the flow of traffic on the freeway in order to reduce
congestion, collisions and travel times to destinations. Different types of metering systems are
used in differing situations, and each has its own benefits and drawbacks, including maintenance
costs and ease of use. Ramp meters have been under development for decades, and have been
proven in many cases to be successful, with benefits far outweighing any drawbacks.
Departments of Transportation (DOT) in several states have performed tests which have proven
the effectiveness of ramp meters, and have included the voice of the public in meter installation
projects in order to gain the acceptance of residents and others who will be affected by the
metering systems. While ramp meters have been proven to be successful, there are some
limitations to these systems. They are very expensive to implement and maintain, and
complicated algorithms are used that will render ramp meters ineffective if there are any errors.
Isolated ramp meters fail to detect upstream or downstream traffic flows, which can result in
serious traffic congestions when there is sudden traffic change. Regardless of these limitations,
ramp meter strategies are expanding nationwide.
Background Literature Review
Ramp Meters in Different States
Several states around the country use ramp metering to control traffic, increase freeway safety,
reduce travel time and maximize freeway throughput. Some of these states include Minnesota
(433 ramp meters), Arizona (300 ramp meters), California (1,000 ramp meters), and Washington
3
(280 ramp meters) (Minnesota Dept. of Transportation; Arizona Dept. of Transportation;
California Dept. of Transportation; Jacobson, Stribiak, Nelson, Sallman). The types of ramp
meters used vary from state to state. In Minnesota, depending on the ramp and traffic conditions,
either fixed time or responsive ramp meters are installed, and are monitored throughout the entire
state in a single system containing many sub-systems (Jacobson, Stribiak, Nelson, Sallman). In
Washington, responsive traffic meters and fuzzy logic are used to run the ramp metering system
statewide (Jacobson, Stribiak, Nelson, Sallman).
The introduction of ramp metering to Minnesota and Washington brought about several benefits,
but also presented each state with some difficulties during the implementation of the metering
systems. Some of the difficulties that were faced by each state’s Department of Transportation
about ramp metering include:
Poor performance in inclement weather or during special events
Vehicle queues force overrides causing the algorithms to restart
Staffing, training, and ramp metering implementation
Complete acceptance by the public
Poor marketing of its benefits and high reciprocity at a low expense
The Departments of Transportation in Minnesota (Mn/DOT) and Washington (WSDOT) are still
facing these issues today (U.S. Dept. of Transportation). With technology improving every day,
however, the difficulties are not as severe as when ramp metering was first introduced onto these
states’ freeways. These difficulties can also cause decisions on ramp metering installation to
take some time, especially if public input is needed to make the decisions. Washington includes
4
the public in its ramp metering program, with public outreach and disseminating information
being vital to any planning of ramp metering installation (Jacobson, Stribiak, Nelson, Sallman).
Minnesota has also implemented this type of method into their future plans for proposed ramp
metering installations after performing an evaluation in 2001 on their ramp metering system in
Twin Cities.
Uses of Ramp Metering
According to the FHWA (Federal Highway Administration),
- Ramp meters are used to regulate and reduce traffic volume on freeways by spreading out
queues of vehicles over a period of time.
- Reduced traffic congestions are a result of traffic meters, increasing freeway speeds and
thereby improving travel time and travel time reliability.
- Metering systems help lessen crashes on freeways around the entrance ramps, in effect
ensuring the increased safety of motorists.
Types of Ramp Metering
There are different types of ramp metering systems that are put in place, each with its own
benefits and limitations.
1. Fixed Ramp Metering
Fixed Ramp Meter systems, also called Pre-timed Ramp Meter systems, operate on a fixed ramp
cycle, or period of time that the meter goes through the colors red and green. This pre-timed
meter cycle is based off of data from past traffic conditions, assuming the patterns of these
5
conditions are fairly constant from day to day (Kang). Different meter cycles are used depending
on how many cars are intended to pass through. A system designed to break up platoons, or
large groups of vehicles, has a cycle between four to seven seconds, with meter rates lasting just
long enough for one or two cars to pass through at a time. During times of the day when traffic
is not expected to be as busy, cycles last ten seconds or more allowing three or more vehicles to
pass at a time. In the present study, the cycle used for the single lane on ramp will be four
seconds and the cycle for the two lane ramp will be 6.56 seconds.
1.1 Benefits
Fixed ramp meter systems have low maintenance costs, and provide drivers with a reliable
pattern to which they can easily adjust (Kang). The pre-timed systems provide benefits
associated with reduced congestion. Travel time and side-swipe accidents that happen when
incoming traffic merges onto the mainline freeway are lessened, while throughput, or the lack of
traffic stand-stills, is increased.
1.2 Limitations
Fixed meter cycles do not respond to any traffic conditions on the freeway mainline, remaining
unaltered even if there are sudden fluctuations in the traffic. There can also be a problem with
fixed meter systems when the amount of vehicles on the on-ramp reaches capacity, because
traffic enters the on-ramp at a greater rate than the meter allows traffic to access the freeway.
6
2. Traffic Responsive Ramp Metering
The meter cycles of responsive ramp meters are based on real-time measurements from sensors
installed along the freeway network shown in Fig. 1. The mainline loops give the occupancy of
the mainline traffic. The passage loop gives the count of vehicles that pass through the meter.
The demand loops relay to the meter when there are vehicles waiting to enter the freeway; when
these sense no vehicles, the meter remains red. The queue loop senses how many vehicles enter
the on-ramp and whether it is full. All of these factors contribute to the meter’s determining of
the meter rate. These meter systems can be either local or coordinated. The local ramp metering
method uses measurements from an area around a single ramp whereas the coordinated ramp
metering system uses data from the entire network. Sites have differing traffic conditions, and
based on these conditions an apt algorithm is used. Depending on the algorithm used,
coordinated responsive systems either sense only traffic from local arterials, streets by the
highway, or communicate with meter systems on adjacent ramps. (Papamichail I., and
Papageorgiou, M.)
7
Figure 1. Responsive ramp metering system diagram
2.1 Benefits
The local and coordinated ramp metering strategies have proven to be more efficient than the
fixed traffic ramp meters because of the sensors that communicate between the freeway and the
ramp meters. There are no backups onto local arterials due to the sensor at the entrance to the
on-ramp. Sensors detecting the current traffic conditions on the mainline freeway allow the
meter to change its rates accordingly. The traffic responsive strategy is a better regulator of
traffic from the ramp joining the freeway.
8
2.2 Limitations
Coordinated ramp meter systems are extremely complex, and thus very expensive to install and
maintain. Isolated systems do not take into account the traffic upstream or downstream of the
on-ramp. This can cause problems if sudden traffic changes occur further out than the isolated
system senses, and the ramp meter allows too much traffic to enter the freeway. (Papamichail I.,
and Papageorgiou, M.)
Goals and Objectives
The objectives of this project are to investigate and understand the effectiveness of ramp
metering placements, and determine the number of installments needed on a stretch of highway.
The effects of single and two lane ramp metering implementation will be observed, through data
collected from I-275 and US-42 Lebanon Road during peak periods, simulations created by the
group in VISSIM, and information gathered from several other sources. The research tasks to be
undertaken are completing data processing of the GPS and video data collected on the I-275 and
US-42 Lebanon road and completion of VISSIM software training. We estimate that the data
collections and processing will be completed by the end of the 4th week and VISSIM training will
be completed by the end of the 5th week. This will allow us to begin simulations during the 6th
and 7th weeks on the software and to investigate the effects of placing ramp meters on the sites of
interest on the I-275. We will provide progress reports on our training and findings in our
biweekly reports and presentations along the way as we work towards completing our final
technical paper, poster, and PowerPoint presentation.
Scope of Study
9
The main focus of this research will be on the traffic conditions at a single lane on-ramp without
a ramp meter, and both single and two lane on-ramps with ramp meters.
The selection of the sites should meet the following criteria:
1) There are elevated locations nearby for placing the camcorder to capture the traffic.
2) Location should be busier in the peak hours than the normal flow of freeway.
Based on the above criteria, the I-275 and US- 42 Lebanon road intersection is the chosen study
site selected for the current research. Video data will be collected and post-processed using a
traffic counter, and a GPS device will be utilized while driving on a given stretch of the road
during peak hours of the day. Traffic flow on the freeway mainline, on-ramp, and arterials will
be observed, and both a single and two lane ramp implementation will be investigated.
Information gained from the observations of these on-ramps will be analyzed in order to
determine which type of ramp metering is most effective and efficient. The gathered data will be
used to create simulations of possible real-world scenarios in VISSIM. The simulations will also
aid in the investigation of future implementation of ramp metering.
Materials and Methods
Research Training
Training on background information for ramp metering was given by our GRA. We received
reading materials and presentations on the origin, progress and status of ramp metering across
the country. We learned how to use the GPS and traffic data collector, and to interpret data
retrieved from these devices. We also received preliminary training on VISSIM and aim to
complete training in the coming weeks.
10
Data Collection
Our team received hands-on training from our faculty mentor and GRA on data collection
methods, which included field work on I-275 to observe the sites of interest between the
Mosteller and Reed Hartman exit ramps. Fig. 2 shows our team at the study site around the
Sharonville exit ramp. We observed the loop detectors that were installed on the ramps and the
loop detector stations that communicated with these detectors. Fig. 2.1 shows a loop detector
station. Fig. 3 displays a GPS device used for tracking and storing information of the route
taken, after which we received training on how to retrieve data from the device for interpretation.
The GPS data collected gave us information on the travel time between the two sites of interest,
route taken, number of trips and time of day data was collected. Another data collection method
was the use of cameras which were installed on elevated surfaces to collect video data of traffic
on the ramps of interest. The cameras recorded traffic data all day thereby giving us traffic data
of the different peak periods in the day. After retrieving the videos from the cameras, we
watched the videos and with the use of the traffic data collector device (Fig. 4) we counted the
number of cars around the sites of interest. Also received training on how to represent the
collected information graphically to be able to understand the average travel time and the peak
hours of traffic.
11
Figure 2. Observing the study site
Figure 2.1. Loop Detector Station
12
Figure 3. GPS device
Figure 4. Traffic Data Collector
13
Simulation
In order to create a simulation model in VISSIM, a network model is built by adding a scaled
aerial background image from a map of a selected route on a freeway. The background images
makes it possible to trace lanes, connectors and links to complete the design of the network
model. Before starting a simulation model, vehicle composition (types of vehicles to be placed
on the freeway), vehicle volume, route decisions and control signals have to be added to the
model to reflect the present traffic situation. After simulation parameters are set, the model is
ready to run simulations. Data such as travel time and link evaluation can be retrieved after a
simulation run. After changes such as placing meters and other control signals are made on the
network model, data changes can be compared and analyzed.
Validation and Calibration
As discussed earlier, traffic simulation models performed in VISSIM make use of traffic
demand, vehicle routing decisions, driver behavior, vehicle compositions, and control signals etc,
to aid in investigating a real world traffic condition on freeway systems. In order to be able to
have accurate results from VISSIM such as travel times from one point to another, the software
has to go through a calibration and validation process as shown in Figure 5. Calibration
parameters can be described in two categories, system calibration and operational calibration.
System calibration investigates input assumptions and operational calibration focuses on detailed
driver behavior features that affect overall traffic operations in the model. Calibration is
described as the adjustment of computer simulation model parameters to accurately imitate the
present conditions of the freeway system. Examples of adjustable parameters are vehicle
acceleration distributions, vehicle speed distributions, car following behavior, route decisions
14
and lane change gap. The proposed calibration methodology includes three major stages; 1) base
model development, 2) planning of calibration approach, and 3) model calibration and
validation.
To shed more light on these adjustable parameters in the network model in order to better
reflect the present traffic conditions is described below.
Car following behavior
This parameter sets the distance and the speed behavior of cars following lead cars. This ensures
that cars are not too close to each other thereby resulting in better lane changes and ramp exit
decisions. This parameter is based on the continued work of Wiedemann. The basic idea of his
model is that a driver can be in one of four driving modes (Wiedemann, 1991); free,
approaching, following, or braking. When a threshold based on speed and distance differences
between the lead and the following cars are crossed, the state changes.
Routing Decisions
A routing decision directs the vehicles in what routes to take. Whether the car will exit, merge
onto the freeway, join arterials, are all determined through the routing decision. There are four
types of routing decisions and routes, known as, static, partial, parking lot and managed lanes.
The static decision is the most common route decision in VISSIM. It has a start point and a
destination and uses a static percentage for each destination.
Priority Rules
In VISSIM, the right of way movements is determined with priority rules. Such priority rules
apply at the merging and diverging part of the traffic.
Desired Speed Changes
15
This is used to determine the changes of free flow speed in VISSIM network. This is got from
site specific and speed limits rules. There are two ways of defining speed changes: Reduced
speed areas which is temporary and a more permanent change known as desired speed decisions.
Validation is the process of comparing simulated model results with the collected data
measurements to verify the accuracy of the simulation model. The main purpose of the validation
stage is to identify parameter settings in the simulation model which helps reach similar results
as the data collected from the field. It’s important to know that once a model is validated, it can
be used to analyze any future traffic situations which may include modifications to trip
distribution, travel demand, etc. The only time this model cannot be used for future traffic
scenarios is when significant changes has been made to the freeway.
16
Figure 5. Calibration Methodology
17
Results and Discussion
In Table 1, we see data of west bound and east bound average travel times on the I-275 from the
Mosteller road ramps to the Reed Hartman road ramps. For each trip, 3-6 loops were made
around the highway. The times displayed below are averages of these loops. The total average is
then taken from these times. The east bound route was divided into two sections and the west
bound route was also divided into two sections. This data was taken in the morning, afternoon
and evening to better understand the different travel times at different times in the day. The
mornings of May 21-May 26 we discovered that the average travel times from the Mosteller on
ramp on to the I-275 east, ranged from 00:45 sec and 00:50 sec on section 1 and 1:59 sec to 2:44
sec which average out to be 00:48 and 2:42 sec respectively. In the afternoon hours of May 19-
May 26 along this same route, the average of the travel times in section 1 was 00:52 sec and
section 2 was 2:19 sec; also in the evenings, travel times average at 00:46 sec in section 1 and
2:24 sec in section 2. After analyzing this data, we can see that there was very little variation in
travel times between these two destinations at different hours of the day. However, when we
consider travel times on the I-275 route heading west bound we discovered the averaged times
during the different hours of the day were slightly more. For sections 1 and 2 travel time
averages were 2:02 sec and 1:30 sec respectively, and for the afternoon, travel times were 2:01
sec and 1:32 sec respectively. Lastly, the evening times showed average times of 1:49 sec and
1:29 sec. After analyzing this information, we can see that there is increase in times compared to
the east bound travel times. This can be due to more volume of cars going west bound at the
different times in the day.
Table 1: Average East Bound travel times on I-275 between Mosteller and Reed Hartman ramps.
18
MorningDate Average Time (min:sec)
Section 1 Section 25/21/14 00:50 02:095/22/14 00:50 03:305/23/14 00:47 03:005/24/14 00:47 01:595/25/14 00:50 02:515/26/14 00:45 02:44
Total Average 00:48 02:42Afternoon
5/19/14 01:05 03:005/20/14 00:50 02:245/21/14 00:52 02:395/22/14 00:55 02:005/23/14 00:53 01:305/24/14 00:45 02:215/25/14 00:49 02:405/26/14 00:47 01:56
Total Average 00:52 02:19Evening
5/21/14 00:47 02:495/24/14 00:48 02:045/25/14 00:45 02:295/26/14 00:45 02:12
Total Average 00:46 02:24
Points 1-2 (Section 1) Coordinates:Lat: 39.285, Lon: 84.417 to Lat: 39.287, Lon: 84.402 (approx.)
Points 2-3 (Section 2) Coordinates:Lat: 39.287, Lon: 84.402 to Lat: 39.285, Lon: 84.371 (approx.)
Table 2: Average West Bound travel times on I-275 between Mosteller and Reed Hartman ramps.
MorningDate Average Time (min:sec)
Section 1 Section 25/22/14 02:33 01:315/23/14 02:33 01:275/24/14 01:32 01:30
19
5/25/14 01:33 01:305/26/14 01:58 01:30
Total Average 02:02 01:30Afternoon
5/19/14 01:50 01:305/20/14 02:01 01:415/21/14 02:07 01:325/22/14 02:15 01:325/23/14 02:27 01:335/24/14 02:07 01:315/25/14 01:31 01:315/26/14 01:52 01:26
Total Average 02:01 01:32Evening
5/21/14 01:27 01:325/24/14 02:05 01:255/25/14 02:10 01:285/26/14 01:32 01:30
Total Average 01:49 01:29
Note: West Bound morning has no input for 5/21/14 due to no usable data being collected for those segments.
Points 1-2 (Section 1) Coordinates:Lat: 39.286, Lon: 84.37 to Lat: 39.291, Lon: 84.388 (approx.)
Points 2-3 (Section 2) Coordinates:Lat: 39.291, Lon: 84.388 to Lat: 39.285, Lon: 84.415 (approx.)
Accomplished Tasks
Background literature review and reading assignments on ramp metering and its uses have been
completed by our team. Also completed are training on the use of the GPS device to gather
information, using the Q-travel software to retrieve the data saved on the GPS and the use of the
traffic data collector to count traffic collected on the video data collected. Preliminary training
has begun on the use of the VISSIM software to simulate traffic conditions on the highway being
investigated. The software however, relies on the data collected, processed and analyzed hence
we are working on processing the data to be used for simulation on VISSIM. Training on the
20
VISSIM software involved first, building a network; this involved adding a background image
from google map which was zoomed in to about 50% and a snapshot taken. The snapshot of the
freeway taken was imported into VISSIM to aid in the drawing of lanes, connectors and links.
After which the user indicates what width and number of lanes was to be used; lanes ranged from
1-4 lane in this project. Upon completion of the lanes, the second step was to add vehicles; the
vehicle composition was determined for the different roads, whether it was a freeway, ramp or
arterials. Routing decisions were also used to guide the vehicles on the right flow of traffic.
Thirdly, controls such as stop and signal controls were added to the simulation to imitate a real
world traffic flow otherwise simulation without controls will result in errors in the program.
Upcoming tasks are to complete successful simulations of the traffic data gathered from the
video from the sites of interest on the I-275 from Mosteller to Reed Hartman rd. and to undertake
a field trip to the Ohio Department of Transportation infrastructure to statewide traffic
management center in Columbus to gather more information on traffic data collection and
analysis.
21
References
Arnold, Jr., E. D. (1998). “Ramp Metering: A Review of the Literature,” Technical Assistance Report No. VTRC 99-TAR5, Virginia Transportation Research Council, Charlottesville, Virginia.
Department of Transportation, California (2007). "Why Are There Signals Installed at Some Freeway Onramps?" Why Are There Signals Installed at Some Freeway Onramps? Web. 16 June 2014.
Department of Transportation, Minnesota (2011). "Ramp Meters." Minnesota Department of Transportation. Web. 16 June 2014.
DeWelles, Angela (2011). "ADOT Blog: Getting the Green Light: Valley Ramp Meters Now More Efficient." ADOT Blog: Getting the Green Light: Valley Ramp Meters Now More Efficient. Web. 16 June 2014.
Federal Highway Administration (2013). "Ramp Metering Presentation." Localized Bottleneck Reduction Program. US Department of Transportation. Web. 16 June 2014.
Jacobson, Leslie N., Jason Stribiak, Lisa Nelson, and Doug Sallman (2006). "Chapter 11 - Case Studies." Ramp Management and Control Handbook. Washington, DC: U.S. Dept. of Transportation, Federal Highway Administration. 11-2-11-29. Print.
Kang, S., Gillen, D. (1999). “Assessing the Benefits and Costs of Intelligent Transportation Systems: Ramp Meters,” California PATH Research Report No. UCB-ITS-PRR-99-19, Institution of Transportation Studies, University of California, Berkley, California.Arizona Department of Transportation. (2003). Ramp Meter Design, Operations, and Maintenance Guidelines.
Papamichail I., and Papageorgiou, M. (2008). “Traffic-Responsive Linked Ramp-Metering Control,” IEEE Transactions on Intelligent Transportation Systems, Vol. 9, No. 1, n.p.
State of California Department of Transportation. “Ramp Metering In Caltrans District 7 (Los Angeles and Ventura Counties).” 2005.
Yu, G., Recker, W., Chu, L. (2009). “Integrated Ramp Metering Design and Evaluation Platform with Paramics,” California PATH Research Report No. UCB-ITS-PRR-2009-10, Institution of Transportation Studies, University of California, Berkley, California.
Zongzhong, T., Nadeem, A. C., Messer, C. J., Chu, C. (2004). “Ramp Metering Algorithms and Approaches for Texas,” Transportation Technical Report No. FHWA/TX-05/0-4629-1, Texas Transportation Institute, The Texas A&M University System, College Station, Texas.
22