uniten arsepe 08 l5

Upload: zaid-chelsea

Post on 02-Jun-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Uniten Arsepe 08 l5

    1/78

    DISTRIBUTION PROTECTION:

    1

    TOWARDS OPTIMAL PERFORMANCE

    CUSTOMER SATISFACTION

    12 Feb 2008

    by Muhamad Subian Sukaimy

  • 8/10/2019 Uniten Arsepe 08 l5

    2/78

    Objectives

    Overview of Distribution Protection Designing for optimal performance

    2

    performance

    fundamental of OCEF coordination*.

    Optimisation project**

  • 8/10/2019 Uniten Arsepe 08 l5

    3/78

    Overview-Type of Protection

    Protection system is to protect equipment.

    - Reliable/dependable

    - Minimum area load disru ted

    3

    Categorised into:

    Unit protectionNon unit protection

  • 8/10/2019 Uniten Arsepe 08 l5

    4/78

    Overview Unit Protection

    Unit protection

    4

    - of coverage.

    - Also referred to as main protection

    - Fast operating time

  • 8/10/2019 Uniten Arsepe 08 l5

    5/78

    Overview-Non unit Protection

    Non Unit protection

    5

    - .- Also known as back-up protection

    - Slower operating time

  • 8/10/2019 Uniten Arsepe 08 l5

    6/78

    Main:

    - Operating timefixed; sensitivity isadjustable

    Overview-Main Vs Backup

    Bus-bar

    Feeder

    HV

    6

    Transformer

    LV Backup:

    - Operating timeand sensitivity areto be adjusted

  • 8/10/2019 Uniten Arsepe 08 l5

    7/78

    Overview-Main Vs Backup

    HV

    Comparison of relay tripping time:-Eqv time X factor

    Differential - 50mS 50mS 1

    REF - 50mS 50mS 1

    7

    LV

    Solkor Rf - 50mS 50mS 1OCEF (11kV feeder) 0.4 S 400mS 8X

    OCEF (33kV feeder) 1.2 S 1200mS 24X

    SBEF Stage 1 - 2 S 2000mS 40X

  • 8/10/2019 Uniten Arsepe 08 l5

    8/78

    Bus-bar

    Examples are:

    - Feeder CurrentDifferential

    -

    Overview-Main Protection

    Feeder

    HV

    8

    LV

    differential,Restricted EarthFault

    - Busbar High/LowImpedance

    Transformer

  • 8/10/2019 Uniten Arsepe 08 l5

    9/78

    Bus-bar

    Examples are:

    - Over-Current andEarth Fault

    -

    Overview-Backup Protection

    Feeder

    HV

    9

    LV

    Fault

    - Can be definite

    time or InverseDefinite MinimumTime

    Transformer

  • 8/10/2019 Uniten Arsepe 08 l5

    10/78

    Bus-bar

    OCEF Relay are:

    - Either 2 OC & 1 EFor 3 OC & 1 EF

    -

    Backup - OCEF Protection

    Feeder

    HV

    10

    LV

    ,transformers forvarious backup

    purposes

    Transformer

  • 8/10/2019 Uniten Arsepe 08 l5

    11/78

    Bus-bar

    OC fault will affectwhole system.

    EF is normallywithin specific

    Fault path

    Feeder

    11

    LV

    .

    - Thus coordination

    of backup isimportant

    Transformer

    oc

    ef

  • 8/10/2019 Uniten Arsepe 08 l5

    12/78

    Bus-bar

    Operate for in

    zone fault.- Normally operate

    more than 1

    Main Protection practice

    Feeder

    HV

    12

    LV

    breaker to isolateequipment

    Transformer

  • 8/10/2019 Uniten Arsepe 08 l5

    13/78

    Bus-bar

    OCEF Relay are:- Time arranged so that

    downstream relayoperates faster

    Backup - OCEF practice

    Feeder

    HV

    c

    d

    13

    LV

    - coordinated for allvoltage level

    - EF required to becoordinated up to thetransformer LV

    Transformer

    a

    b

  • 8/10/2019 Uniten Arsepe 08 l5

    14/78

    Optimal performance

    It requires:

    Planning criteria:

    -

    14

    - few seconds interruption

    - normal

    - Need to simulate fault condition

  • 8/10/2019 Uniten Arsepe 08 l5

    15/78

    Optimal performance

    It requires:

    Proper equipment/installation

    - - -

    15

    ,

    - Proper protection scheme chosen-CT,relaying sheme

  • 8/10/2019 Uniten Arsepe 08 l5

    16/78

    Optimal performance

    Point to note:

    Protection system available are capable ofhandling system design, however systeminstallation and operation may affect

    16

    system protection

  • 8/10/2019 Uniten Arsepe 08 l5

    17/78

    Zero interruption- parallel

    operationFor optimal performance of parallel circuits:

    Same source

    Equal load sharing between c1 & c2

    Max load not exceeding one cable rating

    No other load in between

    source

    c1 c2

    17

    Proper laying method to eliminate induction Unit protection for cable (or directional

    protection if time is not a problem)

    Inter-tripping scheme implemented (atsource)

    Busbar separation scheme( at load s/s)

    Proper back up coordination

  • 8/10/2019 Uniten Arsepe 08 l5

    18/78

    Same source

    Paralleling 2

    different sourceswill result in thepower cable to act

    Diff source

    c1 c2

    Same source

    c1 c2

    18

    -between the twosources. Maycause power swingand systemtripping if it isabove threshold

  • 8/10/2019 Uniten Arsepe 08 l5

    19/78

    Equal load sharing

    Equal load sharing achieved

    by having same resistance(i.e. same capacity, samelen th .

    Same source

    c1 c2

    19

    This is to prevent uneven

    loading which will lead totripping of one cable onover-current

  • 8/10/2019 Uniten Arsepe 08 l5

    20/78

    Cable laying

    Improper cable laying

    (especially for single corecables) may introducemutual inductance

    Same source

    c1 c2M

    20

    This may lead to unbalanced

    phase current and mayresult in one cable trippingon earth fault when load

    picks up

  • 8/10/2019 Uniten Arsepe 08 l5

    21/78

    Unit protection

    Required to prevent double circuit

    tripping occurring when a faultoccurs on one cable (since unitrotection is faster than back u

    source

    c1 c2F

    21

    protection)

  • 8/10/2019 Uniten Arsepe 08 l5

    22/78

    Directional protection

    Directional protection will also

    provide similar effect when thecircuit are in parallel

    source

    c1 c2F

    22

    However it may mal-operate forfaults happening on other

    feeders.

  • 8/10/2019 Uniten Arsepe 08 l5

    23/78

    Inter-tripping scheme

    When source substationbackup protection

    operated, bus-tie may betripped causing bothcable to be the inter-connector now.

    After ope

    c1 c2

    Before ope

    c1 c2

    23

    An inter-tripping schemeneed to be installed todecouple one cable so as

    to prevent both cabletripping and/orpreventing the totalsource tripping

  • 8/10/2019 Uniten Arsepe 08 l5

    24/78

    Busbar separation scheme

    Busbar separation scheme( at

    load s/s) need to be implementedto prevent total load loss forbusbar fault

    c1 c2

    24

  • 8/10/2019 Uniten Arsepe 08 l5

    25/78

    Proper backup protection

    Need to be properly

    coordinated tohave trippingse uence that is

    After ope

    c1 c2

    Before ope

    c1 c2

    25

    coordinated fromdownstreamupwards.

    Setting should alsocover single cable

    outage.

  • 8/10/2019 Uniten Arsepe 08 l5

    26/78

    Few second interruption-

    spur and auto transferFor this :

    Source can be different

    One cable as main, the other as back up.When relay at receiving detect loss ofsupply, it command change over of supply.

    source

    c1 c2

    on on

    on off

    26

    .

    Max load not exceeding one cable rating

    No other load in between

    Unit protection for cable may be an option

    Proper back up coordination Idealy 1 set per circuit.

  • 8/10/2019 Uniten Arsepe 08 l5

    27/78

    Minutes interruption- spur

    and off-point:

    Source can be different One cable as main, the other as

    source

    c1 c2

    on on

    on off

    27

    .either done by manual orsupervisory from control centre

    Max load not exceeding one cablerating

    Proper back up coordination

  • 8/10/2019 Uniten Arsepe 08 l5

    28/78

    Busbar protection using arc method.@

    Optimizing relay maintenance project

    Other initiative

    28

  • 8/10/2019 Uniten Arsepe 08 l5

    29/78

    Given: 10km 33kV cable feed

    into a 33/11kVsubstation

    1 transformer in service; 33kV

    Tutorial

    OCEF 2

    OCEF 1

    Oc plug 100%

    OC tms = 0.475

    At 1.2 sec

    600/5

    600/5

    29

    , , ,

    NER 4 ohmFind: 3 and 1 phase fault

    current at PPU 11kV

    busbar current and TMS for

    overcurrent setting of allrelays

    11kV

    OCEF 3; t=0.8s

    OCEF 4; t=0.4s

    1600/5

    300/5

  • 8/10/2019 Uniten Arsepe 08 l5

    30/78

    Discuss the problem

    with the followingscheme from

    33kV

    Tutorial11kV

    yn

    D

    S

    30

    perspective.

    11kV

    Y

    y

    Yn

    D

  • 8/10/2019 Uniten Arsepe 08 l5

    31/78

    31

    THANK YOU

  • 8/10/2019 Uniten Arsepe 08 l5

    32/78

    DISTRIBUTION PROTECTION:

    BUSBAR ARC PROTECTION

    12 Feb 2008

    by Muhamad Subian Sukaimy

  • 8/10/2019 Uniten Arsepe 08 l5

    33/78

    BUSBAR PROTECTION USING ARC PROTECTION METHOD

    Method Of Sensing:

    Detection of light (arcing) + Overcurrent = Trip

    Sensing of arc using photo sensors

    or bare fibre

    Sensing of overcurrent using current input

    from OCEF

  • 8/10/2019 Uniten Arsepe 08 l5

    34/78

    typical sensor locations for single bus-bar and double bus-bar switchgears

    BUSBAR PROTECTION USING ARC PROTECTION METHOD

    L or Z typemounting plate

    ARC t ti M t Sl

  • 8/10/2019 Uniten Arsepe 08 l5

    35/78

    ARC protection Master-Slave

    Vamp 220 + 12CD:

    ARC protection Basic MV

  • 8/10/2019 Uniten Arsepe 08 l5

    36/78

    ARC protection Basic MV

    application

    3

    Modular Cable

  • 8/10/2019 Uniten Arsepe 08 l5

    37/78

    BUSBAR PROTECTION USING ARC PROTECTION METHOD

    ABB REA 101:

    -Can be independent

    -Constraint: fibre loop distance

  • 8/10/2019 Uniten Arsepe 08 l5

    38/78

    BUSBAR PROTECTION USING ARC PROTECTION METHOD

    ABB REA 101-103:

    - Master-slave

    -Both can have diffloop

    - 101 trip incomer

    ABB REA 101-105:

    - Selective

    -Both can have diff

    loop

    -105 trip feeder

    -101 trip incomer

    ARC protection Installation

  • 8/10/2019 Uniten Arsepe 08 l5

    39/78

    ARC protection Installation

    examples

    ARC protection Installation

  • 8/10/2019 Uniten Arsepe 08 l5

    40/78

    ARC protection Installation

    examples

  • 8/10/2019 Uniten Arsepe 08 l5

    41/78

    Termination fault isolated by ARCProtection 27 Nov 2007

  • 8/10/2019 Uniten Arsepe 08 l5

    42/78

    1

    FUNDAMENTAL OF COORDINATION

    12 Feb 2008

    by Muhamad Subian Sukaimy

  • 8/10/2019 Uniten Arsepe 08 l5

    43/78

    OCEF Relay are:

    - Star connected

    -

    Backup OCEF Protection

    CT

    R

    YB

    2

    Ir+Iy+Ib = 0 OC OC

    EFStarpoint

  • 8/10/2019 Uniten Arsepe 08 l5

    44/78

    Earth Fault On B phase

    - Highlighted relay circuitwill be energized

    -

    OCEF Protection-Illustration

    CT

    R

    YB

    3

    operate OC OC

    EFStarpoint

  • 8/10/2019 Uniten Arsepe 08 l5

    45/78

    OCEF Protection Coordination

    CT

    R

    YB

    OC element are setbased on 3 phase fault

    - EF element are based onearth fault or 1 phase

    4

    OC OC

    EFStarpoint

    fault- Coordination are done

    using simulator or

    coordination software

    - Fundamental ??

  • 8/10/2019 Uniten Arsepe 08 l5

    46/78

    OCEF Coordination Fundamental

    Network Diagram to be coordinated

    Construct Thevenin Eqv diagram Obtain source & circuit impedances

    5

    per unit system is very useful)

    Determine relay operating time

    Obtain relay time multiplier

    M i P t ti ti

  • 8/10/2019 Uniten Arsepe 08 l5

    47/78

    Bus-bar

    Obtain thenetwork to becoordinated

    Obtain the short

    Main Protection practice

    Feeder

    HV

    S

    6

    LV

    circuit impedancesof eachequipment.

    - i.e R+jX+, R+jXoincl length

    Transformer

    Dyn

  • 8/10/2019 Uniten Arsepe 08 l5

    48/78

    Component Short Circuit

    Impedancetypical cable short cct resistance value

    unit in ohm per metre

    kv type MVA R+ jX+ Ro jXo33 o/h 150 silmalec 18 0.000219 0.000373 0.0008 0.00037

    33 u/g 630 Al 1 core 30 0 0.0001296 0 0.0001723 > Fed Pow

    11

    xlpe 240 sq. mm

    3c 0.000129 0.00009 0.00489 0.000031 ]

    7

    11

    xlpe 150 sq. mm

    3c 0.000211 0.000096 0.00578 0.000027 ] fujikura

    11

    xlpe 500 sq. mm

    1c 0.0000647 0.000097 0.001298 0.000086 ]

    typical transformer

    impedance

    kv MVA z%

    33/11 30 10.06

    33/11 15 9.54

    11/0.433 0.75 4

    Th i E N t k

  • 8/10/2019 Uniten Arsepe 08 l5

    49/78

    Thevenin Eqv Network

    S

    R+jXs R+jX

    + seq network

    R+ Xs R+ X

    FaultPoint

    8

    - seq network

    0 seq network

    R+jXs R+jX

    Z+ = Z-

    P U C l l ti (1)

  • 8/10/2019 Uniten Arsepe 08 l5

    50/78

    P.U. Calculation (1)

    Declare:

    - MVA base (normally 100 MVA)

    9

    - ase epen on source eve

    - Z base (this is calculated; at all voltage

    level if required)

    - I base (this is calculated; at all voltage

    level if required)

    P U C l l ti (2)

  • 8/10/2019 Uniten Arsepe 08 l5

    51/78

    P.U. Calculation (2)

    Source impedance formulae:

    Zs+ pu= j MVA base

    10

    au

    Zs0 pu = j [ {3 x MVA base } - 2Zs+ ]

    [ { 1 Fault MVA} ]

    P U Calc lation (3)

  • 8/10/2019 Uniten Arsepe 08 l5

    52/78

    P.U. Calculation (3)

    Useful formulae:

    Z base = (KV base)2 check (V x V)

    11

    ase x

    I base A= (MVA base) check (V x I)

    (KV base) (V)

    P U Calculation (4)

  • 8/10/2019 Uniten Arsepe 08 l5

    53/78

    P.U. Calculation (4)

    Changing of base formulae:

    Z pu new = Z pu old x MVA base new

    12

    ase o

    Z pu = Z () I pu = I (A)

    Z base I base

    Th i E N t k F lt

  • 8/10/2019 Uniten Arsepe 08 l5

    54/78

    Thevenin Eqv Network: Fault

    Simulation (1)

    S

    R+jXs R+jX

    + seq network

    R+ Xs R+ X

    FaultPoint

    3 phase fault:

    - short the

    If

    13

    - seq network

    0 seq network

    R+jXs R+jX

    sequencenetwork only.

    Thevenin Eqv Network: Fault

  • 8/10/2019 Uniten Arsepe 08 l5

    55/78

    Thevenin Eqv Network: Fault

    Simulation (2)

    S

    R+jXs R+jX

    + seq network

    R+ Xs R+ X

    FaultPoint

    phase to

    phase fault:

    If

    14

    - seq network

    0 seq network

    R+jXs R+jX

    -

    positive andnegativesequencenetwork only.

    Thevenin Eqv Network: Fault

  • 8/10/2019 Uniten Arsepe 08 l5

    56/78

    Thevenin Eqv Network: Fault

    Simulation (3)

    S

    R+jXs R+jX

    + seq network

    R+ Xs R+ X

    FaultPoint

    Single phase toground fault:

    - connect allsequence

    If

    If

    15

    - seq network

    0 seq network

    R+jXs R+jX

    networ nseries and shortat fault point.

    - I fault = 3If

    If

    IDMT Curve (1)

  • 8/10/2019 Uniten Arsepe 08 l5

    57/78

    Observe:

    at tms=1:

    At psm=2; t op = 10 sec

    IDMT Curve (1)

    16

    At psm=10; t op = 3 sec

    For psm > 20 t op = t op at psm=20.

    That is the characteristic of anIDMT curve

    IDMT Curve (2)

  • 8/10/2019 Uniten Arsepe 08 l5

    58/78

    Observe:X axis = multiple ofcurrent; increases to

    IDMT Curve (2)

    10.00

    17

    the rightY axis = operatingtime; increases

    vertical

    10800

    TX LV

    0.10

    1.00

    1000.0 10000.0 100000.0

    EQUIVALENT FAULT CURRENT AT REFERENCE BASE IN TABLE BELOW

    OPERATINGT

    IME(S

    IDMT Curve (3)

  • 8/10/2019 Uniten Arsepe 08 l5

    59/78

    Observe:X axis = multiple ofcurrent; increases to

    IDMT Curve (3)

    10.00

    IncreasePlug eg200%

    18

    the rightY axis = operatingtime; increases

    vertical

    10800

    TX LV

    0.10

    .

    1000.0 10000.0 100000.0

    EQUIVALENT FAULT CURRENT AT REFERENCE BASE IN TABLE BELOW

    OPERATINGT

    IME(S

    IDMT Curve (4)

  • 8/10/2019 Uniten Arsepe 08 l5

    60/78

    Observe:X axis = multiple ofcurrent; increases to

    IDMT Curve (4)

    10.00

    IncreaseTMS eg0.2 to 0.4

    19

    the rightY axis = operatingtime; increases

    vertical

    10800

    TX LV

    0.10

    1.00

    1000.0 10000.0 100000.0

    EQUIVALENT FAULT CURRENT AT REFERENCE BASE IN TABLE BELOW

    OPERATINGT

    IME(S

    IDMT Curve

  • 8/10/2019 Uniten Arsepe 08 l5

    61/78

    Observe from last 3 slides:

    by varying these 2 variablesnamely plug (current) setting and

    IDMT Curve

    20

    more relays; the IDMT curve willbe changed!

    This is the basis of OCEFCoordination.

  • 8/10/2019 Uniten Arsepe 08 l5

    62/78

    Optimization of Distribution Protection

    Relays Maintenance

    Involve to Solve

    Slide No. 1 Copyright 2006 TNB Research

    33.2C

    76.9C

    40

    50

    60

    70

    - ower ng neer ng en re

    Project Overview

  • 8/10/2019 Uniten Arsepe 08 l5

    63/78

    Project Overview

    Project Background

    Maintenance cost of distribution protection relays is quite

    sizeable given the large amount of them in the system Large collection of historical test data is available but without

    any analysis/trending study

    Involve to Solve

    Slide No. 2 Copyright 2006 TNB Research

    With the vast amount of data, there is good prospect tooptimise maintenance scheduling through proper dataanalysis/trending

    Project Overview

  • 8/10/2019 Uniten Arsepe 08 l5

    64/78

    Project Overview

    Potential Benefit

    Currently, relays are required to be maintained once a year

    Maintenance Cost: RM140/relay per year

    (Kadar Harga Tetap, Panduan Kejuruteraan Bil.A10/2006)

    Assume 50,000 relays in the system

    Annual Maintenance Cost: RM140x50,000 =

    Involve to Solve

    Slide No. 3 Copyright 2006 TNB Research

    RM7million/year

    If we can reduce the frequency of maintenance (relay test)by half (ie. maintenance every 2 years);

    Saving of RM3.5million/year

    Note:CESI Italy recommends that relay maintenance/testing to be done every 3-4years (Internal Working Report IWR 3a-01, 19 Jan. 2006)

    Total no of relays as of 1 July 2006: 57,590

    Project Overview

  • 8/10/2019 Uniten Arsepe 08 l5

    65/78

    Project Overview

    Project Aims & Objectives

    To develop an intelligent system in identifying problematicrelays and performance trending

    To optimise maintenance schedule of relays

    Deliverables

    A database to store and manage all relay test data

    A system to capture relay test data, with automated/intelligent

    Involve to Solve

    Slide No. 4 Copyright 2006 TNB Research

    algorithm for analysis/trending and maintenance optimisation

    Intelligent

    System

    Relay testresults

    Relayparameters:

    age, make etc

    RelayCriticality

    Analysis/trending of

    relay performance

    Relay Maintenance frequency

    Proposed Research Methodology

  • 8/10/2019 Uniten Arsepe 08 l5

    66/78

    Proposed Research Methodology

    Methodology Flow Diagram

    Initial Phase: Lit. Review & Data Identification

    Hypothesis Development

    Progress Phase: Initial Statistical Data Analysis

    START

    Data Collection, ie. historical data from relay test sets.

    Involve to Solve

    Slide No. 5 Copyright 2006 TNB Research

    Design of Data Structure/Format, System Interfacing

    Development of Intelligent System

    Final Phase: Final analysis & Report of findings

    Adoption strategies

    Results validation, modification & improvement

    END

    Scope of Work

  • 8/10/2019 Uniten Arsepe 08 l5

    67/78

    Scope of Work

    Data collection

    To study the numerical relay data in Negeri Sembilan

    Initial Statistical Data AnalysisEnable identification of patterns/trend from relay test data

    Involve to Solve

    Slide No. 6 Copyright 2006 TNB Research

    To investigate factors that contribute towardsoptimisation of relay maintenance eg. Relay parameters,test data, criticality etc.

    To develop a model for relay maintenance optimisation(AI algorithm for Data Mining Microsoft SQL Server 2005)

    Data Capture

  • 8/10/2019 Uniten Arsepe 08 l5

    68/78

    ata Captu e

    How shall the data be obtained?

    TNB Distribution (Engineering Services) has given

    the consent and commitment to co-operate with datacollection [Tn. Hj. Subian, En. Norazman Atib]

    Data to be obtained from distribution maintenance

    Involve to Solve

    Slide No. 7 Copyright 2006 TNB Research

    eng neers paper copy

    What shall be done to ensure dataintegrity?

    Data obtained will be examined and any doubts willbe verified with TNBD (Engineering Services)

    Data Requirement eg. Relay Inverse Time Test

  • 8/10/2019 Uniten Arsepe 08 l5

    69/78

    Involve to Solve

    Slide No. 8 Copyright 2006 TNB Research

    Data Collection

  • 8/10/2019 Uniten Arsepe 08 l5

    70/78

    All relay overcurrent and earthfault test datawere collected from the state of Negeri

    Sembilan.

    The data collected are historical data dated

    Involve to Solve

    ac rom .

    A total of 1316 no of relays data werecollected. These are the historical data usedin the AI Engine.

    Slide No. 9 Copyright 2006 TNB Research

    Data Analysis

  • 8/10/2019 Uniten Arsepe 08 l5

    71/78

    y

    How shall the data be analysed?

    Depending on the TMS and plug setting, theoperating time T is calculated.

    A healthy relay should fall within +-10% of the

    Involve to Solve

    Slide No. 10 Copyright 2006 TNB Research

    calculated value.

    A collection of historical data for a particular relayshows the deviation (in %) from the referenceoperating time.

    The system developed will analyse the data fortrending/pattern

    Formula for operating

    Time/currentcharacteristics of IDMTrelay

  • 8/10/2019 Uniten Arsepe 08 l5

    72/78

    Where:

    T = operating time

    I = Fault current

    Formula for operating

    time of IDMT relay

    relay

    Involve to Solve

    Slide No. 11 Copyright 2006 TNB Research

    IS = Setting current

    TMS = Time multipliersetting

    Panduan Kejuruteraan

    Bil.A10/2006

    Example:

    Data Analysis

  • 8/10/2019 Uniten Arsepe 08 l5

    73/78

    Example:

    -- Trending for a particular relay using 3 years of test data

    Time(s)

    Test data year 1

    Test data year 2

    Test data year 3

    Involve to Solve

    Slide No. 12

    current

    10%

    Error thickness

    (relay failed)

    Overview of AI

  • 8/10/2019 Uniten Arsepe 08 l5

    74/78

    The scatter will be thetraining data ArtificialNeural Network

    Training data will enablete network to determinethe ri ht wei htin s for

    Involve to Solve

    Slide No. 13

    each perceptron and

    control its sensitivity. A trained network would

    enable the output toindicate if a relay is proneto failure or otherwise.

    The ArtificiaI Intelligence Engine

  • 8/10/2019 Uniten Arsepe 08 l5

    75/78

    Involve to Solve

    Slide No. 14 Copyright 2006 TNB Research

    What can the software reports on?

  • 8/10/2019 Uniten Arsepe 08 l5

    76/78

    Faulty Relay Detector can predict which relay isprone to become faulty for the current year.

    Normal listing of relay information, such as:- list all relays based on different makes

    -

    Involve to Solve

    - list all relays in certain areas/SSUs- list all relays that has been replaced and their test

    results, and many others.

    The reports generated will be updated automaticallyas new relay test data are added in the database.

    Slide No. 15 Copyright 2006 TNB Research

    Conclusions

  • 8/10/2019 Uniten Arsepe 08 l5

    77/78

    This project will save TNB in terms of theirmaintenance cost of protective relays (optimumperiod for routine maintenance)

    Reduces unnecessary power outages due to mal-operation of protection relays

    Increase work efficienc of ro ec ion en ineers

    Involve to Solve

    Slide No. 16 Copyright 2006 TNB Research

    Add value to distribution protection system/protectionrelays test activities by undertaking analysis of testresult

    Identification of problematic relay types/model

    Enhanced decision-making process related tomaintenance frequency for protection relays

    Thank You

  • 8/10/2019 Uniten Arsepe 08 l5

    78/78

    Contacts:-

    Involve to Solve

    Slide No. 17 Copyright 2006 TNB Research

    TNB Research Sdn. Bhd.

    No. 1, Lorong Ayer Itam,

    Kawasan Institusi Penyelidikan,

    43000 Kajang, Selangor, MALAYSIA

    Tel: +603-89268818 Fax: +603-89268828 / 29