uniten arsepe 08 l2

87
“ Add your company slogan ” DISTRIBUTION SYSTEM PLANNING: PRINCIPLES , CRITERIA & METHODS, ISSUES & WAY FORWARD 1 FORWARD ILSAS By: Halim Osman General Manager Asset Management TNB Distribution

Upload: aminbravo

Post on 28-Apr-2015

69 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

DISTRIBUTION

SYSTEM PLANNING:

PRINCIPLES ,

CRITERIA & METHODS,

ISSUES & WAY

FORWARD

1

FORWARD

ILSAS

By:

Halim Osman

General ManagerAsset Management

TNB Distribution

Page 2: UNITEN ARSEPE 08 L2

PRESENTATION OUTLINE

� Distribution Business & ESI

� Regulatory Framework- Standards, Codes, Acts & License

� Performance Standards

� Design Principles/ Considerations/Criteria

www.themegallery.com2ILSAS

� Design Principles/ Considerations/Criteria

� Issues & Challenges in Distribution Planning

� Evolution of Planning Methodologies

� Summary & Conclusions

Page 3: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

DISTRIBUTION

BUSINESS &

ELECTRICITY SUPPLY

INDUSTRY

3

INDUSTRY

ILSAS

Page 4: UNITEN ARSEPE 08 L2

TYPICAL INDUSTRY STRUCTURE & PARTIES

G

Generators

DG

Consumers

DG

External Parties

Directly Connected Customers

Directly Connected Customers

Transmission

THE GRID

SYSTEM

External Parties

www.themegallery.com4

G

GMain InterconnectedTransmission System(500kV and 275kV)

Transmission Systemat 132kV and 66kV

G

Distribution Systemat 33kV and below

Consumers

EmbeddedDistribution

DG

NetworkOperators

GNetwork

OperatorsG

GenerationSystem

TransmissionSystem

DistributionSystem

TOTAL POWER

SYSTEM

Grid Code Distribution Code

Page 5: UNITEN ARSEPE 08 L2

DISTRIBUTION NETWORK BUSINESS

Grid System – Grid System Operator (GSO)

Co

nsu

mers

DG

Distributor

MV ConsumersWith DG

www.themegallery.com5

Distributor

MVConsumers

LVConsumers

DG

DistributedGenerator

MV

C

on

su

mers

EmbeddedDistributor

DG

Page 6: UNITEN ARSEPE 08 L2

ESI ON DISTRIBUTION BUSIENSS

• MORE PLAYERS THUS REQUIRING CONSISTENT,

TRANSPARENT, GUIDED ACTIONS BY MANY PARTIES TO

ENSURE SYSTEM PERFORMANCE – SAFETY, ADEQUACY,

RELIABILITY & ECONOMICS OF SYSTEMS.

• NEEDS FOR CODES, STANDARDS & COMPLIANCE

• DSITRIBUTION BUSINESS – REGULATED MONOPOLY

www.themegallery.com6

• DSITRIBUTION BUSINESS – REGULATED MONOPOLY

• RELIABILITY PERFORMANCE MONITORING & REPORTING

• INDUSTRY TRENDS IN PERFORMANCE STANDARDS

• RELIABILITY LIMITS /SEGMENTED TO RURAL & URBAN

• REPETITIVE FAULTS/CUSTOMERS AFFECTED

• IMPOSITION OF GUARANTEED STANDARD OF PERFORMANCE(GSOP)

ILSAS

Page 7: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

REGULATORY

FRAMEWORK - CODES,

ACTS, STANDARDS

7ILSAS

Page 8: UNITEN ARSEPE 08 L2

G G

Main Interconnected Transmission System

Generation

Transmission

GenerationReliability Standards

TransmissionReliability

Sufficient generation capacityand connections to deliver fullgeneration output for normal and Specific contingencies

GR

ID C

OD

E

Sufficient transmission capacity to meet demand for specified contingencies

Meeting standards performance limits

Criteria for planning, designingand operating of transmission system to meet reliability and

TOTALPOWERSYSTEMS

Transmission System

Reliability Standards

Relationship between Systems, Standards, and Codes

www.themegallery.com8

Transmission radial networkand demand points

Distribution System

Embedded Distribution

Customers

DG

DG

Distribution

Reliability Standards

TransmissionPower Quality

Standards

system to meet reliability and power quality standards

Sufficient transformer capacity to meet demand

Power quality limits atinterfaces

Criteria for planning, designingand operating of distribution

system to meet supply security

and power quality standards

STANDARDS CODES

DIS

TR

IBU

TIO

N C

OD

E

Distribution Supply Security and Power Quality StandardsSYSTEMS

Page 9: UNITEN ARSEPE 08 L2

EXAMPLE OF ACT (‘EXAMPLE OF ACT (‘AKTAAKTA’)’)

www.themegallery.com9

Cover Page First PageILSAS

Page 10: UNITEN ARSEPE 08 L2

EXAMPLE OF RULES (‘EXAMPLE OF RULES (‘PERATURANPERATURAN’)’)

Contoh daripada

www.themegallery.com10

Contoh daripada Akta Bekalan Elektrik 1990

ILSAS

Page 11: UNITEN ARSEPE 08 L2

EXAMPLE OF INDUSTRY CODEEXAMPLE OF INDUSTRY CODE

www.themegallery.com11

Cover Page of Distribution Code

Contents Page of Distribution Code

ILSAS

Page 12: UNITEN ARSEPE 08 L2

PERFORMANCE STANDARDS ~ SUPPLY SECURITYPERFORMANCE STANDARDS ~ SUPPLY SECURITY

1. Normal MV Breakdown:

a.) For single circuit outage (except busbar)

• 50% restoration within 2 hours (syarat 15)

• restoration time 4 hours

b.) For rural areas or MD < 1MW

www.themegallery.com12

b.) For rural areas or MD < 1MW

– restoration time ≤ 24 hours

2. Normal LV Breakdown:

– restoration time ≤ 24 hours

3. Extra-ordinary Breakdown (Force De Majoure):

– restoration time may be > 24 hours

Reference : ‘Distribution Planning Code’ 5.4.2.3

ILSAS

Page 13: UNITEN ARSEPE 08 L2

� Voltage Regulation (Normal Condition):

� MV of 6.6/11/22/33kV : ±±±±5% of nominal voltage

� LV of 240V & 415V : +5% & -10% of nominal voltage

PERFORMANCE STANDARDPERFORMANCE STANDARD-- VOLTAGE LIMITS VOLTAGE LIMITS

www.themegallery.com13

� Voltage Regulation (Contingency Condition):

� MV : ±±±±10% of nominal voltage

� LV : ±±±±10% of nominal voltage

ILSAS

Page 14: UNITEN ARSEPE 08 L2

� Frequency Regulation (Normal Condition):

� System Frequency : ±±±±1% of nominal value of 50Hz

� Frequency Regulation (Exceptional Circumstances):

PERFORMANCE STANDARDPERFORMANCE STANDARD-- FREQUENCY LIMITSFREQUENCY LIMITS

www.themegallery.com14

� Frequency Regulation (Exceptional Circumstances):

� System Frequency : within 47Hz & 52 Hz

ILSAS

Page 15: UNITEN ARSEPE 08 L2

PERFORMANCE STANDARD- SECURITY

LEVELS

LEVEL RESTORATION TIME DESCRIPTION

1 Less than 5 secondsCustomer who specially request for theservice

Selected urban areas, industrial areas,

15

2 Less than 15 minutesSelected urban areas, industrial areas,hospitals & places of nationalimportance

3 Less than 4 hoursAll areas except for rural areas & anyareas or circuit with group peakdemand of < 1MW

4 Less than 1 dayRural area having total demand < 1MW

Page 16: UNITEN ARSEPE 08 L2

� System Average Interruption Duration Index

� It provides information about total average time the

customers are interrupted.

� Measures of reliability of supply

PERFORMANCE INDEX – SAIDI (1/2)

www.themegallery.com16

� Measures of reliability of supply

� Records the frequency and duration of outages that

customers may experience.

� Only loss of supply exceeding 1 minute will be

counted

Page 17: UNITEN ARSEPE 08 L2

Average Interruption time / customer / year

dC

n

PERFORMANCE INDEX – SAIDI (2/2)

SAIDI =Σ Customer Interruptions Duration

Σ No of Customer Served

(= SAIFI x CAIDI)

www.themegallery.com17

N

dC

i

ii∑== 1

Where:

Ci = No of interrupted customers

di = Restoration time of each interruption event (in min)

n = No of interruption event

N = No of customers served

(= SAIFI x CAIDI)

Page 18: UNITEN ARSEPE 08 L2

PERFORMANCE INDEX - CAIDI

� Customer Average Interruption Duration Index

� Average time required to restore service to the averagecustomer per sustained interruption. (Average duration perinterruption)

CAIDI =Σ Customer Interruption Durations

Σ No of Customer Interrupted

www.themegallery.com18

Σ No of Customer Interrupted

=

==n

1i

i

n

1i

ii

C

dC

Where:

Ci = No of interrupted customers

di = Restoration time of each interruption event (in min)

n = No of interruption event

Page 19: UNITEN ARSEPE 08 L2

� System Average Interruption Frequency Index

� Average frequency (no.) of sustained interruptions per customer.

SAIFI =Σ No of Customer Interruptions

Σ No of Customer Served

PERFORMANCE INDEX - SAIFI

www.themegallery.com19

N

Cn

1i

i∑==Where:

Ci = No of interrupted customers

N = No of customers served

n = No of interruption event

Page 20: UNITEN ARSEPE 08 L2

SUBSTATION FIRM CAPACITY

� System must be operated below firm capacity

� Substation uses (PMU/PPU/SSU/PE)

www.themegallery.com20

� Substation uses (PMU/PPU/SSU/PE)

� Uses ‘n-1’ CONCEPT

Page 21: UNITEN ARSEPE 08 L2

FEEDER FIRM CAPACITY & DESIGN CRITERIA (1/2)

� Feeder uses 50% loading concept

� First leg cables from PMU/PPU must be at least of size

240 mm2 3C Al XLPE or any equivalent capacity.

www.themegallery.com21

� No more expansion of cable 70 mm2 Al or equivalent in the

system.

� No bottle-necks in the system.

Page 22: UNITEN ARSEPE 08 L2

� No spur feeder in the system except for rural domestic

load that is less than 1 MW & it is economically far away

from the source.

� Feedback should be from different source where possible.

FEEDER FIRM CAPACITY & DESIGN CRITERIA (2/2)

www.themegallery.com22

� Feedback should be from different source where possible.

� MV Overhead insulated cables can be used & strung on

the same pole as LV cost-effectiveness.

� MV Overhead lines system (33kV in particular) should be

equipped with auto-recloser & sectionaliser.

Page 23: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

PQ STANDARDS

23

Page 24: UNITEN ARSEPE 08 L2

TNB’S LIMITS ON QUALITY OF SUPPLY (1/2)

1. Voltage Regulation (at Customer’s Terminal)

� LV : 415/240 V; -10% < VOLTAGE <+5%

� HV : 6.6/11/22/33 KV; -5% < VOLTAGE < +5%

2. Voltage Unbalance

www.themegallery.com24

� Definition: negative phase sequence voltage, positive phase

sequence voltage

� Causes: Unbalance phase impedance and loads

� Acceptable Unbalance Voltage level is < 2%

Page 25: UNITEN ARSEPE 08 L2

3. Loads Affecting Supply Quality

� Steel Making ARC furnaces, rolling mills, welding equipment,

induction furnaces, power semiconductors rectifiers, computers,

railway traction, etc.

4. Harmonics

TNB’S LIMITS ON QUALITY OF SUPPLY (2/2)

www.themegallery.com25

4. Harmonics

� Caused by nonlinear loads such as rectifiers and other power

semiconductors

� Acceptable limits based on the electrical regulation – MS IEC

61000 Series

Page 26: UNITEN ARSEPE 08 L2

CAUSES, EFFECTS & MITIGATION OF PQ EVENTS (1/2)

EVENTS CAUSES EFFECTS MITIGATION

Sags & Swells

Electromagnetic disturbance (by components failure –fault clearing, utility power system, trees, animals, lightning, 3rd party digging)

Equipment trip / process interrupted

System improvement (utility), power conditioner (customer), improvement of equipment immunity (manufacturer)

www.themegallery.com26MFuad

Harmonics

Electronic gear (3Ø rectifier, power regulator, customer’s capacitive component),welders, arc furnaces, fluorescent ballasts, pc

CB tripping, unexplained fuse operation, capacitor failure, electronic equipment malfunction, flicking lights & telephone interference

Harmonic filter (shunt passive/active filter), ensure minimum harmonic emission on network design stage

Page 27: UNITEN ARSEPE 08 L2

CAUSES, EFFECTS & MITIGATION OF PQ EVENTS (2/2)

EVENTS CAUSES EFFECTS MITIGATION

Flickers

Mainly by huge arcing generated by furnaces in steel mill (cause health problem such as epilepsy), electronic gears, motors

Equipment trip / process interrupted

Flicker compensator

Voltage Fluctuation

Generation voltage, load end, long line-length ⇒ ↑capacitance

Ferranti effect, voltage violation, customer equipment affected

Cap bank, cable sizing, transformer tap, booster

www.themegallery.com27MFuad

affectedtap, booster

Frequency Deviations

Generation Vs loadGeneration ≈ Load (freq unstable)

Maintain healthy spinning margin

Transients Animals, lightning, vegetation

Page 28: UNITEN ARSEPE 08 L2

PQ PERFORMANCE INDEX - SARFI

� System Average RMS Variation Frequency Index

� To show event frequency of supply interruption, voltage sag &

swell

� 2 ways of index representation:

www.themegallery.com28

� 2 ways of index representation:

� SARFIX

� SARFICURVE

LimCY

Page 29: UNITEN ARSEPE 08 L2

SARFIX

� SARFIX ⇒ event frequency of supply interruption, voltage sag & swellunder a defined voltage level within short-duration RMS variationevents (with duration < 60s)

� Example:

a) SARFI90 = 5

5 events of voltage sag & supply interruption occur below 0.9p.u. or 90% of nominal voltage.

www.themegallery.com29

p.u. or 90% of nominal voltage.

b) SARFI70 = 3

3 events of voltage sag & supply interruption occur below 0.7 p.u.or 70% of nominal voltage.

c) SARFI110 = 2

means 2 events of voltage swell occur above 1.1 p.u. or110% of nominal voltage.

LimCY

Page 30: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

LOADING

CRITERIA

30

Page 31: UNITEN ARSEPE 08 L2

LOADING CRITERIA

� Feeders

� Maximum of 50% loading of its rated capacity (for n-1

contingency).

� Transformer

� Initial / Optimum loading – 60% (Refer LV Planning Guideline)

www.themegallery.com31

� Maximum loading of 90% for 24 hours Operation.

� Can load higher than 90% for cyclic loading (E.g: 100kVA ONAN

Transformer can be loaded to 1420kVA for 2 hours.

Page 32: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

MV NETWORK

CONFIGURATION

32

Page 33: UNITEN ARSEPE 08 L2

TYPICAL DISTRIBUTION SYSTEM

12 kV 132kV

33kV

33kV11kV PPU

POWER

TRANSMISSION

LINE

U/G & O/H

www.themegallery.com33

12 kV 132kV

132kV 11kV

415V/240V415V/240V

PMU

POWER

STATION

PEPE

U/G & O/H

DISTRIBUTION

Page 34: UNITEN ARSEPE 08 L2

TYPICAL MV NETWORK

CONFIGURATION

Types of Network

Radial circuit

Mesh

Loop from same supply source

www.themegallery.com34

Loop from different supply sources

Petal configuration

Twin loop

2-1-2 configuration for 33kV urban

Page 35: UNITEN ARSEPE 08 L2

TYPICAL NETWORK STRUCTURE

BULK SUPPLY

X

XX

XX

PMU

B/S

ON

Figure 1 (a): Parallel feeders with n - 1 elements

Network Description

Security Level

Normal State

Parallel feeders supplying bulk customer, 11kV , 22kV or 33kv

Level 1 attainable with feeder unit protection

Bus-section 'ON'

XX X X X

PMU 1PPU / CUSTOM ER PMU 2

www.themegallery.com35

XX

XX

XXX

X X

X

X

X

off

B/S 1 B/S 2

Figure 1 (b). Parallel feeder w ith n - 2 elem ent

Network Description Norm al State Security Level

3 feeder into a PPU bulk custom ers switching station 2 feeder are paralle l

Breaker 'A ' is in 'OFF' position Bus section 1 and Bus section 2 are 'ON'

Level 1 estainable

Page 36: UNITEN ARSEPE 08 L2

XX

XX

XXX

X X

X XX

X

X

Figure 1 (c). Parallel feeders with n - 3 element

OFF

PMU 1PMU 2

PPU / CUSTOMER

A

B

OFF

TYPICAL NETWORK STRUCTURE

www.themegallery.com36

Figure 1 (c). Parallel feeders with n - 3 element

Network Description Normal State Security Level

4 feeder into a PPU or bulk customer switching station 2 feeder are parallel

Breaker A and B are 'OFF' Bus section 1 and 2 are 'ON'

level attainable

Page 37: UNITEN ARSEPE 08 L2

Network Description Security Level

Simple - looped network from one PMU/PPU with n - 1 element

level 1 not attainable with SCADA/DA

Level 3 without SCAD/DA

Figure 2(a). Looped, configuration from one PMU with n -1 element

X

X

X

PMU 1

off

P M U 1 o f f

TYPICAL NETWORK STRUCTURE

www.themegallery.com37

N e tw o r k D e s c r ip t io n N o r m a l S ta te

L o o p c o n f ig u r a t io n f r o m tw o P M U / P P U w i th n - 1 e le m e n t

L e v e l 1 n o t a t t a in a b leL e v e l 2 a t t a in a b le w i t h S C A D A /D AL e v e l 3 w i t h o u t S C A D A /D A

X

X

X

XP M U 1

P M U 2

F ig u r e 2 ( b ) . L o o p e d f r o m tw o P M U w i th n - 1 e le m e n t

o f f

Page 38: UNITEN ARSEPE 08 L2

PMU 1

X

X

X

XPMU 2

off

off

TYPICAL NETWORK STRUCTURE

www.themegallery.com38

Network Configuration Normal State

Loop configuration from two PMU / PPU with n - 2 element

Level 2 attainable with SCADALevel 3 attainable without SCADA / DA

X

Page 39: UNITEN ARSEPE 08 L2

X

X

P M U 1

TYPICAL NETWORK STRUCTURE

www.themegallery.com39

N e tw o rk C o n fig u ra tio n S e c u r ity L e v e l

s p u r fe e d r fro m P M U / P P U

L e v e l 4

L e v e l 1 ,2 & 3 n o t a tta in a b le

F ig u re 3 (c ) .R a d ia l C o n fig u ra tio n , n - 0 e le m e n t

X

Page 40: UNITEN ARSEPE 08 L2

APPLICATION GUIDE

~ SECURITY & CONTINGENCY CRITERIA (1/2)SECURITY

CONTINGENCY

CRITERION

APPLICATION

(YES/NO)

n-1 feeder element Yes

n- 1 transformer element Yes

n-1 bus-bar element No

n-1 feeder element Yes

n- 1 transformer element Yes

Looped radial feeders with

open points and fed by

same PMU or PPU source

No network control or

automation -

SCADA/DA

SCADA, Sub-station

and feeder

APPLICATION POLICY /

GUIDELINES

Parallel feeders into a

customer's bulk supply

switching station ( see fig. )

NETWORK MODELSOPERATIONAL

CONTROL

Level 1

33kV,22kV and 11kV sub-systems

for towns and sub-urban areas and

low demand density industrial

For supply schemes to bulk 11kV

& 33kV customers

www.themegallery.com40

n-1 bus-bar element No

n-1 feeder element Yes

n- 1 transformer element Yes

n-1 bus-bar element Yes

n-2 feeder element Yes

n-1 transformer element Yes

n-1 bus-bar element Yes

SCADA, Sub-station

and feeder

automation

but from different secondary

buses ( see fig.)

Looped radial feeders with

open points and fed by

different PMU or PPU

source ( see fig.

Network configuration with

three (3) feeders into a PPU,

PPU supplied from two

different PMU sources ( see

fig. )

automation

SCADA, Sub-station

and feeder

automationLevel 2

33kV, 22kV and 11kV for urban

areas or similar areas (industrial

estates) with high demand intensity

and readily available reserve

capacity - PMU /PPU sources

low demand density industrial

estates

Application to 33kV network in

Penang & Klang Valley or similar

supply areas with high demand

density and readily available

reserve capacity

Page 41: UNITEN ARSEPE 08 L2

SECURITYCONTINGENCY

CRITERION

APPLICATION

(YES/NO)

n-1 feeder element Yes

n- 1 transformer element Yes

n-1 bus-bar element No

n-1 feeder element Yes

n- 1 transformer element Yes

n-1 bus-bar element Yes

n-2 feeder element Yes

Level 3

No SCADA/DA

Application to 33kV sub-systems Network configuration with

33kV,22kV and 11kV for lesser

important urban areas of low

demand intensity

Looped radial feeders with

open points fed by same

PMU or PPU source but

different bus-bars

No SCADA/DA

33kV, 22kV and 11kV network for

urban areas and industrial estates

with medium load density

Looped radial feeders with

open points and fed by the

different PMU sources

OPERATIONAL

CONTROL

APPLICATION POLICY /

GUIDELINESNETWORK MODELS

APPLICATION GUIDE

~ SECURITY & CONTINGENCY CRITERIA (2/2)

www.themegallery.com41

n-2 feeder element Yes

n- 1 transformer element Yes

n-1 bus-bar element No

n-1 feeder element No

n- 1 transformer element Yes

n-1 bus-bar element No

No SCADA/DA

No network control or

automation

No network control or

automation

Level 4

n-1 feeder element No

n-1 feeder element Yes

Applicable to 33kV, 22kV & 11kV

feeders supplying into remote

rural areas with less than 1 MVA

Radial MV network from a

single PMU source

Generally LV networks are

operated in radial and standby

capacity through gen-sets

Radial low-voltage network

Application to 33kV sub-systems

for supply areas with high demand

density and readily available

reserve capacity - PMUs & PPUs

Network configuration with

three(3) feeders supplying

load points namely PPU with

two PMU sources

No SCADA/DA

Highly selective and customized

application to LV schemes e.g

commercial areas

Looped LV network with

open points

Page 42: UNITEN ARSEPE 08 L2

DESIRED 33 KV NETWORK

~ INFANT STAGE WITH 1 PMU Option for (n-

2) elemen

t

PMUPPU

PPU

PPU

www.themegallery.com42

Network with (n-1) element

~ Not withstanding loss of

PMU, security level 1 & 2 is

attainable with SCADA in

place

PMUPPU

PPU

PPU

PARALLE

L

FEEDE

R

SOURCE

(n-1)

√ L1 L2

X L2 L2

Page 43: UNITEN ARSEPE 08 L2

DESIRED 33 KV NETWORK – 2ND STAGE WITH 2

PMU’SPPU

PMU PPUPPU

PPU

PMU

Network with (n-1) source

www.themegallery.com43

Security level 1 & 2 is attainable with SCADA in place under (n-1) source contingency

PMU

PPU

PPUPPU

PPU

PMU

Page 44: UNITEN ARSEPE 08 L2

DESIRED 33 KV NETWORK - MATURED STAGE WITH MORE THAN 2 PMU’S

PPU PMUPPU PPU PPU

PPU PPUPMU PMU

www.themegallery.com44

• Network with more than 2 sources with (n-1) concept

planned.

• Security level 1 & 2 is attainable with SCADA emplaced

under (n-1) source contingency

PPU PPUPMU PMU

Page 45: UNITEN ARSEPE 08 L2

PARALLEL FEEDER SOURCE (n-1)

√ L1 L2

X L2 L2Level 2 attainable with SCADA

33 KV SYSTEM DESIGN OPTIONS

TO ACHIEVE SECURITY LEVELS 2 & 1

PARALLEL FEEDER SOURCE (n-1)

√ L1 L2

X L2 L2

PMU PMUPPU PPU

PMU PMUPPU PPU

Level 1 & 2 attainable with SCADA

www.themegallery.com45

PARALLEL FEEDER SOURCE

√ N/A N/A

X L2 L2

X L2 L2

PARALLEL FEEDER SOURCE (n-1)

√ L1 L2

X L2 L2

PMU PMUPPU

PMU PMUPPUPPU

Level 1 & 2 attainable with SCADA

Level 1 & 2 attainable with SCADA

Level 2 attainable with SCADA

Page 46: UNITEN ARSEPE 08 L2

MV NETWORK CONFIGURATION (3/4)

� Selection election of network

- Based on the reliability & security levels

� Design criteria

� Safe, fast & easy operation

www.themegallery.com46

� Safe, fast & easy operation

� No overloading of remaining circuit after single cable outage

� Feedback for any single outage contingency

Page 47: UNITEN ARSEPE 08 L2

MV NETWORK CONFIGURATION (4/4)

� Worst requirement (Base on Syarat 15)

• 50% restoration within 2 hours

• Full restoration within 4 hours

� Loading of feeders must be less than 50% to reduce distribution

Performance Criteria

www.themegallery.com47

� Loading of feeders must be less than 50% to reduce distribution

losses

� Reduce number of substations per feeder wherever possible

� Reduce number of customers per feeder

Page 48: UNITEN ARSEPE 08 L2

MV FEEDER CAPACITY & DESIGN CRITERIA (1/2)

� MV feeder uses 50% loading concept

� First leg cables from PMU/PPU must be at least of size 240mm2 Al XLPE

3C or any equivalent capacity

� No more expansion of cable 70mm2 Al or equivalent capacity in the

system

www.themegallery.com48

� No bottle necks in the system

� No spur feeder in the system except for rural domestic load that is less

than 1MW and it is economically far away from the source

� Feedback should be from different source where possible

LooCK

Page 49: UNITEN ARSEPE 08 L2

� MV overhead insulated cables can be used and strung on the same

pole as LV cost effectiveness

� MV overhead bare line system (33kV in particular) should be

MV FEEDER CAPACITY & DESIGN CRITERIA (2/2)

www.themegallery.com49

� MV overhead bare line system (33kV in particular) should be

equipped with auto-recloser & sectionaliser

LooCK

Page 50: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

DISTRIBUTION

PROTECTION

50

Page 51: UNITEN ARSEPE 08 L2

DISTRIBUTION PROTECTION (1/2)

� Ensure distribution network can operate within preset

requirements for the safety of the public, staff and overall

network including equipment items.

OBJECTIVES

www.themegallery.com51

network including equipment items.

� Isolate faults on the network in a minimum time in order to

minimise damages

Page 52: UNITEN ARSEPE 08 L2

DISTRIBUTION PROTECTION (2/2)

� Radial U/G cable operated circuit (6.6, 11 & 22kV)

� Use over-current & earth-fault protection

� Radial O/H lines operated circuit (6.6, 11 & 22kV)

� Use over-current & earth-fault protection

� With auto-recloser

� Parallel circuits (Loop from same PMU/PPU)

www.themegallery.com52

� Parallel circuits (Loop from same PMU/PPU)

� Use directional earth-fault & over-current

� Parallel interconnector

� Use pilot wire / fibre optic cable unit protection

� Use over-current / earth-fault as back-up

Page 53: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

SYSTEM FAULT

LEVEL

53

LEVEL

Page 54: UNITEN ARSEPE 08 L2

IMPORTANCE OF FAULT LEVELS

� Fault level in the distribution system must be identified

� To decide on fault rating of equipment.

� Magnitude of fault current depends on the infeed arrangement

and the impedance of the network configuration.

� Fault level must not exceed short circuit rating of equipment (e.g.

circuit breaker interrupting the fault current).

www.themegallery.com54

� Too low fault current (long & highly loaded feeder) may unable to

operate the protective device

� Need to configure the system to reduce the system impedance.

Page 55: UNITEN ARSEPE 08 L2

INTRODUCTION OF FAULT LEVEL

� Analysis of power system electrical behavior under different fault

conditions

� Effects of these conditions on the power system current &

voltage.

www.themegallery.com55

� Equipment rating

� Under maximum fault, the system components must be rated

such that the resultant heat can be dissipated & mechanical

forces withstand.

Page 56: UNITEN ARSEPE 08 L2

FAULT LEVEL IN TNB’S DISTRIBUTION SYSTEM

� Maximum fault level allowed in the distribution system

Nominal System Voltage (kV)

Rated Voltage (kV)

Fault Current (kA)

33 36 25

22 24 20

www.themegallery.com56

� Withstand the rated fault current for a duration of 3 seconds.

22 24 20

11 12 20

6.6 7.2 20

0.415 1 / 0.415 31.5

Page 57: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

DISTRIBUTION

SYSTEM LOSSES

57

Page 58: UNITEN ARSEPE 08 L2

DISTRIBUTION SYSTEM LOSSES (1/2)

� Technical & non-technical losses

� Technical losses – reduce to optimum level

� Refer to “A Guidebook on Reduction of Distribution Losses”

� Non-technical losses – reduce to minimum level

� MV Losses management

� MV Feeder loading must be less than 50%.

www.themegallery.com58

� MV Feeder loading must be less than 50%.

� Install shunt capacitor bank near the load.

� Optimising network (Off-point)

� Bring injection point to the load

� Load management

Page 59: UNITEN ARSEPE 08 L2

DISTRIBUTION SYSTEM LOSSES (2/2)

� LV losses management

� Reduce feeder loading

� Load transfer

� Use larger size conductor/cable

www.themegallery.com59

� Add new feeder

� Reduce feeder length

� Reduce volt-drop losses (long lines/feeder)

� Load balancing

Page 60: UNITEN ARSEPE 08 L2

WHY VAr MANAGEMENT

� Voltage regulation

� Optimize distribution capacity

www.themegallery.com60

� Reduce losses

� Can Cap Bank reduce harmonics ?

Page 61: UNITEN ARSEPE 08 L2

VAr MANAGEMENT

Cap Bank –sizing/locating - CAPO

� LV Load profiling (include Amp, Volt, VAr, Pf)

� Sub-station

� Pole top

� Customer end

� Other advantages of cap bank

www.themegallery.com61

� Other advantages of cap bank

� Points to note with cap bank

� operation

� safety

� maintenance

Page 62: UNITEN ARSEPE 08 L2

SYSTEM STUDIES & SYSTEM STUDIES &

TECHNICAL PROPOSALTECHNICAL PROPOSAL

www.themegallery.com62Rosemi

Page 63: UNITEN ARSEPE 08 L2

Network data+ loading

(Existing & New)

Performance Diagnosis•Capacity/demand•Loading•Losses•Security•Off points•Reliability-SAIDI – (Good to have)•Fault level•Protection

DISTRIBUTION SYSTEM STUDYDISTRIBUTION SYSTEM STUDY

www.themegallery.com63

Yr2

Modeling ofExisting cct,Yr0

•Protection•Others- PQ (sensitive customer)•Network regime-SCADA,EFI•Operational planning

New Standard•New network structure•Security level•Configuration Criteria•Losses

Yr1

Rosemi

Page 64: UNITEN ARSEPE 08 L2

STEP 1: RECEIVE APPLICATION STEP 1: RECEIVE APPLICATION

FROM CONSULTANT VIA PK/PCFROM CONSULTANT VIA PK/PC

Check for: • Plan• Load details• TNB Specs compliant• Date Supply required• Expected Demand Yearly• Estimated 24hrs load profile• Site Visit

www.themegallery.com64

• Site Visit

Year Yr MDMW

1999 Yr0 0.3

2000 Yr1 0.5

2001 Yr2 0.9

2002 Yr3 1.5

2003 Yr4 2.1

2004 Yr5 2.7 0

0.5

1

1.5

2

2.5

3

1999 2000 2001 2002 2003 2004

MDMW

Projected Customer Demand Growth

Rosemi

Page 65: UNITEN ARSEPE 08 L2

STEP 2: CHECK FOR STEP 2: CHECK FOR

SUPPLY VOLTAGE LEVELSUPPLY VOLTAGE LEVEL

LOAD VOLTAGE LEVEL

< 800kW* LV

800kW to 5MW MV 11kV

5MW to 25MW MV 33kV

www.themegallery.com65

5MW to 25MW MV 33kV

> 25MW MV 132kV

Rosemi

Page 66: UNITEN ARSEPE 08 L2

STEP 3: CHOOSE DESIGN STEP 3: CHOOSE DESIGN

FORMAT FOR (nFORMAT FOR (n--1) SYSTEM1) SYSTEM

B

D E

CA

www.themegallery.com66

PlanSecurity Criteria

Loading CriteriaElement

A (n-1) <50%

B (n-1) <50%

C (n-1) <50%

D (n-2) <50%

E (n-2) <50%

Rosemi

Page 67: UNITEN ARSEPE 08 L2

%Arus Amp %Loss I^2 Act Loss0 0 0.0

10 100 0.1

20 400 0.4

30 900 0.9

40 1600 1.6

50 2500 2.5

60 3600 3.6

70 4900 4.9

80 6400 6.4

90 8100 8.1

100 10000 10.0

LOSSES IN CABLESLOSSES IN CABLES

Loss= I2R

IRON LOSSES IN CABLES

12

www.themegallery.com67

100 10000 10.0

0

2

4

6

8

10

%Arus

Amp

0 10 20 30 40 50 60 70 80 90 100

%Current flow of 100%

Lo

sses

Rosemi

Page 68: UNITEN ARSEPE 08 L2

STEP 4: FIND SITE LOCATION STEP 4: FIND SITE LOCATION

& ELECTRICAL LOCATION& ELECTRICAL LOCATION

www.themegallery.com68

Site LocationSite Location

Electrical LocationElectrical Location

Rosemi

Page 69: UNITEN ARSEPE 08 L2

STEP 5: SUPPLY ADEQUACY CHECK, STEP 5: SUPPLY ADEQUACY CHECK,

FOR CURRENT SYSTEM, WITHOUT NEW LOADFOR CURRENT SYSTEM, WITHOUT NEW LOAD

Check For 100% Feedback w/out • Current Violation ie no Overload• Voltage Violation ie no Vdrop <10%

I Vd <-10%

Limit FiguresCheck

www.themegallery.com69

I1

Limit Figures

300mmp=330A

240mmp=350A

185mmp=250A

150mmp=280A

120mmp=200A

95mmp=210A

70mmp=140A

Voltage Vd <10% 9.9kV

Drop

Check

Overload

I

I1

<100%

<100%

If the system complies,proceed, if not, redesign

Rosemi

Page 70: UNITEN ARSEPE 08 L2

STEP 6: SUPPLY ADEQUECY CHECK, STEP 6: SUPPLY ADEQUECY CHECK,

WITH NEW LOAD INJECTIONWITH NEW LOAD INJECTION

Check For 100% Feedback w/out • Current Violation ie no Overload• Voltage Violation ie no Vdrop <10%

Vd <-10%

Limit FiguresCheck

I

Inject new loadwith maximumMD in final yearwith load scalingfactor considered

www.themegallery.com70

Limit Figures

300mmp=330A

240mmp=350A

185mmp=250A

150mmp=280A

120mmp=200A

95mmp=210A

70mmp=140A

Voltage Vd <10% 9.9kV

Drop

Check

Overload

I

I1

<100%

<100%If the system complies,proceed, if not, redesign

I1

Rosemi

Page 71: UNITEN ARSEPE 08 L2

Start with load in year 5, if comply, proceed, if not go to year 4. Find in what year the system complies the standard criteria (I,V). Suggest improvement for future year yr3,yr4,y5 if any.

I

I1

Vd <-10%

STEP 7: SUPPLY ADEQUACY CHECK, STEP 7: SUPPLY ADEQUACY CHECK,

WITH NEW LOAD INJECTION & LOAD SCALINGWITH NEW LOAD INJECTION & LOAD SCALING

www.themegallery.com71

Year Yr NewPE PE1 PE2 PE3 PE4 PE5 Total Growth

2005 Yr0 0.3 0.10 0.20 0.15 0.20 0.15 1.10

2006 Yr1 0.5 0.10 0.21 0.16 0.21 0.16 1.33 4%

2007 Yr2 0.9 0.11 0.22 0.16 0.22 0.16 1.77 4%

2008 Yr3 1.5 0.11 0.23 0.17 0.23 0.17 2.41 5%

2009 Yr4 2.1 0.12 0.24 0.18 0.24 0.18 3.05 5%

2010 Yr5 2.7 0.13 0.25 0.19 0.25 0.19 3.70 5%

Load in MW

Rosemi

Page 72: UNITEN ARSEPE 08 L2

STEP 8: SECURITY LEVEL SELECTIONSTEP 8: SECURITY LEVEL SELECTION

Select security level for• The customer or• The area

Redesign to includeall features. Systemdesign to follow (n-1)source and element

Level ResTime System Design

www.themegallery.com72

Level ResTime System Design

L1 5 Sec 2 dedicated parallel Cables,

Unit protection, DOC,VCB,SCADA

L2 15 Min VCB,SCADA, Unit Protection

L3 4 hr RMU + VCB

L4 1 day RMU, H Pole

L2,L3

L2,L3

L1,L2,L3

L4

L4

e.g. Penang Island

Rosemi

Page 73: UNITEN ARSEPE 08 L2

STEP 9: LOAD FLOW ANALYSISSTEP 9: LOAD FLOW ANALYSIS

Test for single contingency (n-1)

I

I1

Vd<-10%

and

a) Contingency Criteria (Vd<-10%, I<100% for 100% Feedback)

I

I1

Vd<-10%

www.themegallery.com73

I1

If comply, proceed,if not, redesign.Eg. New injection, reconductor or reconfigure.

Limit Figures 1st leg A 1st leg B OK/NOK

300mmp=330A

240mmp=350A 200A 198A OK

185mmp=250A

150mmp=280A

120mmp=200A

95mmp=210A

70mmp=140A

Voltage Vd <10% 9.9kV 10.01kV 10.02kV OK

Drop

Over Vover >5% 11.55kV No No OK

Voltage

Check

Overload

I

I1

<100%

<100%

Rosemi

Page 74: UNITEN ARSEPE 08 L2

STEP 10: TIE OFF POINT OPTIMIZATION (TOPO)STEP 10: TIE OFF POINT OPTIMIZATION (TOPO)

Run load flow to find the lowest losses ,with different off point, or use TOPO (just an option)

Off Point % Loss Best

PE1 2.00%

www.themegallery.com74

PE2 2.20%

PE3 2.40%

PE4 1.65% MinLoss

PE5 2.00%

PE6 2.30%

Choose PE4 asChoose PE4 asOFF Point.OFF Point.It gives minIt gives min

lossloss

Page 75: UNITEN ARSEPE 08 L2

b) Steady State (Vd <-5%,I< Cable Cap, <50%Feeder Loading, Loss<5%,pf>0.85 )

IbIa

Targeted Actual Actual

Figures Figure A Figure BCheck Limit

STEP 11: LOAD FLOW ANALYSIS (2)STEP 11: LOAD FLOW ANALYSIS (2)

www.themegallery.com75

I1 I2

Vd1 Vd2

Figures Figure A Figure B

Load 50% Ia <50% 195A 105A 100A

of feeder Ib <50% 195A 100A 102A

Voltage Vd1 <-5% >10.45kV 10.91kV 10.92kV

Drop Vd2 <-5% >10.45kV 10.94kV 10.93kV

Over Vd1 >+5% <11.55kV

Voltage Vd2 >+5% <11.55kV

Losses Loss <+5% lowest 2.30% 2.30%

Power pf >0.85 1.0 0.89 0.89

Factor

Rosemi

Page 76: UNITEN ARSEPE 08 L2

STEP 14: IDENTIFY SYSTEM LIMITATIONSTEP 14: IDENTIFY SYSTEM LIMITATION

• Increase load 4%-5% each year (based on load forecast)• Test for steady state and contingency• Find in what year, the system max• Propose system improvement for that year

Growth Total Total Loss Power

% Load(MW) Loss(kW) % O/Load Vd<-10% O/Load Vd<-10% O/Load Vd<-5% Factor

ContingencySteady State

1st legAYear

1st legB

www.themegallery.com76

% Load(MW) Loss(kW) % O/Load Vd<-10% O/Load Vd<-10% O/Load Vd<-5% Factor

Yr0 2005 0 2.52 50.400 2.0 No No No No No No 0.85

Yr1 2006 4 2.62 52.416 2.0 No No No No No No 0.86

Yr2 2007 4 2.73 54.513 2.5 No No No No No No 0.86

Yr3 2008 5 2.83 56.693 2.6 No No No No No No 0.89

Yr4 2009 5 2.95 58.961 2.7 Yes No Yes No Yes Yes 0.76

Yr5 2010 5 3.07 61.319 2.7 Yes Yes Yes Yes Yes Yes 0.71

This system can withstand load growth until Yr3. Systemimprovement is required in Yr4, by laying 240mmp 11kV 1200mfrom PPU A to PE5.

Rosemi

Page 77: UNITEN ARSEPE 08 L2

STEP 15: ANALYSIS SUMMARYSTEP 15: ANALYSIS SUMMARY

Condition Test Yr0 Yr1 Yr2 Yr3 Yr4

Ia>50% No No No Yes Yes

Ib>50% No No No Yes Yes

I o/load No No No Yes Yes

Vd<-5% No No No Yes Yes

pf <0.85 No No No No Yes

Steady state

Yr0 Yr1 Yr2 Yr3 Yr4

Load Forecast 2.52 2.62 2.73 2.83 2.95

%Growth 0 4 4 5 5

www.themegallery.com77

pf <0.85 No No No No Yes

Ia>50% No No No Yes Yes

Ib>50% No No No Yes Yes

I o/load No No No Yes Yes

Vd<-10% No No No Yes Yes

pf <0.85 No No No No Yes

Ia>50% No No No Yes Yes

Ib>50% No No No Yes Yes

I o/load No No No Yes Yes

Vd<-10% No No No Yes Yes

pf <0.85 No No No No Yes

Contingency

B

Contingency

A

Rosemi

Page 78: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

ISSUES &

CHALLENGES

78

Page 79: UNITEN ARSEPE 08 L2

DISTRIBUTION PLANNING & ASSET

MANAGEMENT

� DISTRIBUTION PLANNING FUNCTION – SCOPE & METHODOLOGY

TO SUPPORT ASSET MANAGEMENT OBJECTIVES – OPTIMIZE

PERFORMANCE , COST & RISKS

� DISTRIBUTION PLANNING TO UNDERSTAND EQUIPMENT

RELIABILITY PERFORMANCE, CYLCE COST OF

www.themegallery.com79

RELIABILITY PERFORMANCE, CYLCE COST OF

EQUIPMENT/SYSTEMS.

� INVESTMENT ANALYSIS TO PROVIDE DEAL WITH PERFORMANCE,

COST AND RISK ASSESSMENT SO NEED FOR SUPPORTIVE

METHODOLOGIES.

LooCK

Page 80: UNITEN ARSEPE 08 L2

DISTRIBUTION PLANNING ISSUES(1)

� VOLTAGE SELECTION FOR HIGH GROWTH AREAS

� SECURITY STANDARDS & CONTINGENCY CRITERIA

� SERVICE LEVEL DIFFERENTIATIONS

www.themegallery.com80

� DETERMINISTIC VS PROBABLISTIC CRITERIA.

� NETWORK STRUCTURE & CONFIGURATION

LooCK

Page 81: UNITEN ARSEPE 08 L2

DISTRIBUTION PLANNING ISSUES(2)

� PROTECTION & AUTOMATION

� EQUIPMENT DESIGN, SELECTION & STANDARDIZATION

� ASSET REPLACEMENT DECISIONS & PLANS

www.themegallery.com81

� DG CONNECTIONS

� LOAD FORECASTING

LooCK

Page 82: UNITEN ARSEPE 08 L2

DISTRIBUTION PLANNING ISSUES(3)

� SYSTEM STUDIES: METHODS, TOOLS & DATABASES

� INVESTMENT APPRAISAL METHODS

www.themegallery.com82LooCK

Page 83: UNITEN ARSEPE 08 L2

“ Add your company slogan ”

EVOLUTION IN

PLANNING

METHODOLOGIES

83

METHODOLOGIES

Page 84: UNITEN ARSEPE 08 L2

EVOLUTION IN PLANNING METHODOLOGY

RISK-BASED PLANNING

www.themegallery.com84LooCK

LEAST-COST PLANNING

VALUE-BASED PLANNING

RELIABILITY-BASEDPLANNING

Page 85: UNITEN ARSEPE 08 L2

SUMMARY & CONCLUSIONS

� TRADITIONAL DISTRIBUTION PLANNING FUNCTION REALIGNED TO

FIT OVERALL ASSET MANAGEMENT OBJECTIVES OF UTILITIES

� DISTRIBUTION PLANNERS TO DEVELOP & APPLY

METHODOLOGIES THAT COULD EFFECTIVELY DEAL WITH

www.themegallery.com85

METHODOLOGIES THAT COULD EFFECTIVELY DEAL WITH

RELIABILITY AND RISK ASSESSMENT, LIFE CYCLE COSTING FOR

ASSET DEVELOPMENT AND REPLACEMENT DECISIONS.

LooCK

Page 86: UNITEN ARSEPE 08 L2

SUMMARY & CONCLUSIONS

� PLANNING & DESIGN CRITERIA REMAINS UNCHANGED BUT STILL

LINGERING ISSUES THAT NEED TO BE DEALT WITH PLANNERS

ARISING FROM ENHANCED ROLES & DELIVERABLES.

� OPPORTUNITIES FOR DEVELOPMENT OF NEW METHODS RISK

www.themegallery.com86

� OPPORTUNITIES FOR DEVELOPMENT OF NEW METHODS RISK

ASSESSMENT AND OPTIMIZATION TOOLS FOLLOWING

IMPLEMENTATION OF INTEGTRATED UTILITY IT APPLICATIONS

( GIS-BASED NETWORK MGT SYSTEM, OMS, CBM, SCADA ETC)

LooCK

Page 87: UNITEN ARSEPE 08 L2

THANK YOU!

www.themegallery.com87

THANK YOU!

LooCK