uk electricity market reform - bruegelbruegel.org/wp-content/.../events/breugel_event_emr...the emr...

14
UK Electricity Market Reform The impact to generators & consumers Tim Abraham, UK Department of Energy & Climate Change 19 March 2012

Upload: others

Post on 10-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

UK Electricity Market ReformThe impact to generators & consumersThe impact to generators & consumers

Tim Abraham, UK Department of Energy & Climate

Change

19 March 2012

Page 2: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

Our objectives for the electricity system mirror those for the

wider system

Climate change: • Electricity has a big role in

carbon budgets and long term

climate goals

• Similarly, a large part to play in

delivering 15% renewable

energy by 2020

Security of supply: • Keeping the lights on (short and

long term)

• Diversity of supply

• Resilience

• Electricity demand may double

by 2050

Affordability: • Costs to taxpayer (short and

long term)

• Keeping bills down in short and

long term

Page 3: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

The electricity market has worked well - but we need to make sure this

continues as demand increases; and as we face supply and

decarbonisation challenges

Security of supply:Around a fifth of our plant will close by 2020

700

800

900

1,000

Scenario for electricity generation capacity to 2050

Electricity imports / exports

Non-thermal renewable generation

Tackling climate change:Need to decarbonise power sector by 2030s

25%

30%

35% De-rated capacity margin

3

0

100

200

300

400

500

600

700

TW

h / y

ea

r

generation

Nuclear power

Combustion + CCS

Conventional thermal plant

Domestic demand

We need to manage these challenges at least cost to the consumer

0%

5%

10%

15%

20%

2002 2007 2012 2017 2022 2027

Historic Central Scenario Stress Test

Page 4: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

The current electricity market arrangements will not meet

these challenges

If we do nothing:

• Will not meet the scale of investment needed

• Risk of blackouts due to lack of capacity

Security of supply - ageing and polluting plant are being replaced with more intermittent/less flexible generation

Scale of investment needed - £110bn in generation and transmission

4

Weak carbon signals – current price of carbon is weak meaning no clear signals

for investment in low-carbon

No level playing field for low carbon

capacity – Margins hit 5% with less

generation and more intermittent supply

• Will not decarbonise fast enough to meet our C-budgets

• Consumers pay more for electricity than they need to

intermittent/less flexible generation

Page 5: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

Our aim is transition to a world where low carbon

technologies compete on cost

Long term vision:

An electricity

EMR puts in place the framework for transition towards this goal:

In particular, we have designed a market which :

5

An electricity market where

low carbon technologies compete on

cost

In particular, we have designed a market which :

• Maintains the current liberal wholesale market

• In addition, it puts in place new institutional and incentive arrangements to deliver the investment required to deliver secure low carbon power at least cost to consumers

Page 6: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

The EMR White Paper and Technical Update set out our plan

to reform the market and achieve our three objectives of

secure, affordable and low-carbon electricity

Contracts for Difference

There are four policy instruments in the reform package

Capacity Mechanism

Emissions Performance

StandardCarbon Price Floor

Page 7: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

Carbon Price Floor – bolsters / tops-up the price of carbon in

the EU Emissions Trading System (EU ETS)

Carbon price floor illustration (in real 2009 prices and calendar years)

Source: HM Treasury 2011

The CPF reinforces the concept of “the polluter pays” and strengthens the carbon

price signal to investors encouraging investment in low-carbon technology now

Page 8: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

Feed-in Tariffs with Contracts for Difference (FiT CfD) –provides revenue stabilisation for all low-carbon generation

40

60

80

100

120

Ele

ctr

icit

y p

ric

e £

/MW

h

Generator topped-up to strike price

Strike price

-20

0

20

40

2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

Ele

ctr

icit

y p

ric

e £

/MW

h

Annual average electricity price (reference price) CfD payment Monthly electricity price

Generator paysback

The generator sells power in the market but also receives a “top-up” payment to a

pre-agreed “strike price”. Generator pays back when prices are above the strike

price. Revenue stability lowers the cost of capital - so lower cost to consumers.

Page 9: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

900

800

700

600

New, supercritical coal – c.790

Typical-sized supercritical coal, with around 300MW (net) CCS – c.600

Existing coal – c.900

g/kWh

Emissions Performance Standard – provides a regulatory back-stop on the amount of emissions new fossil fuel power stations are allowed to emit

• EPS will be an annual limit on carbon

emissions, initially equivalent to 450g

CO2/kWh (at baseload) for all new fossil

fuel plants.

• EPS will be grandfathered, providing

guarantees for plant on their EPS level

for a clear and pre-determined period. 600

500

100

400

300

200

EPS Level and 2010 average - c.450

around 300MW (net) CCS – c.600

IGCC - 1 unit coal (with CCS) and 1 unit gas – c.260

New CCGT – c.350-380

for a clear and pre-determined period.

• EPS to be reviewed as part of the

decarbonisation reporting process

required under the Energy Act 2010 – in

practice, first EPS review to report by end

of 2015.

• Exemptions for plant forming part of the

UK CCS Programme.

Page 10: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

Capacity Market – will ensure we have sufficient, reliable capacity to meet demand at all times

• Central body forecasts peak demand

• Total amount of capacity purchased from

providers (potentially including generation

and non-generation approaches)

• Incentives/penalties in place to ensure

capacity available when neededcapacity available when needed

• Range of design choices – e.g. level of

capacity offered, how it is purchased,

incentives/penalties structure

• E.g. US markets (PJM, ISO-NE),

Colombia, Brazil

Page 11: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

Transition from Renewables Obligation (RO) to FiT CfD will

be essential to maintain investment in renewables

• No retrospective changes – accredited schemes will stay in

the RO

• RO will remain open to new accreditations until 31 March

2017

11

• One-off choice of mechanism between the introduction of the

FiT CfD and the 31 March 2017 for new generation

• Limited grace periods around 31 March 2017 – delays in grid

connection and need for radar facilities

Page 12: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

The Institutional framework will balance an independent delivery body with clear Government accountability

Setting the policy

approach and

objectives

Translating the

policy

Government has policy accountability

System Operator advises Government on rules and parameters in the delivery plan

Government sets out key rules and parameters as part of the legislative framework and publishes the delivery plan

12

Monitoring

compliance and

enforcement

Administering the

mechanisms

Reconciling data

and managing

payments

System Operator administers contracts and auctions and reports annually to Government

Settlement agent manages payments, through a payment model backed by a robust and stable legal framework

Ofgem and Government monitor the System Operator’s delivery performance

Ofgem and System Operator monitor suppliers’ and generators’ compliance

Page 13: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

Our Technical Update in December set out the completed market

reform framework

Government

Sets overall policy direction and sets out key parameters

System operator (National Grid)

Will advise government on contract parameters and administer the arrangements

13

arrangements

Investment in low-carbon generation also supported by Carbon Price

Floor & Emissions Performance Standard

Contracts to develop low carbon

generation – contracts for difference

Market wide capacity contracts:

open to all forms of generation

Page 14: UK Electricity Market Reform - Bruegelbruegel.org/wp-content/.../events/Breugel_Event_EMR...The EMR White Paper and Technical Update set out our plan to reform the market and achieve

White Paper

The next stage is the introduction of legislation leading to implementation in 2014

Technical

Royal Assent

2013Consultation Update on White Paper

• CfDs

• CPF

• EPS

July

2011

Technical Update

• Capacity Market

• Institutional Framework

Dec 2011

Legislation introduced

May

2012 (subject to Parliament)

2013

1st CfDs signed:

2014

End of transition 2017

14

ConsultationDocument

December

2010

Update on CfDs, EPS

Spring

2012