u5293105efrwefr individual report 3 trauma crib updated

12
0 | Page Preliminary Project Management Plan (PMP- A) The Bushfire Trauma Crib Project: Providing portable intensive care stations for people affected by rural bushfires.

Upload: gavin-saldanha

Post on 11-Nov-2015

218 views

Category:

Documents


1 download

DESCRIPTION

ewfwe

TRANSCRIPT

  • 0 | P a g e

    Preliminary Project Management Plan (PMP-A)

    The Bushfire Trauma Crib Project: Providing portable intensive care stations for people affected by rural bushfires.

  • 1 | P a g e

    Contents Document Control ............................................................................................................... 2

    Document Information .................................................................................................... 2

    Document History............................................................................................................ 2

    Document Approvals ...................................................................................................... 2

    Planning Foundations ........................................................................................................ 3

    Scope ............................................................................................................................... 3

    Milestones and Inchstones ............................................................................................. 3

    Phases .............................................................................................................................. 4

    Activities .......................................................................................................................... 4

    Work Breakdown Structure ............................................................................................ 5

    Tasks ................................................................................................................................ 6

    Resources and Effort ...................................................................................................... 6

    Budget (labour) ................................................................................................................ 8

    Project Plan ......................................................................................................................... 9

    Schedule .......................................................................................................................... 9

    Precedence and Dependencies .................................................................................... 10

    Assumptions .................................................................................................................. 10

    Constraints .................................................................................................................... 10

  • 2 | P a g e

    Document Control

    Document Information

    Information

    Document ID D1-PMP

    Document Owner Gavin Saldanha

    Issue Date 25/03/2015

    Last Saved Date 04/05/2015

    File Name Trauma_Crib_PMP

    Document History

    Version Issue Date Changes

    [1.0] 25/04/2015 Document created

    [1.1] 1/05/2015 Updating PMP-A for activity breakdown

    Document Approvals

    Role Name Signature Date

    Project Manager

    Gavin Saldanha

    25/04/15

    Project Sponsor

    Liam Waldron

    25/04/15

    User Representative

    Documentation Leader

    Communications Manager (Liaison Officer)

    Project Office Manager (Programme Manager)

  • 3 | P a g e

    Planning Foundations

    Scope Inability to access medical and health resources in remote, rural areas of Australia makes it increasingly dangerous to live, especially during times when bushfires can occurs. The Bushfire Trauma Crib Project aims to investigate affordable and effective mobile intensive care systems for these rural areas. The scope of this project therefore expands, but will not be limited to:

    1) Investigating and creating a conceptual design for a mobile intensive care system for bushfire victims, whilst exploring how it can be also repurposed for victims of other disasters.

    2) Assessing the solutions through performance evaluations and metrics like Cost Benefit Analyses.

    3) Ensuring a prolonged longevity of the project after deliverables have been handed to ensure minimal costs will be incurred for sustainability.

    Milestones and Inchstones The completion of activities that have occurred so far y produced the following outcomes, which have also produced certain deliverables that can be monitored by management to undergo system progress and completion.

    Milestone Description Date Inchstones

    Project Initiation Document approval

    Document detailing project initiation and establishes the baselines and initial scope of the project.

    27/04/2015

    Initial scope established.

    Identification of client and stakeholders.

    Identifying personnel involved.

    Identifying initial activities to be performed for Work Breakdown Structure.

    Initial Design Requirements approval

    Mapping the initial needs of the client and stakeholders to form requirements.

    22/05/2015 Estimate budget to manage breakdown of key system requirements.

    Determine initial resources and skills required to ensure portability and affordability of mobile care system.

    Health and building codes and regulations identified.

    Project Management Plan (PMP-A) delivered

    Detailing the PMP for establishing foundations for the team, along with project schedule.

    29/05/2015 Finalising activities and inclusion of tasks.

    Project plan establishment.

    PMP-A draft feedback and finalisation.

  • 4 | P a g e

    Conceptual design approval

    Report containing the conceptual design will be delivered to stakeholders and client

    Around June 2015

    Risk assessment associated to ensure viability of system

    Surveys from people in rural areas to enhance what they need in the crib.

    Analyses of trauma crib technological efficiencies in catering to people in rural area needs.

    Feedback associated to help reassess and revise PMP-A to PMP-B.

    Final report delivery

    Handing over the final design to client

    TBC Cost and feasibility analysis

    Feedback from client

    Compiling and receiving feedback from draft handover

    Project completion

    Phases The key phases for the project are divided as follows:

    Phase + Sequence Description Deliverables

    Phase 1: Project Initiation and Planning

    Establishing the team and developing a business case and Project Charter. The scope is also defined where initial inputs such as cost, time, and outcomes of the project are identified.

    1) Project Initiation Document

    2) Project Management Plan A (PMP-A)

    Phase 2: Project Execution

    Performing activities mentioned in the PMP-A and tracking project performance and guiding to reaching milestones.

    1) Design Review 2) Project Management

    Plan B (PMP-B)

    Phase 3: Project Closure

    Submission of final design report and project presentation. All activities will be finalised and reflected upon.

    1) Final Design Report 2) Performance Metrics

    Activities The individual activities within the project lifecycle are defined, as per their phases.

    Phase Activity Description Sequence

    Project Initiation and Planning

    Project definition and its processes

    Initial scope and rough schedule definition. Identification of communication plan and rough estimate of user requirements eg. emergency personnel. This will therefore establish a Work Breakdown Structure for team members.

    Included in the Project Identification Document (PID).

    Performing client + stakeholder analysis.

    Determine needs and expectations of clients and stakeholders where milestones are revised to form Business Case.

    Included in PID.

  • 5 | P a g e

    Project Risk Register

    Risks with the project and its impact are observed, as well as mitigation strategies.

    After PID but before PMP-A completion.

    Resource Organisation

    Planning in liaison with medical and building personnel to allocate resources to team members

    After PID until end of project

    Project Execution

    Project performance and updating

    Updating project progress as per schedule actions and adding changes such as with risks.

    Occurs throughout project

    Design development

    Solutions that meet stakeholder + client requirements such as portable burn treatment units are achieved in designs

    After conceptual design approval

    Sustainability review

    Determining the lifecycle analyses and product evaluation through metrics like Cost-Benefit Analysis

    After conceptual design approval

    Risk Management

    Monitoring of risks in project so that corrections can ensure project runs smoothly

    Throughout project

    Project Closure

    Handing deliverables

    Shutting down all activities, sending final report. After deliverable submission

    Identify improvements

    Through metrics like peer assessment reviews reflect to improve relatable projects

    After project

    Work Breakdown Structure

    Bushfire Trauma Crib Project

    1. Project Initiation and Planning

    1.1 Project Definition

    1.2 Project Processes

    1.3 Performing client + stakeholder analysis

    1.4 Project Risk Register

    1.5. Resource Organisation

    2. Project Execution

    2.1 Project Performance and

    Updating

    2.2 Design development

    2.3 Risk Management Plan

    2.4 Sustainability Review

    3. Project Closure

    3.1 Handing deliverables

    3.2 Identify improvements

  • 6 | P a g e

    Tasks

    Phase Activity Tasks Sequence

    Project Initiation and Planning

    Project Definition

    Creating initial scope (boundaries, objectives, deliverables, et cetera) of project

    Rough schedule estimation for reaching milestones

    1 2

    Project Processes Creating communication plan with clients and stakeholders (Business Case)

    Constructing Work Breakdown Structure

    Assigning members + due dates to tasks of project based on skills required

    1 2 3

    Performing client/stakeholder analysis

    Identifying resources required for project

    Determining stakeholder strategies and expectation

    1 2

    Resource organisation

    Classifying facilities and external personnel such as medical team required

    Training team through their skills with motivation

    Create agendas and facilitate meetings

    1 2 3

    Project Risk Register

    Classifying potential risks

    Assessing their impact on project

    1 2

    Project Execution

    Project Performance & Updating

    Reflecting on project and updating plan

    Implementing corrections throughout

    Adhering to codes and ethics

    1 2 3

    Design development

    Manage stakeholder expectations and changes

    Developing test methods for designs

    1 2

    Sustainability review

    Finding life cycle phases and impact assessment

    Finding solutions for integrating feedback

    Identifying if solution can be used for other disasters than bushfires

    1 2 3

    Risk Management Plan

    Review risks involved

    Develop contingency plans for risks

    Communicate and improve on potential risks

    1 2 3

    Project Closure

    Handing deliverables

    Producing final report and designs to clients

    Transition of resources to similar projects

    1 2

    Identifying improvements

    Attaining peer reviews and reporting

    Reflecting on project to improve new ones

    1 2

    Resources and Effort The amount of effort, in number of hours allotted to one person, and resource allocation to complete deliverables of the project are shown. Effort is always subject to change due to behavioural aspects of team and personnel, therefore it is merely an approximate for the project until key deliverables and outcomes are properly identified.

  • 7 | P a g e

    Task Effort (no. of hours)

    Resources required

    Project Definition

    Creating initial scope of project

    Rough schedule estimation for reaching milestones

    15 hours 5 hours

    Project Manager (PM)

    PM

    Project Processes

    Creating communication plan with clients and stakeholders (Business Case)

    Constructing Work Breakdown Structure

    Assigning members + due dates to tasks of project based on skills required

    6 hours 4 hours 3 hours

    Client Liaison PM + Team PM + Lead System Engineer (LSE)

    Performing client/stakeholder analysis

    Identifying resources required for project

    Determining stakeholder strategies and expectation

    30 hours 15 hours

    PM + Team PM + Client Liaison

    Resource organisation

    Classifying facilities and external personnel such as medical team required

    Training team through their skills with motivation

    Create agendas and facilitate meetings

    30 hours 50 hours 80 hours

    PM + Team + Medical Supplies PM PM + Team

    Project Risk Register

    Classifying potential risks

    Assessing their impact on project

    10 hours 12 hours

    Risk Manager Risk Manager

    Project Performance & Updating

    Reflecting on project and updating plan

    Implementing corrections throughout

    Adhering to codes and ethics

    10 hours 10 hours 3 hours

    Team + LSE Team Team + LSE

    Design development

    Manage stakeholder expectations and changes

    Developing test methods for designs

    10 hours 6 hours

    Client Liaison Team + LSE

    Sustainability review

    Finding life cycle phases and impact assessment

    Finding solutions for integrating feedback

    Identifying if solution can be used for other disasters

    12 hours 8 hours 5 hours

    PM + Team + LSE PM + Team + LSE PM + Team + LSE

    Risk Management Plan

    Review risks involved

    Develop contingency plans for risks

    Communicate and improve on potential risks

    10 hours 9 hours 9 hours

    PM + Risk Manager Risk Manager Risk Manager

    Handing deliverables

    Producing final report and designs to clients

    Transition of resources to similar projects

    6 hours 10 hours

    PM + LSE + Team LSE

  • 8 | P a g e

    Budget (labour) A top down estimate of cost for all tasks are given below, where $50 per hour for all team members except the Project Manager and Lead System Engineer; their times are free in aid to the project. Note that the number of members in the team vary with tasks.

    Task Time Resources required Cost

    Project Definition

    Creating initial scope of project

    Rough schedule estimation for reaching milestones

    15 hours 5 hours

    PM

    PM

    0

    0

    Project Processes

    Creating communication plan with clients and stakeholders (Business Case)

    Constructing Work Breakdown Structure

    Assigning members + due dates to tasks of project based on skills required

    6 hours 4 hours 3 hours

    Client Liaison PM + Team (3) PM + Lead System Engineer (LSE)

    300 600 0

    Performing client/stakeholder analysis

    Identifying resources required for project

    Determining stakeholder strategies and expectation

    30 hours 15 hours

    PM + Team (5) PM + Client Liaison

    7500 750

    Resource organisation

    Classifying facilities and external personnel such as medical team required

    Training team through their skills with motivation

    Create agendas and facilitate meetings

    30 hours 50 hours 80 hours

    PM + Team (5) PM PM + Team (5)

    7500 0 20000

    Project Risk Register

    Classifying potential risks

    Assessing their impact on project

    10 hours 12 hours

    Risk Manager Risk Manager

    500 600

    Project Performance & Updating

    Reflecting on project and updating plan

    Implementing corrections throughout

    Adhering to codes and ethics

    10 hours 10 hours 3 hours

    Team (5) + LSE Team (5) Team (5) + LSE

    2500 2500. 750

    Design development

    Manage stakeholder expectations and changes

    Developing test methods for designs

    10 hours 6 hours

    Client Liaison Team + LSE

    500 300

    Sustainability review

    Finding life cycle phases and impact assessment

    Finding solutions for integrating feedback

    Identifying if solution can be used for other disasters

    12 hours 8 hours 5 hours

    PM + Team (5) + LSE PM + Team (5) + LSE PM + Team (5) + LSE

    3000 2000 1250

    Risk Management Plan

    Review risks involved

    Develop contingency plans for risks

    Communicate and improve on potential risks

    10 hours 9 hours 9 hours

    PM + Risk Manager Risk Manager Risk Manager

    500 450 450

  • 9 | P a g e

    Project Plan

    Schedule Provide a summarised schedule for each of the phases and activities within the project.

    Handing deliverables

    Producing final report and designs to clients

    Transition of resources to similar projects

    6 hours 10 hours

    PM + LSE + Team (2) LSE

    600 0

    Total (in AUD$) 52100

  • 10 | P a g e

    Precedence and Dependencies There are four types of dependencies: Finish-to-start (FS), Start-to-start (SS), Start-to-finish (SF) and Finish-to-finish (FF). The following activities have been classified with their deliverable dependencies:

    Activity Depends on Dependency Type

    Project Processes Project Initiation Document (PID) SS Client/Stakeholder Analysis PID FS

    Risk Management Plan PID FS

    Project Work Breakdown Schedule Client Briefing FS

    Resource Organisation Initial Design Requirements FS

    Final Report + Peer Review Project Finalisation Report FS

    Assumptions

    Internal assumptions, or within the team are:

    The project scope will remain bounded.

    The amount of hours allocated for tasks are assumed under ideal scenarios.

    Relevant resource allocation for visualising scenarios will be provided to the team.

    External assumptions, or external to the team:

    The design system will match the behavioural and comfort of victims of bushfires.

    The medical personnel will prefer to use the system as they will have full technical

    knowledge on how to use it.

    Constraints

    Internal constraints, or those imposed by the project scope and the team are:

    Available human resources: Team members might undergo changes due to management issues, therefore task allocation must be effectively implemented in case team members are missing.

    Efficient time management must be carried out, and as a result the milestones have a bit of leverage in their deliverables.

    External constraints, or those placed by external parties not related to the project are:

    Health codes and building safety regulations might constraint how project execution can be carried out.

    Many of the equipment used in the project must provide proper care and safety as they could possibly be damaged by the bushfires.

  • References

    [1] A. Kossiako, W. Sweet, S. Seymour (2011), Systems Engineering Principles

    and Practice, Wiley

    [2] G. Ganewatta and J. Handmer (2006). Bushfire management: What, where and how

    economics matter. Proceeding of Bush re Conference 2006: Life in Fire Prone

    Environment: Translating Science into Practice/

    [3] L. Waldron, Management Skills (2014), Australian National University

    [4] Federation University Australia (2014), Living with Bushfire: A Community

    Conference

    u5293105_Individual_Report_3_trauma_crib.pdfreferences.pdf