truman ms- design development narrative

86
DESIGN DEVELOPMENT NARRATIVE A L B U Q  U E R Q  U E P U B L I C S C H O O L S A L B U Q  U E R Q  U E P U B L I C S C H O O L S JANUARY 12, 2010

Upload: apsarchitect

Post on 30-May-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 1/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  SA  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L 

JANUARY 12, 20

Page 2: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 2/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.  i. APS Design Committee page 1ii. Design Team page 1

II. PROJECT OVERVIEW

i. History Page 2III. DESIGN CONCEPTS

i. Architectural Concepts page 3ii. Landscape page 5iii. Structural Concepts page 6iv. Mechanical Concepts page 8v. ec r ca

 

oncep s page 

vi. Civil page 24vii. LEED Concepts page 26

IV. DESIGN CRITERIA

i. Space Program page 48. Re erences page 49

iii. Site   page 50iv. International Building Code   page 50

V. DRAWINGS

i. AS‐101 Site Plan page 51ii. AS‐102 Phasing Plan page 52iii. A‐101 Renovation Floor Plan page 53iv. A‐111 First Floor Plan page 54v. A‐112 Second Floor Plan page 55vi. A‐113 Clerestory Level Plan page 56vii. A‐141 Roof  Plan page 57 

. ‐

ix. A‐301

 Building

 Sections page 59

VI. COST ESTIMATE page 60VII.  APPENDIX

TABLE OF CONTENTS

i. Meeting Minutes page 73ii. Zone Atlas Map page 84

Page 3: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 3/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

I. PROJECT TEAMS

i. APS Design CommitteeRoldan Pasion, Project  Manager, Staff   Architect 

EDI, LEED consultant 

Kris Callori, Principal 

Matt Hi ins LEED AP ASHREA‐HBDP 

 Amanda Redmond ‐neal, LEED  AP

Commissioning  Agent 

Test Marcx

Robert  Quintana II, Operations Manager 

ii. Design Team

 Architect 

Fanning Bard  Tatum  Architects

 Art  Tatum, Principal ‐in‐Charge

Susan  Johnson, Project   Architect 

Civil  Engineer 

Bohannan Houston

Bruce Stidworthy, 

Structural  Engineer 

Walla Engineering

e  a a, 

Mechanical  Engineer 

Bridgers & Paxton

Rich Rief 

Electrical  Engineer 

Bridgers & Paxton

 John Heck 

Landscape  Architect 

Morrow   Reardon Wilkinson Miller 

Dennis Wilkinson

PAI. P R O J E C T  T E A M S 

Estimating

Balis & Company 

 Jon Balis

Page 4: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 4/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

Truman Middle School , formerly known as Westgate, has undergone a multitude of  additions

and renovations. The initial design was begun in September of  1973.

PAII. P R O J E C T  O V E R V I E W ‐ HISTORY

Page 5: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 5/86

Page 6: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 6/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

USGBC – LEED : This project is a LEED project, and will meet the

requirements set forth by the USGBC to achieve LEED SILVER minimum

certification. Albuquerque Public Schools has contracted separately with a

LEED consultant.

PAIII. DESIGN CONCEPTS ‐ ARCHITECTURAL

Page 7: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 7/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

III. DESIGN CONCEPTS

ii. Landscape

The landscape design concept for Truman Middle School is to represent

an re ect t e nat ve env ronments o uquerque. e an scape

surrounding the school buildings will echo the surrounding xeric landscape

of the West Mesa, while any interior planting areas or courtyards will

represent the nearby landscape of the Rio Grande Bosque. Drop‐

off/pickup areas will have street trees for shade and an appropriate

landscape buffer to separate pedestrian and vehicular traffic. Trees will

.

irrigation system will be highly efficient and will comply with all APS

standards for irrigation. Plants will be chosen in accordance with APS

standards and in keeping with the concept, will be native or naturalized,

low water use, and low maintenance. Wind and dust abatement measures

such as windbreak plantings and re‐vegetation for soil stabilization will be

used to minimize sand blowin on site and create a leasant microclimate.

Overall, the landscape will serve to create a regionally appropriate and

comfortable learning environment.

PAIII. DESIGN CONCEPTS ‐ LANDSCAPE

Page 8: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 8/86

Page 9: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 9/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

iii. Structural Design Parameters ( continued )

STRUCTURAL NARRATIVE

e pro ec s a + ‐ , , wo s ory c assroom, compu er a s, an

science labs addition in Albuquerque NM to the existing school.

The new roof structure will be a steel joist and metal deck roof assembly

supported by primarily masonry walls and some load‐bearing steel beams and

steel columns at the corridor. The joists are pre‐engineered steel members

manufactured by a member of the Steel Joist Institute (SJI) and will be spaced

at 5’‐0” on center. These oists will bear on the masonry walls and on steelbeams at the high roof over the corridor. The deck will be 1‐1/2”deep, 22

gage painted B‐deck with nestable sidelaps.

The new floor structure will have concrete topping over composite steel deck

over composite steel beams that connect into masonry walls. The steel beams

will be W‐section members with ¾ inch diameter headed studs welded to

them through the deck. The steel beams will be spaced at approximately 6 ft

on center and the headed studs spaced at approximately 12 to 24 inches on

center.

Exterior masonry walls are constructed of 8 inch thick CMU reinforced withtruss type joint reinforcing at 16 inches on center and #5 vertical bars at 32

inches on center with multi le bars and/or reinforced cells at amb locations.

Wall openings will be designed with masonry lintels adequate to span the wall

openings and carry gravity, wind, and seismic loads to the jambs.

Steel columns and bearing walls will be supported with cast in place concrete

footings constructed with 3000 psi concrete and steel rebar reinforcing. A 4

inch thick, cast in place slab on grade will serve as the primary floor assembly.

geotechnical report.

Lateral loads will be resisted by masonry shear walls. These masonry shear

walls will be designed to resist both wind and seismic loads. A perimeter deck

angle attachment will transfer diaphragm loads from the floor and roof 

diaphragms to the masonry shear walls and these metal deck diaphragms will

PAIII. DESIGN CONCEPTS ‐ STRUCTURAL

.

Page 10: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 10/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

iv. Mechanical Design Parameters

GENERAL

approach and general recommendations for this facility. The scope of this project

is a 23,000 sq ft two story classroom addition at the existing Truman Middle

School campus. The addition will consist of 10 classrooms, 4 science labs, and 2

computer labs in addition to support space. The building is a traditional double

loaded corridor school building.

REFERENCES

Uniform Mechanical Code (UMC ‐ Latest Edition)

Uniform Plumbing Code (UPC ‐ Latest Edition)

International  Building Code (IBC ‐ Latest  Edition)

National  Fire Protection  Association (NFPA ‐ Latest  Edition)

 American Society  of  Heating, Refrigeration,  Air  Conditioning Engineers (ASHRAE)

 Americans with Disabilities  Act  (ADA)

National  Fire Protection Code & Life Safety  NFPA

 Albuquerque Public School  Design Guidelines

Heating , Ventilating,

 and

 Air

 Conditioning

u oor  es gn  on ons 

Location:  Albuquerque, New Mexico, ASHRAE climate zone 4B

Elevation:  5300 feet above sea level

Winter 99% Design Dry‐bulb:  13°F

Summer 1% Design Dry‐bulb/Wet‐bulb:  93°F /60°F

Latitude:  35.0 N

Longitude:  106.6

PAIII. DESIGN CONCEPTS ‐ MECHANICAL

Page 11: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 11/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

III. DESIGN CONCEPTS

Heating , Ventilating, and Air Conditioning ( continued )

Indoor

 Design

 Conditions

Indoor conditions will be maintained within the acceptable range set forth in 

ASHRAE 55‐2004.

Space Winter Summer Relative Humidity

General 68°F 72°F N/A

Classrooms 68°F 72°F N/A

Mech/Elec Rm 55°F 95°F N/A

IT/Comp Room 68°F 68°F N/A

Energy Conservation

The building will be LEED Certified and will need to exceed the ASHRAE 90.1 ‐

2007 energy performance based on the performance rating method. The

analysis and documentation of the energy performance will be performed by the

Districts LEED Consultant. 

Envelope Construction

The buildings envelope will need to meet or exceed the requirements of  ASHRAE 

90.1 2007 which are as follows for the 4B Climate zone:

Roof  (insulation

 above

 deck):

 R20/U

‐0.048

 assembly

 max

Wall (steel framed):  R13 + R7.5/U‐0.064 assembly max

Wall (block):  R9.5/U‐0.104 assembly max

Slab (on grade):  NR

Glazing:  U‐0.55/SHGC‐0.40

Interior Loads

Equipment: The individual space loads are currently not well defined.  Heating 

and cooling load calculations will be based on ASHRAE Fundamentals and actual 

project requirements as t ey are  eve ope .

People: 

250 British

 thermal

 units

 per

 hour

 (Btu/hr)

 (sensible),

 200

 Btu/hr

 

(latent). Space occupancy will be based on architectural furniture plans and 

ASHRAE standards where no information is available.

Lights: Lighting loads will need to meet or exceed requirements established in 

ASHRAE 90.1‐2007 as listed below.

Classrooms:  1.4w/SF

PAIII. DESIGN CONCEPTS ‐ MECHANICAL

Restrooms:  0.9 w/SF

Corridors:  0.5 w/SF

Elect/Mech 1.5 w/SF

Page 12: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 12/86

Page 13: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 13/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

Plumbing Design Parameters

Plumbing Fixtures

 p um ng  x ures w   e spec e   us ng commerc a  qua y ma er a s an   r m 

and will be fully compliant with all applicable accessibility requirements and 

conservation standards. 

The Albuquerque Public School (APS) System has standardized on American 

Standard fixtures and Sloan flush valve trim.  Lavatory faucets will be automatic 

with 120v controls.  Water closets will be floor mounted with manual flush valve 

(1.28 gpf)

 type.

 Urinals

 will

 be

 wall

 hung

 very

 low

 flow

 (0.125

 gpf)

 type.

 Electric

 water coolers will meet APS standards. 

Service sinks will be specified to be floor mounted. Floor drains with trap primers 

and loose key hose bibbs will be installed in each restroom to facilitate floor 

cleaning. 

Plumbing fixtures in the building were selected to reduce the building’s potable 

water consumption.

Domestic Water 

Domestic hot water supply will be provided by gas fired, electronic ignition (no 

Domestic (potable) cold, hot, and hot water recirculation mains will be routed 

through the facility. 

Tempered hot water will be provided to the lab sinks. 

maintenance. 

Zone valves will be strategically located so as to allow isolation of  segments of  the 

system, thus preventing a system wide shutdown and drain down to facilitate 

maintenance/repair/renovation.

PAGIII. DESIGN CONCEPTS ‐ MECHANICAL

Page 14: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 14/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

Plumbing Design Parameters ( continued )

Sanitary Sewer 

p um ng  x ures w   e connec e   o  e ex s ng conven ona  grav y‐ ype 

sanitary sewer and vent system utilizing cast iron materials.

Hub and spigot cast iron pipe will be used within the building and PVC only 

allowed outside the building. 

All system connections will be trapped and vented with vents routed to 

termination at

 the

 roof 

 level.

 

The sanitary drain system shall be designed to a point 5 feet beyond the building 

perimeter.

Storm Sewer 

Roof  drainage will be by interior piped systems which will daylight at grade.

Natural Gas 

Natural gas will be served by a new yard line served from the schools existing 

meter. 

Gas will be provided to science classrooms if  required by program.

Site Utilities 

Every effort will be made to use the existing utility system and avoid new utility 

work. 

If  required,

 domestic

 water,

 fire

 protection

 water,

 and

 sanitary

 sewer

 will

 be

 

designed to on‐site utility connection points outside the building. 

Provisions for backflow prevention, heated enclosures, various fire protection 

system connections, area isolation valves, and allowances for future expansion 

will be coordinated with APD and the Architect. 

PAGIII. DESIGN CONCEPTS ‐ MECHANICAL

Utility design, from 5 foot beyond the building, for all of  the above systems shall 

be provided under the Civil Engineering Section.

Page 15: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 15/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

v. Electrical Design Parameters

GENERAL

Scope

The purpose of  this narrative is to provide a scope for the electrical systems, 

design approach, and general recommendations for this facility.  The scope of  this 

project is a 23,000 sq ft two story classroom addition at the existing Truman 

Middle School campus.  The addition will consist of  10 classrooms, 4 science labs, 

and 2

 computer

 labs

 in

 addition

 to

 support

 space.

 The

 building

 is

 a

 traditional

 double loaded corridor school building.  Occupancy type E

Codes and Applicable Standards:

 

(National Electrical Code), 72,101, 780.

New Mexico Electrical Code latest edition.

International Building Code (IBC 2006).

n orm  re  o e  .

Illuminating Engineering Society of  North America (IESNA) Handbook.

Uniform Federal Accessibility Standards (UFAS).

New Mexico Night Skies Protection Act.

International Energy

 Conservation

 Code

 (IECC

 2003)

Albuquerque Public Schools Electrical Design Standards

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

Page 16: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 16/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

III. DESIGN CONCEPTS

v. Electrical Design Parameters

GENERALElectrical Distribution

r mary erv ce s r u on:

The Public Service Company of New Mexico (PNM) currently provides 12470V,

3Ph primary service to the project site. At the northeast corner of the existing

building a PNM transformer and meter enclosure are located. Coordination with

PNM and the schools existing and new loads will be required so that PNM can

decide if the existing transformer size will require and increase.

Existing Secondary Equipment:

The existing service equipment is 1200A, 480Y/277V, 3 Ph and will remain in place

and be re‐fed from new electrical equipment as discussed below. The existing

schools peak load will need to be verified through APS energy department and/or

PNM.

New Secondary Electrical Equipment and Distribution:

A new 3000A, 480Y/277V exterior mounted switchboard will be designed to

accommodate serving the existing schools 1200A service, phase I construction(23,000sq.ft.), and future phases of classrooms (24,000sq.ft.), Auxiliary

Gymnasium (8,000sq.ft.), additional dinning space (5,000sq.ft.), and a bus loop.

Secondary Power Distribution: 

480Y/277V, 3 Phase from utility transformers to the new electrical main

distribution equipment. 480Y/277V, 3 Phase electrical Panels will be located

in sub electrical rooms in the layout of each section of the building.

208Y/120V, 3 Phase electrical Panels will be located in sub electrical rooms inthe layout of each section of the building. This voltage will be derived from

transformers connected to each 480Y/277V panel.

Lighting and Mechanical equipment will be on the 480Y/277V, 3 Phase

systems, and receptacle and computer loads will be on the 208Y/120V, 3

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

Motion‐sensor faucets, if incorporated into design will be provided with 120V

single‐phase power.

Page 17: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 17/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

III. DESIGN CONCEPTS

GENERAL  (  continued   )Branch Circuits 

Individual circuits will be used for general lighting and receptacle loads. Device 

quantities on each branch circuit will adhere to NMEC standards. 

Generally, loading on lighting circuits will be limited to 75% or less of  the branch 

breaker rating.

A minimum of  20% spare breakers / space will be allowed in all new branch 

circuit panel boards. 

n mum w re s ze  or  ranc   c rcu s  s no.  copper, excep  a  no. 

AWG copper will be used on 120 volt circuits longer than 75 feet. An equipment 

grounding conductor will be run in each branch circuit.

Emergency Power 

Emergency power will serve the lighting for life safety purposes.

Emergency lighting will be derived via individual battery packs in selected 

fluorescent luminaries.

Fire Alarm

 and

 communication

 systems

 will

 have

 self 

 contained,

 integral

 batteries,

 to operate equipment for a set time in the event of  a power outage.

Surge Suppression 

Surge Protection Devices (SPD) will be installed in panels where computer loads 

are prevalent. 

The SPD is used to minimize damaging internal and externally generated electrical 

transients that can damage electronic equipment.

Grounding System

 

The grounding electrode system will consist of  a new Ufer ground, structural steel 

in each building, ground rod, and cold‐water electrodes. 

All of  these electrodes will be  joined together at a new main grounding bar, 

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

adjacent to the main electrical service. 

All feeders and branch circuits will contain insulated, copper, equipment ground 

conductors. 

Page 18: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 18/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

GENERAL  (  continued   )Telephone Service Primary Service Distribution 

project site. 

The incoming distribution is underground, and extends from a utility pole near the 

north school property line.

Coordination with APS will be required to determine if  this existing 

MDF room in the new Phase I building.

Secondary Telephone and Data Distribution

Underground communication raceways, sized appropriately, will be used between 

MDF room and sub IDF rooms.  Some conduits will be stubbed 5’‐0” beyond 

building for use in future phases.  Raceways will be capped and include a pull 

rope.

Telephone/Data infrastructure throughout the school will be as follows:

Cable tray and/or J‐hooks from MDF or IDF rooms through corridors.

Raceway, minimum 1”, from cable tray/J‐hooks to device. 

Outlets, 4” square, 2½”deep with mud ring at each device location.

Albuquerque Public Schools will have their contracted vendors provide the 

following:

Headed 

equipment 

for 

communication 

systems

Termination of  cable to each device and at equipment source.

Testing of  all terminations and system.

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

Telecommunications consultant will be coordinated with for the requirements 

of  the equipment, cabling, devices, terminations listed above.

Page 19: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 19/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

GENERAL  (  continued   )Exterior Lighting 

,  , 

with lighting, utilizing a combination of  building mounted luminaries and pole 

mounted luminaries. 

Two pedestrian level pole mount luminaries will be provided in the staff  parking 

lot to the east.  Maximum 25’‐0” high and minimum 12’‐0” high poles will be used.

 

Skies Protection Act. 

Lighting levels will be designed in accordance with IESNA recommendations.

Except for the security lighting, the control for the exterior lighting will generally 

be via a programmable panel system, but  a photoelectric control‐on at dusk, time 

switc ‐o   can  e uti ize   i  APS  esires.

The security lighting will be generally be via a programmable panel system, but 

photoelectric control‐on at dusk and photoelectric control‐off  at dawn can be 

utilized if 

 APS

 desires.

 

Astronomical time clocks or the existing, self  contained Powerlink panel will be 

used.

Lighting foot‐candle levels will be designed in accordance to IESNA recommended 

levels.

Egress from building to public way will be designated by the Architect and will be 

provided with emergency lighting along path to public way or to distances as 

dictated by code.

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

Page 20: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 20/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

III. DESIGN CONCEPTS

GENERAL  (  continued   )Interior

 Lighting

 

Lighting design will consider ease of  maintenance, energy efficiency and suitability 

or  e env ronmen .  uorescen  amps w   e  or compac  uorescen  w   a 

color temperature of  3500 Kelvin, with energy saving electronic ballasts to 

minimize energy use.  Illumination levels will be in accordance with IESNA 

standards and APS electrical design standards.

Classrooms: 

Linear direct/indirect pendant luminaires will be utilized to provide a better 

teaching and learning environment. Luminaires will be mounted 18in. below 

ceiling level with ceiling heights at approximately 10ft. AFF.  Illumination levels 

will be targeted for 50 foot‐candles, measured horizontally at desk‐height.

Computer Labs: 

Linear direct/indirect pendant luminaires will be utilized to provide a better 

teaching and learning environment. Luminaires will be mounted 18in. below 

ceiling level

 with

 ceiling

 heights

 at

 approximately

 10ft.

 AFF.

 Illumination

 levels

 

will be targeted for 30‐40 foot‐candles, measured horizontally at desk‐height.

Offices: 

Linear direct/indirect pendant luminaires will be utilized to provide a better 

teaching and learning environment. Luminaires will be mounted 18in. below 

ceiling level with ceiling heights at approximately 10ft. AFF. Illumination levels 

‐ ‐ ‐  ,  . 

This 

will 

be 

determined 

based 

on 

the 

task 

in 

office.

Corridors: 

2X4 troffer luminaires will be utilized. Luminaires will be recess‐mounted flush 

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

  . 

foot‐candles, measured horizontally at the floor.  Special consideration will be 

given to common areas.

Page 21: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 21/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

Interior Lighting (  continued   )

Storage Spaces/Utility rooms: 

Fluorescent surface mounted utility strips will be used for general illumination. 

Illumination levels will be targeted for 15 foot‐candles, measured horizontally at 

the floor.

Media Center: 

If  included, will incorporate Linear direct/indirect pendant luminaires will be 

utilized to provide a better teaching and learning environment. Luminaires will be 

mounted 18in. below ceilin   level with ceilin   hei hts at a roximatel   10ft. AFF. 

Illumination levels

 will

 be

 targeted

 for

 30

‐40

 foot

‐candles,

 measured

 horizontally

 

at desk‐height.

Cafeteria/Dining:

‐,  . 

mounted flush within a new suspended ceiling. Illumination levels will be targeted 

for 15‐20 foot‐candles, measured horizontally at the floor.

Gymnasium: 

 joist/beam structure in room.  Luminaires will be vandal resistant.  Foot‐candle 

levels will be approximately 50‐80 measured in the vertical and horizontal plane 

over court

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

Page 22: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 22/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

Li htin   Controls 

Lighting control will consider ease of maintenance, energy efficiency and

suitability of the environment. The following areas will be controlled per APS

standards. Lighting control will follow APS standard Option 1 unless otherwisedirected by APS.

Classrooms: 

Master control of  room will be via dual technology ceiling mounted sensors. In 

some rooms the sensor may be wall mounted.  Sensor will turn on and off  

room switch control.

wo  ogg e sw c es w   e  ns a e   a  en ry  o c assrooms. ne sw c   w  

control single inboard lamp and one switch will control two outboard lamps of  

luminaries.  By utilizing dual switching we can provide four different levels of  

lighting: off, one lamp, two lamps, and three lamps.  Teacher has full control of  

room and environment.

Day‐lighting control will be used in rooms that incorporate Architectural day‐

light design. A sensor will be located in room to shut off  the two outboard 

lamps of  luminaries in room.  Teacher will still perceive control because the 

inboard lamps will be controlled by the teacher.

Offices: 

Offices will have toggle switch and occupancy type control.  Per APS standards. 

In large office spaces ceiling mounted occupancy sensors should be utilized.

Large open areas:

Dual technolo   sensors mounted on wall at several locations will be used.

Sensor will turn on and off  room switch control.

Keyed toggle switches will be installed at entry to room. Single or three‐way 

switching switch will control single inner lamps and will also control two 

outboard lamps of  luminaries by utilizing dual switching we can provide four 

different levels of  lighting: off, one lamp, two lamps, and three lamps.

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

Custodian will have full control of  room and environment.

Page 23: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 23/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

Lighting Controls (  continued   ) 

Gymnasium:

Master control will be with occupancy sensors will be master control for gym 

luminaires on and off.

Momentary contact switches will be installed at entry to gymnasium for 

secondary control.  One switch will control class time lamps/luminaires and 

one switch will control sports lighting during an event.

If  day‐light is incorporated architecturally sensors will be incorporated.

Teacher/Coach has full control of  room and environment.

Corridor:

Lighting will be controlled with keyed switches at each end of  corridor or at all 

entry points to the corridor.  No sensors will be used in the corridors. 

Corridors may also be programmed via a programmable system to turn on at 

6am and off  at 11 m.

No night lighting for security per APS standards.

Exterior building

 mounted,

 roadway,

 and

 parking

 area

 luminaries:

 

programmable system.  This will allow programming by APS M&O 

department.

Lighting for building and roadway will be on at dusk and off  at dawn.

Parking area lighting will be on at dusk and off  at midnight.  APS may require 

lighting on through the night for security reasons.  This will be determined 

.

Utility type rooms, i.e. Janitors closets, custodians and the like:

Master control of  rooms will be via a dual technology ceiling or wall mounted 

sensor.  Sensor will turn on and off  switch control.

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

Toggle and keyed switches will be installed at the entry to room..

Page 24: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 24/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

OTHER ELECTRICAL SYSTEMS

Fire Alarm, Television, Security, Intercom, Public Address, and Voice/Data

For all s stems listed above a racewa ath will be desi ned er APS contracted

vendors requirements. Coordination of raceway paths will be performed during

design. APS contracted vendor(s) will provide the following:

Head end equipment for all systems.

Termination of  cable to each device and at equipment source.

Testing of  all terminations and systems.

,  ,  ,  ,  , 

plates for

 all

 systems

 devices.

APS contracted vendor(s) will be coordinated with for the requirements of  the 

equipment, cabling, devices, and terminations listed above

Fire Alarm System

T is renovation to t e sc oo may inc u e new ire a arm system evices,

connected to the existing main panel located in the main building. This system is a

Class A, supervised, 24‐volt DC‐powered, multiplexed, addressable fire alarm

system.

The system is battery backed‐up in accordance with NFPA‐72. The system is

remote‐station monitored via a digital communicating device. HVAC equipment,

and flow and tamper switches in the building will be interlocked to the fire alarm

system in accordance with NFPA standards

Television System

A television infrastructure system with raceways, cables, is in place throughout 

the facilit . No  roblems with the s stem were identified b   the owner.  One‐inch 

conduits will be routed from each new device outlet to new cable tray (or J‐hook) 

system mounted above a new suspended ceiling within the Corridors. At a 

minimum, one television outlet will be installed in each individual classroom. 

It is envisioned that a separate outlet box will house the new television  jacks. 

Exact configurations and requirements will need to be verified with the APS 

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

  .

Page 25: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 25/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

OTHER ELECTRICAL SYSTEMS  (  continued   )

Security/Alarm System

It is antici ated that some t e of securit s stem is in lace for this School. The

requirements for additions to this system require further input from the school

district. When determined, devices will be indicated, and a raceway infrastructure

will be designed.

Lightning Protection System

A lightning protection system is anticipated as not being required for this project.

Such systems are optional for these types of buildings and their need is judged

based on a risk assessment. This requires final verification from APS.

Clock System

The clock system is existing, and requires no further modification. Where

necessary, new 120 volt clock outlets will be provided. The clocks will be stand

alone 120V analog clocks. Clocks will be provided by APS contracted vendor. This

approach should be verified with the owner.

Intercom System

Intercom system consists of Intercom system speakers and call switches in all

classrooms and other locations as required by the owner.

Pu ic A ress System

The requirement for additional public address system components needs to be

verified with APS. Currently, no large common spaces are designed for the new

renovation.

PAGIII. DESIGN CONCEPTS ‐ ELECTRICAL

Page 26: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 26/86

Page 27: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 27/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

.

FIRE PROTECTION, WATER, AND WASTEWATER

According to the COA Water System Maps, there is an internal 8” waterline that

runs from north to south through the site, connecting the waterlines within

Benavides Rd and Camino San Martin. It is assumed that Fire protection,

Domestic and Irrigation water will likely be available from this line.

According to the COA Sewer Systems Maps, there are is an existing 12” sanitary

sewer main line within Snow Vista Blvd and an existing 8” SAS main within

Benavides Rd that may be utilized for the SAS service to the new buildings.

Further survey and as‐built invert information of these existing lines will be

needed to confirm the direction the new development will drain.

Coordination with the Albuquerque Bernalillo Water Authority will be required for

final determination of the water and sanitary sewer layouts. Also, onsite fire

hydrants will be required to insure adequate fire protection coverage of the new

construction.

TRAFFIC

The traffic circulation on site will be reconfigured to address a number of existing

concerns. There will be an additional 40 car parking lot on the west side of school

with a revised cafeteria delivery zone and dumpster enclosures, the existing

parking lot lighting will be improved, and improvements to the existing traffic

,

visitor & faculty parking will be addressed. Also an internal fire department access

way will be provided with the appropriate all weather surface required by the fire

department.

ISSUES AND CONCERNS

,

stairs, could be of greater scope than allocated in the budget. This will need to beaddressed as the project moves forward.

PAGIII. DESIGN CONCEPTS ‐ CIVIL

Page 28: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 28/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 29: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 29/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 30: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 30/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 31: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 31/86

Page 32: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 32/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 33: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 33/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 34: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 34/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 35: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 35/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 36: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 36/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 37: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 37/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 38: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 38/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 39: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 39/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 40: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 40/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 41: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 41/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 42: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 42/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 43: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 43/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 44: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 44/86

Page 45: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 45/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 46: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 46/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 47: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 47/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 48: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 48/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIII. DESIGN CONCEPTS ‐ LEED

Page 49: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 49/86

Page 50: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 50/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGIV. D E S I G N  C R I T E R I A   – SPACE PROGRAM

Page 51: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 51/86

Page 52: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 52/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

IV.  DESIGN CRITERIA

iii. SITE

Plat :  Truman Middle School

c n ty  ap :  ‐ ‐

Site Area : 18.68 +/‐ acres

Zone : R‐D

Height : cannot exceed 45 degree 

angle from property line 

Parking : 1 space per employee

 

iv. INTERNATIONAL BUILDING CODE CRITERIA

 – 

Construction Type : IIB  – sprinklered

PAGIV. D E S I G N  C R I T E R I A

Page 53: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 53/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S   – AS‐101 SITE PLAN

Page 54: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 54/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S   – AS‐102 PHASING PLAN 

Page 55: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 55/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S  – A‐101 RENOVATION FLOOR PLAN

Page 56: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 56/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S  – A‐111 FIRST FLOOR PLAN

Page 57: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 57/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S  – A‐112 SECOND FLOOR PLAN

Page 58: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 58/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S  – A‐113 CLERESTORY LEVEL PLAN

Page 59: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 59/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S  – A‐141 ROOF PLAN

Page 60: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 60/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S  – A‐201 BULIDING ELEVATIONS

Page 61: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 61/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGV. D R A W I N G S  – A‐301 BUILDING SECTIONS

Page 62: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 62/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

VI. COST ESTIMATE

COST ESTIMATE SUMMARY , January 12, 2010

During the development of the following cost estimate, the Design Team has had

. ,

established by APS, was based upon $149 per square foot. Based upon current

market conditions, this price is reasonable. The concern, for which we know APS

understands, is the volatility of the market experienced over the last four years

has proven there are no dependable rules of thumb cost numbers for any single

project. We know the highly competitive nature of the current market has kept

the bid prices below 2003 market values for the last year and this project’s budget

s ase upon t s type o mar et. ow ong t ese pr ces w o s somet ng noone can foresee. That being said, we will continue to watch the market including

bids of similar projects across the state to identify any changes in the current

trends and keep you abreast of this information as the project continues to

develop.

As part of the Building Systems discussion with APS’s M&O Department on

December 1, 2009, the direction was to proceed with a Variable Refrigerant

System for the building’s main heating and cooling system. As Bridgers & Paxton

and Environmental Dynamics Inc. reported during that meeting, this system does

have a higher first cost but significant life cycle cost savings. In assembling this

estimate, we felt the impact of this higher first cost. We have accounted for theincrease in the estimate and will continue to watch the numbers. Please be aware

of this issue as your planning department develops budgets for future projects

under LEED guidelines.

The current overall estimate of probable construction cost, base bid, stands at

$4,896,530.00 which is approximately 2% over the allowable Contract MACC of 

$4,809,556.50. The overall building footprint location, program and organization

have been addressed and resolved as part of our Design Development effort. We

will continue to address the concerns listed above as we move forward with the

Design Development of this project.

PAGVI. E S T I M A T E

Page 63: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 63/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 64: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 64/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 65: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 65/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 66: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 66/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 67: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 67/86

Page 68: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 68/86

Page 69: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 69/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 70: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 70/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 71: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 71/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 72: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 72/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 73: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 73/86

Page 74: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 74/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVI. E S T I M A T E

Page 75: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 75/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 76: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 76/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 77: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 77/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 78: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 78/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 79: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 79/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 80: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 80/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 81: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 81/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 82: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 82/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 83: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 83/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 84: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 84/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S

PAGVII. A P P E N D I X    – MEETING MINUTES : 12‐15‐09

Page 85: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 85/86

Page 86: Truman MS- Design Development Narrative

8/14/2019 Truman MS- Design Development Narrative

http://slidepdf.com/reader/full/truman-ms-design-development-narrative 86/86

DESIGN DEVELOPMENT NARRAT

A  L  B  U  Q   U  E  R  Q   U  E  P  U  B  L  I  C  S  C  H  O  O  L  S