transmission substations - phoenix forums europe 2012 - dnv kema... · transmission substations...

17
Transmission Substations Applying lessons learnt from substation automation in high voltage transmission networks to medium-low voltage distribution networks Peter Vaessen IntelliSub Europe, Frankfurt, October 4 th , 2012

Upload: dokhuong

Post on 23-May-2018

221 views

Category:

Documents


1 download

TRANSCRIPT

Transmission SubstationsApplying lessons learnt from substation automation in high voltage transmission networks to medium-low voltage distribution networks

Peter VaessenIntelliSub Europe, Frankfurt, October 4th, 2012

Questions

What automation (functionalities) should be implemented to support the future smart grid ?

Which substations should be automated ?

How should be automated to support future requirements (e.g. IEC 61850) ?

What are the lessons learnt ?

2

New functionalities for transmission substations

3

430

320120.000

8.000.000100.000.000+

The pyramid challenge is real (example for The Netherlands)

4

Choices have to be made; where and how to measure?

5

Grid operating regimes change

6

Dynamic rating needs reliable sensors and rules PT’s

CT’s

Meters

Indicators

Weather information

and …..

7

Also acting on aging assets is required

Grey wave from the 1970-ties

Less money available

Different component life cycles

Maintenance / Replacement ?

8

Transmission grid functionality transferred

9

load

gene

ratio

n

time

overload

constraint

interruption

nominal capacity

allowable capacity

load/generation

Example: MV ring with overload situation

10

load generation storage

Medium Voltage

Possible solutions

Upgrade / reinforce

Measure (and temporary allow)

Corrective measures

Preventive measures

11

Move grid opening

Install storage system Active demand

Developments New components , e.g. smart transformers, electronic power flow and voltage

support, non conventional instrument transformers, grid connected storage systems

New functions, e.g. DG/RES facilitation, demand response, controlled islanding

Hardware (primary) and Software (secondary) integration

From component to System testing; using the grid as part of the test setup

12

Flexible Power Grid Laboratory capabilities

1 MVA in 4 quadrant operation

3.3 kV 3 phases (up to 24kV)

Overload 1.25 p.u. 10 seconds,

3 p.u 1 second

Frequency from DC to 75 Hz

Harmonic distortion up to 2400 Hz

Available loads 500 kW, 1 MVAr

Stationary and dynamic voltage

1 MVA

2.4 kHz

24 kV

1 MVA

A free programmable “nightmare” grid

13

Testing of intelligent components

Smart substation, now connected to Alliander’s grid

14

PV inverter testing and model verification

15

Lessons learned

Do not forget the hardware (limitations)

De-risk grid deployment (simulation & testing)

Copy existing High Voltage automation concepts

IT can solve it all

16

www.dnvkema.com

www.dnv.com

17