transelectrica - den res-e impact on transmission grid and power system reserves update romanian...
TRANSCRIPT
TRANSELECTRICA - DENTRANSELECTRICA - DENTRANSELECTRICA - DENTRANSELECTRICA - DEN
RES-E Impact on Transmission Grid and Power RES-E Impact on Transmission Grid and Power System ReservesSystem Reserves
RES-E Impact on Transmission Grid and Power RES-E Impact on Transmission Grid and Power System ReservesSystem Reserves
Update Romanian Renewable Market02 apr 2012
Florin BalasiuDirector of Operational Planning Division
1. Benefits and Challenges to Integrate RES1. Benefits and Challenges to Integrate RES
2. Technical Topics Regarding RES Integration2. Technical Topics Regarding RES Integration
Connection schemes. Network development Power system stability topics Shortcircuit withstand Protective schemes Power quality
Connection schemes. Network development Power system stability topics Shortcircuit withstand Protective schemes Power quality
ContentContent
3. Conclusions3. Conclusions
1. Benefits and Challenges to Integrate RES-E1. Benefits and Challenges to Integrate RES-E
New challenges arise from:
Variable nature of the RES
Distributed nature
Different electrical technologies
Larger forecast errors
New challenges arise from:
Variable nature of the RES
Distributed nature
Different electrical technologies
Larger forecast errors
Developing and integration of RES (wind and photovoltaic) contribute to:
Actions to mitigate climate changes
Secure energy requirements
Increase competitiveness and wealth
Developing and integration of RES (wind and photovoltaic) contribute to:
Actions to mitigate climate changes
Secure energy requirements
Increase competitiveness and wealth
0
100
200
300
400
500
600
700
800
900
1000
3/29/20120:00
3/29/20122:24
3/29/20124:48
3/29/20127:12
3/29/20129:36
3/29/201212:00
3/29/201214:24
3/29/201216:48
3/29/201219:12
3/29/201221:36
3/30/20120:00
Eolian [Mw]
Fluctuating Nature of RESFluctuating Nature of RES
Increase 340 MW; 2 h Decrease 390 MW; 1 h
Peak - 926 MW
Contract+Functie Contract+Functie+ATR Zona P instalat [MW] P instalat [MW]
CEE Dobrogea 2700 6500 CEE Moldova 840 2050
RET 400 kV + 220 kV
CEE Banat 0 1400
CEE 5280 8050 Total 110 kV CFE 230 570
CEE 8820 18000 TOTAL SEN CFE 230 570
Distributed Nature of RESDistributed Nature of RES
2. Technical Topics on RES Integration2. Technical Topics on RES Integration
Connection scheme depends on: region, installed capacity, existing lines, active power generation-load balance of the region
Power System Stability – rotor angle, frequency and voltage stability
Frequency stability – balance between total active power generation and load at Romanian power grid level, including load, export and storage
Voltage stability – balance between reactive power generation and absorption capability
Shortcircuit withstand – symmetrical and asymmetrical (SLG) faults
Protective schemes of the generating units and of the network
Power quality – voltage drops, swings, flicker, operational performance indexes
Total investment costs• 4
Connection scheme depends on: region, installed capacity, existing lines, active power generation-load balance of the region
Power System Stability – rotor angle, frequency and voltage stability
Frequency stability – balance between total active power generation and load at Romanian power grid level, including load, export and storage
Voltage stability – balance between reactive power generation and absorption capability
Shortcircuit withstand – symmetrical and asymmetrical (SLG) faults
Protective schemes of the generating units and of the network
Power quality – voltage drops, swings, flicker, operational performance indexes
Total investment costs• 4
Network developmentNetwork development
S/s modernization;
Transmission lines reinforcement vs new lines
increase transmission capacity by use of high temperature conductors
optimal power flow management
New lines: 400 kV Cernavoda-Gura Ialomitei-Stalpu
400 kV Suceava-Gadalin
400 kV Gutinas-Smardan
400 kV Portile de Fier-Resita-(Pancevo)-Timisoara-Arad
Typical 110 kV connection diagrams• 4
S/s modernization;
Transmission lines reinforcement vs new lines
increase transmission capacity by use of high temperature conductors
optimal power flow management
New lines: 400 kV Cernavoda-Gura Ialomitei-Stalpu
400 kV Suceava-Gadalin
400 kV Gutinas-Smardan
400 kV Portile de Fier-Resita-(Pancevo)-Timisoara-Arad
Typical 110 kV connection diagrams• 4
Typical 110 kV Connection Layouts for Renewable Medium Size (1)Typical 110 kV Connection Layouts for Renewable Medium Size (1)
Visible for system operators
Operational security => N-1 fulfilled
Reliable protective system: Dependability Security Critical clearing time
Visible for system operators
Operational security => N-1 fulfilled
Reliable protective system: Dependability Security Critical clearing time
Substation A
Renewable Generating Unit
80 MW
Substation BNew Distribution
Substation
UGL 110 kV
ST=40 MVA
20 kV
ST=40 MVA
20 kV
110 kV
110 kV 110 kV
110 kV
Generation Substation
Visible for system operators
Operational security => N-1 not fulfilledIslanding issues
The protective system: Difficulties to avoid unwanted trips or delayed ones Difficulties to provide remote back-up
thus not recommended
Visible for system operators
Operational security => N-1 not fulfilledIslanding issues
The protective system: Difficulties to avoid unwanted trips or delayed ones Difficulties to provide remote back-up
thus not recommended
Typical 110 kV Connection Layouts for Renewable Medium Size (2)Typical 110 kV Connection Layouts for Renewable Medium Size (2)
Substation A Substation B
OHL 110 kV
ST=40 MVA
20 kV
ST=40 MVA
20 kV
Renewable Generating Unit
80 MW
110 kV
Generation Substation
Power System Stability TopicsPower System Stability Topics
Frequency control – balance between load and generationFrequency control – balance between load and generation
Aim – to maintain the balance between load and generation within a synchronous area
Based on three control actions:
Primary frequency control is a local control to maintain load-generation balance and stabilise frequency after large disturbances
Secondary frequency control – centralised automatic generation control (AGC) to bring back the frequency to its reference value. It restores the interchanges with surrounding power systems
Tertiary frequency control – to restore primary and secondary reserves
Aim – to maintain the balance between load and generation within a synchronous area
Based on three control actions:
Primary frequency control is a local control to maintain load-generation balance and stabilise frequency after large disturbances
Secondary frequency control – centralised automatic generation control (AGC) to bring back the frequency to its reference value. It restores the interchanges with surrounding power systems
Tertiary frequency control – to restore primary and secondary reserves
Secure system operation is only possible by close cooperation between owners of Power Generating Facilities and the Network Operators. In particular, the system behavior in disturbed operating conditions depends upon the response of Power Generating Facilities to deviations from nominal values of voltage and frequency.
Secure system operation is only possible by close cooperation between owners of Power Generating Facilities and the Network Operators. In particular, the system behavior in disturbed operating conditions depends upon the response of Power Generating Facilities to deviations from nominal values of voltage and frequency.
Effects – frequency range of operationEffects – frequency range of operation
0.8
0.85
0.9
0.95
1
1.05
1.1
47 47.5 48 48.5 49 49.5 50 50.5 51 51.5 52
Nelimitat
90 m
in
>90
min
, pot
fi im
puse
de
TSO
90 m
in
180 min
30 min
60 min
U/Un [ur]
f [Hz]
cerinte locale TSO
Effects – active power frequency responseEffects – active power frequency response
Active Power frequency response of Generating Units in Frequency Sensitive ModeActive Power frequency response of Generating Units in Frequency Sensitive Mode
P = the change in MW output from the generatorf = the frequency deviation in the networkPmax = the max capacity to which P is related
P = the change in MW output from the generatorf = the frequency deviation in the networkPmax = the max capacity to which P is related
Effects – tertiary reservesEffects – tertiary reserves
Tertiary frequency control is performed manually in order to restore primary and secondaryreserves.
Tertiary control may be achieved by:
connection of generating units – fast startup, enough generating units
changes in the dispatching of units
changes in the interchanges program
load control – energy storage
Actual limit for RES in the grid – about 3000 MW installed capacity
Tertiary frequency control is performed manually in order to restore primary and secondaryreserves.
Tertiary control may be achieved by:
connection of generating units – fast startup, enough generating units
changes in the dispatching of units
changes in the interchanges program
load control – energy storage
Actual limit for RES in the grid – about 3000 MW installed capacity
Voltage stability – reactive power controlVoltage stability – reactive power control
Voltage stability refers to the ability of the power system to maintain voltages at all busbarswithin the operational ranges during normal operation as well as after being subjected todisturbances in the network.
Sufficient reactive power support is the most important part for voltage control and voltage stability in a transmission and distribution network. As reactive power can not be transported over long distances, the reactive power has to be supplied where required.
Consequently, increasing amount of wind generation reduces reactive power reserves in thetransmission system, which is defined by available reactive power of the synchronousgenerators, SVCs and shunt capacitors minus reactive power consumption in the networkincluding reactive power of the switchable inductors.
Voltage stability refers to the ability of the power system to maintain voltages at all busbarswithin the operational ranges during normal operation as well as after being subjected todisturbances in the network.
Sufficient reactive power support is the most important part for voltage control and voltage stability in a transmission and distribution network. As reactive power can not be transported over long distances, the reactive power has to be supplied where required.
Consequently, increasing amount of wind generation reduces reactive power reserves in thetransmission system, which is defined by available reactive power of the synchronousgenerators, SVCs and shunt capacitors minus reactive power consumption in the networkincluding reactive power of the switchable inductors.
Power System Stability TopicsPower System Stability Topics
Effects – voltage range of operationEffects – voltage range of operation
0.8
0.85
0.9
0.95
1
1.05
1.1
47 47.5 48 48.5 49 49.5 50 50.5 51 51.5 52
Nelimitat
90 m
in
>90
min
, pot
fi im
puse
de
TSO
90 m
in
180 min
30 min
60 min
U/Un [ur]
f [Hz]
cerinte locale TSO
Effects – fault ride through (FRT)Effects – fault ride through (FRT)
Ability of non-conventional generators to stay connected in the case of network faults
It is of particular importance to transmission system operators, that wind farms and photo-voltaic generators stay connected, in case of faults at transmission or distribution levels that lead to a voltage dips in a wide area.It is mandatory for RES to be equipped with FRT-capability
Ability of non-conventional generators to stay connected in the case of network faults
It is of particular importance to transmission system operators, that wind farms and photo-voltaic generators stay connected, in case of faults at transmission or distribution levels that lead to a voltage dips in a wide area.It is mandatory for RES to be equipped with FRT-capability
FRT profile of a RES connected at 110 kV or above voltage levels. Boundaries for a voltage-against-time profile at the Connection Point
FRT profile of a RES connected at 110 kV or above voltage levels. Boundaries for a voltage-against-time profile at the Connection Point
Transient stability – critical fault clearing timeTransient stability – critical fault clearing time
The main aspects having a possible impact on transient stability issues are: RES are usually connected at different locations than conventional power stations. Hence, power flows are considerable different in the presence of a high amount of renewable power and actual power systems are typically not optimized for renewable power transport. This aspect is relevant for Dobrogea area Renewable generating units are usually based on different technologies than conventional synchronous generators and new tools for modeling and calculations are needed
Based on these differences two phenomena can be distinguished, which can be affected by RES generation: Global effects which can result in loss of synchronism of generators:
Transient stability (large-disturbance effect) Local effects
Trip of RES generators after subjected to a disturbance (w/o FLTR)
The main aspects having a possible impact on transient stability issues are: RES are usually connected at different locations than conventional power stations. Hence, power flows are considerable different in the presence of a high amount of renewable power and actual power systems are typically not optimized for renewable power transport. This aspect is relevant for Dobrogea area Renewable generating units are usually based on different technologies than conventional synchronous generators and new tools for modeling and calculations are needed
Based on these differences two phenomena can be distinguished, which can be affected by RES generation: Global effects which can result in loss of synchronism of generators:
Transient stability (large-disturbance effect) Local effects
Trip of RES generators after subjected to a disturbance (w/o FLTR)
Power System Stability TopicsPower System Stability Topics
Transient stability = the ability of the power system to maintain synchronism during and after severe disturbances, for example short circuits or generator trips
The behaviour of the system is highly dependent on the type and duration of disturbance, thus to ensure transient stability in a system often a number of critical contingencies have to be simulated at different locations
For transient stability, the Critical Clearing Time is of utmost importance and represents an useful measure for characterizing the transient stability performance of a given dispatch scenario
To counteract against transient stability problems:Fast protection tripping time + fast CB opening time => teleprotection schemesFast bus-bar faults clearing time => BBP and BFP
Transient stability = the ability of the power system to maintain synchronism during and after severe disturbances, for example short circuits or generator trips
The behaviour of the system is highly dependent on the type and duration of disturbance, thus to ensure transient stability in a system often a number of critical contingencies have to be simulated at different locations
For transient stability, the Critical Clearing Time is of utmost importance and represents an useful measure for characterizing the transient stability performance of a given dispatch scenario
To counteract against transient stability problems:Fast protection tripping time + fast CB opening time => teleprotection schemesFast bus-bar faults clearing time => BBP and BFP
Transient stability – critical fault clearing timeTransient stability – critical fault clearing time
3. Conclusions3. Conclusions
Large scale renewable power integration in the Romanian Power System is
possible by taking plenty technical measures
The installed RES (wind and photovoltaic) integration capability depends
on transmission and distribution lines and S/s development as well as
balancing capabilities and available reserves
Secure system operation is only possible by close cooperation among
owners of Power Generating Facilities, Network Operators and ANRE
Large scale renewable power integration in the Romanian Power System is
possible by taking plenty technical measures
The installed RES (wind and photovoltaic) integration capability depends
on transmission and distribution lines and S/s development as well as
balancing capabilities and available reserves
Secure system operation is only possible by close cooperation among
owners of Power Generating Facilities, Network Operators and ANRE
Thank You !Thank You !Thank You !Thank You !
Florin Balasiu
Update Romanian Renewable Market02 apr 2012