TOPIC 4TOPIC 4
STOPWATCH TIME STUDY
![Page 2: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/2.jpg)
4.1 Equipment and forms
4.2 Time study procedure
OutlineOutline
TOPIC 4 : STOPWATCH TIME STUDY
4.2.1 Preparation4.2.2 Data collection4.2.3 Calculations
![Page 3: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/3.jpg)
Learning Learning OutcomeOutcome
Upon successful completion of this topic, the student will be able to:
Perform:
�� Time study using stopwatchTime study using stopwatch
�� Calculate cycle timeCalculate cycle time
�� AnalyseAnalyse the time studythe time study
![Page 4: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/4.jpg)
TOPIC 4.1 : Equipment and FormsTOPIC 4.1 : Equipment and Forms
![Page 5: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/5.jpg)
Time Study EquipmentsTime Study Equipments
The following equipment is needed for time study:
� Timing device
� Time study observation sheet� Time study observation sheet
� Time study observation board
Other equipments (pencil, eraser, device like tachometer etc.)
![Page 6: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/6.jpg)
Time Study EquipmentsTime Study Equipments
![Page 7: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/7.jpg)
• The stop watch is the most widely used timing device used for time study
• Although electronic timer is also sometimes used
Timing DevicesTiming Devices
sometimes used
• Electronic timer can measure time accurately to the third decimal of a second and can keep a large volume of time data in memory
![Page 8: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/8.jpg)
Cumulative Timing• In this method stop watch runs
continuously through out the study.
• Watch is started at first elements of workcycle to be timed and not stopped until
Timing elementTiming element
cycle to be timed and not stopped untilwhole study is completed
• At the end each element watch reading isrecorded.
• Time for each individual element iscalculated later by successive subtractions.
• This procedure gives the total time duringwhich job done is recorded in the study
![Page 9: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/9.jpg)
Fly back timing• In this method hands of the watch are
return to zero at the end of each elementand are allowed to start immediately fornext elements.
Timing elementTiming element
next elements.
• Time of each element is obtained directly.
• Time on and time off (study stated/ ended)are also mentioned.
• These are called check times anddifference elapsed time
• Sum of all elemental times, ineffective timeand check time is called recorded time.
![Page 10: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/10.jpg)
• It is printed form with spaces providedfor noting down the necessaryinformation about the operation beingstudied:
Time Study Time Study
Observation SheetObservation Sheet
studied:
o Name of operation
o Drawing number
o Name of the worker
o Name of time study person
o Date and place of study
![Page 11: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/11.jpg)
• Spaces are also provided in the form forwriting detailed description of theprocess (element wise):
- Recorded time or stopwatch reading s
Time Study Time Study
Observation SheetObservation Sheet
- Recorded time or stopwatch reading sfor each element of the process
- Performance rating (s) of operator
- Computation
![Page 12: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/12.jpg)
• It is a light weight board used for holdingthe observation sheet and stopwatch inposition
• It is of size slightly larger than that ofobservation sheet
Time Study BoardTime Study Board
observation sheet
• Generally, the watch is mounted nearthe upper right-hand corner of the board
• The board has a clamp to hold theobservation sheet
![Page 13: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/13.jpg)
Time Study BoardTime Study Board
![Page 14: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/14.jpg)
TOPIC 4.2 : Time Study ProcedureTOPIC 4.2 : Time Study Procedure
![Page 15: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/15.jpg)
Time Study ProcedureTime Study Procedure
Step 1 : Define objective of the study.Thisinvolves statement of the use ofthe result, the precision desired,and the required level ofconfidence in the estimated timestandardsstandards
Step 2 : Verify that the standard methodand conditions exist for theoperation and the operation isproperly trained.
If need is felt for method study or furthertraining of operator, the same may becompleted before starting the time study
![Page 16: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/16.jpg)
Time Study ProcedureTime Study Procedure
Step 3 : Select operator to be studied ifthere are more than one operatordoing the same task
Step 4 : Record information about thestandard method, operation,operator, product, equipment,standard method, operation,operator, product, equipment,and conditions on the Time Studyobservation sheet
Step 5 : Divide the operation intoreasonably small elements, andrecord them on the Time Studyobservation sheet
![Page 17: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/17.jpg)
Time Study ProcedureTime Study Procedure
Step 6 : Time the operator for each of theelements. Record the data for afew number of cycles on theTime Study observation sheet.
To estimate the total number ofobservations to be takenTo estimate the total number ofobservations to be taken
Step 7 : Collect and record the data forrequired number of cycles bytiming and rating the operator
![Page 18: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/18.jpg)
Time Study ProcedureTime Study Procedure
Step 8 : Calculated the representativewatch time for each element ofoperation. Multiply it by ratingfactor to get normal time
Normal time = Observed time x Rating factorNormal time = Observed time x Rating factor
Calculate the normal time for the wholeoperation by adding the normal time of itsvarious elements.
![Page 19: Topic 4 - STOPWATCH TIME STUDY.ppt - Motion & … PowerPoint - Topic 4 - STOPWATCH TIME STUDY.ppt [Compatibility Mode] Author azalan Created Date 5/11/2011 9:00:23 AM](https://reader034.vdocuments.us/reader034/viewer/2022050804/5b1fbade7f8b9aca0a8b6579/html5/thumbnails/19.jpg)
Time Study ProcedureTime Study Procedure
Step 9 : Determine allowances for fatigueand various allowances.
Step 10: Determine standard time ofoperation.
Standard time = Normal time X (1+ allowances%)