TOP TERMINAL BATTERY CABINET4/07/15Typical Battery Cabinet Design Issues by Design

UPSBattery CabinetBattery CabinetBattery Cabinet2 MThis height mismatch can cost $1000s inElectricians cost for conduit installation. Hidden costs of installation can be avoided with the proper height equipment. Typical Battery Cabinet Design Issues by Design

UPSBattery CabinetBattery CabinetBattery Cabinet2 MTypically, No individual battery preemptive failure monitoring Full UPS Systems MonitoringExtending battery life by 20% - 35% saves big in recurring battery costsTypical Battery Cabinet Design Issues by Design

UPSBattery CabinetBattery CabinetBattery Cabinet2 MTypical cool down 10 - 12 hours after deep discharge event.Full UPS Cooling SystemsBattery sulfating can be greatly reduced & longevity increased by increasing cool down rates. Typical Battery Cabinet Design Issues by Design

UPSBattery CabinetBattery CabinetBattery Cabinet2 MIntelligent monitoring of Individual batteries with integrated controller which reports to UPS SystemFull UPS Cooling SystemsFully integrated systems ensure UPTIME and reduce system power failures. Evaluating Total Systems Approach

UPS Systems are not Complete Systems as many do not include the battery monitoring.

The Following pages Address an Alternate Systems Design Approach

Other Battery Cabinet Enhancements are also addressed

Cabinet Target Objectives

INDUSTRY FIRSTS

1. First Top Terminal Battery cabinet to meet the 2 Meter requirement to match UPS Heights. NOTE: Many UPS systems are 2 Meters Tall.

2. First tube frame welded battery cabinet with no sharp edges or corners.

3. First battery cabinet to be lifted from top. (Using Load spreaders).

4. CFD engineered cool down of 1.5 hours after major discharge event of 30 minutes or more.

5. First cabinet to use laminated bus bars to simplify tier to tier cabling.

6. First cabinet to use best in class 4/0 ~6,000 strand cables with fusion lugs. Best Flexure, Lowest IR Drop in the industry.

7. Highest repeatable tolerance cabinet in the industry using engineered weldment fixtures.

8. Achieved $2,200 per Cabinet Price Objective in Quantity.

9. Preemptive battery failure monitoring.

10. Cable pass through directly into UPS system with no Conduits. Fastest install times.

11. Breaker access through front door.

12. Passed GR-63 Issue 4 Zone 4 Seismic on the first pass.4/07/15Cabinet at a Glance

32.74578.7TT Cabinet

1,100 lbs - Cabinet

4,500 lbs - Batteries

5,600 lbs - Max WeightTT Battery Range40 Battery String

VRLA 350 A - 540 A

High Line - 550 Vdc192.5 KVA 297 KVA

Low Line - 420 Vdc147 KVA 226.8 KVA4/07/15Cable Pass Through

Cable Pass through.4/07/15Breaker Mfgr

To meet the 2 Meter heightObjective this cabinet is a Siemens Breaker only cabinet. (600A or less).

No breaker handle is required.4/07/15

Optional Fan Assembly

Optional Bolt on Fan Bracket.4/07/15

Top Lift Using Load Spreader Bars

15,000 lb Eyebolts for top lift using load spreader bars.4/07/15Bus Bar

Double Insulated Tier to Tier Bus Bar.

Removes approximately15 ft. of 4/0 cable. 4/07/15Spacers & Shims for Unique Battery Size

4/07/15End Page