Hi,
Please find discussed in morning TBT.
1. HSSENo information
2. QCRaised the question if everybody knows the meaning of what is FPD? Because if you raised a random question to any workers at site regardless of what ICs, 99% cannot answer correctly.Need everybodys help to raise the awareness of FPD to workers for if they dont understand, how can they execute Flawless Project Delivery.
3. Construction- Installation of overhead crane and hand over to operations. Also hydrotesting
work, now we are in peak time.- Cooling Tower finishing level for complete handover to mechanical- Loop check today and rest activity continue- Akimoto announced daily Target test package is 20
4. Precom
-F20000 drying activity and UTOC area flushing and air blow
5. TA update70 days to go before TA-Tagging tie in work 50% completed and need to tag also spading works for 2,000 locations.
6. Morning talk with Procurement Ishitsuka-Inform that last Saturday sent out the Vendor Site Service Form and inform need to include schedule and work scope information.
7. FM messageWe have only 4 weeks before end of August- extra effort for this month, Piping test must finish by end of this month
morning toolbox (4.Aug.2014)
mark as unreadTago Dianon CleofeMon 8/4/2014 8:26 AM
DELETE REPLY REPLY ALL FORWARD
Page 1 of 1morning toolbox (4.Aug.2014)
4/8/2014https://outlook.office365.com/owa/Print to PDF without this message by purchasing novaPDF (http://www.novapdf.com/)