Hi, Please find discussed in morning TBT. 1. HSSE No information 2. QC Raised the question if everybody knows the meaning of what is FPD? Because if you raised a random question to any workers at site regardless of what IC’s, 99% cannot answer correctly. Need everybody’s help to raise the awareness of FPD to workers for if they don’t understand, how can they execute Flawless Project Delivery. 3. Construction - Installation of overhead crane and hand over to operations. Also hydrotesting work, now we are in peak time. - Cooling Tower finishing level for complete handover to mechanical - Loop check today and rest activity continue - Akimoto announced daily Target test package is 20 4. Precom -F20000 drying activity and UTOC area flushing and air blow 5. TA update 70 days to go before TA -Tagging tie in work 50% completed and need to tag also spading works for 2,000 locations. 6. Morning talk with Procurement Ishitsuka -Inform that last Saturday sent out the Vendor Site Service Form and inform need to include schedule and work scope information. 7. FM message “We have only 4 weeks before end of August- extra effort for this month, Piping test must finish by end of this month” morning toolbox (4.Aug.2014) mark as unread Tago Dianon Cleofe Mon 8/4/2014 8:26 AM DELETE REPLY REPLY ALL FORWARD Page 1 of 1 morning toolbox (4.Aug.2014) 4/8/2014 https://outlook.office365.com/owa/ Print to PDF without this message by purchasing novaPDF (http://www.novapdf.com/)

Upload: alouis

Post on 14-Nov-2015

6 views

Category:

Documents


0 download

DESCRIPTION

This is tool box

TRANSCRIPT

  • Hi,

    Please find discussed in morning TBT.

    1. HSSENo information

    2. QCRaised the question if everybody knows the meaning of what is FPD? Because if you raised a random question to any workers at site regardless of what ICs, 99% cannot answer correctly.Need everybodys help to raise the awareness of FPD to workers for if they dont understand, how can they execute Flawless Project Delivery.

    3. Construction- Installation of overhead crane and hand over to operations. Also hydrotesting

    work, now we are in peak time.- Cooling Tower finishing level for complete handover to mechanical- Loop check today and rest activity continue- Akimoto announced daily Target test package is 20

    4. Precom

    -F20000 drying activity and UTOC area flushing and air blow

    5. TA update70 days to go before TA-Tagging tie in work 50% completed and need to tag also spading works for 2,000 locations.

    6. Morning talk with Procurement Ishitsuka-Inform that last Saturday sent out the Vendor Site Service Form and inform need to include schedule and work scope information.

    7. FM messageWe have only 4 weeks before end of August- extra effort for this month, Piping test must finish by end of this month

    morning toolbox (4.Aug.2014)

    mark as unreadTago Dianon CleofeMon 8/4/2014 8:26 AM

    DELETE REPLY REPLY ALL FORWARD

    Page 1 of 1morning toolbox (4.Aug.2014)