tom wakeman design portfolio

147
TOM WAKEMAN BSc/MArch Selection of Works

Upload: tom-wakeman

Post on 08-Apr-2016

219 views

Category:

Documents


0 download

DESCRIPTION

Collection of Works

TRANSCRIPT

  • T O M WA K E M A N

    B S c / M A r c h

    S elec t ion of Works

  • About me

    I am trained in the field of Architecture and design, currently holding a BSc in Architecture, and completing my MArch at Cardiff University

    My most recent experience includes working with an award-winning Architectural firm, Vicente Burin Architects, in Fairfield Connecticut, USA as a design intern

    Previously, I have worked with a prestigious property development firm, Portfolio Homes as a design coordinator, as well as getting my hands dirty at a local construction firm, both based in my hometown of Sevenoaks, Kent, UK

    Particular interests and research areas include: Architecture and interior design, graphics & media, lifestyle & photography and industrial design

    I love working on screen as much as I love working with my hands, for me, my biggest joy in life is getting to work, picking up tools and getting stuck in with a project

  • A g l imse in to my work in A rch i tec tu re

    and Des ign , and some of the peop le

    and p laces tha t have in sp i red me

    an

    SELECTION OF WORKS

  • HIGHL IGHTS FROM WSA BSc & MArch

    PROGRAMME EXHIB IT IONS

    CURATED

  • THOMAS WAKEMANCARDIFF MULTIFAITH RETREAT CENTER

    Design and Access Statement

    Proposal: On-Campus retreat centre: a multi-use space to accommodate for gatherings, pastoral care, multifaith activities, contemplation and reading. The centre it so sit alongside other university accommodation, providing an unparalleled environment with out-of-hours access to cater for the needs of a multinational and multifaith student and staff community, as well as providing connections with the greater Cardiff community. The building must accommodate for a range of different activities which will vary in scale and profile, from large gathering space for religious ceremony, performances and open-day events to individual cellular spaces for private prayer and reflection, also communal facilities spaces for receptions, classes such as yoga and meditation and refreshments. The building will therefore need to be highly versatile and able to adapt to the inherent range of environmental, practical and social requirements that come with the different activities occurring in these spaces. With a revised budget of 3 Million and a total permitted floor plan of 1000m2, the project provides scope for a design of substantial quality.

    (A) Main Gated Entrance

    Site Entrance through arched gateway

    Site Proposal: Key Spaces and Aerial InformationColonnade of arches: to become internal coffee house boothsMain Entrance archway with french doors access to addition above

    Established tree periphery

    31382

    26910

    3189

    2190

    8830

    9234

    9400

    25840

    13829

    34031

    51770

    3761

    North

    Aberdare Hall

    School of Music

    Floor 0 Music Library& dorms

    library and dormentrance

    Commercial KitchensBasement accessand oil tank

    Queen AnneSquare Corbett Road

    Column Terrace

    Parking Lot

    Parking lot andturning

    entrance

    entrance

    formal entrance

    Girls Dorm entrance

    Substation

    Construction traffic

    vehicular access

    ramp to parkinglot

    footpath

    lawns

    footpath

    offices

    patio

    archway

    arched connecting'bridge'

    Residential homes and yards

    garages

    3307

    8370

    boundary wall

    boundarywall

    implied facadeboundary

    demolished60's block

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRODUCED

    BY AN

    AUTOD

    ESK STUDEN

    T PRO

    DUCTPRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRO

    DUC

    ED B

    Y AN

    AUT

    OD

    ESK

    STUD

    ENT

    PRO

    DUC

    T

    Existing Site Conditions, Access and Development Phases

    Norwich Cathedral Refectory, Hopkins Architects

    Birch ply used as interior wall material: individual prayer roomsRead-Nest, Dorte Mandrup Arkitekte

    Zen-inspired couryard rock garden enclosed by inward-facing glazingWater Cherry House, Kengo Kuma Architects

    Entrance: superhuman quality: spine stone wall, matching foundation, full height doorsWhitelee Windfarm, Hypostyle Architects & House Roces, Govaert & Vanhoutte

    Simple, exposed rafters & steel columns: connecting walkwayViking Long House, Ireland, Jane D Burnside Architects

    Raw, understated quality: natural materials, polished concrete: meditation & worshipWerkhaus, tka - Thomas Krger

    Upper floor exposed wood rafters and light quality: intimate space for worshipMilitary building, Bureau SLA

    0 Ground Floor & Landscaping Level 1:100 829,207 13%545,877 25%788,470 20%1,000000 37%Total

    Electric light and power. Alarms.95,000

    Electrics. Lift. Alarms, data cables, audio/visual195,447

    Electrics, Lift. Alarms, CCTV, PA, data cables, BMS, emergency lights132,970

    150,000Electrical, lifts, e.t.c.

    unknown: special acoustic considerations

    8% (124,456)unknown10% (56,000): costing provides for standard framed, drylined partitions. Contingency may include extra acoustic insulation considerations for areas requiring special sound proofing

    Internal walls (acoustic considerations included)

    Red cedar dado walls with block above; cedar boarding, Glasroc with render and Kalwall curtain walling. Curved and flat Glulam roof with metal cladding; flat concrete with sedum. Aluminium windows and doors, medium sustainability credentials359,707

    Facing brick, render, curtain walling. Plastic clad timber pitched roof; glazing. Double glazed aluminium windows, poor sustainability credentials223,860

    Black standing seam metal cladding, low surface area (sandwiched between existing buildings). Low maintenance, medium sustainability credentials~157,500

    Cheap, economical cladding material: high environmental performance, low maintenance costs, large surface area cladding (no direct sunlight), high performance glazing, frameless doors/windows, sedum and glazed roof on timber/steel frame, high sustainability credentials250,000

    Cladding (performance/sustainable credentials)

    Paving, timber deck, brick retaining wall, timber fencing, landscaping, services, drainage and alterations to existing 285,000

    Extensive hard landscaping: paving, retaining walls, metal railings, services, drainage, site lighting, cycle shelter, demolition of existing buildings 148,000

    Extensive excavation/site works, minimal landscaping (some hard landscaping)299,000

    Extensive soft landscaping, paving, decking/walkways, car park levelling/reinstatement, wall demolition and bike storage/lighting, demolition of existing building and asbestos removal (demolition material reused on site for carparklevelling400,000

    Groundworks/landscaping/ecology

    Gas heating, 89,500Underfloor Heating, gas boiler secondary ventilation, 126,570

    Heat Pump, Gas DHW boiler, Radiant Underfloor Heat, secondary ventilation, 199,000

    Heat Pump, Thermal store, MVHR, ducted delivery200,000

    HVAC system

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    Build cost estimation: Multifaith Centre Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    829,207 13%545,877 25%788,470 20%1,000000 37%Total

    Electric light and power. Alarms.95,000

    Electrics. Lift. Alarms, data cables, audio/visual195,447

    Electrics, Lift. Alarms, CCTV, PA, data cables, BMS, emergency lights132,970

    150,000Electrical, lifts, e.t.c.

    unknown: special acoustic considerations

    8% (124,456)unknown10% (56,000): costing provides for standard framed, drylined partitions. Contingency may include extra acoustic insulation considerations for areas requiring special sound proofing

    Internal walls (acoustic considerations included)

    Red cedar dado walls with block above; cedar boarding, Glasroc with render and Kalwall curtain walling. Curved and flat Glulam roof with metal cladding; flat concrete with sedum. Aluminium windows and doors, medium sustainability credentials359,707

    Facing brick, render, curtain walling. Plastic clad timber pitched roof; glazing. Double glazed aluminium windows, poor sustainability credentials223,860

    Black standing seam metal cladding, low surface area (sandwiched between existing buildings). Low maintenance, medium sustainability credentials~157,500

    Cheap, economical cladding material: high environmental performance, low maintenance costs, large surface area cladding (no direct sunlight), high performance glazing, frameless doors/windows, sedum and glazed roof on timber/steel frame, high sustainability credentials250,000

    Cladding (performance/sustainable credentials)

    Paving, timber deck, brick retaining wall, timber fencing, landscaping, services, drainage and alterations to existing 285,000

    Extensive hard landscaping: paving, retaining walls, metal railings, services, drainage, site lighting, cycle shelter, demolition of existing buildings 148,000

    Extensive excavation/site works, minimal landscaping (some hard landscaping)299,000

    Extensive soft landscaping, paving, decking/walkways, car park levelling/reinstatement, wall demolition and bike storage/lighting, demolition of existing building and asbestos removal (demolition material reused on site for carparklevelling400,000

    Groundworks/landscaping/ecology

    Gas heating, 89,500Underfloor Heating, gas boiler secondary ventilation, 126,570

    Heat Pump, Gas DHW boiler, Radiant Underfloor Heat, secondary ventilation, 199,000

    Heat Pump, Thermal store, MVHR, ducted delivery200,000

    HVAC system

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    Build cost estimation: Multifaith Centre Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    Environmental and Services Cost Breakdown: Precedent Estimates

    829,207 13%545,877 25%788,470 20%1,000000 37%Total

    Electric light and power. Alarms.95,000

    Electrics. Lift. Alarms, data cables, audio/visual195,447

    Electrics, Lift. Alarms, CCTV, PA, data cables, BMS, emergency lights132,970

    150,000Electrical, lifts, e.t.c.

    unknown: special acoustic considerations

    8% (124,456)unknown10% (56,000): costing provides for standard framed, drylined partitions. Contingency may include extra acoustic insulation considerations for areas requiring special sound proofing

    Internal walls (acoustic considerations included)

    Red cedar dado walls with block above; cedar boarding, Glasroc with render and Kalwall curtain walling. Curved and flat Glulam roof with metal cladding; flat concrete with sedum. Aluminium windows and doors, medium sustainability credentials359,707

    Facing brick, render, curtain walling. Plastic clad timber pitched roof; glazing. Double glazed aluminium windows, poor sustainability credentials223,860

    Black standing seam metal cladding, low surface area (sandwiched between existing buildings). Low maintenance, medium sustainability credentials~157,500

    Cheap, economical cladding material: high environmental performance, low maintenance costs, large surface area cladding (no direct sunlight), high performance glazing, frameless doors/windows, sedum and glazed roof on timber/steel frame, high sustainability credentials250,000

    Cladding (performance/sustainable credentials)

    Paving, timber deck, brick retaining wall, timber fencing, landscaping, services, drainage and alterations to existing 285,000

    Extensive hard landscaping: paving, retaining walls, metal railings, services, drainage, site lighting, cycle shelter, demolition of existing buildings 148,000

    Extensive excavation/site works, minimal landscaping (some hard landscaping)299,000

    Extensive soft landscaping, paving, decking/walkways, car park levelling/reinstatement, wall demolition and bike storage/lighting, demolition of existing building and asbestos removal (demolition material reused on site for carparklevelling400,000

    Groundworks/landscaping/ecology

    Gas heating, 89,500Underfloor Heating, gas boiler secondary ventilation, 126,570

    Heat Pump, Gas DHW boiler, Radiant Underfloor Heat, secondary ventilation, 199,000

    Heat Pump, Thermal store, MVHR, ducted delivery200,000

    HVAC system

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    Build cost estimation: Multifaith Centre Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    829,207 13%545,877 25%788,470 20%1,000000 37%Total

    Electric light and power. Alarms.95,000

    Electrics. Lift. Alarms, data cables, audio/visual195,447

    Electrics, Lift. Alarms, CCTV, PA, data cables, BMS, emergency lights132,970

    150,000Electrical, lifts, e.t.c.

    unknown: special acoustic considerations

    8% (124,456)unknown10% (56,000): costing provides for standard framed, drylined partitions. Contingency may include extra acoustic insulation considerations for areas requiring special sound proofing

    Internal walls (acoustic considerations included)

    Red cedar dado walls with block above; cedar boarding, Glasroc with render and Kalwall curtain walling. Curved and flat Glulam roof with metal cladding; flat concrete with sedum. Aluminium windows and doors, medium sustainability credentials359,707

    Facing brick, render, curtain walling. Plastic clad timber pitched roof; glazing. Double glazed aluminium windows, poor sustainability credentials223,860

    Black standing seam metal cladding, low surface area (sandwiched between existing buildings). Low maintenance, medium sustainability credentials~157,500

    Cheap, economical cladding material: high environmental performance, low maintenance costs, large surface area cladding (no direct sunlight), high performance glazing, frameless doors/windows, sedum and glazed roof on timber/steel frame, high sustainability credentials250,000

    Cladding (performance/sustainable credentials)

    Paving, timber deck, brick retaining wall, timber fencing, landscaping, services, drainage and alterations to existing 285,000

    Extensive hard landscaping: paving, retaining walls, metal railings, services, drainage, site lighting, cycle shelter, demolition of existing buildings 148,000

    Extensive excavation/site works, minimal landscaping (some hard landscaping)299,000

    Extensive soft landscaping, paving, decking/walkways, car park levelling/reinstatement, wall demolition and bike storage/lighting, demolition of existing building and asbestos removal (demolition material reused on site for carparklevelling400,000

    Groundworks/landscaping/ecology

    Gas heating, 89,500Underfloor Heating, gas boiler secondary ventilation, 126,570

    Heat Pump, Gas DHW boiler, Radiant Underfloor Heat, secondary ventilation, 199,000

    Heat Pump, Thermal store, MVHR, ducted delivery200,000

    HVAC system

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    Build cost estimation: Multifaith Centre Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    Environmental and Services Cost Breakdown: Precedent Estimates

    Preliminary Cost EstimateREVISED Cost Estimate

    Services, mechanical & sustainable products (including frame & external walls) reflected as 50% total build cost

    1000m2

    Heat pump, Thermal store, MVHR, associated 280,000Soft landscaping, sunken garden, as-sociated trees and planting, decking/patio, bike storage, existing demoli-tion/levelling, asbestos removal(major site works & basement excavation included in substructure estimates)350,000

    Sustainable products and systems:Cedar shingle cladding & roof; 34kW PV array; low-grade UK spruce box frame with SIP system, high perfor-mance frameless doors/curtain wall glazing, small % southern exposure to upper storeys, minimising solar gain, high sustainability & high returns600,000

    Simple drylined/birch ply-faced partitions, with extra for acoustic treatment. Birch-faced SIP panels to form interior surface of external walls54000Electrical, mech, lifts, data, CCTV, alarms, BMS, audio, access, theatre435,000

    1,800000 55%

    Total 3,300000 (for review)

    16721,704,4611960168794520911568445Tender Price Update

    100%~28002,758,750100%1,4801,508,373100%1,8061,555,710

    100%2,014 1,511,026 Total Contract sum

    --3%48 49,750 0 0 0 0 9 Design Fees

    100%27582,758,75097%1,431 1,458,623100%1,806 1,555,710

    100%2,014 1,511,026 Total (less Design Fees)

    9%250250,0000 0 4%64 55,475 7%150 112,933 8 Contingencies

    10%280280,00017%248 253,378 8%150 129,390 10%210 157,917 7 Preliminaries

    20%550550,00019%279 285,051 10%172 148,872 20%398 299,066 6 External Works

    20%530530,00013%195 199,332 25%452 389,345 20%399 299,793 5 Services

    2%3030,0001%0 0 2%27 23,723 1%20 15,341 4 Fittings and Furnishings

    5%150150,5006%94 96,102 7%124 106,769 6%113 84,888 3 Finishes

    30%850850,00035%518 528,517 39%699 602,335 31%631 473,283 2 Superstructure

    4%120120,2506%94 96,243 6%115 99,801 4%90 67,805 1 Substructure

    %Costper m2

    Total cost%Costper m2

    Total cost%Costper m2

    Total cost%Costper m2

    Total cost

    Sketch Design Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    16721,704,4611960168794520911568445Tender Price Update

    100%~28002,758,750100%1,4801,508,373100%1,8061,555,710

    100%2,014 1,511,026 Total Contract sum

    --3%48 49,750 0 0 0 0 9 Design Fees

    100%27582,758,75097%1,431 1,458,623100%1,806 1,555,710

    100%2,014 1,511,026 Total (less Design Fees)

    9%250250,0000 0 4%64 55,475 7%150 112,933 8 Contingencies

    10%280280,00017%248 253,378 8%150 129,390 10%210 157,917 7 Preliminaries

    20%550550,00019%279 285,051 10%172 148,872 20%398 299,066 6 External Works

    20%530530,00013%195 199,332 25%452 389,345 20%399 299,793 5 Services

    2%3030,0001%0 0 2%27 23,723 1%20 15,341 4 Fittings and Furnishings

    5%150150,5006%94 96,102 7%124 106,769 6%113 84,888 3 Finishes

    30%850850,00035%518 528,517 39%699 602,335 31%631 473,283 2 Superstructure

    4%120120,2506%94 96,243 6%115 99,801 4%90 67,805 1 Substructure

    %Costper m2

    Total cost%Costper m2

    Total cost%Costper m2

    Total cost%Costper m2

    Total cost

    Sketch Design Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    REVISED PROPOSAL

    1000m2

    Total: 3,300000

    Total cost Cost/m2 %

    513,900 513 16%

    672,455 670 21%

    325,136 325 10%

    201,990 202 6%

    775,350 775 23%

    350,000 350 11%

    406,000 406 13%

    3,300,000 3300 100%

    3,300,000 3300 100%

    Greyfriars Community Centre

    Henley College

    St Andrews

    Proposal

    For many international students, students with special needs or disability and students from diverse religious backgrounds, starting university, sometimes in a new country is an exciting and enlightening opportunity, but it can also be an overwhelming and perplexing experience to those unfamiliar with the cultural and environmental ramifications of the new place they are living. The centre must provide an impartial environment, a sanctuary within which people can temporarily escape the academic environment as well as the general busy, hectic stresses of modern life in a UK city. the building should create a sense of removal from the immediate environment, allowing people to become acutely unaware of the strong cultural qualities that typically define a place, religious reference or sense of hierarchy. These qualities can often be prohibitive or structured to accommodate some more than others. The intention is of a level playing field whereby our attention is taken from the everyday career-driven, money-oriented and materialistic. The building should be the embodiment of the simple, physical, exis-tential and spiritual needs common to everybodys well-being. With a strong focus on the physical environment: the elements, light, sky, weather, ecology, earth and water, the building will provide a suggestive space where individuals can feel united by common ground and free to express themselves without feeling alienated as a minority. To reflect this concept, the interior of the building must portray a vision of simplicity and functional form, removed from unnecessary excess, reckless design statement pieces or visual complexity. A refined material palette must provide simple solutions, driven by functional components, the range of durability required, the desired longevity and the environmental quality to be achieved. As such, the built form must be economically justified in the sense of lifespan, truth to materials and en-vironmental credentials. From an original budget of 1 million to a revised 3 million, the extra funding does not aim to provide scope for a more lavish architectural response, but instead caters for additional complementing use types previously unidentified by the university. These in themselves invest higher capital costs, but provide much greater value for money within the annual running of the building. As well as this, it will fund a strong emphasis on integration with the outside environment beyond basic landscaping, providing well-designed, garden spaces that can be enjoyed and utilised throughout the seasons. Substantial additional expenses identified during the analysis stage in relation to site preparation, access and mechanical requirements, as well as works to adjoining buildings, parking, services e.t.c. to facilitate the new accommodation have also been considered in the application for a revised budget.

    Site Selection and Design Philosophy

    Site B is the preferred choice for construction of the new building. Located in a courtyard between the School of Music and Aberdare Hall, comprising two historic red brick buildings completed in 1893, and connected by an arched walkway, forming the primary entrance to the site. Included within the Cathays Conservation Area, the proposal is to demolish the 60s accommodation block to the south west, opening up a prime plot, bordering the boundary of Queen Anne Square. The site is chosen for a number of reasons. Firstly, the nature of the building suggests a need for quiet and contemplation and a strong connection with the outside environment. This site naturally meets these requirements providing the ideal setting, set back from the main road, with very few outside sources of disruption. The site is particularly inward-facing, with strong boundaries. For many projects, especially those with a commercial focus, this would propose a significant challenge, but is fundamentally well suited to the secluded and understated nature of a retreat centre. Borrowing from the original concept stage, the design philosophy is to utilise lightweight construction methods, highly appropriate for intermittent use, low thermal mass and air-delivered heating and environmental control. Sitting in strong contrast with the surrounding heavyweight brick buildings, this is not only a practical and budgetary incentive, but fundamentally appropriate to the feel of the space. Unlike traditional places of worship, often iconic buildings of solidity and permanent internal layouts that feel as though they will remain unchanged for many generations, this building should instead be a testament to a changing, multinational and multifaith society. The building should be a reflection of change and progression, to feel very much of its time, designed not as a monument, but as a space that can facilitate change, adapting during its lifetime, and designed with a strong consideration for user interaction and the materials and finishes important to that user.

    The design philosophy is heavily influenced by the Zen style of design, adapted as a Japanese concept promoting the importance of the meditative state and contemplation over ritual or study of scriptures. Although the building must be designed to accommodate ritual worship and individual expression, the idea that this is a place where everybody is able to contemplate and reflect under the same roof whilst going about their daily activities acts to unite many different cultures with a common ground. Traditional Zen style buildings, although striking and beautiful, are fundamentally very simple, very lightweight, often timber and surrounded by screens with a strong connection with the outside elements. The buildings sit, poised over a firmly grounded foundation stone, which often extends into the immediate landscape as rocks, boulders and pebbles designed to represent the hills and geology of the greater landscape. Wild mosses, ferns and grasses weave between these heavy ground elements, often with a focus on a pool or steam, representing the impermanence, fragility and constantly changing nature of the environment we inhabit. As opposed to hard landscaping, manicured lawns and formal planting, the landscape must be unkempt, rough and able to naturally evolve with minimal maintenance. The main structural elements of the building should be driven by necessity and function, with simple connections and structural solutions used in favour of the complex or highly engineered. The majority of the structure will utilise efficient timber framing comprised of small sections, with steel elements where required. Components such as walls will be constructed from cheap and readily available materials, and doubling as storage and acoustic partition. Elements such as floor finishes, doors and glazing, furniture and the special components that must resist heavy user interaction, and those important to the activities taking place can be more hard-wearing and higher spec. For example, envelope walls and ceilings can be simple plasterboarded finishes, structural elements left as they come, with minimal use of decora-tion or ornament. Shadow gaps should be used around frames and special components, with clear boundaries between the small number of different materials. Floor finishes may be of polished concrete or polished timber, according to traffic or activity with glazing creating an unobscured interaction with the outside: floor to ceiling in communal spaces, and focused or carefully orientated in private or secular spaces. Lighting is of great importance, and the overall scheme should use both natural and artificial light with equal importance, with the building potentially used to a high extent out of hours. Lighting should be subtle and not overbearing, but the overall effect creating a strong sense of drama. For example, it may not be necessary to evenly light the entire space, but rather highlight particular areas, with strong use of shadow and low light to the peripheries. To separate the different parts and uses of the building, so they are visually connected, but at the same time private and acoustically isolated, internal rooms may become sculptural elements in themselves, incorporating religious objects and artefacts where needed, with rooms appearing as pieces of sculpted furniture. This creates a feeling of domesticity within such a large building envelope without being too literal. This also takes the impetus away from the items and furnishings placed within the room, promoting a space that feels greater than the sum of its parts. Exterior courtyards placed internally in plan, with lightwell gardens which separate indoor rooms by outside space will create excellent acoustic separation, whilst visually uniting different parts of the building and bringing large volumes of natural light to the interior plan. Site Considerations: Programme Constraints and Opportunities, Access, Logistics and Part L:

    Placing the building on this site opens up great potential for the school of music to coexist with additional performance space and refreshment/restaurant facilities, ensuring year-round occupation and a strong source of revenue outside of passers by and minority groups. This coincides with the universitys long term development strategy for expanding the campus and better integrating its peripheries. Economically, the approach to balancing materials between those that are purely practical and structural, and those integral to user interaction dictates where the budget will be concentrated most heavily. Frame, cladding and structural elements must be use cheap, readily available and sustainable materials in a practical and low-maintenance way, in small enough sections for access to the confined site, but prefabricated wherever possible to minimise waste and construction time. Softwood should be chosen over hardwood, therefore timber elements should not be exposed to the exterior, with steel elements used where connecting timbers. The interior design may therefore want to dominate the users attention away from the structure itself, only revealing glimpses of the building in carefully chosen areas. On the exterior, a durable, sustainable cladding material should be chosen, potentially incorporating or future-proofing for energy generating systems. As the site has restricted access with a narrow archway which will form the primary access route for the final building as well as day-to-day construction access, an additional access point will be made through the wall connecting the rear access road for infrequent and bulk deliveries of materials. Negotiations will need to be made with the council, the telephone distribution board relocated and upgraded, and hoarding erected. Following asbestos removal, demolition and excavation materials from the 60s structure will be used to grade the adjacent music school car park, creating a temporary site holding area and office. No access is to be made through Queen Anne Square, and justification may be made to creating a minimal frontage to Queen Anne square, which would otherwise be competing with the Georgian style detached houses and generate undesired disruption to the local residents. The building should instead front, with main glazing into the interior courtyard. The existing arches and red brick buildings offer huge potential for glazed connecting structures, possibly for com-munal circulation and cafe/retail space, which will require considerable attention to detail and sympathy to the listed building fabrics. Strong consideration needs to be placed on service access and storage space in the basement, where space is at a premium, and the additional mechanical and acoustic requirements for performance-use considered from the outset and designed in to the building. The nature of the construction dictates that BREEAM very good/excellent status can be aimed for, with an impetus on sustainable materials, local ecology and low heating costs. This will be achieved using air-delivery heat generated from a heat pump system using borehole loops on the confined site, with simple, user-friendly and zoned controls designed to work around inhabited periods. On completion, it is essential that an ongoing management and monitoring process is maintained to ensure long-term efficient operation and that the building is performing for its users in a positive and beneficial way.

    Aerial view of site Early Sketch Scheme Proposals Budgetary Proposal Elemental Breakdown (refer to detailed itemised breakdown)

    Main proposal cross section, showing all main spaces (facing South-East toward Aberdare Hall)

  • THOMAS WAKEMANCARDIFF MULTIFAITH RETREAT CENTER

    Design and Access Statement

    Proposal: On-Campus retreat centre: a multi-use space to accommodate for gatherings, pastoral care, multifaith activities, contemplation and reading. The centre it so sit alongside other university accommodation, providing an unparalleled environment with out-of-hours access to cater for the needs of a multinational and multifaith student and staff community, as well as providing connections with the greater Cardiff community. The building must accommodate for a range of different activities which will vary in scale and profile, from large gathering space for religious ceremony, performances and open-day events to individual cellular spaces for private prayer and reflection, also communal facilities spaces for receptions, classes such as yoga and meditation and refreshments. The building will therefore need to be highly versatile and able to adapt to the inherent range of environmental, practical and social requirements that come with the different activities occurring in these spaces. With a revised budget of 3 Million and a total permitted floor plan of 1000m2, the project provides scope for a design of substantial quality.

    (A) Main Gated Entrance

    Site Entrance through arched gateway

    Site Proposal: Key Spaces and Aerial InformationColonnade of arches: to become internal coffee house boothsMain Entrance archway with french doors access to addition above

    Established tree periphery

    31382

    26910

    3189

    2190

    8830

    9234

    9400

    25840

    13829

    34031

    51770

    3761

    North

    Aberdare Hall

    School of Music

    Floor 0 Music Library& dorms

    library and dormentrance

    Commercial KitchensBasement accessand oil tank

    Queen AnneSquare Corbett Road

    Column Terrace

    Parking Lot

    Parking lot andturning

    entrance

    entrance

    formal entrance

    Girls Dorm entrance

    Substation

    Construction traffic

    vehicular access

    ramp to parkinglot

    footpath

    lawns

    footpath

    offices

    patio

    archway

    arched connecting'bridge'

    Residential homes and yards

    garages

    3307

    8370

    boundary wall

    boundarywall

    implied facadeboundary

    demolished60's block

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRODUCED

    BY AN

    AUTOD

    ESK STUDEN

    T PRO

    DUCT

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRO

    DUC

    ED B

    Y AN

    AUT

    OD

    ESK

    STUD

    ENT

    PRO

    DUC

    T

    Existing Site Conditions, Access and Development Phases

    Norwich Cathedral Refectory, Hopkins Architects

    Birch ply used as interior wall material: individual prayer roomsRead-Nest, Dorte Mandrup Arkitekte

    Zen-inspired couryard rock garden enclosed by inward-facing glazingWater Cherry House, Kengo Kuma Architects

    Entrance: superhuman quality: spine stone wall, matching foundation, full height doorsWhitelee Windfarm, Hypostyle Architects & House Roces, Govaert & Vanhoutte

    Simple, exposed rafters & steel columns: connecting walkwayViking Long House, Ireland, Jane D Burnside Architects

    Raw, understated quality: natural materials, polished concrete: meditation & worshipWerkhaus, tka - Thomas Krger

    Upper floor exposed wood rafters and light quality: intimate space for worshipMilitary building, Bureau SLA

    0 Ground Floor & Landscaping Level 1:100 829,207 13%545,877 25%788,470 20%1,000000 37%Total

    Electric light and power. Alarms.95,000

    Electrics. Lift. Alarms, data cables, audio/visual195,447

    Electrics, Lift. Alarms, CCTV, PA, data cables, BMS, emergency lights132,970

    150,000Electrical, lifts, e.t.c.

    unknown: special acoustic considerations

    8% (124,456)unknown10% (56,000): costing provides for standard framed, drylined partitions. Contingency may include extra acoustic insulation considerations for areas requiring special sound proofing

    Internal walls (acoustic considerations included)

    Red cedar dado walls with block above; cedar boarding, Glasroc with render and Kalwall curtain walling. Curved and flat Glulam roof with metal cladding; flat concrete with sedum. Aluminium windows and doors, medium sustainability credentials359,707

    Facing brick, render, curtain walling. Plastic clad timber pitched roof; glazing. Double glazed aluminium windows, poor sustainability credentials223,860

    Black standing seam metal cladding, low surface area (sandwiched between existing buildings). Low maintenance, medium sustainability credentials~157,500

    Cheap, economical cladding material: high environmental performance, low maintenance costs, large surface area cladding (no direct sunlight), high performance glazing, frameless doors/windows, sedum and glazed roof on timber/steel frame, high sustainability credentials250,000

    Cladding (performance/sustainable credentials)

    Paving, timber deck, brick retaining wall, timber fencing, landscaping, services, drainage and alterations to existing 285,000

    Extensive hard landscaping: paving, retaining walls, metal railings, services, drainage, site lighting, cycle shelter, demolition of existing buildings 148,000

    Extensive excavation/site works, minimal landscaping (some hard landscaping)299,000

    Extensive soft landscaping, paving, decking/walkways, car park levelling/reinstatement, wall demolition and bike storage/lighting, demolition of existing building and asbestos removal (demolition material reused on site for carparklevelling400,000

    Groundworks/landscaping/ecology

    Gas heating, 89,500Underfloor Heating, gas boiler secondary ventilation, 126,570

    Heat Pump, Gas DHW boiler, Radiant Underfloor Heat, secondary ventilation, 199,000

    Heat Pump, Thermal store, MVHR, ducted delivery200,000

    HVAC system

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    Build cost estimation: Multifaith Centre Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    829,207 13%545,877 25%788,470 20%1,000000 37%Total

    Electric light and power. Alarms.95,000

    Electrics. Lift. Alarms, data cables, audio/visual195,447

    Electrics, Lift. Alarms, CCTV, PA, data cables, BMS, emergency lights132,970

    150,000Electrical, lifts, e.t.c.

    unknown: special acoustic considerations

    8% (124,456)unknown10% (56,000): costing provides for standard framed, drylined partitions. Contingency may include extra acoustic insulation considerations for areas requiring special sound proofing

    Internal walls (acoustic considerations included)

    Red cedar dado walls with block above; cedar boarding, Glasroc with render and Kalwall curtain walling. Curved and flat Glulam roof with metal cladding; flat concrete with sedum. Aluminium windows and doors, medium sustainability credentials359,707

    Facing brick, render, curtain walling. Plastic clad timber pitched roof; glazing. Double glazed aluminium windows, poor sustainability credentials223,860

    Black standing seam metal cladding, low surface area (sandwiched between existing buildings). Low maintenance, medium sustainability credentials~157,500

    Cheap, economical cladding material: high environmental performance, low maintenance costs, large surface area cladding (no direct sunlight), high performance glazing, frameless doors/windows, sedum and glazed roof on timber/steel frame, high sustainability credentials250,000

    Cladding (performance/sustainable credentials)

    Paving, timber deck, brick retaining wall, timber fencing, landscaping, services, drainage and alterations to existing 285,000

    Extensive hard landscaping: paving, retaining walls, metal railings, services, drainage, site lighting, cycle shelter, demolition of existing buildings 148,000

    Extensive excavation/site works, minimal landscaping (some hard landscaping)299,000

    Extensive soft landscaping, paving, decking/walkways, car park levelling/reinstatement, wall demolition and bike storage/lighting, demolition of existing building and asbestos removal (demolition material reused on site for carparklevelling400,000

    Groundworks/landscaping/ecology

    Gas heating, 89,500Underfloor Heating, gas boiler secondary ventilation, 126,570

    Heat Pump, Gas DHW boiler, Radiant Underfloor Heat, secondary ventilation, 199,000

    Heat Pump, Thermal store, MVHR, ducted delivery200,000

    HVAC system

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    Build cost estimation: Multifaith Centre Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    Environmental and Services Cost Breakdown: Precedent Estimates

    829,207 13%545,877 25%788,470 20%1,000000 37%Total

    Electric light and power. Alarms.95,000

    Electrics. Lift. Alarms, data cables, audio/visual195,447

    Electrics, Lift. Alarms, CCTV, PA, data cables, BMS, emergency lights132,970

    150,000Electrical, lifts, e.t.c.

    unknown: special acoustic considerations

    8% (124,456)unknown10% (56,000): costing provides for standard framed, drylined partitions. Contingency may include extra acoustic insulation considerations for areas requiring special sound proofing

    Internal walls (acoustic considerations included)

    Red cedar dado walls with block above; cedar boarding, Glasroc with render and Kalwall curtain walling. Curved and flat Glulam roof with metal cladding; flat concrete with sedum. Aluminium windows and doors, medium sustainability credentials359,707

    Facing brick, render, curtain walling. Plastic clad timber pitched roof; glazing. Double glazed aluminium windows, poor sustainability credentials223,860

    Black standing seam metal cladding, low surface area (sandwiched between existing buildings). Low maintenance, medium sustainability credentials~157,500

    Cheap, economical cladding material: high environmental performance, low maintenance costs, large surface area cladding (no direct sunlight), high performance glazing, frameless doors/windows, sedum and glazed roof on timber/steel frame, high sustainability credentials250,000

    Cladding (performance/sustainable credentials)

    Paving, timber deck, brick retaining wall, timber fencing, landscaping, services, drainage and alterations to existing 285,000

    Extensive hard landscaping: paving, retaining walls, metal railings, services, drainage, site lighting, cycle shelter, demolition of existing buildings 148,000

    Extensive excavation/site works, minimal landscaping (some hard landscaping)299,000

    Extensive soft landscaping, paving, decking/walkways, car park levelling/reinstatement, wall demolition and bike storage/lighting, demolition of existing building and asbestos removal (demolition material reused on site for carparklevelling400,000

    Groundworks/landscaping/ecology

    Gas heating, 89,500Underfloor Heating, gas boiler secondary ventilation, 126,570

    Heat Pump, Gas DHW boiler, Radiant Underfloor Heat, secondary ventilation, 199,000

    Heat Pump, Thermal store, MVHR, ducted delivery200,000

    HVAC system

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    Build cost estimation: Multifaith Centre Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    829,207 13%545,877 25%788,470 20%1,000000 37%Total

    Electric light and power. Alarms.95,000

    Electrics. Lift. Alarms, data cables, audio/visual195,447

    Electrics, Lift. Alarms, CCTV, PA, data cables, BMS, emergency lights132,970

    150,000Electrical, lifts, e.t.c.

    unknown: special acoustic considerations

    8% (124,456)unknown10% (56,000): costing provides for standard framed, drylined partitions. Contingency may include extra acoustic insulation considerations for areas requiring special sound proofing

    Internal walls (acoustic considerations included)

    Red cedar dado walls with block above; cedar boarding, Glasroc with render and Kalwall curtain walling. Curved and flat Glulam roof with metal cladding; flat concrete with sedum. Aluminium windows and doors, medium sustainability credentials359,707

    Facing brick, render, curtain walling. Plastic clad timber pitched roof; glazing. Double glazed aluminium windows, poor sustainability credentials223,860

    Black standing seam metal cladding, low surface area (sandwiched between existing buildings). Low maintenance, medium sustainability credentials~157,500

    Cheap, economical cladding material: high environmental performance, low maintenance costs, large surface area cladding (no direct sunlight), high performance glazing, frameless doors/windows, sedum and glazed roof on timber/steel frame, high sustainability credentials250,000

    Cladding (performance/sustainable credentials)

    Paving, timber deck, brick retaining wall, timber fencing, landscaping, services, drainage and alterations to existing 285,000

    Extensive hard landscaping: paving, retaining walls, metal railings, services, drainage, site lighting, cycle shelter, demolition of existing buildings 148,000

    Extensive excavation/site works, minimal landscaping (some hard landscaping)299,000

    Extensive soft landscaping, paving, decking/walkways, car park levelling/reinstatement, wall demolition and bike storage/lighting, demolition of existing building and asbestos removal (demolition material reused on site for carparklevelling400,000

    Groundworks/landscaping/ecology

    Gas heating, 89,500Underfloor Heating, gas boiler secondary ventilation, 126,570

    Heat Pump, Gas DHW boiler, Radiant Underfloor Heat, secondary ventilation, 199,000

    Heat Pump, Thermal store, MVHR, ducted delivery200,000

    HVAC system

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    Build cost estimation: Multifaith Centre Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    Environmental and Services Cost Breakdown: Precedent Estimates

    Preliminary Cost EstimateREVISED Cost Estimate

    Services, mechanical & sustainable products (including frame & external walls) reflected as 50% total build cost

    1000m2

    Heat pump, Thermal store, MVHR, associated 280,000Soft landscaping, sunken garden, as-sociated trees and planting, decking/patio, bike storage, existing demoli-tion/levelling, asbestos removal(major site works & basement excavation included in substructure estimates)350,000

    Sustainable products and systems:Cedar shingle cladding & roof; 34kW PV array; low-grade UK spruce box frame with SIP system, high perfor-mance frameless doors/curtain wall glazing, small % southern exposure to upper storeys, minimising solar gain, high sustainability & high returns600,000

    Simple drylined/birch ply-faced partitions, with extra for acoustic treatment. Birch-faced SIP panels to form interior surface of external walls54000Electrical, mech, lifts, data, CCTV, alarms, BMS, audio, access, theatre435,000

    1,800000 55%

    Total 3,300000 (for review)

    16721,704,4611960168794520911568445Tender Price Update

    100%~28002,758,750100%1,4801,508,373100%1,8061,555,710

    100%2,014 1,511,026 Total Contract sum

    --3%48 49,750 0 0 0 0 9 Design Fees

    100%27582,758,75097%1,431 1,458,623100%1,806 1,555,710

    100%2,014 1,511,026 Total (less Design Fees)

    9%250250,0000 0 4%64 55,475 7%150 112,933 8 Contingencies

    10%280280,00017%248 253,378 8%150 129,390 10%210 157,917 7 Preliminaries

    20%550550,00019%279 285,051 10%172 148,872 20%398 299,066 6 External Works

    20%530530,00013%195 199,332 25%452 389,345 20%399 299,793 5 Services

    2%3030,0001%0 0 2%27 23,723 1%20 15,341 4 Fittings and Furnishings

    5%150150,5006%94 96,102 7%124 106,769 6%113 84,888 3 Finishes

    30%850850,00035%518 528,517 39%699 602,335 31%631 473,283 2 Superstructure

    4%120120,2506%94 96,243 6%115 99,801 4%90 67,805 1 Substructure

    %Costper m2

    Total cost%Costper m2

    Total cost%Costper m2

    Total cost%Costper m2

    Total cost

    Sketch Design Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    16721,704,4611960168794520911568445Tender Price Update

    100%~28002,758,750100%1,4801,508,373100%1,8061,555,710

    100%2,014 1,511,026 Total Contract sum

    --3%48 49,750 0 0 0 0 9 Design Fees

    100%27582,758,75097%1,431 1,458,623100%1,806 1,555,710

    100%2,014 1,511,026 Total (less Design Fees)

    9%250250,0000 0 4%64 55,475 7%150 112,933 8 Contingencies

    10%280280,00017%248 253,378 8%150 129,390 10%210 157,917 7 Preliminaries

    20%550550,00019%279 285,051 10%172 148,872 20%398 299,066 6 External Works

    20%530530,00013%195 199,332 25%452 389,345 20%399 299,793 5 Services

    2%3030,0001%0 0 2%27 23,723 1%20 15,341 4 Fittings and Furnishings

    5%150150,5006%94 96,102 7%124 106,769 6%113 84,888 3 Finishes

    30%850850,00035%518 528,517 39%699 602,335 31%631 473,283 2 Superstructure

    4%120120,2506%94 96,243 6%115 99,801 4%90 67,805 1 Substructure

    %Costper m2

    Total cost%Costper m2

    Total cost%Costper m2

    Total cost%Costper m2

    Total cost

    Sketch Design Proposal(Services/environmental 23% overall build cost-excluding eco cladding/roof design)1000m2

    Total: 2,679550

    Henley College(Services/environmental 13% overall build cost excluding eco cladding/roof design)1019m2

    Total: 1,508373

    St Andrews Church, Devon(Services/environmental 25% overall build cost excluding eco cladding/roof design)861m2

    Total: 1,555710

    Greyfriars Community Centre, Edinburgh(Services/environmental 20% overall build cost excluding eco cladding/roof design)750m2

    Total: 1,511026

    REVISED PROPOSAL

    1000m2

    Total: 3,300000

    Total cost Cost/m2 %

    513,900 513 16%

    672,455 670 21%

    325,136 325 10%

    201,990 202 6%

    775,350 775 23%

    350,000 350 11%

    406,000 406 13%

    3,300,000 3300 100%

    3,300,000 3300 100%

    Greyfriars Community Centre

    Henley College

    St Andrews

    Proposal

    For many international students, students with special needs or disability and students from diverse religious backgrounds, starting university, sometimes in a new country is an exciting and enlightening opportunity, but it can also be an overwhelming and perplexing experience to those unfamiliar with the cultural and environmental ramifications of the new place they are living. The centre must provide an impartial environment, a sanctuary within which people can temporarily escape the academic environment as well as the general busy, hectic stresses of modern life in a UK city. the building should create a sense of removal from the immediate environment, allowing people to become acutely unaware of the strong cultural qualities that typically define a place, religious reference or sense of hierarchy. These qualities can often be prohibitive or structured to accommodate some more than others. The intention is of a level playing field whereby our attention is taken from the everyday career-driven, money-oriented and materialistic. The building should be the embodiment of the simple, physical, exis-tential and spiritual needs common to everybodys well-being. With a strong focus on the physical environment: the elements, light, sky, weather, ecology, earth and water, the building will provide a suggestive space where individuals can feel united by common ground and free to express themselves without feeling alienated as a minority. To reflect this concept, the interior of the building must portray a vision of simplicity and functional form, removed from unnecessary excess, reckless design statement pieces or visual complexity. A refined material palette must provide simple solutions, driven by functional components, the range of durability required, the desired longevity and the environmental quality to be achieved. As such, the built form must be economically justified in the sense of lifespan, truth to materials and en-vironmental credentials. From an original budget of 1 million to a revised 3 million, the extra funding does not aim to provide scope for a more lavish architectural response, but instead caters for additional complementing use types previously unidentified by the university. These in themselves invest higher capital costs, but provide much greater value for money within the annual running of the building. As well as this, it will fund a strong emphasis on integration with the outside environment beyond basic landscaping, providing well-designed, garden spaces that can be enjoyed and utilised throughout the seasons. Substantial additional expenses identified during the analysis stage in relation to site preparation, access and mechanical requirements, as well as works to adjoining buildings, parking, services e.t.c. to facilitate the new accommodation have also been considered in the application for a revised budget.

    Site Selection and Design Philosophy

    Site B is the preferred choice for construction of the new building. Located in a courtyard between the School of Music and Aberdare Hall, comprising two historic red brick buildings completed in 1893, and connected by an arched walkway, forming the primary entrance to the site. Included within the Cathays Conservation Area, the proposal is to demolish the 60s accommodation block to the south west, opening up a prime plot, bordering the boundary of Queen Anne Square. The site is chosen for a number of reasons. Firstly, the nature of the building suggests a need for quiet and contemplation and a strong connection with the outside environment. This site naturally meets these requirements providing the ideal setting, set back from the main road, with very few outside sources of disruption. The site is particularly inward-facing, with strong boundaries. For many projects, especially those with a commercial focus, this would propose a significant challenge, but is fundamentally well suited to the secluded and understated nature of a retreat centre. Borrowing from the original concept stage, the design philosophy is to utilise lightweight construction methods, highly appropriate for intermittent use, low thermal mass and air-delivered heating and environmental control. Sitting in strong contrast with the surrounding heavyweight brick buildings, this is not only a practical and budgetary incentive, but fundamentally appropriate to the feel of the space. Unlike traditional places of worship, often iconic buildings of solidity and permanent internal layouts that feel as though they will remain unchanged for many generations, this building should instead be a testament to a changing, multinational and multifaith society. The building should be a reflection of change and progression, to feel very much of its time, designed not as a monument, but as a space that can facilitate change, adapting during its lifetime, and designed with a strong consideration for user interaction and the materials and finishes important to that user.

    The design philosophy is heavily influenced by the Zen style of design, adapted as a Japanese concept promoting the importance of the meditative state and contemplation over ritual or study of scriptures. Although the building must be designed to accommodate ritual worship and individual expression, the idea that this is a place where everybody is able to contemplate and reflect under the same roof whilst going about their daily activities acts to unite many different cultures with a common ground. Traditional Zen style buildings, although striking and beautiful, are fundamentally very simple, very lightweight, often timber and surrounded by screens with a strong connection with the outside elements. The buildings sit, poised over a firmly grounded foundation stone, which often extends into the immediate landscape as rocks, boulders and pebbles designed to represent the hills and geology of the greater landscape. Wild mosses, ferns and grasses weave between these heavy ground elements, often with a focus on a pool or steam, representing the impermanence, fragility and constantly changing nature of the environment we inhabit. As opposed to hard landscaping, manicured lawns and formal planting, the landscape must be unkempt, rough and able to naturally evolve with minimal maintenance. The main structural elements of the building should be driven by necessity and function, with simple connections and structural solutions used in favour of the complex or highly engineered. The majority of the structure will utilise efficient timber framing comprised of small sections, with steel elements where required. Components such as walls will be constructed from cheap and readily available materials, and doubling as storage and acoustic partition. Elements such as floor finishes, doors and glazing, furniture and the special components that must resist heavy user interaction, and those important to the activities taking place can be more hard-wearing and higher spec. For example, envelope walls and ceilings can be simple plasterboarded finishes, structural elements left as they come, with minimal use of decora-tion or ornament. Shadow gaps should be used around frames and special components, with clear boundaries between the small number of different materials. Floor finishes may be of polished concrete or polished timber, according to traffic or activity with glazing creating an unobscured interaction with the outside: floor to ceiling in communal spaces, and focused or carefully orientated in private or secular spaces. Lighting is of great importance, and the overall scheme should use both natural and artificial light with equal importance, with the building potentially used to a high extent out of hours. Lighting should be subtle and not overbearing, but the overall effect creating a strong sense of drama. For example, it may not be necessary to evenly light the entire space, but rather highlight particular areas, with strong use of shadow and low light to the peripheries. To separate the different parts and uses of the building, so they are visually connected, but at the same time private and acoustically isolated, internal rooms may become sculptural elements in themselves, incorporating religious objects and artefacts where needed, with rooms appearing as pieces of sculpted furniture. This creates a feeling of domesticity within such a large building envelope without being too literal. This also takes the impetus away from the items and furnishings placed within the room, promoting a space that feels greater than the sum of its parts. Exterior courtyards placed internally in plan, with lightwell gardens which separate indoor rooms by outside space will create excellent acoustic separation, whilst visually uniting different parts of the building and bringing large volumes of natural light to the interior plan. Site Considerations: Programme Constraints and Opportunities, Access, Logistics and Part L:

    Placing the building on this site opens up great potential for the school of music to coexist with additional performance space and refreshment/restaurant facilities, ensuring year-round occupation and a strong source of revenue outside of passers by and minority groups. This coincides with the universitys long term development strategy for expanding the campus and better integrating its peripheries. Economically, the approach to balancing materials between those that are purely practical and structural, and those integral to user interaction dictates where the budget will be concentrated most heavily. Frame, cladding and structural elements must be use cheap, readily available and sustainable materials in a practical and low-maintenance way, in small enough sections for access to the confined site, but prefabricated wherever possible to minimise waste and construction time. Softwood should be chosen over hardwood, therefore timber elements should not be exposed to the exterior, with steel elements used where connecting timbers. The interior design may therefore want to dominate the users attention away from the structure itself, only revealing glimpses of the building in carefully chosen areas. On the exterior, a durable, sustainable cladding material should be chosen, potentially incorporating or future-proofing for energy generating systems. As the site has restricted access with a narrow archway which will form the primary access route for the final building as well as day-to-day construction access, an additional access point will be made through the wall connecting the rear access road for infrequent and bulk deliveries of materials. Negotiations will need to be made with the council, the telephone distribution board relocated and upgraded, and hoarding erected. Following asbestos removal, demolition and excavation materials from the 60s structure will be used to grade the adjacent music school car park, creating a temporary site holding area and office. No access is to be made through Queen Anne Square, and justification may be made to creating a minimal frontage to Queen Anne square, which would otherwise be competing with the Georgian style detached houses and generate undesired disruption to the local residents. The building should instead front, with main glazing into the interior courtyard. The existing arches and red brick buildings offer huge potential for glazed connecting structures, possibly for com-munal circulation and cafe/retail space, which will require considerable attention to detail and sympathy to the listed building fabrics. Strong consideration needs to be placed on service access and storage space in the basement, where space is at a premium, and the additional mechanical and acoustic requirements for performance-use considered from the outset and designed in to the building. The nature of the construction dictates that BREEAM very good/excellent status can be aimed for, with an impetus on sustainable materials, local ecology and low heating costs. This will be achieved using air-delivery heat generated from a heat pump system using borehole loops on the confined site, with simple, user-friendly and zoned controls designed to work around inhabited periods. On completion, it is essential that an ongoing management and monitoring process is maintained to ensure long-term efficient operation and that the building is performing for its users in a positive and beneficial way.

    Aerial view of site Early Sketch Scheme Proposals Budgetary Proposal Elemental Breakdown (refer to detailed itemised breakdown)

    Main proposal cross section, showing all main spaces (facing South-East toward Aberdare Hall)

  • 20ft320ft3

    20ft320ft3

    20ft320ft3

    20ft320ft3

    20ft320ft3

    16 x (2x1) x 108 x (2x6) x 1016 x (2x4) x 1034 x (4x1) x 10

    =200ft3

    ~1ft3

    ~20ft

    Floor area = 150m2 (1500ft2)

    Typical 220m2 oak frame house = 800ft3 timber (50 trees)Typical 150m2 oak frame = 550ft3 timber (30 trees)). 150m2 ecient oak frame =200ft3 timber (10 trees) = 65% less timber

    26 x 1.5m sonotube pile footings

    10 trees

  • 20ft320ft3

    20ft320ft3

    20ft320ft3

    20ft320ft3

    20ft320ft3

    16 x (2x1) x 108 x (2x6) x 1016 x (2x4) x 1034 x (4x1) x 10

    =200ft3

    ~1ft3

    ~20ft

    Floor area = 150m2 (1500ft2)

    Typical 220m2 oak frame house = 800ft3 timber (50 trees)Typical 150m2 oak frame = 550ft3 timber (30 trees)). 150m2 ecient oak frame =200ft3 timber (10 trees) = 65% less timber

    26 x 1.5m sonotube pile footings

    10 trees

  • 123

    4

    5 6

    1 . I N D U S T R I A L

    2 . E D U C A T I O N

    3 . A C C O M M O D A T I O N

    4 . L I V E - W O R K U N I T S

    5 . T I M B E R S T O R A G E

    6 . L I B R A R Y

    S I T E S C H E M A T I C

  • Work fo r V i cen te Bur in A rch i tec t s

    & Por t fo l io Homes

    PL ANS , ELEVAT IONS & CGI S

    n

    PROFESSIONAL DESIGN

  • Proposed Ground Floor PlanScale 1:100

    N Proposed Basement PlanScale 1:100

    Wine celler

    Cinema Room

    GYM

    Plant/mechanical

    Store

    Games Room

    Sauna / Shower / Steam Room

    svp

    PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

    PRO

    DU

    CED

    BY

    AN

    AU

    TOD

    ESK

    ED

    UC

    ATI

    ON

    AL

    PRO

    DU

    CT

    PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

    PRO

    DU

    CED

    BY A

    N A

    UTO

    DESK

    EDU

    CA

    TION

    AL PR

    OD

    UC

    T

    Laundry

    Living

    Coa

    ts /

    Boo

    ts

    Proposed Ground Floor PlanScale 1:100

    N

    Study / library

    WC

    Timber Decking

    Dining

    Porch

    900 Fridge

    Larder

    Coa

    ts /

    Boo

    ts

    workarea

    garage

    Kitchen/breakfast

    300mm Bookcases

    Recessed fire/tv above

    WasherDryer

    svp

    svp

    svp

    svp

    svpbetween studs

    svpbetween studs

    svpbetween studs

    svpbetween studs

    brooms

    Bureau

    PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCTPR

    OD

    UC

    ED B

    Y A

    N A

    UTO

    DES

    K E

    DU

    CA

    TIO

    NA

    L PR

    OD

    UC

    T

    PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

    PRO

    DU

    CED

    BY A

    N A

    UTO

    DESK

    EDU

    CA

    TION

    AL PR

    OD

    UC

    T

  • Proposed First Floor PlanScale 1:100

    Bedroom 2

    Gallery Landing

    1500mm CH

    2400mm CH

    RL

    Bedroom 4 Bedroom 3

    RL

    RL

    RL

    RL

    N

    1500mm CH

    2400mm CH

    600mm CH

    2000mm CH

    RL

    full-heightmirror

    closet

    closet

    closet closet

    closet

    800x1600 shower

    void

    Master Bed 1

    Master Bath

    1800 free standing bath

    800 glass screen

    cleaning supplies, towels

    Family Bath

    niche

    Bedroom 5

    cleaning supplies, towelssvp

    under floor

    mirror mirror

    600mm CH

    600mm CH 600mm CH600mm CH600mm CH

    600mm CH

    2400mm CH 2400mm CH2400mm CH

    Ensuite

    2400mm CH

    2000mm CH

    800x1200 shower

    window seat

    800x1200 shower800x1200 shower

    800x1200 shower

    closet

    closet

    cleaning supplies, towels

    cleaning supplies, towels

    Ensuite Ensuite

    2000mm CH

    window seat window seat window seat

    PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

    PRO

    DU

    CED

    BY

    AN

    AU

    TOD

    ESK

    ED

    UC

    ATI

    ON

    AL

    PRO

    DU

    CT

    PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

    PRO

    DU

    CED

    BY A

    N A

    UTO

    DESK

    EDU

    CA

    TION

    AL PR

    OD

    UC

    T

  • STORE

    WC

    STORE

    BATHROOM

    ENSUITE

    BED

    BED

    BED

    BED

    UTILITY

    STUDY

    HALL

    TV ROOM

    LIVING

    GARAGE

    ENSUITE

    DRESSING

    CONSERVATORY

    GROUND FLOOR PLAN FIRST FLOOR PLAN5m0 1

    1:50@A1

    5m

    0 1

    1:50@A1

    Master telephone point located 450mm (underside) above ffl

    Single socket outlet located 450mm (underside) above ffl

    Double switched socket outlet located 150mm above work surface

    Double socket outlet located 450mm (underside) above ffl

    (underside) above ffl

    Single switched socket outlet located 150mm above work surface

    Television aerial jackpoint - TV/FM or C-Cable TV - located 450mm

    Light switch

    Light switch one way located 1050mm above ffl

    Telephone junction box/point located 450mm (underside) above ffl

    switched

    switched two way located 1050mm above ffl

    switchedLight switch three way located 1050mm above ffl

    Dimmer switch located 1050mm above ffl

    Down lighter (to accord with RD's as appropriate)

    Pendant Light (LE denotes Low Energy Bulb)

    Wall light

    External wall light - PIR indicates passive infra redfitting

    Note -LE alongside symbolindicates fitting thatwill only acceptcompact flourescentlamps in accordancewith Table 4 ADL1 ofthe BuildingRegulations

    Electrical Legend

    Down lighters to be no nearer than 900mm apart.

    Permanent wired, fused & switched spur with indicator light connected tolow level unswitched socket outlet (except immersion which is to be wireddirectly to heater)IH-Immersion WM-Washing Machine DW-Dishwasher FF-Fridge FreezerTD-Tumble Dryer WD-Washer Dryer

    Cooker Control Panel

    Electricity consumer unit (located at high level)

    Gridswitch controlling kitchen appliancesvia low level unswitched socket outlet asindicated

    Shaver socket/point

    External water tap

    Gas point

    Door entry phone speaker door release

    Alarm key pad panel

    Extract fan isolation switch located above door outside Bathrooms/Wc's etc.or at high level near fan in Kitchen

    Door bell

    ( Switch to be centred above WC / Bathroom doorway )

    Ionisation Smoke detector Mains operated smoke detectors and sounders, interconnected withbattery backup and wired to AOV at head of stairs. Installed in accordancewith BS: 5446: Part 1 or BS: 5839-6: 2004 to an LD2 standard

    Heat detectorMains operated heat detectors and sounders, interconnected with batterybackup. Installed in accordance with BS: 5446: Part 1 or BS: 5839-6:2004 to an LD2 grade D standard.Positioned not within 300mm of any light fitting or wall.

    Note:Three in every Four fixedlight fittings should be energyefficient

    5A lighting circuit socket outlet located 450mm (underside) above ffl

    Fluorescent strip light with plastic diffuser

    2090

    3295

    600

    500

    300

    900 45 300 600

    1200

    818

    1690

    fridge/freezer

    Optical Smoke detector Mains operated smoke detectors and sounders, interconnected withbattery backup and wired to AOV at head of stairs. Installed in accordancewith BS: 5446: Part 1 or BS: 5839-6: 2004 to an LD2 standard

    Carbon Monoxide detectorMains operated heat detectors and sounders, interconnected with batterybackup. Installed in accordance with BS: 5446: Part 1 or BS: 5839-6:2004 to an LD2 grade D standard.Positioned not within 300mm of any light fitting or wall.

    Spur plate above overhead kitchen cupboards for under-cupboard lights

    ovenoven

  • STORE

    WC

    STORE

    BATHROOM

    ENSUITE

    BED

    BED

    BED

    BED

    UTILITY

    STUDY

    HALL

    TV ROOM

    LIVING

    GARAGE

    ENSUITE

    DRESSING

    CONSERVATORY

    GROUND FLOOR PLAN FIRST FLOOR PLAN5m0 1

    1:50@A1

    5m

    0 1

    1:50@A1

    Master telephone point located 450mm (underside) above ffl

    Single socket outlet located 450mm (underside) above ffl

    Double switched socket outlet located 150mm above work surface

    Double socket outlet located 450mm (underside) above ffl

    (underside) above ffl

    Single switched socket outlet located 150mm above work surface

    Television aerial jackpoint - TV/FM or C-Cable TV - located 450mm

    Light switch

    Light switch one way located 1050mm above ffl

    Telephone junction box/point located 450mm (underside) above ffl

    switched

    switched two way located 1050mm above ffl

    switchedLight switch three way located 1050mm above ffl

    Dimmer switch located 1050mm above ffl

    Down lighter (to accord with RD's as appropriate)

    Pendant Light (LE denotes Low Energy Bulb)

    Wall light

    External wall light - PIR indicates passive infra redfitting

    Note -LE alongside symbolindicates fitting thatwill only acceptcompact flourescentlamps in accordancewith Table 4 ADL1 ofthe BuildingRegulations

    Electrical Legend

    Down lighters to be no nearer than 900mm apart.

    Permanent wired, fused & switched spur with indicator light connected tolow level unswitched socket outlet (except immersion which is to be wireddirectly to heater)IH-Immersion WM-Washing Machine DW-Dishwasher FF-Fridge FreezerTD-Tumble Dryer WD-Washer Dryer

    Cooker Control Panel

    Electricity consumer unit (located at high level)

    Gridswitch controlling kitchen appliancesvia low level unswitched socket outlet asindicated

    Shaver socket/point

    External water tap

    Gas point

    Door entry phone speaker door release

    Alarm key pad panel

    Extract fan isolation switch located above door outside Bathrooms/Wc's etc.or at high level near fan in Kitchen

    Door bell

    ( Switch to be centred above WC / Bathroom doorway )

    Ionisation Smoke detector Mains operated smoke detectors and sounders, interconnected withbattery backup and wired to AOV at head of stairs. Installed in accordancewith BS: 5446: Part 1 or BS: 5839-6: 2004 to an LD2 standard

    Heat detectorMains operated heat detectors and sounders, interconnected with batterybackup. Installed in accordance with BS: 5446: Part 1 or BS: 5839-6:2004 to an LD2 grade D standard.Positioned not within 300mm of any light fitting or wall.

    Note:Three in every Four fixedlight fittings should be energyefficient

    5A lighting circuit socket outlet located 450mm (underside) above ffl

    Fluorescent strip light with plastic diffuser

    2090

    3295

    600

    500

    300

    900 45 300 600

    1200

    818

    1690

    fridge/freezer

    Optical Smoke detector Mains operated smoke detectors and sounders, interconnected withbattery backup and wired to AOV at head of stairs. Installed in accordancewith BS: 5446: Part 1 or BS: 5839-6: 2004 to an LD2 standard

    Carbon Monoxide detectorMains operated heat detectors and sounders, interconnected with batterybackup. Installed in accordance with BS: 5446: Part 1 or BS: 5839-6:2004 to an LD2 grade D standard.Positioned not within 300mm of any light fitting or wall.

    Spur plate above overhead kitchen cupboards for under-cupboard lights

    ovenoven

  • DN

    DN

    DN

    DN

    6 mStudy

    21 mFamily Room

    15 mDining/Den

    7 mAnnex Kitchen

    10 mAnnex Bed 1

    1 mCloset

    26 mGarage

    4 mBath

    Tank

    1 mBoiler

    1 mManifolds, CU0 m

    Brooms SVP

    1 mWC

    SVP

    RSJaboveopening

    2 mNew Exterior Porch

    10 mAnnex Bed 2

    27 mAnnex Living

    3 mNew annex Porch

    Demo

    Demo

    Demo

    Demo

    Demo

    Porch roofremoved

    Soil pipe toensuite aboveceiling void

    New SVP incloset

    New foul runthroughkitchen floor

    Foul run teesup to behindWC

    Demo

    New 125 Insulatedext Stud Wall w/councealed cistern

    Openingnarrowed

    1 mUnderstairs Cup'd

    Windowfilled in

    Demo

    Demo

    Demo

    Demo

    New step runningaround entire plinth

    Existingdoor filled in

    Whitesymmetrical900 Georgianbar door withtwo 300Georgian barsidelights

    New 125Insulated extStud Wall

    Doorremoved, wallfilled in withmatchingwindow to left

    BroomsWasher

    Dryer

    5 mUtility

    Stub

    1000AmericanFridgeFreezer

    Pull-outlarder

    Pull-outlarder

    Oven

    oven

    27 mKitchen

    New FrenchDoors in placeof window?

    Gasmain

    Panelledopening(18x80mmmdf panelling)

    Panelledopening(18x80mmmdf panelling)

    Stormwatersoakaway

    New door to utility

    ExistingCombinedGully

    SVP

    new raindownspoutgully

    new raindownspoutgully

    new raindownspoutgully

    new raindownspoutgully

    ExistingCombinedGully

    GreyGully

    GreyGully

    new raindownspoutgully

    Stormwatersoakaway

    ExistingInspectionChamber

    rain downspoutto permeablegrade

    rain downspoutto permeablegrade

    18 mHall

    Scale

    Drawn by

    Date

    Manor Lodge77 Pilgrims WayOtford

    TN14 5JH

    1 : 50 14/05

    /201

    4 14

    :08:

    28

    1 of 3 GroundFloor

    Manor LodgeVersion 1

    Portfolio Homes

    May 2014

    Wakeman

    No. Description Date1 of 3 Ground 1:502 of 3 First 1:503 of 3 Site 1:200

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRODUCED

    BY AN

    AUTOD

    ESK STUDEN

    T PRO

    DUCT

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRO

    DUC

    ED B

    Y AN

    AUT

    OD

    ESK

    STUD

    ENT

    PRO

    DUC

    T

  • DN

    DN

    DN

    DN

    6 mStudy

    21 mFamily Room

    15 mDining/Den

    7 mAnnex Kitchen

    10 mAnnex Bed 1

    1 mCloset

    26 mGarage

    4 mBath

    Tank

    1 mBoiler

    1 mManifolds, CU0 m

    Brooms SVP

    1 mWC

    SVP

    RSJaboveopening

    2 mNew Exterior Porch

    10 mAnnex Bed 2

    27 mAnnex Living

    3 mNew annex Porch

    Demo

    Demo

    Demo

    Demo

    Demo

    Porch roofremoved

    Soil pipe toensuite aboveceiling void

    New SVP incloset

    New foul runthroughkitchen floor

    Foul run teesup to behindWC

    Demo

    New 125 Insulatedext Stud Wall w/councealed cistern

    Openingnarrowed

    1 mUnderstairs Cup'd

    Windowfilled in

    Demo

    Demo

    Demo

    Demo

    New step runningaround entire plinth

    Existingdoor filled in

    Whitesymmetrical900 Georgianbar door withtwo 300Georgian barsidelights

    New 125Insulated extStud Wall

    Doorremoved, wallfilled in withmatchingwindow to left

    BroomsWasher

    Dryer

    5 mUtility

    Stub

    1000AmericanFridgeFreezer

    Pull-outlarder

    Pull-outlarder

    Oven

    oven

    27 mKitchen

    New FrenchDoors in placeof window?

    Gasmain

    Panelledopening(18x80mmmdf panelling)

    Panelledopening(18x80mmmdf panelling)

    Stormwatersoakaway

    New door to utility

    ExistingCombinedGully

    SVP

    new raindownspoutgully

    new raindownspoutgully

    new raindownspoutgully

    new raindownspoutgully

    ExistingCombinedGully

    GreyGully

    GreyGully

    new raindownspoutgully

    Stormwatersoakaway

    ExistingInspectionChamber

    rain downspoutto permeablegrade

    rain downspoutto permeablegrade

    18 mHall

    Scale

    Drawn by

    Date

    Manor Lodge77 Pilgrims WayOtford

    TN14 5JH

    1 : 50 14/05

    /201

    4 14

    :08:

    28

    1 of 3 GroundFloor

    Manor LodgeVersion 1

    Portfolio Homes

    May 2014

    Wakeman

    No. Description Date1 of 3 Ground 1:502 of 3 First 1:503 of 3 Site 1:200

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRODUCED

    BY AN

    AUTOD

    ESK STUDEN

    T PRO

    DUCT

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRO

    DUC

    ED B

    Y AN

    AUT

    OD

    ESK

    STUD

    ENT

    PRO

    DUC

    T

  • 6 mMaster Bath

    13 mBedroom 34 m

    Ensuite

    3 mCloset

    8 mBedroom 2

    1 mCloset

    14 mMaster Bed

    3 mMaster Ensuite

    9 mHall

    Scale

    Drawn by

    Date

    Manor Lodge77 Pilgrims WayOtford

    TN14 5JH

    1 : 50 14/05

    /201

    4 14

    :10:

    55

    2 of 3 First

    Manor LodgeVersion 1

    Portfolio Homes

    May 2014

    Wakeman

    No. Description Date1 of 3 Ground 1:502 of 3 First 1:503 of 3 Site 1:200

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRODUCED

    BY AN

    AUTOD

    ESK STUDEN

    T PRO

    DUCT

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRO

    DUC

    ED B

    Y AN

    AUT

    OD

    ESK

    STUD

    ENT

    PRO

    DUC

    T

  • 6 mMaster Bath

    13 mBedroom 34 m

    Ensuite

    3 mCloset

    8 mBedroom 2

    1 mCloset

    14 mMaster Bed

    3 mMaster Ensuite

    9 mHall

    Scale

    Drawn by

    Date

    Manor Lodge77 Pilgrims WayOtford

    TN14 5JH

    1 : 50 14/05

    /201

    4 14

    :10:

    55

    2 of 3 First

    Manor LodgeVersion 1

    Portfolio Homes

    May 2014

    Wakeman

    No. Description Date1 of 3 Ground 1:502 of 3 First 1:503 of 3 Site 1:200

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRODUCED

    BY AN

    AUTOD

    ESK STUDEN

    T PRO

    DUCT

    PRODUCED BY AN AUTODESK STUDENT PRODUCT

    PRO

    DUC

    ED B

    Y AN

    AUT

    OD

    ESK

    STUD

    ENT

    PRO

    DUC

    T

  • DISCOVER ING A LOST C IT Y

    Location: Bristol, UK. Slave Trade Museum Proposal

    URBAN FRAGMENT

  • 1955 View of Redcliffe Way, Bristol, from the top of Redcliffe Church

    rrepaeparraation:tion:

    Thomas Wakeman.Year 3.Bristol Redcliffe Concept Development

  • 1955 View of Redcliffe Way, Bristol, from the top of Redcliffe Church

    rrepaeparraation:tion:

    Thomas Wakeman.Year 3.Bristol Redcliffe Concept Development

  • INDEPENDENT PROPERT Y PROJECTS

    INTER IOR PHOTOS

    houzz.com/uk/pro/tom-wakeman

    INTERIOR DESIGN

  • GRAPHIC DES IGN & PHOTOGRAPHY

    Not all those who wander are lost

    SATURDAYS

  • L 0 C A L 4I N S P I R E D B Y L O C A L C O M M U N I T Y A N D D E S I G N

  • PROJECTS IN T IMBER

    Studio in the Woods and Big Span

    CONSTRUCTED

  • HOUSE OF ST ICKS

    Featuring the buildings and people of the outer Cape

    THESIS

  • HOUSE OF ST ICKS

    Featuring the buildings and people of the outer Cape

    THESIS