to environmental & social impact assessment (esia) report · nsl renewable power private...
TRANSCRIPT
DRAFTDRAFTDRAFTDRAFT
NNNooonnn TTTeeeccchhhnnniiicccaaalll EEExxxeeecccuuutttiiivvveee SSSuuummmmmmaaarrryyy
tttooo
EEEnnnvvviiirrrooonnnmmmeeennntttaaalll &&& SSSoooccciiiaaalll IIImmmpppaaacccttt
AAAsssssseeessssssmmmeeennnttt (((EEESSSIIIAAA))) RRReeepppooorrrttt
100 MW TIDONG HYDROELECTRIC POWER PROJECT OOOfff
111000000 MMMWWW TTTiiidddooonnnggg---111 HHHyyydddrrrooo EEEllleeeccctttrrriiiccc PPPrrrooojjjeeecccttt
fffooorrr
NNNSSSLLL RRREEENNNEEEWWWAAABBBLLLEEE PPPOOOWWWEEERRR PPPRRRIIIVVVAAATTTEEE LLLIIIMMMIIITTTEEEDDD
SSSeeepppttteeemmmbbbeeerrr 222000111111
PPPRRREEEPPPAAARRREEEDDD BBBYYY:::
AAAEEECCCOOOMMM IIINNNDDDIIIAAA PPPRRRIIIVVVAAATTTEEE LLLIIIMMMIIITTTEEEDDD
999ttthhh FFFllloooooorrr,,, IIInnnfffiiinnniiitttyyy TTTooowwweeerrr---CCC,,,
CCCyyybbbeeerrrccciiitttyyy,,, DDDLLLFFF PPPhhhaaassseee---IIIIII,,,
GGGuuurrrgggaaaooonnn ---111222222000000222
IIINNNDDDIIIAAA
ESIA for 100MW Tidong1 HEP, 2011
Contents 1. Background ................................
2. Project Description ................................
3. Applicable Regulatory Requirement and IFC PSs
4. Public Consultation & Disclosure
5. Grievance Redressal ................................
6. Baseline Environment ................................
7. Key EHS Impacts and Mitigations due to Tidong
8. Key Social Impacts and Mitigations due to Tidong
9. Key EHS & Social Impacts and Mitigations due to Transmission Line
10. Rehabilitation and Resettlement
11. Monitoring and Auditing Plan and Costs
Non Technical Executive Summary
................................................................................................................................
...........................................................................................................................
ble Regulatory Requirement and IFC PSs ................................................................
Public Consultation & Disclosure ................................................................................................
................................................................................................
................................................................................................
Impacts and Mitigations due to Tidong1 Hydro Electric Project ................................
Key Social Impacts and Mitigations due to Tidong1 Hydro Electric Project ................................
Key EHS & Social Impacts and Mitigations due to Transmission Line................................
Rehabilitation and Resettlement .............................................................................................
Monitoring and Auditing Plan and Costs ................................................................
i
....................................... ii
........................... iv
............................................ vii
..................................... ix
.......................................................... x
....................................................... x
..................................... xv
................................ xxiv
........................................... xxvi
............................. xxvii
.................................................. xxix
ESIA for 100MW Tidong1 HEP, 2011
1. Background
NSL Renewable Power Private Limited (
proposes to set up 100 MW Tidong
Himachal Pradesh in India.
Company NSL Tidong Power Generation Private Limited (NTGPL).
the Tidong Khad (Stream), a tributary of river Satluj in Kinnaur district. It is a run of the river
scheme, proposed to harness the hydro potential of Tidong Khad in its lower reach betw
Lambar and Rispa villages. The project site is situated 270 km from Shimla on National Highway
22 upto a place near Moorang and thereafter 21 km on state road upto village L
construction of this project started in mid 2008 and
2013. The project location map is as given in Figure
RITES Ltd conducted the EIA study based in the project details given in the Pre
of 2005. The field work for the EIA was undertaken in 2005 and the repor
2006. The Environmental Clarence was accorded by Ministry of Environment and Forests (MoEF)
in 2006 based on the notification of 1994 and its subsequent amendments under Environment
Protection Act of 1986. The existing EIA report (by RI
accordance with IFC requirements.
Non Technical Executive Summary
NSL Renewable Power Private Limited (NTPGL), a private limited company incorporated in India,
up 100 MW Tidong1 Hydroelectric Project in Tehsil Moorng, District Kinnaur,
Himachal Pradesh in India. The project is being set up by NTPGL’s wholly held subsidiary
er Generation Private Limited (NTGPL). The Tidong1 HEP is located on
the Tidong Khad (Stream), a tributary of river Satluj in Kinnaur district. It is a run of the river
proposed to harness the hydro potential of Tidong Khad in its lower reach betw
Lambar and Rispa villages. The project site is situated 270 km from Shimla on National Highway
22 upto a place near Moorang and thereafter 21 km on state road upto village L
construction of this project started in mid 2008 and is expected to be completed by end of year
The project location map is as given in Figure 1.
RITES Ltd conducted the EIA study based in the project details given in the Pre
of 2005. The field work for the EIA was undertaken in 2005 and the report was submitted in
2006. The Environmental Clarence was accorded by Ministry of Environment and Forests (MoEF)
in 2006 based on the notification of 1994 and its subsequent amendments under Environment
The existing EIA report (by RITES, 2005) was updated by AECOM
IFC requirements.
ii
, a private limited company incorporated in India,
Moorng, District Kinnaur,
’s wholly held subsidiary
1 HEP is located on
the Tidong Khad (Stream), a tributary of river Satluj in Kinnaur district. It is a run of the river
proposed to harness the hydro potential of Tidong Khad in its lower reach between
Lambar and Rispa villages. The project site is situated 270 km from Shimla on National Highway
22 upto a place near Moorang and thereafter 21 km on state road upto village Lambar. The
be completed by end of year
RITES Ltd conducted the EIA study based in the project details given in the Prefeasibility report
t was submitted in
2006. The Environmental Clarence was accorded by Ministry of Environment and Forests (MoEF)
in 2006 based on the notification of 1994 and its subsequent amendments under Environment
TES, 2005) was updated by AECOM in
ESIA for 100MW Tidong1 HEP, 2011
100 MW Tidong HEP
Himachal Pradesh, India
Non Technical Executive Summary
100 MW Tidong HEP
Kinnaur,
Himachal Pradesh, India
Figure 1: Tidong HEP Location Map
Himachal Pradesh,
India
Kinnaur,
Himachal Pradesh
iii
ESIA for 100MW Tidong1 HEP, 2011
2. Project Description
Project Appurtenance
This runoftheriver project will have a 10 m high concrete barrage at about
from the confluence of Tidong and Satluj
hectares and divert the water into
The water will be transmitted through 8461 m long D
m long pressure shaft. The over ground power house will have 2 x 50 MW Vertical Shaft Pelton
turbines.
The project will use existing PWD road starting from NH
located near villager Lambar. However, addition roads of about 11 km
access various appurtenances like diversion structure, HRT, Intake, powerh
and surge shaft. Water from the project will be discharged into the Tidong stream after
generation of power through 50 m long open Tail Race Channel. The project will have a 120 m
high surge shaft with 8 m diameter.
The project will also have a colony which will be constructed towards the closing phase of the
construction period. Two labour colonies, one at head works and the other near power house is
in advanced stage of construction. There are 4 muck disposal areas for the project and all are
operational. The water supply for the labour cam
from the Tidong river. The project area will have a proper municipal waste disposal system and
the collected waste will be incinerated through an incinerator.
Land Requirement
The total land requirement of
land and 3.2011 hectares of private land. The
diverted in favour of NTPGL
i.e. 3.2011 ha., required for this project
Acquisition Act (LAA), 1894 and has been
of private land and other structures as per LAA
along with statutory interests and s
rate of land that has been paid and
compensation.
Non Technical Executive Summary
river project will have a 10 m high concrete barrage at about
from the confluence of Tidong and Satluj River. The barrage will submerge an area of about 0.5
hectares and divert the water into a 4 hours peaking reservoir of 237000m3 storage capacity.
The water will be transmitted through 8461 m long Dshaped Head Race Tunnel (HRT) to a 1200
m long pressure shaft. The over ground power house will have 2 x 50 MW Vertical Shaft Pelton
e project will use existing PWD road starting from NH22 near Moorang upto Barrage site
located near villager Lambar. However, addition roads of about 11 km are be
access various appurtenances like diversion structure, HRT, Intake, powerhouse, pressure shaft
and surge shaft. Water from the project will be discharged into the Tidong stream after
generation of power through 50 m long open Tail Race Channel. The project will have a 120 m
high surge shaft with 8 m diameter. Different project appurtenances are given in the Figure
The project will also have a colony which will be constructed towards the closing phase of the
construction period. Two labour colonies, one at head works and the other near power house is
truction. There are 4 muck disposal areas for the project and all are
operational. The water supply for the labour camps and the permanent colony will
from the Tidong river. The project area will have a proper municipal waste disposal system and
he collected waste will be incinerated through an incinerator.
The total land requirement of the project is 42.2557 ha. which includes 39.0546 ha. of forest
tares of private land. The forest land (with 1261 numbers of tr
NTPGL by Ministry of Environment and Forests (MoEF). All the private land
i.e. 3.2011 ha., required for this project was acquired by the state government under the Land
, 1894 and has been transferred in favour of the company.
and other structures as per LAA has been paid to the respective
interests and solatium. However, the land owners are unhappy with the
rate of land that has been paid and have filed a petition in the court for higher rate of
iv
river project will have a 10 m high concrete barrage at about 9.8 km upstream
. The barrage will submerge an area of about 0.5
a 4 hours peaking reservoir of 237000m3 storage capacity.
shaped Head Race Tunnel (HRT) to a 1200
m long pressure shaft. The over ground power house will have 2 x 50 MW Vertical Shaft Pelton
22 near Moorang upto Barrage site
ing constructed to
ouse, pressure shaft
and surge shaft. Water from the project will be discharged into the Tidong stream after
generation of power through 50 m long open Tail Race Channel. The project will have a 120 m
appurtenances are given in the Figure 2.
The project will also have a colony which will be constructed towards the closing phase of the
construction period. Two labour colonies, one at head works and the other near power house is
truction. There are 4 muck disposal areas for the project and all are
ps and the permanent colony will be drawn
from the Tidong river. The project area will have a proper municipal waste disposal system and
the project is 42.2557 ha. which includes 39.0546 ha. of forest
1261 numbers of trees) was
. All the private land
was acquired by the state government under the Land
favour of the company. Compensation
respective land owners
the land owners are unhappy with the
filed a petition in the court for higher rate of
ESIA for 100MW Tidong1 HEP, 2011
Transmission Line
Power evacuation will be through 220 kV DC Line from Tidong to Kashang, to be constructed and
operated by HPPTCL. NTPGL
system on metering at Tidong. However, the exact routing of transmission line has not yet been
decided by HPPTCL.
Non Technical Executive Summary
Power evacuation will be through 220 kV DC Line from Tidong to Kashang, to be constructed and
NTPGL will pay open access charges for the power evacua
system on metering at Tidong. However, the exact routing of transmission line has not yet been
v
Power evacuation will be through 220 kV DC Line from Tidong to Kashang, to be constructed and
will pay open access charges for the power evacuation transmission
system on metering at Tidong. However, the exact routing of transmission line has not yet been
ESIA for 100MW Tidong1 HEP, 2011
3. Applicable Regulatory Requirement and IFC PSs
Indian Requirements
The ESIA for the proposed project was conducted
Clearance from MoEF on 7
also received the Forest Clearance from MoEF on
18Jun2008 after a payment of Rs.
diversion of forest and Rs. 26,676,610/
has deposited Rs. 72,484,026/
A summary of regulations
status is as mentioned below;
Table 1: Applicable Legal framework and
Regulation
The Environmental Impact Assessment (EIA)
Notification, 1994 and 2006
The Forest (Conservation) Act, 1980 as amended in
1988 and The Forest (Conservation) Rules 2003
The Environment (Protection) Act, 1986, amended in
1991 and Rules 1986
Air (Prevention and Control of Pollution) Act, 1981,
amended 1987 and Rules 1982, 1983
Water (Prevention and Control of Pollution) Act, 1974
and Rules 1975 as amended up to 1988
Water (Prevention and Control of Pollution) Cess Act,
1977
Hazardous Wastes (Management, Handling and
Transboundary Movement) Rules 2008
The Land Acquisition Act, 1894
Rules for the regulation of Rights in the Demarcated
and Undemarcated Forest of the Sutlej Valley under
the Schedule of Bashahr Lease, 1920
Child Labour (Prohibition and Regulation) Act, 2000
Non Technical Executive Summary
Applicable Regulatory Requirement and IFC PSs
The ESIA for the proposed project was conducted by RITES Ltd and received the Environmental
7th Sep 2007 under the Environment Protection Act 1986
also received the Forest Clearance from MoEF on under the Forest Conservation Act, 1980 on
2008 after a payment of Rs. 24,488,773/ as cost of Net Present Value of the proposed
26,676,610/ as a cost of Compensatory afforestation. Further,
,026/ towards Catchment Area Treatment with HP Forest Department.
A summary of regulations applicable during construction period and respective
status is as mentioned below;
egal framework and Compliance Status
Regulation Compliance
The Environmental Impact Assessment (EIA)
Notification, 1994 and 2006
Complied by obtaining
Environmental Clearance
The Forest (Conservation) Act, 1980 as amended in
The Forest (Conservation) Rules 2003
Complied by obtaining
Clearance
The Environment (Protection) Act, 1986, amended in The EIA report has been prepared
in accordance with the guidelines
of this act. The proposed project
will fully abide
Control of Pollution) Act, 1981,
amended 1987 and Rules 1982, 1983
Complied by obtaining Consent to
Establish from HPSPCB
Water (Prevention and Control of Pollution) Act, 1974
and Rules 1975 as amended up to 1988
Complied by obtaining Consent to
Establish HPSPCB
Water (Prevention and Control of Pollution) Cess Act, Not complied
Hazardous Wastes (Management, Handling and
Transboundary Movement) Rules 2008
Not complied
The Land Acquisition Act, 1894 Complied for acquisition of
private land
r the regulation of Rights in the Demarcated
demarcated Forest of the Sutlej Valley under
the Schedule of Bashahr Lease, 1920
NTPGL has paid the compensation
but villagers have not received.
The matter will be resolved within
one year of release of
Child Labour (Prohibition and Regulation) Act, 2000 Complied. No child labour was
observed employed in the project
vii
received the Environmental
under the Environment Protection Act 1986. The project
under the Forest Conservation Act, 1980 on
cost of Net Present Value of the proposed
cost of Compensatory afforestation. Further, NTPGL
towards Catchment Area Treatment with HP Forest Department.
respective compliance
Compliance Status
Complied by obtaining
Environmental Clearance
Complied by obtaining Forest
The EIA report has been prepared
in accordance with the guidelines
of this act. The proposed project
Complied by obtaining Consent to
from HPSPCB
Complied by obtaining Consent to
Complied for acquisition of
NTPGL has paid the compensation
but villagers have not received.
The matter will be resolved within
one year of release of this report
Complied. No child labour was
observed employed in the project
ESIA for 100MW Tidong1 HEP, 2011
Building and Other Construction Workers (Regulation
of Employment and Conditions of Service) Act, 1996
Himachal Pradesh Building and Other Construction
Workers (Regulation of Employment and Conditions of
Service) Rules, 2008
The Contract Labour (Regulation & Abolition) Act, 1970
and Rules
Payment of Wages Act, 1936 (Amended)
Wages Act, 1948 (Amended)
Workmen Compensation Act, 1923 as amended by
Amendment Act No.6 of 1976
Maternity Benefit Act, 1961
Employees Provident Fund Act
NTPGL has paid required amount (Rs. 11,100,000/
Department of Fisheries, Government of Himachal Pradesh.
also deposited an amount of Rs. 32,100,000/
as per the requirements of Government of Himachal Pradesh. While granting the Consent to
Establish, HP State Pollution Control Board had stipulated a condition of depositing the
environment monitoring cost for the project, the same has also been deposited.
The other requirements like labour license, NOC from Department of Fisheries, NOC from Public
Works Department, NOC from Irrigation and Public Health Dept. have been obtained by
However, application for the registration under Building and Other Construction Workers Act
has been submitted by Project
The Project proponent, to
project has paid an amount of
and Rs. 10 million to the Thangi and Rispa
committed under LADA (Local Area Development Authority), R&R Plan (Resettlement and
Rehabilitation Plan) & EMP (Environmental Management Plan) by the proponent.
IFC Requirements
As per IFC, the Tidong1 HEP falls under category A. Therefore,
Performance Standards of IFC for this project and should also ensure that the contractors /
subcontracts (subcontractors of the contracts) appointed by
performance standards on Environmental and Social Sustainab
� PS 1 :Social and Environmental Assessment and Management System
� PS 2 :Labor and working conditions
Non Technical Executive Summary
Building and Other Construction Workers (Regulation
of Employment and Conditions of Service) Act, 1996
Building and Other Construction
Workers (Regulation of Employment and Conditions of
Complied by applying for
registration
The Contract Labour (Regulation & Abolition) Act, 1970 Complied by obtaining labour
license
f Wages Act, 1936 (Amended) and Minimum
Wages Act, 1948 (Amended)
Complied by payment of
minimum wages
Workmen Compensation Act, 1923 as amended by
Amendment Act No.6 of 1976
Complied by payment of
compensation to the workers.
Maternity Benefit Act, 1961 (Amended) Complied
Employees Provident Fund Act Complied
has paid required amount (Rs. 11,100,000/) towards Fisheries development to
Department of Fisheries, Government of Himachal Pradesh. In addition to above, project has
mount of Rs. 32,100,000/ to the Local Area Development Authority (LADA)
as per the requirements of Government of Himachal Pradesh. While granting the Consent to
HP State Pollution Control Board had stipulated a condition of depositing the
onment monitoring cost for the project, the same has also been deposited.
The other requirements like labour license, NOC from Department of Fisheries, NOC from Public
Works Department, NOC from Irrigation and Public Health Dept. have been obtained by
However, application for the registration under Building and Other Construction Workers Act
has been submitted by Project and is pending with the government.
grant the compensation towards direct and indirect impacts of the
has paid an amount of Rs. 20 million each to the Gram Panchayats of
Thangi and Rispa of Moorang. This amount is apart from the provisions
committed under LADA (Local Area Development Authority), R&R Plan (Resettlement and
Rehabilitation Plan) & EMP (Environmental Management Plan) by the proponent.
1 HEP falls under category A. Therefore, NTPGL will hav
Performance Standards of IFC for this project and should also ensure that the contractors /
subcontracts (subcontractors of the contracts) appointed by NTPGL all follow the IFC
performance standards on Environmental and Social Sustainability as listed below,
PS 1 :Social and Environmental Assessment and Management System
PS 2 :Labor and working conditions
viii
Complied by applying for
Complied by obtaining labour
Complied by payment of
Complied by payment of
compensation to the workers.
) towards Fisheries development to
In addition to above, project has
the Local Area Development Authority (LADA)
as per the requirements of Government of Himachal Pradesh. While granting the Consent to
HP State Pollution Control Board had stipulated a condition of depositing the
onment monitoring cost for the project, the same has also been deposited.
The other requirements like labour license, NOC from Department of Fisheries, NOC from Public
Works Department, NOC from Irrigation and Public Health Dept. have been obtained by NTPGL.
However, application for the registration under Building and Other Construction Workers Act
grant the compensation towards direct and indirect impacts of the
to the Gram Panchayats of Thangi and Rispa
. This amount is apart from the provisions
committed under LADA (Local Area Development Authority), R&R Plan (Resettlement and
Rehabilitation Plan) & EMP (Environmental Management Plan) by the proponent.
will have to follow all the
Performance Standards of IFC for this project and should also ensure that the contractors /
all follow the IFC
as listed below,
ESIA for 100MW Tidong1 HEP, 2011
� PS 3 :Pollution prevention and Abatement
� PS 4 :Community health, safety and security
� PS 5 :Land Acquisition and Involuntary Resettl
� PS 6 :Biodiversity Conservation and Sustainable Natural Resource Management
� PS 7 :Indigenous Peoples
� PS 8 :Cultural Heritage
4. Public Consultation & D
As a part of Environmental Clearance under EIA notification,
conducted on 21 July 2006 by HP State Pollution Control Board at Village Rispa and Lambar.
residents of Village Rispa did not attend this hearing as they did not want the project road pass
through their village. The road alignment was changed accordingly.
Project has also obtained t
panchayats dated 13Jan
accorded by gram panchayats after entering into three separate
These agreements with the panchayats include the following major commitments from the
project proponent.
� Grant of the compensation towards direct and indirect impacts of the project
20 million for Thangi and Risp
� Provision of employment to project affected people in the project, based on their
qualifications and related available vacancies. A total of 38 persons from the three project
affected panchayats have been employed by
are from project affected families.
� Priority to be given to villagers in the contract works based on their ability and competitive
bidding. Already 42 no. of contracts have been given to villagers of project af
� Provision of water if any such source in the project area dries up due to project activities,
installation of street lights, compensation for loss of crops, if any, due to project activities,
pollution and dust abatement, limited blasting, etc
Another Stakeholder Consultation was conducted with members of villages, gram panchayats of
all three affected villages, district administration and other concerned government departments
as a part of Clean Development Mechanism (CDM)
Apart from the above consultations, s
during 2006 to 2011 with three affected Gram Panchayats, for seeking support for the execution
of project. About 20 consultations with the members of village and Gram Panchayat Ri
consultations with Gram Panchayat Thangi and about 10 consultations with the members of
village and Gram Panchayat Morang were conducted during the mentioned period. All the
Non Technical Executive Summary
PS 3 :Pollution prevention and Abatement
PS 4 :Community health, safety and security
PS 5 :Land Acquisition and Involuntary Resettlement
PS 6 :Biodiversity Conservation and Sustainable Natural Resource Management
PS 7 :Indigenous Peoples
Public Consultation & Disclosure
As a part of Environmental Clearance under EIA notification, 1994, a Public hearing was
06 by HP State Pollution Control Board at Village Rispa and Lambar.
residents of Village Rispa did not attend this hearing as they did not want the project road pass
The road alignment was changed accordingly.
Project has also obtained the No Object Certificates (NOCs) from Thangi, Rispa and
2009, 5Apr2009 and 1Apr2009 respectively. These NOCs were
accorded by gram panchayats after entering into three separate agreements with the
These agreements with the panchayats include the following major commitments from the
the compensation towards direct and indirect impacts of the project
million for Thangi and Rispa each and Rs. 10 million for Morang.
Provision of employment to project affected people in the project, based on their
qualifications and related available vacancies. A total of 38 persons from the three project
affected panchayats have been employed by NTPGL in the project. Out of this, 10 persons
are from project affected families.
Priority to be given to villagers in the contract works based on their ability and competitive
bidding. Already 42 no. of contracts have been given to villagers of project af
Provision of water if any such source in the project area dries up due to project activities,
installation of street lights, compensation for loss of crops, if any, due to project activities,
pollution and dust abatement, limited blasting, etc.
Another Stakeholder Consultation was conducted with members of villages, gram panchayats of
all three affected villages, district administration and other concerned government departments
Clean Development Mechanism (CDM).
above consultations, series of project specific consultations were conducted
during 2006 to 2011 with three affected Gram Panchayats, for seeking support for the execution
of project. About 20 consultations with the members of village and Gram Panchayat Ri
consultations with Gram Panchayat Thangi and about 10 consultations with the members of
village and Gram Panchayat Morang were conducted during the mentioned period. All the
ix
PS 6 :Biodiversity Conservation and Sustainable Natural Resource Management
a Public hearing was
06 by HP State Pollution Control Board at Village Rispa and Lambar. The
residents of Village Rispa did not attend this hearing as they did not want the project road pass
from Thangi, Rispa and Morang
. These NOCs were
agreements with the company.
These agreements with the panchayats include the following major commitments from the
the compensation towards direct and indirect impacts of the project amounting Rs.
Provision of employment to project affected people in the project, based on their
qualifications and related available vacancies. A total of 38 persons from the three project
in the project. Out of this, 10 persons
Priority to be given to villagers in the contract works based on their ability and competitive
bidding. Already 42 no. of contracts have been given to villagers of project affected area.
Provision of water if any such source in the project area dries up due to project activities,
installation of street lights, compensation for loss of crops, if any, due to project activities,
Another Stakeholder Consultation was conducted with members of villages, gram panchayats of
all three affected villages, district administration and other concerned government departments
eries of project specific consultations were conducted
during 2006 to 2011 with three affected Gram Panchayats, for seeking support for the execution
of project. About 20 consultations with the members of village and Gram Panchayat Rispa, 18
consultations with Gram Panchayat Thangi and about 10 consultations with the members of
village and Gram Panchayat Morang were conducted during the mentioned period. All the
ESIA for 100MW Tidong1 HEP, 2011
landowners and Panchayat members of Morang, Rispa and Thangi were consulte
representatives of IFC and AECOM during reconnaissance visit in March and April 2011.
Project representatives have also consulted with Gram Panchayat, Rispa and Tidong Valley
Paryavaran Samrakshan Vikas Samiti in Jul
enumeration of affected trees on adjacent forest land by State Forest Department along with
project representatives.
Project proponent will continue the consultation and disclosure with the stakeholders on
various developments in the project as and when they are scheduled
new excavation site shall be shared with concerned villagers, movement of oversized or
overloaded consignment expected on road shall be consulted with road users such as PWD and
villagers, induction of new batch of workforce in the project will be informed to the respective
villagers and Gram Panchayts, Diversion of water for barrage construction to be informed to all
three gram panchayts, diversion of water into HRT for before commis
all three panchayats, commissioning of project will be informed to respective government
departments, media, local NGOs and local villagers etc.
5. Grievance Redressal
In order to appreciate the primary needs
project affected families, villagers, etc and for everybody, a Grievance Redressal
be established along with the constitution of
cell is to record the grieva
employment, disputes with project activities, damages to private property, community
development needs, socio
to impacts arising out of the Project
The Grievance Redressal Cell (GRC) for this project has been partially constituted at the project
site, Project head office at Rec
Headquarter at Hyderabad. However, governmen
be incorporated. The cell structure of GRC is given below.
Site level GRC: Sr. DGM, AGM, Representatives of Village Panchyats of Morang, Rispa and Thangi
Project Head office Level GRC:
Representative of the District Administration, Representatives of Village Panchyats of Morang,
Rispa and Thangi.
Project Head Quarter Level GRC:
Corporate Level GRC: CEO and
Non Technical Executive Summary
landowners and Panchayat members of Morang, Rispa and Thangi were consulte
representatives of IFC and AECOM during reconnaissance visit in March and April 2011.
Project representatives have also consulted with Gram Panchayat, Rispa and Tidong Valley
Paryavaran Samrakshan Vikas Samiti in Jul2006. Villagers of Rispa were involved for
enumeration of affected trees on adjacent forest land by State Forest Department along with
Project proponent will continue the consultation and disclosure with the stakeholders on
in the project as and when they are scheduled such as information of any
new excavation site shall be shared with concerned villagers, movement of oversized or
overloaded consignment expected on road shall be consulted with road users such as PWD and
agers, induction of new batch of workforce in the project will be informed to the respective
villagers and Gram Panchayts, Diversion of water for barrage construction to be informed to all
three gram panchayts, diversion of water into HRT for before commissioning to be informed to
all three panchayats, commissioning of project will be informed to respective government
departments, media, local NGOs and local villagers etc.
Grievance Redressal
In order to appreciate the primary needs and address the concerns of the stakeholders including
project affected families, villagers, etc and for everybody, a Grievance Redressal
be established along with the constitution of Grievance Redressal Cell (GRC). The
record the grievances and find mutually acceptable solutions for problems like
employment, disputes with project activities, damages to private property, community
economic development of villages and any other concerns pertaining
g out of the Project etc.
The Grievance Redressal Cell (GRC) for this project has been partially constituted at the project
site, Project head office at Reckong Peo, Project Head Quarter at Shimla and Corporate
Headquarter at Hyderabad. However, government and village representatives in the GRC are to
be incorporated. The cell structure of GRC is given below.
Sr. DGM, AGM, Representatives of Village Panchyats of Morang, Rispa and Thangi
Project Head office Level GRC: Sr. DGM, AGM, Finance Representative, HR Representative,
Representative of the District Administration, Representatives of Village Panchyats of Morang,
Project Head Quarter Level GRC: Divisional Head, HR Head, SDM of the District
CEO and HR head of NSL
x
landowners and Panchayat members of Morang, Rispa and Thangi were consulted with by the
representatives of IFC and AECOM during reconnaissance visit in March and April 2011.
Project representatives have also consulted with Gram Panchayat, Rispa and Tidong Valley
were involved for joint
enumeration of affected trees on adjacent forest land by State Forest Department along with
Project proponent will continue the consultation and disclosure with the stakeholders on
such as information of any
new excavation site shall be shared with concerned villagers, movement of oversized or
overloaded consignment expected on road shall be consulted with road users such as PWD and
agers, induction of new batch of workforce in the project will be informed to the respective
villagers and Gram Panchayts, Diversion of water for barrage construction to be informed to all
sioning to be informed to
all three panchayats, commissioning of project will be informed to respective government
of the stakeholders including
project affected families, villagers, etc and for everybody, a Grievance Redressal Mechanism will
Grievance Redressal Cell (GRC). The purpose of the
solutions for problems like
employment, disputes with project activities, damages to private property, community
and any other concerns pertaining
The Grievance Redressal Cell (GRC) for this project has been partially constituted at the project
ong Peo, Project Head Quarter at Shimla and Corporate
t and village representatives in the GRC are to
Sr. DGM, AGM, Representatives of Village Panchyats of Morang, Rispa and Thangi
Representative, HR Representative,
Representative of the District Administration, Representatives of Village Panchyats of Morang,
ESIA for 100MW Tidong1 HEP, 2011
GRC formation at all levels has to be completed and made operation within next 15 days after
the release of this report.
6. Baseline Environment
Climate
The project area falls in temperate climate zone with winters from November to April and
summers from May to October. The winter season is a little extended by virtue of elevation of
the area. The summer season in itself includes the rainy season from July to September. The
transition period from April to May and from September to October corre
and autumn seasons of the area. The monthly mean of maximum daily air temperatures at Kalpa
meteorological centre varies from 24.5 to 6.1 °C. The monthly mean of minimum daily air
temperatures varies from
and 2005 was about 222 mm in 2001 and 552 mm in 2005 minimum and maximum respectively.
The annual average wind speed and direction
condition to above 15 km/ hr.
14 km/hr. During the morning the wind blows from northeast and during the evening the wind is
from southwest.
Geology
Stratigraphically the area belongs to Wantoo, Rampur and Jutogh formations.
lies in Mehbar and Maldi gneisses comprised of kyanite and psamatic gneisses with bands of
schist and quartzite. Some of the rocks are well foliated. The general trends are North
with moderate dips towards East. These are transacted
foliation and strike joints are the most predominant followed in frequency by steeply dipping
transverse joints.
Seismology
The proposed Tidong hydropower project area lies in the seismic zone
most active. However, available
Richter scale) in past 5 years.
Non Technical Executive Summary
GRC formation at all levels has to be completed and made operation within next 15 days after
Baseline Environment
The project area falls in temperate climate zone with winters from November to April and
ummers from May to October. The winter season is a little extended by virtue of elevation of
the area. The summer season in itself includes the rainy season from July to September. The
transition period from April to May and from September to October correspond to the spring
and autumn seasons of the area. The monthly mean of maximum daily air temperatures at Kalpa
meteorological centre varies from 24.5 to 6.1 °C. The monthly mean of minimum daily air
2.9 to 12.1 °C. Annual rainfall recorded in Moorang
was about 222 mm in 2001 and 552 mm in 2005 minimum and maximum respectively.
nnual average wind speed and direction for synoptic hours refer varies from calm
condition to above 15 km/ hr. the majority of the time the wind velocity is more than lower than
14 km/hr. During the morning the wind blows from northeast and during the evening the wind is
Stratigraphically the area belongs to Wantoo, Rampur and Jutogh formations.
lies in Mehbar and Maldi gneisses comprised of kyanite and psamatic gneisses with bands of
schist and quartzite. Some of the rocks are well foliated. The general trends are North
with moderate dips towards East. These are transacted by a number of joints of which the
foliation and strike joints are the most predominant followed in frequency by steeply dipping
The proposed Tidong hydropower project area lies in the seismic zoneIV, where Zone V is the
available data suggests that there were only three low intensity (less 4.0
Richter scale) in past 5 years.
xi
GRC formation at all levels has to be completed and made operation within next 15 days after
The project area falls in temperate climate zone with winters from November to April and
ummers from May to October. The winter season is a little extended by virtue of elevation of
the area. The summer season in itself includes the rainy season from July to September. The
spond to the spring
and autumn seasons of the area. The monthly mean of maximum daily air temperatures at Kalpa
meteorological centre varies from 24.5 to 6.1 °C. The monthly mean of minimum daily air
l recorded in Moorang between 2001
was about 222 mm in 2001 and 552 mm in 2005 minimum and maximum respectively.
for synoptic hours refer varies from calm
e time the wind velocity is more than lower than
14 km/hr. During the morning the wind blows from northeast and during the evening the wind is
Stratigraphically the area belongs to Wantoo, Rampur and Jutogh formations.The project area
lies in Mehbar and Maldi gneisses comprised of kyanite and psamatic gneisses with bands of
schist and quartzite. Some of the rocks are well foliated. The general trends are NorthSouth
by a number of joints of which the
foliation and strike joints are the most predominant followed in frequency by steeply dipping
, where Zone V is the
data suggests that there were only three low intensity (less 4.0
ESIA for 100MW Tidong1 HEP, 2011
Hydrology
Tidong is primarily a snow fed stream. It also receives inflow from rainfall and snowfall.
catchment area of Tidong at proposed barrage site is about 571 sq km, out of which about 95%
is above permanent snowline (EL 4200m), which is either stony or snowbound area.
Discharged data as 10 days average flow of Tidong River at the proposed barrage site between
Dec2004 and Jul2010 suggests
4.53 cumec and the maximum flow of 75.149 cumec in July 2006.
is calculated at 2889.40 msl and at Tail Race it has been calculated as 2250 msl
Table 2: Mean Monthly flow of Discharge data (Dec 2004 to July 2010)
Month
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
The 6 years average minimum and maximum discharge recorded at the barrage site between
December 2004 and July 2010 is given in
Water Quality
Surface water in the form of streams, rivers and springs is the main source of water in the area.
Most of them are semiperennial in nature being fed by the glaciers.
parameters measured during the EIA study (2005) conforms to the drinking water standards (
105001991).
Non Technical Executive Summary
Tidong is primarily a snow fed stream. It also receives inflow from rainfall and snowfall.
Tidong at proposed barrage site is about 571 sq km, out of which about 95%
is above permanent snowline (EL 4200m), which is either stony or snowbound area.
Discharged data as 10 days average flow of Tidong River at the proposed barrage site between
2010 suggests that the minimum flow observed was on January 2005 and is
4.53 cumec and the maximum flow of 75.149 cumec in July 2006. Highest flood level at Barrage
is calculated at 2889.40 msl and at Tail Race it has been calculated as 2250 msl
: Mean Monthly flow of Discharge data (Dec 2004 to July 2010)
Min Max
6.11 6.67
6.04 6.47
6.51 7.34
6.79 9.50
11.39 16.18
16.23 40.41
40.41 54.68
61.95 47.28
59.60 20.22
34.14 7.95
14.43 6.51
7.74 6.08
The 6 years average minimum and maximum discharge recorded at the barrage site between
December 2004 and July 2010 is given in Table 2.
Surface water in the form of streams, rivers and springs is the main source of water in the area.
perennial in nature being fed by the glaciers. All the w
parameters measured during the EIA study (2005) conforms to the drinking water standards (
xii
Tidong is primarily a snow fed stream. It also receives inflow from rainfall and snowfall. The total
Tidong at proposed barrage site is about 571 sq km, out of which about 95%
is above permanent snowline (EL 4200m), which is either stony or snowbound area.
Discharged data as 10 days average flow of Tidong River at the proposed barrage site between
he minimum flow observed was on January 2005 and is
Highest flood level at Barrage
is calculated at 2889.40 msl and at Tail Race it has been calculated as 2250 msl.
The 6 years average minimum and maximum discharge recorded at the barrage site between
Surface water in the form of streams, rivers and springs is the main source of water in the area.
All the water quality
parameters measured during the EIA study (2005) conforms to the drinking water standards (IS
ESIA for 100MW Tidong1 HEP, 2011
Ecology
Flora: The major forest type of the project area is temperate mixed evergreen forest. A total
number of 94 plant species were r
diversity of the project area
herbs including 6 species of climbers and 8 species of grasses.
The habitats were dominated by
of the tree species are very old and their girth ranged from 3
Parts of many wild plants available in the forest
raw. These include fruits of
which are eaten raw. In addition to these, leaves of certain wild plant species provide good
source of minerals in the diet of the local people.
Rumex nepalensis, and Urtica dioica
area are not classified as threatened
Fauna: Catchment area of Tidong Hydropower project is inhabited by more than 13 speci
mammals which together constitute around 8 families. Most of the species are restricted to the
high altitudes of Himalayas.
(Panthera uncia) were noticed in the area.
other endangered species namely M
endangered of all the species of deer.
endangered species as per
The catchment area of Tidong H
it harbours nearly 40 species of birds comprising of Kite, Vulture, Chukor partridge, Tragopan,
Monal, Pigeons, Parakeet, Owl, Hoo
Crow, Bulbuls, Flycatcher, Redstart, Chat, Thrushes, Tits, Wagtails, Sparrows, Finches, buntings,
etc.
The species of Snow trout (
present at the sampling site very close to the confluence of Tidong Khad and Satluj River and at
the lowest altitude (2,260 m above m.s.l.) of the Project area.
fishes was recorded based on a one month study in September 20
richardsonii) has been included in the IUCN Red List of threatened species
conservation status of Salmo trutta fario
Alternative analysis
The project was envisaged and initial site selection was undertaken by the state government.
NTPGL was awarded the project at the site chosen by the state government and therefore did
Non Technical Executive Summary
The major forest type of the project area is temperate mixed evergreen forest. A total
number of 94 plant species were recorded during the floristic survey in the project area. Plant
diversity of the project area include 20 species of trees, 30 species of shrubs and 30 species of
herbs including 6 species of climbers and 8 species of grasses.
dominated by a dense forest of Pinus gerardiana and Cedrus deodara
of the tree species are very old and their girth ranged from 37m.
available in the forest are used by local people as vegetables or eaten
raw. These include fruits of Juglans regia, Pyrus malus, Prunus armeniaca and
which are eaten raw. In addition to these, leaves of certain wild plant species provide good
source of minerals in the diet of the local people. Amaranthus viridis, Chenopodium album,
Urtica dioica are important plant source of minerals.
threatened in the IUCN Red List of Threatened Species
Catchment area of Tidong Hydropower project is inhabited by more than 13 speci
mammals which together constitute around 8 families. Most of the species are restricted to the
high altitudes of Himalayas. During the EIA study conducted in 2005, pugmarks of Snow leopard
) were noticed in the area. Tidong area is also reported to be the habitat of two
other endangered species namely Musk Deer and Himalayan Brown Bear. Musk deer is the most
endangered of all the species of deer. The Snow Leopard and musk Deer has been classified as
IUCN Red List of Threatened Species.
The catchment area of Tidong HEP is poor in avifaunal species richness. Including influence zone
it harbours nearly 40 species of birds comprising of Kite, Vulture, Chukor partridge, Tragopan,
Monal, Pigeons, Parakeet, Owl, Hoopoe, Woodpeckers, Martin, Swallow, Shrike, Magpie, cough,
Crow, Bulbuls, Flycatcher, Redstart, Chat, Thrushes, Tits, Wagtails, Sparrows, Finches, buntings,
he species of Snow trout (Schizothorax richardsonii) and Brown trout (Salmo trutta fario
present at the sampling site very close to the confluence of Tidong Khad and Satluj River and at
the lowest altitude (2,260 m above m.s.l.) of the Project area. In other two upstream sites no
based on a one month study in September 2005. Snow trout (
has been included in the IUCN Red List of threatened species
Salmo trutta fario has not been evaluated by IUCN.
The project was envisaged and initial site selection was undertaken by the state government.
was awarded the project at the site chosen by the state government and therefore did
xiii
The major forest type of the project area is temperate mixed evergreen forest. A total
ecorded during the floristic survey in the project area. Plant
0 species of trees, 30 species of shrubs and 30 species of
Cedrus deodara. Most
are used by local people as vegetables or eaten
Rosa macrophylla
which are eaten raw. In addition to these, leaves of certain wild plant species provide good
Amaranthus viridis, Chenopodium album,
Species found the
IUCN Red List of Threatened Species.
Catchment area of Tidong Hydropower project is inhabited by more than 13 species of
mammals which together constitute around 8 families. Most of the species are restricted to the
During the EIA study conducted in 2005, pugmarks of Snow leopard
so reported to be the habitat of two
sk Deer and Himalayan Brown Bear. Musk deer is the most
The Snow Leopard and musk Deer has been classified as
is poor in avifaunal species richness. Including influence zone
it harbours nearly 40 species of birds comprising of Kite, Vulture, Chukor partridge, Tragopan,
poe, Woodpeckers, Martin, Swallow, Shrike, Magpie, cough,
Crow, Bulbuls, Flycatcher, Redstart, Chat, Thrushes, Tits, Wagtails, Sparrows, Finches, buntings,
Salmo trutta fario) were
present at the sampling site very close to the confluence of Tidong Khad and Satluj River and at
In other two upstream sites no
Snow trout (Schizothorax
has been included in the IUCN Red List of threatened species. However, the
The project was envisaged and initial site selection was undertaken by the state government.
was awarded the project at the site chosen by the state government and therefore did
ESIA for 100MW Tidong1 HEP, 2011
not have much of options
were carried out by the project authority w.r.t. alignment of HRT and access r
environmental and social impacts.
The access road to the power was initially designe
However, due to the social concerns expressed Villagers of Rispa the
redesigned on the right bank near Village Moorang.
Non Technical Executive Summary
options for alternate sites. However, some modifications
were carried out by the project authority w.r.t. alignment of HRT and access r
environmental and social impacts. The HRT was aligned on the left bank instead of right bank.
The access road to the power was initially designed on the left bank through Village Rispa.
However, due to the social concerns expressed Villagers of Rispa the road
redesigned on the right bank near Village Moorang.
xiv
s in project layout
were carried out by the project authority w.r.t. alignment of HRT and access road to reduce
The HRT was aligned on the left bank instead of right bank.
d on the left bank through Village Rispa.
road alignment was
ESIA for 100MW Tidong1 HEP, 2011
7. Key Environmental, Health & Safety (EHS) I
Electric Project
7.1 Impacts Due to Project Construction
Aspect Impact Mitigation Measure
Flora Loss of
Biodiversity
Plantation in double the area than that has been
acquired for the project
Plantation of diverse species to maintain biodiversity
Provision of free fuel to workers to avoid further
degradation of forest
Loss of wood Plantation
Terrestrial
Fauna
Wildlife may
get scared due
to ground
vibrations
during blasting
and migrate to
other areas
causing altered
preypredator
ratio
Increase the
animals and
Create awareness
of animal density in the forest adjoining areas
Controlled blasting practices to reduce ground vibration
Non Technical Executive Summary xv
Environmental, Health & Safety (EHS) Impacts and Mitigations due to Tidong
Mitigation Measure Schedule
Construction Operation
Plantation in double the area than that has been
acquired for the project
Plantation of diverse species to maintain biodiversity
Provision of free fuel to workers to avoid further
degradation of forest
Increase the forest area to accommodate scared
animals and improve habitat;
Create awareness amongst villagers on cause and effect
of animal density in the forest adjoining areas.
Controlled blasting practices to reduce ground vibration
1 Hydro
Management
PlanOperation
Compensatory
Afforestation (CA)
on 79 ha. forest
land by HP Forest
Department
Afforestation as a
part of Catchment
Area Treatment
(CAT) Plan
Construction
Labour
Management Plan
CA & CAT Plan
Compensatory
afforestation
CAT Plan
Pollution
Abatement Plan
ESIA for 100MW Tidong1 HEP, 2011
Retribution
killing
Training to local population for wildlife protection
Increased
possibility of
poaching of
wild animals
due to
increased
accessibility
and increase in
labour
population
Intensive patrolling for anti
the forest department;
Surveillance and restriction on movement of workers
within project area;
Intimation to forest department for sterilization of feral
dogs, in case they are noticed in the vicinity of the
human habitation, labour
Aquatic Fauna Water
pollution (TSS)
causing
decrease in
fish population
Wastewater from underground works to be treated for
silt removal before discharging in the stream
Muck to be disposed only in designated areas and
maintenance of the disposal structures to avoid breachs.
Protection of exposed earth from surface runoff
Landuse
pattern
Change in land
use pattern of
permanent and
temporary
type
A systematic land development plan to be prepared by
NTPGL
areas such as muck disposal area, batching plant, labour
camp, quarry sites, etc.
As general practice all the closed sites to be seeded with
grass to prevent air and water pollution.
Non Technical Executive Summary xvi
Training to local population for wildlife protection
Intensive patrolling for antipoaching with the help of
the forest department;
Surveillance and restriction on movement of workers
within project area;
Intimation to forest department for sterilization of feral
dogs, in case they are noticed in the vicinity of the
human habitation, labour camps.
Wastewater from underground works to be treated for
silt removal before discharging in the stream
Muck to be disposed only in designated areas and
maintenance of the disposal structures to avoid breachs.
Protection of exposed earth from surface runoff
A systematic land development plan to be prepared by
NTPGL for ecorestoration of temporarily changed land
areas such as muck disposal area, batching plant, labour
camp, quarry sites, etc.
As general practice all the closed sites to be seeded with
ss to prevent air and water pollution.
Provisions in CAT
Plan
Terrestrial Ecology
Management Plan
Pollution
Abatement Plan
Erosion
abatement and
muck/ spoil
management plan
ESIA for 100MW Tidong1 HEP, 2011
Erosion and
Siltation
Erosion of
excavated area
Siltation from
excavated area
Tunnel discharge to be provided with retention tanks to
hold water for at least 2
discharge into Tidong stream
All the excavated areas should be protected through
garland drains to avoid siltation of adjacent area from
surface runoff.
Slopes in the excavated areas to be protected against
sliding throug
exceeds beyond 3 meters
Silt arrested in
into the river at periodic intervals only during high
discharge seasons
Provision of a
trace cutting works
Silt reduction measures in the catchment area.
Earthquake Flooding in
Tidong stream
due to breach
of reservoir
wall in case of
high intensity
earthquakes
Suitable design to with stand high intensity earth quakes
with adequate safety factor
Modified
months from release of this report.
Water sources Drying of water
stream and
springs in the
tunnel
alignment
HRT has been designed to obtain a thick rock cover of
about 157 m to minimize the impacts on Gara Khad,
Duba Khad, and other springs along the tunnel
alignment.
In case of drying of water
compensate the water users by the providing piped
water.
Non Technical Executive Summary xvii
Tunnel discharge to be provided with retention tanks to
hold water for at least 2 hours for silt elimination before
discharge into Tidong stream
All the excavated areas should be protected through
garland drains to avoid siltation of adjacent area from
surface runoff.
Slopes in the excavated areas to be protected against
sliding through benching if the height of the excavation
exceeds beyond 3 meters
Silt arrested in desilting chambers to be flushed back
into the river at periodic intervals only during high
discharge seasons
Provision of adequate retaining wall or breast wall for all
ace cutting works during road construction.
Silt reduction measures in the catchment area.
Suitable design to with stand high intensity earth quakes
with adequate safety factor
Modified Emergency Preparedness Plan (EPP) within two
months from release of this report.
HRT has been designed to obtain a thick rock cover of
about 157 m to minimize the impacts on Gara Khad,
Duba Khad, and other springs along the tunnel
alignment.
In case of drying of water sources, project proponent to
compensate the water users by the providing piped
water.
Pollution
Abatement Plan
Erosion
Abatement and
Muck/ spoil
Management Plan
CAT plan
Emergency
Preparedness Plan
Project design
ESIA for 100MW Tidong1 HEP, 2011
Ambient Air
Quality
Air Pollution
due to
fugitive
emissions from
construction
activities
burning of
fossil fuel in
equipment,
vehicles, and
DG Sets
Water sprinkling on project PWD roads to
fugitive dust emission due to the movement of vehicles..
Grading operation to be suspended when the wind
speed exceeds 20 km /hr.
All storage piles to
with plastic sheets to ensure the protection of ambient
air from fugitive emission during high wind.
All the stone crushers to be have water sprinkler at the
dust generating points.
The DG sets to confirm to the emission n
Ambient Noise
level
Health effect
on workers due
to drilling,
blasting,
concrete
mixing, casting,
material
movement etc.
Provision of adequate acoustic enclosure
high n
Regular maintenance of noise generating equipment of
vehicles.
Limiting high noise works and material transport during
day time only.
Restriction on pressure horns.
Provision of ear plugs to the construction workers
Non Technical Executive Summary xviii
Water sprinkling on project PWD roads to suppress the
fugitive dust emission due to the movement of vehicles..
Grading operation to be suspended when the wind
speed exceeds 20 km /hr.
All storage piles to be adequately wetted or covered
with plastic sheets to ensure the protection of ambient
air from fugitive emission during high wind.
All the stone crushers to be have water sprinkler at the
dust generating points.
The DG sets to confirm to the emission norms of HPPCB
Provision of adequate acoustic enclosure and muffler on
oise generating equipment.
Regular maintenance of noise generating equipment of
vehicles.
Limiting high noise works and material transport during
day time only.
Restriction on pressure horns.
Provision of ear plugs to the construction workers
Pollution
Abatement Plan
Pollution
Abatement Plan
ESIA for 100MW Tidong1 HEP, 2011
Surface water
quality
Water
pollution due
wastewater
discharge in
the Tidong
stream from
labour camps,
offices, staff
colony and
open
defecation
Segregation of storm water and domestic water drains.
Provision of Toilets and Bathrooms in the labour camps,
work area
Septic tank to be provided for treatment of wastewater
at labour camps and work areas.
Once the septic tank is full, it should be cleaned and
collected sludge to be disposed to composting facility at
Shimla. Alternatively, another septic
for sewage and abandon the old septic tank after
complete utilization.
No discharge from the septic tanks.
Adequate garbage management system to protect the
contamination of storm water;
Reduction in
photosynthetic
efficiency due
to high
turbidity
caused by
untreated
discharge from
tunnels,
construction
wastes, muck
slide from
breached
retaining walls
of muck
disposal area.
Tunnel discharge to be
Muck to be disposed i
Muck disposal areas protected with gabion walls against
any possible slide/slope failure.
Monitored the protection walls to identify the breach in
the initial stage. The breached found to be repaired
immediately
vegetation after leveling and dressing once the
dumping is completed.
Non Technical Executive Summary xix
Segregation of storm water and domestic water drains.
Provision of Toilets and Bathrooms in the labour camps,
work areas and offices.
Septic tank to be provided for treatment of wastewater
at labour camps and work areas.
Once the septic tank is full, it should be cleaned and
collected sludge to be disposed to composting facility at
Shimla. Alternatively, another septic tank to be provided
for sewage and abandon the old septic tank after
complete utilization.
No discharge from the septic tanks.
Adequate garbage management system to protect the
contamination of storm water;
Tunnel discharge to be treated in sedimentation tanks.
Muck to be disposed in the designated area.
Muck disposal areas protected with gabion walls against
any possible slide/slope failure.
Monitored the protection walls to identify the breach in
the initial stage. The breached found to be repaired
immediately Muck disposal sites to be restored with
vegetation after leveling and dressing once the
dumping is completed.
Pollution
Abatement Plan
Pollution
Abatement Plan
ESIA for 100MW Tidong1 HEP, 2011
Health Generation of
disease vectors
due to garbage
accumulation
in and around
the project
area
Garbage bins should be
labour camps, offices and staff colony to collect organic,
plastic, glass and other garbage separately;
All the waste from project area to be collected by
and incinerated through installed specifically for this
purpose;
The double
control equipment to meet all the air quality
standards as prescribed by the Central Pollution
Control Board;
Metals, plastics and glasses in the garbage will be sold to
vendors;
Generation of
disease vectors
due
accumulation
of domestic
wastewater in
and around the
project area
Proper leveling of the site and provision of drainage
Measures suggested to protect surface water quality
from domestic wastewater
water quality section.
Possible spread
of diseases due
to migratory
workforce
Provision of safe drinking water,
facilities
Mandatory
workforces by
A Primary Health Centre (PHC) near staff colony at
Morang
PHC to
villagers of Morang, Lamb
Non Technical Executive Summary xx
Garbage bins should be provided at different places in
labour camps, offices and staff colony to collect organic,
plastic, glass and other garbage separately;
All the waste from project area to be collected by NTPGL
and incinerated through installed specifically for this
purpose;
The double chambered incinerator with air pollution
control equipment to meet all the air quality
standards as prescribed by the Central Pollution
Control Board;
Metals, plastics and glasses in the garbage will be sold to
vendors;
Proper leveling of the site and provision of drainage
Measures suggested to protect surface water quality
from domestic wastewater as referred above in Surface
water quality section.
Provision of safe drinking water, good sanitation
facilities, garbage management and healthcare facilities.
Mandatory Preemployment health checkup for entire
workforces by NTPGL and contractors.
A Primary Health Centre (PHC) near staff colony at
Morang to be operated and maintained by NTPGL. The
to provide free treatment and medicines to the
villagers of Morang, Lambar and Rispa villages.
Construction
Labour
Management Plan
Pollution
Abatement Plan
Public Health and
Occupational
Safety
Management Plan
ESIA for 100MW Tidong1 HEP, 2011
Traffic Traffic
congestion
Planning of logistics in coordination with local police and
PWD, for oversized and overload project equipment and
vehicles.
Widening of roads and
coordination of PWD at strategic points if required.
Deployment of traffic coordinators at congestion points
on the PWD road from NH
the project vehicle movements from the area.
Probability of
increase in
accidents
Training to drivers for defensive driving
Training to villagers regarding requirements of vehicle
movement, possible human mistakes.
Training of villagers on first aid and provision of first aid
boxes in villages on the traffic routes.
7.2 Impacts Due to Project Operation
Aspect Impact
Conservation
of Natural
Resources
Conservation of fossil fuel
Air
Environment
Avoidance of about 3.3
million tons of CO2
emissions in addition to
other pollutants like SO2,
NOx, CO etc. from burning
fossil fuel per year
Non Technical Executive Summary xxi
Planning of logistics in coordination with local police and
PWD, for oversized and overload project equipment and
vehicles.
Widening of roads and strengthening of bridges in
coordination of PWD at strategic points if required.
Deployment of traffic coordinators at congestion points
on the PWD road from NH22 to village lambar during
the project vehicle movements from the area.
Training to drivers for defensive driving
Training to villagers regarding requirements of vehicle
movement, possible human mistakes.
Training of villagers on first aid and provision of first aid
boxes in villages on the traffic routes.
Mitigation Measure Schedule
Construction Operation
The impact is likely to be beneficial therefore
no mitigation measures required
The impact is likely to be beneficial therefore
no mitigation measures required
Traffic
Management Plan
Traffic
Management Plan
Management
PlanOperation
Not required
Not required
ESIA for 100MW Tidong1 HEP, 2011
Water
Environment
Pollution in Tidong river due
to discharge from staff colony
Waste
Generation
Pollution of land and surface
water
Fauna Return of wildlife in the
adjacent forest which might
have moved away from the
project site due to blasting.
Systematic ecological order in
absence of construction
workers;.
Improve in ecology due to
Implementation of
Compensatory Afforestation,
Catchment Area Treatment
Plan, Fisheries Management
Plan and absence of labour
force.
Non Technical Executive Summary xxii
colony
Domestic wastewater from the staff colony
will be treated in Sewage Treatment Plant to
meet the regulatory standards before
discharge.
Proper waste collection, transportation and
incineration through incinerator
Return of wildlife in the
which might
have moved away from the
in
absence of construction
Improve in ecology due to
Implementation of
Compensatory Afforestation,
Catchment Area Treatment
Plan, Fisheries Management
and absence of labour
Timely completion of CA and CAT.
Waste
Management Plan
Follow up with
Forest and
Fisheries
department
ESIA for 100MW Tidong1 HEP, 2011
Aquatic Fauna Impact due to reduced
flow.
Adverse impact on
spawning of fishes
Adverse impact on
survival of Fry which
may fall prey to birds
in shallow waters
Mortality of fry due to
change in water
temperature
Forests Reduction of deforestation
due to replacement of
firewood with electricity
generated by hydro power
projects and decreased
labour force
Increase illegal entries into
the forests due to improved
access through project roads;
Increased pressure on the
forest resources due to
increased human activity in
the area.
Non Technical Executive Summary xxiii
Mortality of fry due to
NTPGL has deposited money to
Directorate of Fisheries, Government of
Himachal Pradesh for Fisheries
Development Plan. The plan includes
development of fish farm at Sangla,
sustainable fisheries in Tiding1 reservoir
and adequate replacement of riverine fish
fauna through stocking.
Engagement of reputed fisheries
expert/institution to understand the
impact of fishes due to reduced flow.
deforestation
due to replacement of
firewood with electricity
generated by hydro power
projects and decreased
The impact is likely to be beneficial therefore
no mitigation measures required.
into
due to improved
access through project roads;
pressure on the
resources due to
increased human activity in
HP Forest department to improve
surveillance
NTPGL to depute security personnel to
check the forest entrants from the project
areas.
Aquatic Ecology
Management Plan
Not required
Terrestrial Ecology
Management Plan
ESIA for 100MW Tidong1 HEP, 2011
8. Key Social Impacts and Mitigation
Aspect Impact Mitigation Measure
Recreation
and Tourism
Improvement
in recreation
and tourism
potential
The impact is
measures required.
Tourism will increase money circulation and benefit the
villagers.
Ancillary
Development
Improved
Ancillary
development
The impact is likely to be beneficial
measures required.
Infrastructure Improvement
of
infrastructure
like better
roads,
availability of
electricity
The impact is likely to be beneficial
measures required.
Provision of 1% free power to state government for Local
Area Development for providing regular stream of revenue
for income generation and welfare schemes, creation of
additional infrastructure and common facilities.
Physical or
economic
displacement
of people due
to acquisition
of private land
Adverse impact
on livelihood of
villagers due to
loss of private
land
NTPGL
amount to the villagers as decided by the court in
response to the petition filed by
R&R Plan
NTPGL
Non Technical Executive Summary xxiv
itigations due to Tidong1 Hydro Electric Project
Mitigation Measure Schedule
Construction Operation
impact is likely to be beneficial therefore no mitigation
measures required.
will increase money circulation and benefit the
impact is likely to be beneficial therefore no mitigation
measures required.
impact is likely to be beneficial therefore no mitigation
measures required.
Provision of 1% free power to state government for Local
Area Development for providing regular stream of revenue
for income generation and welfare schemes, creation of
additional infrastructure and common facilities.
NTPGL will provide additional compensation
amount to the villagers as decided by the court in
response to the petition filed by the villagers
R&R Plan to be prepared and implemented by
NTPGL
Management
PlanOperation
Not Required
Not Required
Not Required
Preparation of
R&R Plan and its
implementation
within one year
from the date of
release of this
report.
ESIA for 100MW Tidong1 HEP, 2011
Diversion of
forest land
Adverse impact
on livelihood of
villagers due to
loss of Non
Timber Forest
Produce (NTFP)
Compensation towards loss of NTFP produced to be
paid to villagers.
Local Culture Conflicts with
the migrant
population
Provision of Labour camps to accommodate all the
workers within the project area to avoid their stay in
villages;
Training to contractors about social obligations of
NTPGL
Social obligations of
conditions in the contact document;
Contractors to have a Community Officer (CO) for all
community interaction on behalf of the contractor.
NTPGL
contractors and ensure consistency in approach to
communicating
resolving grievances.
Employment
Opportunities
Improvement
in employment
opportunities
Training to villagers to avail employment opportunities
Non Technical Executive Summary xxv
Compensation towards loss of NTFP produced to be
paid to villagers.
Provision of Labour camps to accommodate all the
workers within the project area to avoid their stay in
villages;
Training to contractors about social obligations of
NTPGL prior to award of contract;
Social obligations of NTPGL to be a part of
conditions in the contact document;
Contractors to have a Community Officer (CO) for all
community interaction on behalf of the contractor.
NTPGL to appoint a Social Officer to interact with
contractors and ensure consistency in approach to
communicating with the Community and in
resolving grievances.
Training to villagers to avail employment opportunities
Preparation of
R&R Plan and its
implementation
within one year
from the date of
release of this
report.
Construction
Labour
Management Plan
Socioeconomic
Management Plan
ESIA for 100MW Tidong1 HEP, 2011
9. Key EHS & Social I
Line
A Transmission line of 220kV DC capacity is envisaged for evacuation of power from
Tidong1 and the stretch from Kashang to Tidong
facility’ as per IFC guidelines. Himachal Pradesh Power Transmission Corporation
Limited (HPPTCL), a State Transmission Utility, will construct and operate this facility and
will charge NRPPL for wheeling. The land acquisition for the same will also be c
by HPPTCL. Execution of this associated facility may have impact due to diversion of
forest land, due to acquisition of private land, involuntary displacement, health impacts,
community conflict, labour involvement, tree felling, etc. However, t
be estimated as the routing of the routing of the transmission line is yet to be finalized.
Mitigation
The Tidong1 to Kashang line is under planning stage and the routing will be decided
after the study is complete. As per the norms of H
will be tentatively proposed and the route with the least environmental and social
impact will be chosen for construction and operation. The final decision on the line
routing is yet to be taken. HPPTCL has received
Transmission Investment Programme and have formulated an Environmental and Social
Safeguard Policy. The construction of the transmission line is likely to be monitored by
ADB as per the Environmental Framework Policy.
HEP, 2011 Non Technical Executive Summary
EHS & Social Impacts and Mitigations due to Transmission
A Transmission line of 220kV DC capacity is envisaged for evacuation of power from
1 and the stretch from Kashang to Tidong1 HEP is considered as an ‘associated
facility’ as per IFC guidelines. Himachal Pradesh Power Transmission Corporation
Limited (HPPTCL), a State Transmission Utility, will construct and operate this facility and
will charge NRPPL for wheeling. The land acquisition for the same will also be c
by HPPTCL. Execution of this associated facility may have impact due to diversion of
forest land, due to acquisition of private land, involuntary displacement, health impacts,
community conflict, labour involvement, tree felling, etc. However, t
be estimated as the routing of the routing of the transmission line is yet to be finalized.
1 to Kashang line is under planning stage and the routing will be decided
after the study is complete. As per the norms of Himachal Pradesh, initially three routes
will be tentatively proposed and the route with the least environmental and social
impact will be chosen for construction and operation. The final decision on the line
routing is yet to be taken. HPPTCL has received loan from ADB under the Clean Energy
Transmission Investment Programme and have formulated an Environmental and Social
Safeguard Policy. The construction of the transmission line is likely to be monitored by
ADB as per the Environmental Framework Policy.
Non Technical Executive Summary xxvi
s due to Transmission
A Transmission line of 220kV DC capacity is envisaged for evacuation of power from
1 HEP is considered as an ‘associated
facility’ as per IFC guidelines. Himachal Pradesh Power Transmission Corporation
Limited (HPPTCL), a State Transmission Utility, will construct and operate this facility and
will charge NRPPL for wheeling. The land acquisition for the same will also be carried out
by HPPTCL. Execution of this associated facility may have impact due to diversion of
forest land, due to acquisition of private land, involuntary displacement, health impacts,
community conflict, labour involvement, tree felling, etc. However, the impact cannot
be estimated as the routing of the routing of the transmission line is yet to be finalized.
1 to Kashang line is under planning stage and the routing will be decided
imachal Pradesh, initially three routes
will be tentatively proposed and the route with the least environmental and social
impact will be chosen for construction and operation. The final decision on the line
loan from ADB under the Clean Energy
Transmission Investment Programme and have formulated an Environmental and Social
Safeguard Policy. The construction of the transmission line is likely to be monitored by
ESIA for 100MW Tidong1 HEP, 2011
10. Rehabilitation and Resettlement
The private land 3.0211 ha. was acquired through Land Acquisition Act, 1894. Though the
project has extended several benefits like jobs, petty contracts to the local villagers and the
affected families, no systematic R&R Plan was implemented. AECOM has suggested an
entitlement framework in spirit of National Rehabilitation and Resettlement Policy, 2007. A R&R
Plan need to be drawn and implemented by the project based on the entitlement framework as
given below,
Table 3: Entitlement Framework for R&R
Sl.
No.
Entitlement
Resettlement Grant
1 One time grant for
construction of working shed
or shop
2 One time grant for
construction of cattle shed
3 One time grant for shifting of
the family, building materials,
belongings and cattle
Employment & Skill Development
4 Preference in providing
employment in the project,
subject to the availability of
vacancies and suitability,
5 project proponent will arrange
for training
6 offer scholarships and other
skill development
opportunities
7 rehabilitation grant
8 Monthly subsistence allowance
for a period of one (1) year
from the date of displacement
9 Monthly pension for the life,
through Annuity Policy by
NTPGL
10 Exgratia
HEP, 2011 Non Technical Executive Summary
Rehabilitation and Resettlement
The private land 3.0211 ha. was acquired through Land Acquisition Act, 1894. Though the
project has extended several benefits like jobs, petty contracts to the local villagers and the
no systematic R&R Plan was implemented. AECOM has suggested an
entitlement framework in spirit of National Rehabilitation and Resettlement Policy, 2007. A R&R
Plan need to be drawn and implemented by the project based on the entitlement framework as
Entitlement Framework for R&R
Minimum Amount (Rs.) Who all covered
construction of working shed
37,000/ Rural artisan, small trader or
person and is a financially or physically
displaced person
construction of cattle shed
22,000/ Affected family if has lost cattle shed /
structure and owns cattle
One time grant for shifting of
materials,
belongings and cattle
15,000/ Each affected family if displaced physically
Employment & Skill Development
Preference in providing
employment in the project,
subject to the availability of
vacancies and suitability,
At least one person per nuclear family of
the affected families whose land has been
acquired for the Project or whose
livelihood was dependent on the private
land acquired for the project,
project proponent will arrange The affected persons, so as to enable such
persons to take on suitable jobs
offer scholarships and other To the eligible persons from the affected
families
500 days current
minimum agricultural
wages
Affected families whose land has been
acquired for the project or whose
livelihood was dependent on the private
land acquired for the project
Monthly subsistence allowance
for a period of one (1) year
from the date of displacement
25 days minimum
agricultural wages per
month
Affected family
acquired for the Project or whose
livelihood was dependent on the private
land acquired for the project
Monthly pension for the life,
through Annuity Policy by
750/ Vulnerable affected persons
30,000/ Each affected family whose only a narrow
stretch of land is acquired for the linear
Non Technical Executive Summary xxvii
The private land 3.0211 ha. was acquired through Land Acquisition Act, 1894. Though the
project has extended several benefits like jobs, petty contracts to the local villagers and the
no systematic R&R Plan was implemented. AECOM has suggested an
entitlement framework in spirit of National Rehabilitation and Resettlement Policy, 2007. A R&R
Plan need to be drawn and implemented by the project based on the entitlement framework as
Who all covered
ural artisan, small trader or selfemployed
person and is a financially or physically
displaced person
ffected family if has lost cattle shed /
structure and owns cattle
Each affected family if displaced physically
t least one person per nuclear family of
the affected families whose land has been
acquired for the Project or whose
livelihood was dependent on the private
land acquired for the project,
persons, so as to enable such
persons to take on suitable jobs
o the eligible persons from the affected
d families whose land has been
acquired for the project or whose
livelihood was dependent on the private
land acquired for the project
Affected family whose land has been
acquired for the Project or whose
livelihood was dependent on the private
land acquired for the project
Vulnerable affected persons
Each affected family whose only a narrow
stretch of land is acquired for the linear
ESIA for 100MW Tidong1 HEP, 2011
11 The affected families may be
given the option to take a
lumpsum amount in lieu of
one or more of the benefits as
entitled and specified in the
framework.
12 Fishing rights in the reservoir
area of the irrigation or hydel
projects.
Secondary Employment
13 Preference in the allotment of
outsourced contracts, shops or
other economic opportunities
coming up in or around the
project site
14 Preference while engaging
labourers in the project during
the construction phase
15 Necessary training facilities for
development of
entrepreneurship, technical
and professional skills for self
employment
Entitlement for Community
16 Compensation towards NTFP
including chilgoza, fuelwood,
fodder lost from grazing land
along the river in the upstream
work of the project, and other
forest produces including on
account of the involuntary
nature of loss of access to the
forests/customary rights, of
the 39.0546 ha. diverted forest
land
HEP, 2011 Non Technical Executive Summary
acquisitions such as transmission line of the
project or is utilised for right of way.
The affected families may be
given the option to take a
sum amount in lieu of
one or more of the benefits as
entitled and specified in the
Fishing rights in the reservoir
area of the irrigation or hydel
All the affected Scheduled Tribes, other
traditional forest dwellers and the
Scheduled Castes families having fishing
rights in a river or pond , or dam in the
affected area
reference in the allotment of
outsourced contracts, shops or
other economic opportunities
up in or around the
to the affected persons or their groups or
cooperatives
reference while engaging
labourers in the project during
the construction phase
To willing landless labourers and
unemployed affected persons
training facilities for
entrepreneurship, technical
and professional skills for self
The affected persons
Compensation towards NTFP
including chilgoza, fuelwood,
fodder lost from grazing land
the river in the upstream
work of the project, and other
forest produces including on
account of the involuntary
nature of loss of access to the
forests/customary rights, of
the 39.0546 ha. diverted forest
This compensation
amount to be formally
fixed by a committee
comprising of company
representative, village
Panchayat members,
forest officials and local
opinion leaders.
Residents of three affected panchayats i.e.
Morang, Rispa and Thangi who had right on
the forest under “
Bushahr State, 1921
Non Technical Executive Summary xxviii
acquisitions such as transmission line of the
project or is utilised for right of way.
All the affected Scheduled Tribes, other
traditional forest dwellers and the
Scheduled Castes families having fishing
rights in a river or pond , or dam in the
to the affected persons or their groups or
o willing landless labourers and
unemployed affected persons
The affected persons
Residents of three affected panchayats i.e.
, Rispa and Thangi who had right on
the forest under “Forest Settlement of
ahr State, 1921”
ESIA for 100MW Tidong1 HEP, 2011
11. Monitoring and
NTPGL will establish an Environment, Health, Safety and Social organization structure to
implement and monitor the suggested mitigation measures.
headed by GM EHS&S,
lead by Environment Manager, Safety officer, Community Liaison Officer and a Health
Manager respectively. Each of these team leader
for implementing the m
measures will be conducted as suggested in t
aspects to be monitored during Construction period and operation period are
mentioned in Table
be carried out every quarter during the entire construction period. Project will prepare a
time bound Corrective Action Plan to close the findings of the third party audit.
Total cost of mitigation measures has been estimated to Rs. 226.35 Millions. Out of
which an amount of Rs. 188.5 millions have already been deposited towards the cost of
CAT Plan, Compensatory Afforestation, Cost of Trees, Net Present Value of the diverted
forest, Fisheries Management, LADA Works, and environmental monitoring by HPSPCB.
Rest of the i.e. Rs. 37.85 million is to be allocated by project on various mitigations
measures including 1 year fisheries study, installation of incinerator, sewage treatment
plant, monitoring of environmental parameters, third party EHS&S quarterly audit for 2
years, primary Health centre, demographic survey, annuity policy of vulnerable families,
etc.
Table 4: Key Aspects to be Monitored
Sl. No. Type
1 Ambient Air
Quality
� Lambar village
� Ruwang village
� Rispa Village
2 Stack
emission
� DG Sets
� Incinerator
2 River Water � 500 metres Upstream &
1000 meters
Downstream of diversion
structure
� 500 meters Upstream &
Downstream of Tidong
stream at powerhouse
HEP, 2011 Non Technical Executive Summary
onitoring and Auditing Plan and Costs
will establish an Environment, Health, Safety and Social organization structure to
implement and monitor the suggested mitigation measures. The organization will be
EHS&S, who will leader of Environment, Safety, Health and Social teams
lead by Environment Manager, Safety officer, Community Liaison Officer and a Health
Manager respectively. Each of these team leaders will be supported by respective team
for implementing the mitigation measures. Regular monitoring of all mitigation
measures will be conducted as suggested in the ESIA report by the EHS&S team. Key
aspects to be monitored during Construction period and operation period are
Table 4. In addition to internal monitoring, a third party EHS&S Audit will
be carried out every quarter during the entire construction period. Project will prepare a
orrective Action Plan to close the findings of the third party audit.
Total cost of mitigation measures has been estimated to Rs. 226.35 Millions. Out of
which an amount of Rs. 188.5 millions have already been deposited towards the cost of
nsatory Afforestation, Cost of Trees, Net Present Value of the diverted
forest, Fisheries Management, LADA Works, and environmental monitoring by HPSPCB.
Rest of the i.e. Rs. 37.85 million is to be allocated by project on various mitigations
ding 1 year fisheries study, installation of incinerator, sewage treatment
plant, monitoring of environmental parameters, third party EHS&S quarterly audit for 2
years, primary Health centre, demographic survey, annuity policy of vulnerable families,
onitored
Locations Parameters Frequency
Lambar village
Ruwang village
Rispa Village
SO2, NOx, CO,
PM10, PM2.5
24 hourly 1
sample /
week /
location
DG Sets
Incinerator
SO2, NOx, CO,
SPM
1 sample /
month /
location
500 metres Upstream &
1000 meters
Downstream of diversion
structure
500 meters Upstream &
Downstream of Tidong
stream at powerhouse
BOD, DO, TSS,
Conductivity &
Turbidity
Coliform
1 sample /
month /
location
Non Technical Executive Summary xxix
will establish an Environment, Health, Safety and Social organization structure to
The organization will be
who will leader of Environment, Safety, Health and Social teams
lead by Environment Manager, Safety officer, Community Liaison Officer and a Health
will be supported by respective team
Regular monitoring of all mitigation
he ESIA report by the EHS&S team. Key
aspects to be monitored during Construction period and operation period are
oring, a third party EHS&S Audit will
be carried out every quarter during the entire construction period. Project will prepare a
orrective Action Plan to close the findings of the third party audit.
Total cost of mitigation measures has been estimated to Rs. 226.35 Millions. Out of
which an amount of Rs. 188.5 millions have already been deposited towards the cost of
nsatory Afforestation, Cost of Trees, Net Present Value of the diverted
forest, Fisheries Management, LADA Works, and environmental monitoring by HPSPCB.
Rest of the i.e. Rs. 37.85 million is to be allocated by project on various mitigations
ding 1 year fisheries study, installation of incinerator, sewage treatment
plant, monitoring of environmental parameters, third party EHS&S quarterly audit for 2
years, primary Health centre, demographic survey, annuity policy of vulnerable families,
Duration of
Monitoring
Construction phase
Construction and
operation phase
Construction and
operation phase
ESIA for 100MW Tidong1 HEP, 2011
area before confluence
with Satluj
3 Waste
water
� Seepage water from
underground works
� Labour camp discharge
� STP outlet
4 Drinking
water
� Work area,
� labour camps and
� colony
5 Noise Levels � Barrage
� PWD Road Nr Barrage
� Power House
� PWD Road Nr Barrage
� Lambar village
� Ruwang village
� Rispa Village
6 Ecology Study on impact and
mitigation on fishes
7 Afforestatio
n and CAT
activities
Follow up with forest
department
8 Emergency
Preparedne
ss
� Preparation and
implementation of plan
9 Social
Parameters
� Preparation and
Implementation of R&R
� Compensations in lieu
of forest produce
� Community facilities
(Sanitation, Water
Supply, Sewerage etc.)
� Community
development work
� Functioning of
Grievance Redressal
cell
� Functioning of Public
Consultation and
disclosure plan
HEP, 2011 Non Technical Executive Summary
area before confluence
with Satluj
Seepage water from
underground works
Labour camp discharge
STP outlet
TDS
BOD, COD, TSS,
TDS,
Conductivity
2 samples
/month /
location
Work area,
labour camps and
colony
Drinking water
parameters as
per IS:10500
2 samples
/month /
location
Barrage
PWD Road Nr Barrage
Power House
PWD Road Nr Barrage
Lambar village
Ruwang village
Rispa Village
Equivalent
noise levels
1smaple 24
hourly day
and night
/month /
location
Study on impact and
mitigation on fishes
Progress of
study
Quarterly
Follow up with forest
department
Quarterly
Preparation and
implementation of plan
Progress of
work
Fortnightly
Preparation and
Implementation of R&R
Preparation and
Implementation
Once a
month
Compensations in lieu
of forest produce
Progress of
compensation
Community facilities
(Sanitation, Water
Supply, Sewerage etc.)
Progress of
work
Once a
month
Community
development work
Progress of
work
Once a
month
Functioning of
Grievance Redressal
cell
Effectiveness of
functioning and
number of
received and
redressed
Quarterly
Functioning of Public
Consultation and
disclosure plan
Effectiveness
and number of
meetings
Quarterly
Non Technical Executive Summary xxx
Construction phase
STP outlet to be
monitored during
operation phase
Construction phase
Construction phase
till the completion
of study
till the completion
of CAT and
afforestation
till the work is
completed
till completion
Construction and
operation
Construction and
operation