thermal binding walter g bischoff brunswick station duke energy
TRANSCRIPT
Background- Brunswick Feedwater system
• 2 Unit station
• 2 feedwater trains per unit
• 2 Condenser shells (A and B) each with North and South regions
• 2 FWH streams cascading 5 to 4, 4 to single common dearator
• 1 dearator with normal drain to pumps, and dump to condenser
• Steam Driven GE turbines driven pumps
• Total Feedwater flow is approximately 12.25 MLB/hr
• Each RFPT uses a Woodward 5009 controller and steam control valves to adjust speed to meet RPV demand
• Exhaust steam flows to the main condenser
• Moisture drains collect liquid and direct effluent to the condenser via gravitational force
Conditions progressing to the event
• Unit 1 completed the B120R1 refueling outage
• Upgraded the RFP impeller design• More stable • Less efficient • Requires additional speed• Calculations support single pump operation as high as 70% RTP• Slightly less maximum RTP for single pump operation with new impeller
• Factory acceptance testing was satisfactory
• Pump rebuild satisfactory
Issue: Elevated RFPT exhaust casing drains
• Unit 1 achieved 60% reactor power
• RFP Inservice testing was progressing as expected
• Control room operators received Hi-Hi RFPT casing drain alarm
• Normal casing drain levels are <2 inches
• Casing drain levels reached as high as 7 inches before tripping RFP/T
Troubleshooting the issue
• Unit 1 remained at 60% reactor power
• B RFP was used to feed the RPV
• Calibration check indicated satisfactory level instrument performance
• Isolation drain valve was found open
• Steam inlet stop/isolation valves were closed
• Level remained between 7-8 inches
• Condenser level was 12 inches
• Heater drain dearator was dumping back to the condenser.
Piping geometry and hotwell configuration
• The RFPT exhaust casing elevation is 24’ 1” plant elevation (el).
• From the 1A RFPT exhaust casing (24’ 1” el), there is a 1’ 3(1/2)” vertical drop to 22’ 9(1/2)” el.
• Drain piping flows horizontally through a total of 60’ 2(3/4)” with (3) 90 degree horizontal piping bends.
• Piping elevation slopes downward on a 45 degree angle and drops 4” in elevation.
• The remaining 5(1/2)” elevation drop occurs over a 10’ 2(7/8)” length of pipe.
• Drain pipe center point penetrates the condenser at 22’-0” el.
• The drain pipe is 4” in diameter
Hotwell indications
• The ‘Normal hotwell water level’ of 0” equals 21’ 1(5/8)” el
• Hotwell level of +8(3/8)” equals 21’ 10” el and will begin to submerge the 1A RFPT casing drain line.
• Hotwell level of +12(3/8) equals 22’ 2” el and will completely submerge the 1A RFPT casing drain line.
• Level reached 10.5” at the time of the issue
• Heater drain dearator dump valve is located immediately below the 1A RFPT drain line
Troubleshooting the issue
• Operations started a second dearator drain pump and closed V-57 dump to the condenser
• RFPT casing level immediately dropped to 0 inches
• Level in the condenser remained unchanged at approximately 10.5 inches
• Original theory was the drain liquid was blocked due to elevated condenser hotwell level
Communicating Vessel theory and the hydrostatic paradox
• RFPT drain case is 2’ 1” above the condenser penetration
• Hotwell level would have had to rise another 2 feet to block the drain line
• Communicating vessels is a name given to a set of containers containing a homogeneous fluid
• When the liquid settles, it balances out to the same level in all of the containers regardless of the shape and volume of the containers.
• If additional liquid is added to one vessel, the liquid will again find a new equal level in all the connected vessels.
Saturation point
• RFPT moisture collected in the bottom of the tank is a liquid, however at or near saturation point
• Although the drain was partially submerged, liquid should have continued to drain
• Heater drain dearator was at 60 psi and 235 degrees F
• The dearator dump line discharges just below the RFPT drain penetration.
• For condenser vacuum 2.25 inHg boiling temperature is approximately 106 degrees F
2 phase flow
Hotter discharge
CoolerInlet
• Dearator dump liquid heats the hotwell condensate including liquid at the RFPT drain.
• RFPT drain liquid at or slightly below boiling point is heated by dearator dump liquid
• Long 60 feet run of pipe contributes to head losses and slows flow
• Steam flows up the pipe forming a ‘wall’ blocking liquid flow
• Liquid that approaches the condenser boils to steam and tries to flow up the pipe until it condenses back to liquid and the cycle repeats itself
Troubleshooting the issue
• Operations started a second dearator drain pump and closed V-57 dump to the condenser
• This stopped the flow of hot water to the condenser at the RFPT drain line
• Without a source of heat, the RFPT drain liquid no longer boiled to steam
• The drain case was able to drain freely again.
• Continued with power ascension and RFPT mod acceptance testing.
Failure mode relevant to equipment other than RFPT
• Steam binding may occur in other equipment such as heaters and other components that drain to the condenser
• Reduced drain flows lesser than anticipated with no explanation
• More likely to occur in smaller bore piping
• Could be seen in FWH drains and FWH dump lines