8/27/04
Paul A. JensenOperations Research Models and Methods
Copyright 2004 - All rights reserved
The Theory of Constraints
Now that we know the Goal, how do we use it to improve our
system?
2
The Theory of Constraints Step 1: Identify the system's constraint(s). Step 2: Decide how to exploit the system's
constraint(s). Step 3: Subordinate everything else to the
decisions of Step 2. Step 4: Elevate the system's constraint(s). Step 5: If a constraint is broken in Step 4, go
back to Step 1.
3
Step 1: Identify the system’s constraint(s).
What is the Goal? What is Throughput? What is Inventory? What is Operating Expense?
4
Step 2: Decide how to exploit the system’s constraint(s).
What is the constraint? How do we get as much throughput as
possible?
5
Step 3: Subordinate everything else to the decisions of Step 2
Throughput? Inventory? Operating Expense?
6
Step 4: Elevate the system’s constraint(s).
Throughput? Inventory? Operating Expense?
7
Step 5: If a constraint is broken in Step 4, go back to Step 1.
What might happen if the constraint is elevated?
8
Summary: The Theory of Constraints Step 1: Identify the system’s constraint(s). Step 2: Decide how to exploit the system’s
constraint(s). Step 3: Subordinate everything else to the
decisions of Step 2. Step 4: Elevate the system’s constraint(s). Step 5: If a constraint is broken in Step 4, go
back to Step 1.
9
Application in Manufacturing
10
$90/U 100 U/Wk
P
$100/U 50 U/Wk
Q
D 10 min./U
D 5 min./U
C 10 min./U
C 5 min./U
B 15 min./U
A 15 min./U
B 15 min./U
A 10 min./U
RM1 $20/U
RM2 $20/U
RM3 $20/U
Purchase Part $5/U
A,B,C,D: 1 each Available Time: 2400 Min/Wk OE not including RM: $6000 per wk
11
Step 1: Identify the system’s constraint(s).
What is the Goal? What is Throughput? What is Inventory? What is Operating Expense?
$90/U 100 U/Wk
P
$100/U 50 U/Wk
Q
D 10 min./U
D 5 min./U
C 10 min./U
C 5 min./U
B 15 min./U
A 15 min./U
B 15 min./U
A 10 min./U
RM1 $20/U
RM2 $20/U
RM3 $20/U
Purchase Part $5/U
A,B,C,D: 1 each Available Time: 2400 Min/Wk OE not including RM: $6000 per wk
12
To Identify the Resource Constraint Compute the load on each production
resource assuming market demands. Compare the resource loads with the
resource capacities. Those resources for which the loads exceed
the capacities are constraints (bottlenecks). If no production resource load exceeds its
capacity, the market demands are the constraints. the constraints are external to the manufacturing
system.
13
Compute the loads and compare with capacities. Production P=100, Production Q=50 A: Load =2000, Capacity = 2400 Minutes B: Load =3000, Capacity = 2400 Minutes C: Load =1750, Capacity = 2400 Minutes D: Load =1250, Capacity = 2400 Minutes What is the constraint?
14
Step 2: Decide how to exploit the system’s constraint(s).
$90/U 100 U/Wk
P
$100/U 50 U/Wk
Q
D 10 min./U
D 5 min./U
C 10 min./U
C 5 min./U
B 15 min./U
A 15 min./U
B 15 min./U
A 10 min./U
RM1 $20/U
RM2 $20/U
RM3 $20/U
Purchase Part $5/U
A,B,C,D: 1 each Available Time: 2400 Min/Wk OE not including RM: $6000 per wk
15
Exploiting the constraint Assume a single constraint is identified. Rank the products in order of the ratio:
Throughput dollars per minute of constraint use. Select the product mix so that the products
with greater ratios are produced in preference to the products with smaller ratios.
What goal is this method trying to achieve? How does this method achieve the goal?
16
What and how much to produce?
P: TP/Unit = 45, B Min/Unit=15
Q: TP/Unit = 60, B Min/Unit=30
TP/Min = 4515 $3 / min
TP/Min = 6030 $2 / min
17
Calculate Solution Produce as much P as possible
Use the remainder of the constraint resource for Q
What is the profit for this product mix?
P 100
Q2400 15 100
30 90030 30
Profit = TP - OC
= 100 45 30 60 3000
4500 1800 6000 300
18
Step 3: Subordinate everything else to the decisions of Step 2.
$90/U 100 U/Wk
P
$100/U 50 U/Wk
Q
D 10 min./U
D 5 min./U
C 10 min./U
C 5 min./U
B 15 min./U
A 15 min./U
B 15 min./U
A 10 min./U
RM1 $20/U
RM2 $20/U
RM3 $20/U
Purchase Part $5/U
A,B,C,D: 1 each Available Time: 2400 Min/Wk OE not including RM: $6000 per wk
19
Subordinating Production Production P=100, Production Q=30 A: Load =1800, Capacity = 2400 Minutes B: Load =2400, Capacity = 2400 Minutes C: Load =1650, Capacity = 2400 Minutes D: Load =1150, Capacity = 2400 Minutes What determines the load on the non-
constraints?
20
Step 4: Elevate the system’s constraint(s).
Where should process improvements be focused?
What is the benefit of elevating the constraint?
What is the benefit of elevating a non-constraint?
$90/U 100 U/Wk
P
$100/U 50 U/Wk
Q
D 10 min./U
D 5 min./U
C 10 min./U
C 5 min./U
B 15 min./U
A 15 min./U
B 15 min./U
A 10 min./U
RM1 $20/U
RM2 $20/U
RM3 $20/U
Purchase Part $5/U
A,B,C,D: 1 each Available Time: 2400 Min/Wk OE not including RM: $6000 per wk
21
Step 5: If a constraint is broken in Step 4, go back to Step 1.
What might happen if the constraint is elevated?
What happens if there are no more internal constraints?
$90/U 100 U/Wk
P
$100/U 50 U/Wk
Q
D 10 min./U
D 5 min./U
C 10 min./U
C 5 min./U
B 15 min./U
A 15 min./U
B 15 min./U
A 10 min./U
RM1 $20/U
RM2 $20/U
RM3 $20/U
Purchase Part $5/U
A,B,C,D: 1 each Available Time: 2400 Min/Wk OE not including RM: $6000 per wk
22
Say we add another machine of type B. Production P=100, Production Q=50 A: Load =2000, Capacity = 2400 Minutes B: Load =3000, Capacity = 4800 Minutes C: Load =1750, Capacity = 2400 Minutes D: Load =1250, Capacity = 2400 Minutes How much should we produce? What is the new constraint? How do we elevate the new constraint?
23
Summary: The Theory of Constraints Step 1: Identify the system’s constraint(s). Step 2: Decide how to exploit the system’s
constraint(s). Step 3: Subordinate everything else to the
decisions of Step 2. Step 4: Elevate the system’s constraint(s). Step 5: If a constraint is broken in Step 4, go
back to Step 1.