the safety of personnel in temporary buildings during ... during plant start-up john henderson,...
TRANSCRIPT
Engineering Solutions . . . Delivering Results
The safety of personnel in temporary buildings The safety of personnel in temporary buildings during plant startduring plant start--upup
John Henderson, Principal Safety Engineer, CB&I LummusJohn Henderson, Principal Safety Engineer, CB&I Lummus
2
Introduction to CB&IIntroduction to CB&I
Chicago Bridge & Iron Company N.V.
CB&I Lummus CB&I Steel PlateStructures
LummusTechnology
• Upstream• Offshore• LNG Liquefaction• LNG Regasification• Gas Processing• Pipelines• U/G Gas Storage
• Downstream• Refining• Petrochemical
• Low Temperature Storage• Floating Roof Tanks• Flat Bottom Tanks• Water• Nuclear Containment• Cryogenic Spheres
• Clean Fuels• Hydrocracking• Hydrotreating• FCC• Visbreaking• CLG• CDTECH• Randall Gas• Sulphur• Hydrogen
3
Integrated Technology and EPFC ContractorIntegrated Technology and EPFC Contractor
Engineering Procurement Technology Fabrication
Introduction to CB&IIntroduction to CB&I
Construction MechanicalInstallation
Operator Training
Start-up and Commissioning
Engineering Solutions . . . Delivering Results
Structure of the presentationStructure of the presentation
•• Description of the issue.Description of the issue.•• The Texas City incident The Texas City incident –– a turning point.a turning point.•• Development of new codes, guidelines and Development of new codes, guidelines and
improved consequence modelling.improved consequence modelling.•• CB&ICB&I’’s assessment process.s assessment process.•• Typical mitigation measures for buildings.Typical mitigation measures for buildings.•• An example of detailed analysis.An example of detailed analysis.•• Summary of key recommendations.Summary of key recommendations.
4
Engineering Solutions . . . Delivering Results
Expansion of LNG terminal Expansion of LNG terminal
5
Engineering Solutions . . . Delivering Results
Typical temporary buildings and hazardTypical temporary buildings and hazard
Pipeline valves
Timber framed cabins
Steel framed cabins with
steel window shutters
Steel clad
cabins
6
Engineering Solutions . . . Delivering Results
Significant Hazards Significant Hazards
•• Explosions (require congestion or confinement)Explosions (require congestion or confinement)– Building collapse– Building components become projectiles (e.g. glass,
wall panels)
•• Flammable gas cloudsFlammable gas clouds– Flash fire (short duration)
• Failure of doors/windows – flame penetration• Direct radiation exposure via windows
– High dose to personnel– Secondary internal fires
– Internal explosion
•• Heat (thermal radiation) from jet or pool firesHeat (thermal radiation) from jet or pool fires•• (Toxic gas clouds)(Toxic gas clouds)
7
Engineering Solutions . . . Delivering Results
Explosion damage to temporary buildingsExplosion damage to temporary buildings
8
Engineering Solutions . . . Delivering Results
Explosion damage: lightwood cabinExplosion damage: lightwood cabin
9
Engineering Solutions . . . Delivering Results
Explosion damage: local control roomExplosion damage: local control room
10
Engineering Solutions . . . Delivering Results
•• Publication of API RP 753Publication of API RP 753• ‘Management of Hazards Associated with Location of
Process Plant Portable Buildings’ June 2007.
•• Industry initiatives such as those by FABIG (Fire Industry initiatives such as those by FABIG (Fire and Blast Industry Group)and Blast Industry Group)
•• Buildings with fire and blast rating for special Buildings with fire and blast rating for special applications such as maintenance of live plant.applications such as maintenance of live plant.
•• Use of CFD (computational fluid dynamics) models: Use of CFD (computational fluid dynamics) models: • predict explosion and fire consequences more accurately.
•• Use of QRA (quantitative risk analysis):Use of QRA (quantitative risk analysis):• determines the probability of a hazard occurring and the
consequent probability of fatalities in a particular location.
Developments since 2005Developments since 2005
11
Engineering Solutions . . . Delivering Results
•• Consider temp buildings early in the project cycleConsider temp buildings early in the project cycle• Part of construction / contract planning• Process safety (fire & explosion) assessments available.• Identify temp building requirements and obtain building
data.• If possible, locate temp buildings in same areas as
permanent buildings.
•• Hazard identificationHazard identification• Identify the hazards, area-by-area, using plant layouts and
fire & explosion assessments produced at the design stage. Compare the hazards to the building locations.
•• Evacuation PlanEvacuation Plan• Cannot rely on evacuation as hazards may develop
quickly and present dilemmas.
Assessment processAssessment process--11
12
Engineering Solutions . . . Delivering Results
•• Review the guidance availableReview the guidance available• API RP 753• Guidance for the location and design of..buildings,
appendix 5 (Chemical Industries Association)• Baker Report on Texas City
•• Define the Define the ‘‘design scenariosdesign scenarios’’ for assessing each for assessing each building or group of buildingsbuilding or group of buildings• Explosions• Gas dispersion / flash fires• Jet or pool fires• Obtain safety assessment /consequence model for each
scenario.
Assessment processAssessment process-- 22
13
Engineering Solutions . . . Delivering Results
Explosion modelling Explosion modelling -- 11
14
Blast Overpressure Decay
0.000
0.050
0.100
0.150
0.200
0.250
0 250 500 750 1000 1250 1500
Distance from centre of confined volume (m)
Stat
ic O
verp
ress
ure
(bar
g)
Material : Methane
Engineering Solutions . . . Delivering Results
Explosion modelling Explosion modelling -- 22
15
Example of computational fluid dynamic modelling of an explosion within a structure
Engineering Solutions . . . Delivering Results
•• Decide on simple criteria (limits) or a riskDecide on simple criteria (limits) or a risk--based based approach. approach. • Simple criteria, e.g. API codes – RP 753 and RP 521• Risk based – probability of the design scenario combined
with impact analysis, occupancy of building, and chance of survival to give overall risk that can be compared with standard criteria, e.g. probability of individual fatality of less than 1 in 10000 per year.
Assessment processAssessment process-- 33
16
Engineering Solutions . . . Delivering Results
•• Examples of simple criteria applied to a Examples of simple criteria applied to a ‘‘light wood light wood trailertrailer’’::• Explosion: API RP 753 – zonal approach
• <40 mbar unrestricted; >60 mbar unacceptable• Between 40 – 60 mbar a detailed assessment is required.
• Gas cloud gas concentration above 0.5 LFL unacceptable.• Fire: API RP 521
• Thermal radiation above 6.3 or 9 kW/m2 (depending on evacuation time) is unacceptable.
•• Predict the impact for each building or group of Predict the impact for each building or group of buildingsbuildings• Compare consequence model to criteria.• Detailed structural assessment may be necessary.• Mitigation (other than relocation) may be possible.• Care needed when simple criteria appear met.
Assessment process Assessment process –– 44
18
Engineering Solutions . . . Delivering Results
•• Depending on the consequences, classify each Depending on the consequences, classify each building or group of buildings:building or group of buildings:• Class 0: the building can be closed-down and taken off the
site before commissioning.• Class 1: the building can be retained in its location without
any changes to design or function.• Class 2: the building cannot stay in its location without
mitigation measures or changing its function.• Class 3: the building cannot stay in its current location• The number of people in the building may affect its
classification.
Assessment process Assessment process -- 55
19
Engineering Solutions . . . Delivering Results
•• Typical mitigation measures for buildings in class 2:Typical mitigation measures for buildings in class 2:– Signed escape routes with adequate lighting routed away
from hazards to clearly marked muster areas.– Check if site gas and fire alarms are audible / visible –
consider additional.– Architectural features: no heavy equipment on roof (a/c),
protective films / shutters on windows, emergency exits on side away from hazard, structural stiffening.
– Position unoccupied buildings as barrier.– Demount any stacked container type.
Typical mitigation measuresTypical mitigation measures
20
Engineering Solutions . . . Delivering Results
•• Consider a large building approx 250m from a gas Consider a large building approx 250m from a gas compressor building.compressor building.
•• Building 33 m x 24 m x 3 mBuilding 33 m x 24 m x 3 m•• 25 kitchen staff present 10 hours/day25 kitchen staff present 10 hours/day•• 275 construction workers present 2 hours/day275 construction workers present 2 hours/day
Detailed assessment of a large buildingDetailed assessment of a large building
21
Engineering Solutions . . . Delivering Results
Typical large temporary buildingTypical large temporary building
22
Engineering Solutions . . . Delivering Results
Detailed assessment of a large buildingDetailed assessment of a large building
23
Engineering Solutions . . . Delivering Results
•• Impact and consequence assessmentImpact and consequence assessment• Risk due to gas compressor building located approx 250m
away.• 40 mbar overpressure occurs at a frequency of between 1
and 3 x 10-4 per year.• Building analysis predicts collapse at about 20 mbar
• Large modular building not designed for non-normal loads• Construction plan modified to relocate building prior to
commissioning.
Detailed assessment of large buildingDetailed assessment of large building
24
Engineering Solutions . . . Delivering Results
• Do assessment and planning as early as practical in the project cycle. Several teams are involved: HSE, Safety Engineering, Construction and Project Management.
• Consider all hazard types and analyze the impacts.• As far as practical, administrative and back-up staff should
be excluded from buildings within hazard ranges.• Use prescriptive guidelines critically and be prepared to
modify or use more sophisticated techniques, especially where large numbers of people involved.
• Where it’s acceptable to maintain buildings in position through commissioning, ensure reasonable mitigation measures are taken to reduce the risk.
Key recommendationsKey recommendations
25