11/10/2016 1 How a $150 sensor saved $15,000 and other fun facts: Why you want to commission your building? Michael Chimack, PE, PMP, QCxP, CEM Principal ICF October 27, 2016 5.5 1 2.5 12.5 3.5 5 0.25 Northrup Grummen Energy Resourcs Ctr Consulting University of Illinois Consulting 2.0 Siemens ICF Introduction:  My Experience (years)

Upload: alison-hooks

Post on 14-Apr-2017

89 views

Category:

Engineering


3 download

TRANSCRIPT

Page 1: The Quick Guide to Building Commissioning

11/10/2016

1

How a $150 sensor saved $15,000 and other fun facts: Why you want to commission your building?

Michael Chimack, PE, PMP, QCxP, CEMPrincipal

ICFOctober 27, 2016

5.5

1

2.5

12.5

3.5

5

0.25

Northrup Grummen Energy Resourcs Ctr

Consulting University of Illinois

Consulting 2.0 Siemens

ICF

Introduction:  My Experience (years)

Page 2: The Quick Guide to Building Commissioning

11/10/2016

2

Today’s Agenda• What is Building Commissioning?

• History, nomenclature

• How does it work?

• What is the value proposition?

• How did a sensor save so much money?

• How you can maximize the PSO incentives to reduce my energy use!

• Hall of Shame.

“Building Commissioning Industry…” Why?• Most buildings are old (>20 years) and were designed on a lowest first cost basis

• Many systems were overdesigned which leads to performance and efficiency loss 

when operating buildings at “normal conditions”

• Current facility requirements are different than original design

• Months, seasons, years of deferred maintenance (reactionary maintenance)

• Understaffed operations personnel who are more like “fire fighters” 

• Could use more training

• Stricter/new codes, mandates, desire for “green” buildings

Page 3: The Quick Guide to Building Commissioning

11/10/2016

3

Progression of the Industry

OriginationCreation and Definition ASHRAE and BPA define and test Federal Government issues first

executive order Early adopters implement and

provide first case studies

AcceptedMarket accepts Cx asstandard practice

Utilities develop programs

Retro Commissioning created for existing buildings

Streamlines processes and definition, resulting in provenenergy and operational savings

Technology leveraged to create tools for better analysis of data

First government agenciespass new Cx code

Certification programs startedto standardize professionaltraining

ComprehensiveFocus on end to end delivery Market demands comprehensive

solution including Retro and Persistentcommissioning together

The focus is implementationfor recommendations from Retro and Persistent Cx withfocus on productivity of customers’people and processes, with

technology as the enabler As in the past, actionable

information is provided to make better decisions, and now scope is expanded to:

Data analytics andoptimization strategies

Remote monitoring andmaintenance of systems

Proactive service Energy Management

Sustainability

Mid 80s to mid 90sMid 90s to mid 00sMid 00s to present

What is Building Commissioning…"…a systematic process for investigating, analyzing, 

and optimizing the performance of building systems 

through the identification and implementation of low/no cost 

and capital intensive Facility Improvement Measures and 

ensuring their continued performance over time. The Existing 

Building Commissioning process assists in making the building 

systems perform interactively to meet the Current Facility 

Requirements. 

"Commissioning is arguably the single most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today."

Evan Mills, Lawrence Berkeley National Laboratory

Page 4: The Quick Guide to Building Commissioning

11/10/2016

4

Industry Data

Commissioning NomenclatureType of Commissioning Description Purpose

Commissioning (Cx) • For new buildings• Structured verification of systems 

against intended design

Ensure the building will operate per customer needs(lowest LCC, "Life Cycle Cost")

Re‐Commissioning (ReCx) • Existing building• Has previously been commissioned• Usually done every 3–5 years

Maintain optimal performance

Retro‐CommissioningAka "Existing Building Commissioning" and "Total Building Commissioning"

• Existing building• Has NOT previously been 

commissioned• May include corrections and repairs 

before commissioning

• Create building operations spec (CFR)

• Identify and implement low and no cost improvements

Monitoring‐Based Commissioning (MBCx)Aka "On‐going Commissioning" and "Continuous Commissioning"

• Existing commissioned building• Monitor key indicators to confirm 

optimal performance

Maintain optimal performance and identify additional improvement opportunities

Page 5: The Quick Guide to Building Commissioning

11/10/2016

5

Your concern…Owning and Operating Costs(Generic Example)

Sources: IFMA, GSA, and other industry sources.Half of all buildings in current use were constructed prior to 1980. Energy Information Administration (EIA) and 2012 Commercial Building Energy Consumption Survey (CBECS)

Section Examples/Description

Energy and  Utility Costs The largest operating expense, including electricity, gas, water

Premature Major Equipment Repair Costs

Lack of maintenance results in shortenedequipment useful life and increased repairs

Cost of System Replacement All equipment has a finite useful life – typically less than the life of the facility

Tools, Small Parts, &Maintenance Materials

Consumables and purchases of supplies for in‐house maintenance

In‐House Staff Employees performing facility maintenance and operating work (e.g., building technicians, custodians)

Purchased Outside Services Third party maintenance and service providers

Administrative Labor needed for oversight, payment of invoices and utility bills, overall planning

The Building Commissioning Process…

Project DevelopmentMulti‐facility 

PlanningAssessment Investigation

Implementation Hand Off Persistence Phase

Page 6: The Quick Guide to Building Commissioning

11/10/2016

6

Customer Facility Requirements (CFRs)

• CFRs are the specification to which a building is commissioned

• Accurate CFRs are essential to a successful EBCx project

• Part of the Assessment Phase (Commissioning Plan)

• Need input from all the building stakeholders

• Cast a wide net when identifying stakeholders

• CFRs define requirements only

• Commissioning process will determine solutions

How can EBCx Improve Operations and Save Energy?•Design deficiencies that have never 

been addressed

•Systems or components 

not being maintained

•Operational approaches 

that waste energy

•Control strategies 

that are not optimal

Identify Corrections Needed

• Oversized equipment

• Undersized distribution

• Short‐circuiting of flows

• Sensors in wrong or poor location

• Improper zoning

• Tenant improvements that didn't 

address changed HVAC needs

Page 7: The Quick Guide to Building Commissioning

11/10/2016

7

How can EBCx Improve Operations and Save Energy?•Design deficiencies that have 

never been addressed

•Systems or components 

not being maintained

•Operational approaches 

that waste energy

•Control strategies 

that are not optimal

Identify Corrections Needed

• Failed controls

• Wrong application of controls

• Failed actuators

• Dampers or valves stuck or without full range 

of motion

• Torn flex connectors; warped access panels

• Missing/damaged pipe & duct insulation

• Unmaintained filters/coils obstruction flow

How can EBCx Improve Operations and Save Energy?•Design deficiencies that have 

never been addressed

•Systems or components 

not being maintained

•Operational approaches 

that waste energy

•Control strategies 

that are not optimal

Identify Corrections Needed

• Excessive run time

• Fixed schedules with no optimization

• Constant volume equipmentfor variable volume loads

• Variable loads without variable set points (i.e. no reset function)

• Imbalanced load between system components (e.g. chiller v. tower, airflow v. CHW/HW flow)

• Simultaneous operation of heating and cooling

• Setpoints not commissioned

Page 8: The Quick Guide to Building Commissioning

11/10/2016

8

Multi Facility Planning PhaseKey Activities

Deliverables1. Create EBCx program 

planning team2. Define EBCx program goals 

and objective3. Develop EBCx program plan4. Performance and Savings 

Verification Approach5. Assessment phase pre 

planning

EBCx Program Plan

Facilities ranked 

Project 

Development

Multi‐facility 

PlanningAssessment Investigation

Implementation Hand OffPersistence 

Phase

Assessment Phase (Plan)Key Activities Deliverables

Perform Assessment

• Assign proj. team and roles

• Kick off meeting/CFRs

• Obtain any missing fac. data

• Initial EBCx plan and implementation budget

• Develop plan for trending/trend

• Identify initial issues

• Estimate savings and costs

• Develop Systems Manual outline

• Develop M&V requirements

• Develop report formats

Assessment Report

• Current Facility Requirements

• EBCx Plan

• Draft Investigation Plan

• Draft Implementation Plan

• Draft Training Plan

• Issues Matrix

• Initial issues with estimated savings/costs

• Updated implementation budget

Project 

Development

Multi‐facility 

PlanningAssessment Investigation

Implementation Hand OffPersistence 

Phase

Page 9: The Quick Guide to Building Commissioning

11/10/2016

9

Investigation Phase (Identify)

Investigate Systems

• Review of documents/records

• Update Investigation Plan

• Assess condition and analyze performance of systems

• Continue issue identification

• Estimate savings and costs

• Rank recommendations

• Update Implementation Plan

• Update Training Plan

• Obtain quotes for 3rd party work (if applicable)

Investigation Report

• Updated Current Facility Requirements

• Updated EBCx Plan

• Updated Issues Matrix with benefits analyses

• Updated Implementation Budget

• Measurement data (e.g., trend logs)

• Implementation plan

Key Activities Deliverables

Project 

Development

Multi‐facility 

PlanningAssessment Investigation

Implementation Hand OffPersistence 

Phase

Implementation Phase (Change)Key Activities Deliverables

Implement Opportunities• Update Implementation Plan

• Select appropriate implementers for each issue identified

• Conduct independent testing and evaluation of implemented recommendations• Per Verification Plan

• Compare predicted performance enhancements with actual• Reevaluate if necessary

• Update Training Plan

Implementation Report• Updated EBCx Plan

• Implementation Plan

• Verification Plan

• Training Plan

• Updated Issues Matrix with benefits analyses

• Updated Systems Manual

Project 

Development

Multi‐facility 

PlanningAssessment Investigation

Implementation Hand OffPersistence 

Phase

Page 10: The Quick Guide to Building Commissioning

11/10/2016

10

Hand‐Off Phase (Train)Key Activities Deliverables

Train Staff

• Verify training effectiveness

• Conduct Lessons Learned Workshop

• Finalize MBCx Plan/Proposal

• Complete Systems Manual

• Transfer final report to customer

• Update EBCx Plan for MBCx

Final EBCx Report• Final Systems Manual

• Complete EBCx Report

• Final issues Matrix

• M&V report

• Updated EBCx Plan

• Monitoring Based Commissioning Plan 

• Lessons Learned Report

Project 

Development

Multi‐facility 

PlanningAssessment Investigation

Implementation Hand OffPersistence 

Phase

Persistence Phase (Maintain)Key Activities Deliverables

• Revisit and review previous customer data (e.g., non‐implemented opportunities) 

• Create a strategy for on‐going monitoring of systems

• Identify additional ECMs and possible FIMs (facility improvement measures) for potential implementation

Periodic Reports

• Persistent verification of savings from implemented measures 

• Recommendations for other improvements

Project 

Development

Multi‐facility 

PlanningAssessment Investigation

Implementation Hand OffPersistence 

Phase

Page 11: The Quick Guide to Building Commissioning

11/10/2016

11

• Operational costs will naturally escalate throughout the building's lifecycle

• Implementing an EBCx project lowers operational costs significantly

• Supply-side services such as energy procurement consulting further lowers operational costs

• Without demand-side and supply-side on-going services, operational costs can rise to original levels

• Savings persist through implemen-tation of persistence methodology

• Savings increase as additional opportunities are identified and additional FIMs are implemented

• EBCx cost << Total realized value

Value of an Existing Building Commissioning Program

LEGENDOne-time Project Fees

On-going Service Fees

Implement EBCx

Implement Supply-side

Services

Implement Additional

FIMs

ADDED VALUE

Value Proposition

Bu

ild

ing

Op

erat

ion

al C

ost

s

Existing Buildings

Years of Operation

Implement MBCx

So…how did a $150 sensor save $15,000?

• Commissioned a 500 ksf building (4 floors) in Palo Alto, CA

• Typical commercial office building

• Constructed  in early 1980’s

• Objectives of Cx project

• Reduce energy consumption by 10‐20%

• Ability to partner with their real estate management companies

• Prove energy savings through M&V (trends, reports, etc.)

Page 12: The Quick Guide to Building Commissioning

11/10/2016

12

Issues & Results• Documented dozens of issues (sensors to improper air changes)

• Documented existing sequence of operations (SOO) and developed new SOO based on current facility requirements.

• Programed new SOO into BAS and completed prescribed functional testing.

• Identification and execution of 10 highest priority issues predicted an energy savings of over $58,000 per year (11% savings)

• One outdoor temperature sensor for 4 AHUs, two problems...     

It was reading high by 5oF AND it was improperly installed

• BIN analysis demonstrated savings of ~$11,000 (verified to >$15,000)

Finally, for the 10 implemented measures:

• Total first year measured savings > $79,000 (15% savings)

PSO EBCx Rebate offering• PSO Business rebates ran Retrocommissioning program since 2013. 

• The PSO Business Rebates RCX program has evolved overtime 

• Now it is currently offered under PSO Custom program for performance based RCx projects. 

• The reason behind the performance based approach is to ensure that Customers are getting what they are expecting

• If you are interested in these programs we have PSO Custom program Specialist here: Jiten Gautam. 

• You can also visit the PSO business rebates booth outside.

Page 13: The Quick Guide to Building Commissioning

11/10/2016

13

PSO program Project Example• Location: Tulsa

• Building Type: Stand Alone Commercial building

• Building Type: Retail Fast Food Restaurant and Party Services

• Building SF: 93,000 SF

• Existing/Baseline Energy Usage: 1,995,873 KWH

• Proposed Savings: 9.92%

• Actual Savings Weekdays: 29.72 %

• Actual Savings Weekends: 11.63 %

Graph Courtesy: Trane

Before

After

Existing Building Commissioning‐Summary

• 5‐30% reduction in utility expenditures

• Improved operational efficiency/fewer operational issues

• Greener building portfolio

• Control costs by actively managing demand‐side energy use and potentially supply‐side energy costs

• Additional business value for vertical market (e.g. better test scores in schools, better productivity in office/manufacturing, address compliance issues in hospitals and labs, etc.)

• You get a Systems Manual‐repository of building information

What is the value to the you?

• CxA is a comprehensive building performance and energy optimization program designed to drastically improve the way facility managers operate their facilities.  

• Rigorous, process‐based methodology to ensure current facility requirements are defined and the building(s) and corresponding operating systems are made to meet the requirements using the minimum amount of energy.

What is it?

Don’t forget…

• Identifying issues without implementing changes saves you ZERO!!

• Watch out for people selling “black box” solutions 

Most favorable building characteristics

• Highly dissatisfiedwith current facility operation

• High energy users (combined utilities >$500K annually)

• Have goals to reduce GHG and/or utility budget

• Have goals to become LEED certified

• Want to understand how to operate their buildings more efficiently,including addressing deferred building maintenance

• Have a budget for implementing building improvements

Page 14: The Quick Guide to Building Commissioning

11/10/2016

14

Want more information…

Building Commissioning Association‐tools, techniques, company directory, education http://www.bcxa.org/

ASHRAE‐guidelines, standards, educationhttps://ashrae.org/

ACEEE‐market studieshttp://www.aceee.org

LBNL‐researchhttp://cx.lbl.gov/documents/2009‐assessment/lbnl‐cx‐cost‐benefit.pdf

Some of the issues we hope not to find during EBCx projects

Page 15: The Quick Guide to Building Commissioning

11/10/2016

15

Controls Configuration/Functionality

Maintenance‐related Issues

Page 16: The Quick Guide to Building Commissioning

11/10/2016

16

The control air was removed from the chilled water control valve, the valve stem was pulled up.Coil running 100% wild!

The date the picture was taken: 7/15/2010

Maintenance‐related Issues

Outside air damper frozen shut! This pre‐filter never made it on the maintenance log.

Maintenance‐related Issues

Page 17: The Quick Guide to Building Commissioning

11/10/2016

17

Valve shown in minimum closed position (actually ~40% open)

The first “V” in VAV means Variable!

Maintenance‐related Issues

Throttled Valves

Page 18: The Quick Guide to Building Commissioning

11/10/2016

18

Actuators Connected?

Do Air Filters Fit Properly?

Page 19: The Quick Guide to Building Commissioning

11/10/2016

19

Coil Maintenance?

Low Resistance Duct Design?

Page 20: The Quick Guide to Building Commissioning

11/10/2016

20

Is that a tree in a cooling tower, or a cooling tower in a tree?

Other Issues

Discussion