the influence of the lamar dc tie on the black hills ... · colorado electric 115 kv system –...
TRANSCRIPT
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
1
The Influence of the Lamar DC Tie on the Black Hills
Colorado Electric 115 kV System – Preliminary Study
PREPARED
BY
BLACK HILLS CORPORATION
TRANSMISSION PLANNING
August 22, 2012
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
2
Table of Contents
1. Introduction ............................................................................................................................... 5
2. Study Methodology ................................................................................................................... 7
2.1. Study Criteria ...................................................................................................................... 7
2.2. Study Case Development .................................................................................................... 7
2.3. Scenario Cases Studied ....................................................................................................... 8
3. Steady-State Assessment .......................................................................................................... 9
3.1. Benchmark Case ................................................................................................................. 9
3.2. Second Boone 230-115 kV Transformer Case ................................................................. 15
3.3. New Boone – Nyberg 115 kV Transmission Line Case ................................................... 17
4. Conclusions .............................................................................................................................. 21
Appendix A .................................................................................................................................... A-1 Appendix B .................................................................................................................................... B-1
Appendix C .................................................................................................................................... C-1
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
3
Executive Summary
Background
Transmission Planning identified the need to increase the reliability of the Rocky Ford/La Junta
portion of the Black Hills system and proposed the “Second Boone 230/115 kV Transformer”
project. The benefit of adding a second 230-115 kV transformer at Boone to the reliability of the
Rocky Ford/La Junta portion of the Black Hills system was outlined in the “Second Boone 230/115
kV Transformer Project – Review” study report (April 23, 2012). This study also identified a new
Boone – Nyberg 115 kV transmission line as a viable alternative to the second Boone 230-115 kV
transformer.
This summer the Boone – DOT Tap – Nyberg 115 kV transmission line experienced heavy loading,
especially during periods of high transfers on the Lamar DC Tie and various combinations of
planned transmission line outages on the neighboring 230 kV & 345 kV systems.
The objective of the study was to review the performance of the “Second 230/115 kV Transformer”
project and the “New Boone – Nyberg 115 kV Transmission Line” during periods of high East-
West & West-East flows on the Lamar DC Tie. Also, determine whether the overloads observed on
the Boone – DOT Tap – Nyberg 115 kV were attributable to the generation at Pueblo Airport
Generating Station (PAGS) or the magnitude and direction of the flows on the Lamar DC Tie.
The heavy loading observed on the Boone – DOT Tap – Nyberg 115 kV is exacerbated when the
wind generation at Colorado Green is online, specifically during periods of high East-West flows
on the Lamar DC Tie.
Conclusions
In general the results show that a second 230-115 kV transformer at Boone does little to relieve the
heavy loading observed on the Boone – DOT Tap – Nyberg 115 kV transmission line during
periods of high transfers on the Lamar DC Tie coupled with Colorado Green wind generation. A
series of upgrades are required to create a robust system that meets the required performance
criteria for all but the most extreme scenarios (NERC/WECC Category D).
A new Boone – Nyberg 115 kV transmission line, constructed as a double circuit to
facilitate the upgrade of the existing Boone – DOT Tap – Nyberg 115 kV and to 230 kV
design standard. New 115 kV line positions at Nyberg and Boone. (Q4 2014 - $10M based
upon Baculite Mesa – West Station 115 kV 2011 project).
A second Boone 230-115 kV transformer to relieve the overloads on the existing
transformer during the worst case scenarios. (Q4 2014 - $7.9M TSG&T/Xcel Energy
estimate May 14, 2012).
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
4
Rebuild the Boone 115 kV facility rather than add more elements to the single bus. As
discussed in the “Second Boone 230/115 kV Transformer Project – Review” study report
the new line or the new transformer do not mitigate the impact of Boone 115 kV bus
contingency. (Cost & Schedule to be determined).
All stated costs are preliminary and do not convey any commitment of behalf of the affected
entities.
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
5
1. Introduction
Transmission Planning identified the need to increase the reliability of the Rocky Ford/La Junta
portion of the Black Hills system and proposed the “Second Boone 230/115 kV Transformer”
project. The benefit of adding a second 230-115 kV transformer at Boone to the reliability of the
Rocky Ford/La Junta portion of the Black Hills system was outlined in the “Second Boone 230/115
kV Transformer Project – Review” study report (April 23, 2012). This study also identified a new
Boone – Nyberg 115 kV transmission line as a viable alternative to the second Boone 230-115 kV
transformer.
This summer the Boone – DOT Tap – Nyberg 115 kV transmission line experienced heavy loading,
especially during periods of high transfers on the Lamar DC Tie and various combinations of
planned transmission line outages on the neighboring 230 kV & 345 kV systems.
Figure 1: Boone 230/115/69 kV Transmission Substation
The objectives of the study were:
To review the performance of the “Second 230/115 kV Transformer” project and the “New
Boone – Nyberg 115 kV Transmission Line” during periods of high East-West & West-East
flows on the Lamar DC Tie.
To determine whether the overloads observed on the Boone – DOT Tap – Nyberg 115 kV
were attributable to the generation at Pueblo Airport Generating Station (PAGS) or the
magnitude and direction of the flows on the Lamar DC Tie.
The heavy loading observed on the Boone – DOT Tap – Nyberg 115 kV was exacerbated when the
wind generation at Colorado Green was online, specifically during periods of high East-West flows
on the Lamar DC Tie.
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
6
Figure 2: Expected 2015 Black Hills Colorado Electric Transmission System
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
7
2. Study Methodology
The BHCE transmission system was evaluated with planned system additions for 2015 under peak
summer load levels to identify any deficiencies in system performance. Steady state voltage and
thermal analyses was performed. Additional upgrades were identified and modeled as necessary to
mitigate any reliability criteria violations. A list of prior and forced outages used in the study
process was included in Appendix A.
2.1. Study Criteria
The criteria used in this analysis is consistent with the NERC TPL Reliability Standards, WECC
TPL – (001 thru 004) – WECC – 1 – CR ─ System Performance Criteria. Pre-existing voltage and
thermal loading violations outside the localized study area were ignored during the evaluation.
2.1.1. Steady State Voltage Criteria
Under system intact conditions, steady state bus voltages must remain between 0.95 and 1.05 per
unit. Following a Category B or C contingency, bus voltages must remain between 0.90 and 1.10
per unit.
2.1.2. Steady State Thermal Criteria
All line and transformer loading must be less than 100% of their established continuous rating for
system normal conditions (NERC/WECC Category A). All line and transformer loadings must be
less than 100% of their established continuous or emergency rating under outage conditions
(NERC/WECC Category B and C). BHCE utilizes an allowable overload on transformers of up to
125% of the continuous thermal rating for emergency situations. Normal continuous ratings are
assumed for all non-BHCE facilities.
2.2. Study Case Development
A modified WECC approved 2014 heavy summer case used for the BHCT-G10 Generation LGIR
Study and the Second Boone 230-115 kV Transformer Review Study was used to test the
performance of the 2015 scenario. The case included the following planned system upgrades and
changes:
Pueblo Generation Units 5 & 6 suspend operations 2012
Busch Ranch I Wind Project in-service date 12-31-2012
W.N. Clark Generation Units 1 & 2 retirement 2013
Busch Ranch II Wind Project in-service date 10-01-2014
Pueblo Airport Generating Station Unit 3, 40 MW simple-cycle, natural gas-fired turbine,
preliminary in-service date 2016 (included)¹ BHCE/BHCI FAC-009 Facility Rating Document Revision U (08-10-2012)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
8
Reader-Rattlesnake Butte 115 kV line – 2012
Greenhorn-Reader 115 kV line upgrade – 2012
Portland – West Station 115 kV #1 line upgrade and #2 new line - 2012
Pueblo-Hyde Park-West Station 115 kV line upgrade – 2013
Reader 115-69 kV transformers T1 & T2 replacement - 2013
Canon City 115 kV Capacitor Bank - 2013
La Junta – Tri-State Interconnect project (2014) o New 115 kV transmission line between La Junta (BHCE) and La Junta (TSG&T) o La Junta (BHCE) 115/69 kV transformer T1, replaced with unit rated 42 MVA o La Junta (BHCE) 115/69 kV transformer T2, new unit rated 42 MVA o La Junta (BHCE)-Rocky Ford 69 kV CT increase rating to conductor limit o Boone-La Junta (BHCE) 115 kV CT increase rating to conductor limit o Boone-Boone Tap 69 kV CT increase rating to conductor limit o Rocky Ford-S. Fowler Tap 69 kV CT increase rating to conductor limit
Overton 115 kV substation and Baculite Mesa-Overton-Northridge 115 kV upgrade –
2015 (project not fully defined so not included)
Colorado Green wind generation at 20 MW
It should be noted that the San Luis Valley-Calumet-Comanche transmission project and the Lamar
Front Range transmission project were not included in the 2015 study cases. A detailed listing of
the case updates is available upon request.
2.3. Scenario Cases Studied
The benchmark study was with all facilities in-service and the output of the Lamar DC Tie set at
200 MW East -West, 100 MW East - West, 100 MW West – East and 200 MW West – East. A set
of contingency studies were then performed under each of the following scenarios:
Benchmark, system prior to any upgrades.
Second Boone 230/115 kV 150 MVA Transformer (planned 2014) in-service
New Boone – Nyberg 115 kV Transmission Line in-service.
1 PAGS Unit #3 was included in the case based on the Baseline Expansion Plan within the 2012 BHCE Electric
Resource Plan. Actual siting of this resource is TBD.
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
9
3. Steady-State Assessment
The BHCE transmission system consists of three distinct regions within the BHCE service
territory. The Cañon City area is located at the western end of the system, and is served via
230/115 kV transformer at West Cañon, the West Cañon-Poncha 115 kV line, and the Portland-
West Station 115 kV lines. The Pueblo area lies in the center of the service territory and consists of
the region surrounding the city of Pueblo, extending eastward to Boone. The Rocky Ford area is
on the east end of the service territory and extends from Boone to La Junta. This study was
intended to illustrate the impact of the Lamar DC Tie upon the BHCE 115 kV System. Specifically
the loading on the Boone-DOT Tap-Nyberg 115 kV line during west to east flows on the tie and
loading West Station-Desert Cove-Fountain Valley-Midway (WAPA) during east to west flows.
The results are described below. All stated costs are preliminary estimates based upon 2012 dollars
and do not convey any commitment of behalf of the affected entities.
3.1. Benchmark Case
3.1.1. Benchmark Results
Figure 3: Benchmark Case with System Intact (All Lines in Service)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
10
With the system intact all facilities were within their voltage and thermal limits for maximum East-
West & West-East flows at Lamar. It was noted that with 200 MW West-East at Lamar the Boone
– DOT Tap 115 kV line was loaded to 96% of its 100 MVA rating. Also, for 200 MW East-West at
Lamar the West Station-Desert Cove 115 kV line was loaded to 79% of its 80 MVA rating.
Figure 4: Benchmark Case with N-1 Contingency (Boone – Comanche 230 kV) & Lamar DC
Tie (200 MW West – East)
For West-East flows on the Lamar DC Tie, with respect to the Boone – DOT Tap 115 kV line
loading, the generation at the Pueblo Airport Generating Station (PAGS) was 15% effective and the
Lamar DC Tie was 17% effective. For East-West flows on the Lamar, with respect to the West
Station – Desert Cove 115 kV line loading, the generation at PAGS was 11% effective and Lamar
3% effective.
The term “effective” refers to the impact of the source (PAGS or Lamar) has on the loading of the
identified element. So an increase of 10 MW at PAGS produces an increase of 1.1 MW on the
West Station – Desert Cove 115 kV line for East-West flows on the Lamar DC Tie and a Boone –
Comanche 230 kV contingency. A decrease of 10 MW at PAGS produces reduction of 1.1 MW on
the West Station – Desert Cove 115 kV line for East-West flows on the Lamar DC Tie and a Boone
– Comanche 230 kV contingency.
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
11
With a planned/forced outage of the Boone – Comanche 230 kV line and 200 MW flowing West–
East on the Lamar DC Tie as shown in Figure 4, the following was observed:
Boone – DOT Tap 115 kV line 158% of its 100 MVA rating
Nyberg - DOT Tap 115 kV line 136% of its 119 MVA rating
Lamar DC Tie 36% effective and PAGS 14% effective
Figure 5: Benchmark Case with N-1-1 Contingency (Boone – Comanche 230 kV and Boone –
Midway 230 kV) & Lamar DC Tie (200 MW West – East)
With a planned/forced outage of the Boone – Comanche 230 kV and the Boone – Midway (PSCo)
line and 200 MW flowing West–East on the Lamar DC Tie as shown in Figure 5, the following
was observed:
Boone – DOT Tap 115 kV line 286% of its 100 MVA rating
Nyberg - DOT Tap 115 kV line 244% of its 119 MVA rating
Boone 230-115 kV T1 transformer 123% of its 150 MVA rating
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
12
Lamar DC Tie 119% effective and PAGS 0% effective (MW’s at the Lamar DC Tie produce a
change in MVA on the effected elements)
Also, with a planned/forced outage of the Boone – Comanche 230 kV and the Boone – Midway
(PSCo) line and 200 MW flowing East-West on the Lamar DC Tie, the following was observed:
Boone – DOT Tap 115 kV line 141% of its 100 MVA rating
Nyberg - DOT Tap 115 kV line 114% of its 119 MVA rating
Figure 6: Benchmark Case with N-1-1 Contingency (Midway – Fuller 230 kV and Midway –
Midway 230 kV) & Lamar DC Tie (200 MW East-West)
With a planned/forced outage of the Midway (PSCo) – Fuller 230 kV and the Midway (WAPA) –
Midway (PSCo) line and 200 MW flowing East-West on the Lamar DC Tie as shown in Figure 6,
the following was observed:
Fountain Valley – Desert Cove 115 kV line 113% of its 115 MVA rating
Fountain Valley – Midway (WAPA) 115 kV line 161% of its 80 MVA rating
Portland – Skala 115 kV line 125% of its 80 MVA rating
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
13
Desert Cove – West Station 115 kV line 192% of its 80 MVA rating
Lamar DC Tie 8-10% effective and PAGS 10-17% effective
Overloads on the Fountain Valley – Midway (WAPA) 115 kV and Desert Cove – West Station 115
kV lines were also observed for West-East flows on the Lamar DC Tie.
A complete list of the results can be found in Appendix C (Table C-1).
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
14
3.1.2. Benchmark Summary
West-East flows at the Lamar DC Tie increase the loading on the Boone – DOT Tap – Nyberg 115
kV line for N-0, N-1 and N-1-1 contingencies. The worst case contingency is a planned/forced
outage of the Boone – Comanche 230 kV and the Boone – Midway (PSCo) 230 kV lines with 200
MW flowing West–East on the Lamar DC Tie. The observed overloads on the Boone – DOT Tap
115 kV line (286%), Nyberg - DOT Tap 115 kV line (244%) and Boone 230-115 kV T1
transformer (123%) were directly attributable to the magnitude and direction of the flows on the
Lamar DC Tie. Although, for the majority of N-1-1 230 kV & 345 kV contingencies studied the
impact of the Lamar DC Tie was only twice that of the generation at PAGs (Lamar DC Tie 35%
effective and PAGS 14% effective).
Table 1: Benchmark Case – Worst Case Results (red) with Prior Outages (yellow)
Boone - Midway (PSCo) 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 94.9
DESRTCOV 115.00-W.STATON 115.00 #1 95.5
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 114.4 143.5 244.2
BOONE 115.00-DOT_TAP 115.00 #1 140.5 166.5 286
BOONE 115.00-BOONE 230.00 #T1 99.7 122.7
DESRTCOV 115.00-W.STATON 115.00 #1 105.6
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 121.4 111.9
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 124.8 111.6
Boone - Comanche 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 121.6 158
NYBERG 115.00-DOT_TAP 115.00 #1 105.3 136
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 111.6 104.7
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 121.8 109
Midway (PSCo) - Fuller 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 95.1
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 99.5 129.3
BOONE 115.00-DOT_TAP 115.00 #1 114.5 149.8
Midway (WAPA) - Nixon 115 kV #1 FTN_VLY 115.00-MIDWAYBR 115.00 #1 98.5
DESRTCOV 115.00-W.STATON 115.00 #1 129 123.6 112.3 106.6
MIDWAYBR 115.00-MIDWAYBR 230.00 #1 127.5 123.7 115.8 111.6
Midway (WAPA) - Midway (PSCo) 230 kV #1 FTN_VLY 115.00-DESRTCOV 115.00 #1 113 104.6
FTN_VLY 115.00-MIDWAYBR 115.00 #1 160.5 148.3 122.9 109.9
PORTLAND 115.00-SKALA 115.00 #1 125.1 114.5
DESRTCOV 115.00-W.STATON 115.00 #1 192.1 179.7 153.9 140.8
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 124 111.5
Contingency Overloaded ElementDC Tie 200
MW E-W
(%)
DC Tie 100
MW E-W
(%)
DC Tie 100
MW W-E
(%)
DC Tie 200
MW W-E
(%)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
15
East-West flows at the Lamar DC Tie increase the loading on the West Station – Midway (WAPA)
115 kV and Portland – West Canon 115 kV lines for N-0, N-1 and N-1-1 contingencies. The worst
case contingency is a planned/forced outage of the Midway (PSCo) – Fuller 230 kV line and the
Midway (WAPA) – Midway (PSCo) 230 kV bus tie with 200 MW flowing East-West on the
Lamar DC Tie. The observed overloads on the Fountain Valley – Desert Cove 115 kV line (113%),
Fountain Valley – Midway (WAPA) 115 kV line (161%), Portland – Skala 115 kV line (125%)
and Desert Cove – West Station 115 kV line (192%) were more attributable to the generation at
PAGS than the magnitude and direction of the flows on the Lamar DC Tie.
3.2. Second Boone 230-115 kV Transformer Case
3.2.1. Second Boone 230-115 kV Transformer Results
The benefit of adding a second 230-115 kV transformer at Boone to the reliability of the Rocky
Ford/La Junta portion of the Black Hills system was outlined in the “Second Boone 230/115 kV
Transformer Project – Review” study report. Unfortunately it has little impact on reducing the
loading of the Boone - DOT Tap - Nyberg 115 kV line during west to east flows on the tie.
Figure 7: Second Boone 230-115 kV Transformer Case with N-1-1 Contingency (Boone –
Comanche 230 kV and Boone – Midway 230 kV) & Lamar DC Tie (200 MW West – East)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
16
With a planned/forced outage of the Boone – Comanche 230 kV and the Boone – Midway (PSCo)
line and 200 MW flowing West–East on the Lamar DC Tie as shown in Figure 7, the following
was observed:
Boone – DOT Tap 115 kV line 284% of its 100 MVA rating
Nyberg - DOT Tap 115 kV line 243% of its 119 MVA rating
3.2.2. Second Boone 230-115 kV Transformer Summary
The benefit of adding a second 230-115 kV transformer at Boone to the reliability of the Rocky
Ford/La Junta portion of the Black Hills system was outlined in the “Second Boone 230/115 kV
Transformer Project – Review” study report. Unfortunately it has little impact on reducing the
loading of the Boone - DOT Tap - Nyberg 115 kV line during west to east flows at Lamar.
Table 2: Second Boone 230-115 kV Case – Worst Case Results (red) with Prior Outages
(yellow)
Boone - Midway (PSCo) 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
DESRTCOV 115.00-W.STATON 115.00 #1 96
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 114.6 143.7 242.7
BOONE 115.00-DOT_TAP 115.00 #1 140.7 166.8 284.3
BOONE 115.00-BOONE 230.00 #T1
DESRTCOV 115.00-W.STATON 115.00 #1 105.7
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 121.8 112.3
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 125 111.8
Boone - Comanche 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 125.1 162.1
NYBERG 115.00-DOT_TAP 115.00 #1 108.3 139.5
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 111.9 104.8
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 121.9 109
Midway (PSCo) - Fuller 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 103.2 134.1
BOONE 115.00-DOT_TAP 115.00 #1 118.9 155.5
Midway (WAPA) - Nixon 115 kV #1 FTN_VLY 115.00-MIDWAYBR 115.00 #1 98.8
DESRTCOV 115.00-W.STATON 115.00 #1 129.2 123.9 112.6 106.9
MIDWAYBR 115.00-MIDWAYBR 230.00 #1 127.4 123.6 115.7 111.5
Midway (WAPA) - Midway (PSCo) 230 kV #1 FTN_VLY 115.00-DESRTCOV 115.00 #1 113.3 104.8
FTN_VLY 115.00-MIDWAYBR 115.00 #1 160.9 148.7 123.2 110.2
PORTLAND 115.00-SKALA 115.00 #1 125.4 114.7
DESRTCOV 115.00-W.STATON 115.00 #1 192.4 180.1 154.3 141.1
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 124.1 111.6
Contingency Overloaded ElementDC Tie 200
MW E-W
(%)
DC Tie 100
MW E-W
(%)
DC Tie 100
MW W-E
(%)
DC Tie 200
MW W-E
(%)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
17
Although, in some contingencies studied the reduction in impedance at Boone 230 kV actually
increases the overloads on the Boone – DOT Tap – Nyberg 115 kV line. See Table 4.
3.3. New Boone – Nyberg #2 115 kV Transmission Line Case
3.3.1. New Boone – Nyberg #2 115 kV Transmission Line Results
The benefit of adding a new Boone – Nyberg 115 kV transmission line to the reliability of the
Rocky Ford/La Junta portion of the Black Hills system was outlined in the “Second Boone 230/115
kV Transformer Project – Review” study report. It also reduces the loading of the existing Boone -
DOT Tap - Nyberg 115 kV line during west to east flows on the tie. Unfortunately it increases the
loading upon the existing Boone 230-115 kV T1 transformer.
Figure 8: New Boone – Nyberg 115 kV Line Case with N-1-1 Contingency (Boone –
Comanche 230 kV and Boone – Midway 230 kV) & Lamar DC Tie (200 MW West – East)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
18
With a planned/forced outage of the Boone – Comanche 230 kV and the Boone – Midway (PSCo)
line and 200 MW flowing West–East on the Lamar DC Tie as shown in Figure 8, the following
was observed:
Boone – DOT Tap 115 kV line 129% of its 100 MVA rating
Nyberg - DOT Tap 115 kV line 112% of its 119 MVA rating
Boone 230–115 kV T1 transformer 118% of its 150 MVA rating
Table 3: New Boone – Nyberg 115 kV Case – Worst Case Results (red) with Prior Outages
(yellow)
Boone - Midway (PSCo) 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
DESRTCOV 115.00-W.STATON 115.00 #1 96.1
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 112.3
BOONE 115.00-DOT_TAP 115.00 #1 129.3
BOONE 115.00-BOONE 230.00 #T1 100.8 117.7
DESRTCOV 115.00-W.STATON 115.00 #1 106.1
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 121.9 111.8
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 125 111.6
Boone - Comanche 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
NYBERG 115.00-DOT_TAP 115.00 #1
BOONE 115.00-BOONE 230.00 #T1 72.3
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 111.8 104.1
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 121.8 108.8
Midway (PSCo) - Fuller 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1
BOONE 115.00-DOT_TAP 115.00 #1
Midway (WAPA) - Nixon 115 kV #1 FTN_VLY 115.00-MIDWAYBR 115.00 #1 98.4
DESRTCOV 115.00-W.STATON 115.00 #1 128.9 123 110.8 104.7
MIDWAYBR 115.00-MIDWAYBR 230.00 #1 127.5 123.9 116.3 112.4
Midway (WAPA) - Midway (PSCo) 230 kV #1 FTN_VLY 115.00-DESRTCOV 115.00 #1 113.2 104.4
FTN_VLY 115.00-MIDWAYBR 115.00 #1 160.8 148.2 122.1 108.7
PORTLAND 115.00-SKALA 115.00 #1 125.3 114.4
DESRTCOV 115.00-W.STATON 115.00 #1 192.3 179.6 153.1 139.6
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 124 111.2
Contingency Overloaded ElementDC Tie 200
MW E-W
(%)
DC Tie 100
MW E-W
(%)
DC Tie 100
MW W-E
(%)
DC Tie 200
MW W-E
(%)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
19
3.3.2. New Boone – Nyberg 115 kV Transmission Line Summary
The benefit of adding a new Boone – Nyberg 115 kV transmission line to the reliability of the
Rocky Ford/La Junta portion of the Black Hills system was outlined in the “Second Boone 230/115
kV Transformer Project – Review” study report. It also reduces, but does not eliminate the loading
of the Boone - DOT Tap - Nyberg 115 kV line during west to east flows on the tie. Also, it
increases the loading upon the Boone 230-115 kV T1 transformer during high west to east flows.
Table 4: BHCE 115 kV System – Worst Case Results (red) with Prior Outages (yellow)
Reader - Airport Memorial 115 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 101.1
West Station - Bacul i te Mesa 115 kV #1 & #2 NYBERG 115.00-DOT_TAP 115.00 #1 144.9 153.4 170.6 178.9
BACULITE MSA115.00-NTHRIDGE 115.00 #1 164.9 156.8 140.6 132.2
BOONE 115.00-DOT_TAP 115.00 #1 168.4 178.5 199 206
MIDWAYPS 115.00-NTHRIDGE 115.00 #1 160.9 151.5 132.6 122.8
Portland - West Station 115 kV #1 & #2 DESRTCOV 115.00-W.STATON 115.00 #1 108.3 103.3
W.CANON 115.00-W CANON 230.00 #T1 124.3 122 117.3 115
BOONE 115.00-DOT_TAP 115.00 #1 109.1
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 113.6 106.1
Midway - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 122.8 110.1
Reader - Airport Memorial 115 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 100.6
West Station - Bacul i te Mesa 115 kV #1 & #2 NYBERG 115.00-DOT_TAP 115.00 #1 154.1 162.4 178.1 185.9
BACULITE MSA115.00-NTHRIDGE 115.00 #1 156.6 149.1 133.8 126
BOONE 115.00-DOT_TAP 115.00 #1 179.4 189.2 207.9 217
MIDWAYPS 115.00-NTHRIDGE 115.00 #1 151.2 142.5 124.7 115.6
Portland - West Station 115 kV #1 & #2 DESRTCOV 115.00-W.STATON 115.00 #1 107.9 103
W.CANON 115.00-W CANON 230.00 #T1 124.3 122 117.3 115
BOONE 115.00-DOT_TAP 115.00 #1 98.1 113
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 113.7 106.2
Midway - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 122.8 110.1
Reader - Airport Memorial 115 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
West Station - Bacul i te Mesa 115 kV #1 & #2 NYBERG 115.00-DOT_TAP 115.00 #1
BACULITE MSA115.00-NTHRIDGE 115.00 #1 152.5 143.6 125.7 116.8
BOONE 115.00-DOT_TAP 115.00 #1 103.2 108.8
MIDWAYPS 115.00-NTHRIDGE 115.00 #1 146.4 136.1 115.2 104.7
BOONE 115.00-BOONE 230.00 #T1 109.9 105.2
Portland - West Station 115 kV #1 & #2 DESRTCOV 115.00-W.STATON 115.00 #1 107.2 101.6
W.CANON 115.00-W CANON 230.00 #T1 124.4 122 117.3 115.1
BOONE 115.00-DOT_TAP 115.00 #1
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 113.3 105.3
Midway - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 122.6 109.7
BOONE - NYBERG 115 PROJECT
BOONE 230-115 T2 PROJECT
NO SYSTEM UPGRADES
Contingency Overloaded ElementDC Tie 200
MW E-W
(%)
DC Tie 100
MW E-W
(%)
DC Tie 100
MW W-E
(%)
DC Tie 200
MW W-E
(%)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
20
With respect to contingencies on the BHCE 115 kV System around the Pueblo Airport Generating
Station (PAGS), the worst case scenario is a planned/forced outage of the West Station – Baculite
Mesa 115 kV Double Circuit and the Reader – Airport Memorial 115 kV line. It is interesting to
note that while the addition of the new Boone – Nyberg 115 kV line reduces the impact upon the
existing Boone – DOT Tap 115 kV line during west to east flows, it increases the loading upon the
Boone 230-115 kV T1 transformer during high east to west flows. The observed overloads on the
Boone – DOT Tap 115 kV line (206%), Nyberg - DOT Tap 115 kV line (179%) were mainly due
to the generation at PAGS (52%) rather than the magnitude and direction of the flows on the Lamar
DC Tie (8%). See Table 4: BHCE 115 kV – Worst Case Results.
Table 5: New Boone – Nyberg 115 kV Case – Colorado Green Wind Sensitivity (red) with
Prior Outages (yellow)
Boone - Midway (PSCo) 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
DESRTCOV 115.00-W.STATON 115.00 #1 96.1 100.6
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 110.3
BOONE 115.00-DOT_TAP 115.00 #1 135.2
BOONE 115.00-BOONE 230.00 #T1 100.8 177.9
DESRTCOV 115.00-W.STATON 115.00 #1 106.1 115.5
LAMAR_CO 115.00-LAMAR_CO 230.00 #T1 113.3
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 121.9 126.6
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 125 134.1
Boone - Comanche 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
NYBERG 115.00-DOT_TAP 115.00 #1
BOONE 115.00-BOONE 230.00 #T1
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 111.8 115.9
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 121.8 130.7
Midway (PSCo) - Fuller 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1
BOONE 115.00-DOT_TAP 115.00 #1
Midway (WAPA) - Nixon 115 kV #1 FTN_VLY 115.00-MIDWAYBR 115.00 #1 98.4 100.6
DESRTCOV 115.00-W.STATON 115.00 #1 128.9 131.2
MIDWAYBR 115.00-MIDWAYBR 230.00 #1 127.5 131.3
Midway (WAPA) - Midway (PSCo) 230 kV #1 FTN_VLY 115.00-DESRTCOV 115.00 #1 113.2 118.9
FTN_VLY 115.00-MIDWAYBR 115.00 #1 160.8 168.9
PORTLAND 115.00-SKALA 115.00 #1 125.3 132.5
DESRTCOV 115.00-W.STATON 115.00 #1 192.3 200.6
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 124 132.7
Contingency Overloaded ElementDC Tie 200 MW E-W
Co Green Wind 20 MW
(%)
DC Tie 200 MW E-W Co
Green Wind 160 MW
(%)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
21
The heavy loading observed on the Boone – DOT Tap – Nyberg 115 kV is exacerbated when the
wind generation at Colorado Green is included, specifically during periods of high East-West flows
on the Lamar DC Tie. See Table 5: New Boone – Nyberg 115 kV Case – Colorado Green Wind
Sensitivity.
4. Conclusions
Transmission Planning identified the need to increase the reliability of the Rocky Ford/La Junta
portion of the Black Hills system and proposed the “Second Boone 230/115 kV Transformer”
project. The benefit of adding a second 230-115 kV transformer at Boone to the reliability of the
Rocky Ford/La Junta portion of the Black Hills system was outlined in the “Second Boone 230/115
kV Transformer Project – Review” study report (April 23, 2012). This study also identified a new
Boone – Nyberg 115 kV transmission line as a viable alternative to the second Boone 230-115 kV
transformer.
This summer the Boone – DOT Tap – Nyberg 115 kV transmission line experienced heavy loading,
especially during periods of high transfers on the Lamar DC Tie and various combinations of
planned transmission line outages on the neighboring 230 kV & 345 kV systems.
The objective of the study was to review the performance of the “Second 230/115 kV Transformer”
project and the “New Boone – Nyberg 115 kV Transmission Line” during periods of high East-
West & West-East flows on the Lamar DC Tie. Also, determine whether the overloads observed on
the Boone – DOT Tap – Nyberg 115 kV were attributable to the generation at Pueblo Airport
Generating Station (PAGS) or the magnitude and direction of the flows on the Lamar DC Tie.
The heavy loading observed on the Boone – DOT Tap – Nyberg 115 kV is exacerbated when the
wind generation at Colorado Green is online, specifically during periods of high East-West flows
on the Lamar DC Tie.
In general the results show that a second 230-115 kV transformer at Boone does little to relieve the
heavy loading observed on the Boone – DOT Tap – Nyberg 115 kV transmission line during
periods of high transfers on the Lamar DC Tie and the Colorado Green wind generation online. A
new Boone – Nyberg 115 kV transmission line meets the required performance in all but the worst
case scenarios. A series of upgrades are required to create a robust system that meets the required
performance criteria for all but the most extreme scenarios (NERC/WECC Category D).
A new Boone – Nyberg 115 kV transmission line, constructed as a double circuit to
facilitate the upgrade of the existing Boone – DOT Tap – Nyberg 115 kV and to 230 kV
design standard. New 115 kV line positions at Nyberg and Boone. (Q4 2014 - $10M based
upon Baculite Mesa – West Station 115 kV 2011 project).
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
22
A second Boone 230-115 kV transformer to relieve the overloads on the existing
transformer during the worst case scenarios. (Q4 2014 - $7.9M TSG&T/Xcel Energy
estimate May 14, 2012).
Rebuild the Boone 115 kV facility rather than add more elements to the single bus. As
discussed in the “Second Boone 230/115 kV Transformer Project – Review” study report
the new line or the new transformer do not mitigate the impact of Boone 115 kV bus
contingency. (Cost & Schedule to be determined).
All stated costs are preliminary and do not convey any commitment of behalf of the affected
entities.
.
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
A-1
Appendix A
Steady State
Prior and Forced Outage Lists
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
A-2
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
A-3
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
A-4
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
B-1
Appendix B
Load and Resource
Assumptions
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
B-2
Table B1: Black Hills Colorado Load and Resource Assumptions
SCENARIO CA
NO
N_55
70083
CA
NO
N_59
70084
E_C
AN
ON
70160
PP
_M
INE
70306
PU
B_D
SL
S
70334
PU
EB
PL
NT
G1
70337
PU
EB
PL
NT
G2
70337
R.F
.DS
LS
70344
AP
T_D
SL
S
71001
BA
C_M
SA
GE
N1
71001
BA
C_M
SA
GE
N2
71002
BA
C_M
SA
GE
N3
71003
BA
C_M
SA
GE
N3
71003
BA
C_M
SA
GE
N3
71003
BA
C_M
SA
GE
N4
71004
BA
C_M
SA
GE
N4
71004
BA
C_M
SA
GE
N4
71004
BA
C_M
SA
GE
N5
71005
BU
SC
HR
WT
G1
71009
BU
SC
HR
WT
G2
71012
CO
MA
NC
HE
C1
70119
CO
MA
NC
HE
C2
70120
CO
MA
NC
HE
C3
70777
CO
GR
EE
N W
1
70701
CO
GR
EE
N W
2
70702
2015 Heavy Summer 0 0 0 0 10 20 7 10 10 90 90 40 40 20 40 40 20 40 29 29 355 360 804 10 10
Total BHCE Generation 535 MW
Total BHCE Load 466 MW
Area Import -69 MW
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
C-1
Appendix C
Comparison of the Study Results
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
C-2
Table C1: Benchmark Study Case Results (red) with Prior Outages (yellow)
Daniels Park - Comanche 345 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 96.6
DESRTCOV 115.00-W.STATON 115.00 #1 98.6
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 111.2 140.6
BOONE 115.00-DOT_TAP 115.00 #1 128.4 163.2
Daniels Park - Comanche 345 kV #2 COMANCHE 230.00-WALSENBG 230.00 #1 100
FTN_VLY 115.00-MIDWAYBR 115.00 #1 120.8 114.1 100.1
PALMER 115.00-MONUMENT 115.00 #1 111.3 104.7
PORTLAND 115.00-SKALA 115.00 #1 130.9 121.7 102.3
DESRTCOV 115.00-W.STATON 115.00 #1 148.8 146.1 131.6 124.4
KETTLECK 115.00-FLYHORSE 115.00 #1 103.7 98.4
MIDWAYPS 115.00-MIDWAYPS 230.00 #T1 104.2 98
Midway (WAPA) - Midway (PSCo) 230 kV #1 FTN_VLY 115.00-MIDWAYBR 115.00 #1 109.1
DESRTCOV 115.00-W.STATON 115.00 #1 133.9 131.2 112.9 103.8
PORTLAND 115.00-SKALA 115.00 #1 110.6
Midway - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 139 125.8
Boone - Midway (PSCo) 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 94.9
DESRTCOV 115.00-W.STATON 115.00 #1 95.5
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 114.4 143.5 244.2
BOONE 115.00-DOT_TAP 115.00 #1 140.5 166.5 286
BOONE 115.00-BOONE 230.00 #T1 99.7 122.7
DESRTCOV 115.00-W.STATON 115.00 #1 105.6
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 121.4 111.9
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 124.8 111.6
Boone - Comanche 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 121.6 158
NYBERG 115.00-DOT_TAP 115.00 #1 105.3 136
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 111.6 104.7
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 121.8 109
Comanche - Midway (PSCo) 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 96.4
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 110.9 140.3
BOONE 115.00-DOT_TAP 115.00 #1 128 162.9
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 117.9 110.5
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 123.3 110.7
DC Tie 200
MW E-W
(%)
Contingency Overloaded ElementDC Tie 100
MW E-W
(%)
DC Tie 100
MW W-E
(%)
DC Tie 200
MW W-E
(%)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
C-3
Table C1: Benchmark Study Case Results (red) with Prior Outages (yellow)
…..continued
System Intact BOONE 115.00-DOT_TAP 115.00 #1 95.1
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 99.5 129.3
BOONE 115.00-DOT_TAP 115.00 #1 114.5 149.8
Midway (WAPA) - Nixon 115 kV #1 FTN_VLY 115.00-MIDWAYBR 115.00 #1 98.5
DESRTCOV 115.00-W.STATON 115.00 #1 129 123.6 112.3 106.6
MIDWAYBR 115.00-MIDWAYBR 230.00 #1 127.5 123.7 115.8 111.6
Midway (WAPA) - Midway (PSCo) 230 kV #1 FTN_VLY 115.00-DESRTCOV 115.00 #1 113 104.6
FTN_VLY 115.00-MIDWAYBR 115.00 #1 160.5 148.3 122.9 109.9
PORTLAND 115.00-SKALA 115.00 #1 125.1 114.5
DESRTCOV 115.00-W.STATON 115.00 #1 192.1 179.7 153.9 140.8
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 124 111.5
Midway (WAPA) - Nixon 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 94.7
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 99.6 129.4
BOONE 115.00-DOT_TAP 115.00 #1 114.6 149.9
Midway (PSCo) - Ful ler 230 kV #1 AS ABOVE - - - -
Midway (WAPA) - Lincoln 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 96.6
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 104 133.8
BOONE 115.00-DOT_TAP 115.00 #1 119.8 155.2
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 125.2 118.6 104.8
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 116.6 103.7
Midway (WAPA) - West Canon 230 kV #1
System Intact PORTLAND 115.00-SKALA 115.00 #1 121.8 109.2
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 98.6 129.1
BOONE 115.00-DOT_TAP 115.00 #1 113.5 149.6
Portland - West Station 115 kV #2 PORTLAND 115.00-W.STATON 115.00 #1 115.5 107.9
West Canon - Ponchar (WAPA) 230 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 95.7
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 101.2 131.1
BOONE 115.00-DOT_TAP 115.00 #1 116.5 151.9
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 108.1 101.7
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 106.6 99.5
Contingency Overloaded ElementDC Tie 200
MW E-W
(%)
DC Tie 100
MW E-W
(%)
DC Tie 100
MW W-E
(%)
DC Tie 200
MW W-E
(%)
_________________________________________________________________________________________________________________
Lamar DC Tie and the BHCE 115 kV System August 22, 2012
C-4
Table C1: Benchmark Study Case Results (red) with Prior Outages (yellow)
…..continued
System Intact BOONE 115.00-DOT_TAP 115.00 #1 96.6
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 102 131.6
BOONE 115.00-DOT_TAP 115.00 #1 117.4 152.6
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 123.1 110.6
Midway (WAPA) - Nixon 115 kV #1
System Intact BOONE 115.00-DOT_TAP 115.00 #1 96.2
Boone - Comanche 230 kV #1 NYBERG 115.00-DOT_TAP 115.00 #1 101.8 131.5
BOONE 115.00-DOT_TAP 115.00 #1 117.3 152.4
Midway (WAPA) - Midway (PSCo) 230 kV #1 DESRTCOV 115.00-W.STATON 115.00 #1 104.1
Midway (WAPA) - West Canon 230 kV #1 PORTLAND 115.00-SKALA 115.00 #1 122.1 109.6
Contingency Overloaded ElementDC Tie 200
MW E-W
(%)
DC Tie 100
MW E-W
(%)
DC Tie 100
MW W-E
(%)
DC Tie 200
MW W-E
(%)