Process Hazard Analysis: Study Enhancement Keith V. Farrell, MS ChE PSM Coordinator INVISTA, Orange Plant 10/27/2009 1

Upload: kvfarrell

Post on 12-Jan-2015

274 views

Category:

Documents


1 download

DESCRIPTION

This is the Mary Kay OConner PSM symp. in 2009 for improvement of PHA speed and quality by introduction of simple tech.

TRANSCRIPT

Page 1: Kv Farell Pha Study Enhancement

Process Hazard Analysis: Study Enhancement

Keith V. Farrell, MS ChE

PSM Coordinator

INVISTA, Orange Plant

10/27/2009 1

Page 2: Kv Farell Pha Study Enhancement

Keith V. Farrell10/27/2009 2

Page 3: Kv Farell Pha Study Enhancement

Beginning Thoughts

The Three Laws of TechnologyThe Three Laws of Technology

By Arthur C. Clark

• When an engineer states that something is possible, he is almost certainly RIGHT. When he states that something is impossible, he is very probably WRONG.

• Any sufficiently advanced technology is indistinguishable from magic.

Keith V. Farrell10/27/2009 3

Page 4: Kv Farell Pha Study Enhancement

Study Objectives

• Federal Requirements

• Companies Requirements

• Tools

• Training

• “Bringing all Together”

• Cost and Savings

Keith V. Farrell10/27/2009 4

Page 5: Kv Farell Pha Study Enhancement

Federal Requirements

• OSHA CFR Title 29 §1910.119

– Process Safety Management of Highly Hazardous Chemicals

• EPA CFR Title 40 Part 68

– Chemical Accident Prevention Provisions

Keith V. Farrell10/27/2009 5

Page 6: Kv Farell Pha Study Enhancement

Company Requirements

• Accuracy and Precision

• Compliance

• Speed

Keith V. Farrell10/27/2009 6

Page 7: Kv Farell Pha Study Enhancement

Accuracy and Precision

• Right Recommendations

• Vague Recommendations

• Constrictive Recommendations

• Wrong Recommendations

Keith V. Farrell10/27/2009 7

Page 8: Kv Farell Pha Study Enhancement

Speed

• TIME IS MONEY!!!!

• Too Quick of a Pace for the Study

– Team Fails by Being Rushed

– Missed Consequences

• Too Slow of a Pace for the Study

– Team Fails by Tiring of Thinking

– Missed Consequences

– Unnecessary Consequences (Whines)

Keith V. Farrell10/27/2009 8

Page 9: Kv Farell Pha Study Enhancement

Tools

• Willing People

• Deep Knowledge

• Accessible Information

• Archiving and Accessing Captured Information for Study

• Equipment

• EIS

Keith V. Farrell10/27/2009 9

Page 10: Kv Farell Pha Study Enhancement

Tools

• People, Knowledge, Information, Computer Programs, Archiving Information, Access to Information

• Typical for All PHAs

Keith V. Farrell10/27/2009 10

Page 11: Kv Farell Pha Study Enhancement

Tools: Equipment

• Displaying Information

– Eye strain

– Comfort

• Markups of P&IDs

– To Keep the Team on Same “Page”

– Verbal Directions of Nodes

– Not Quick

• Derailing the Thought Train

Keith V. Farrell10/27/2009 11

Page 12: Kv Farell Pha Study Enhancement

Tools: Equipment, cont.

•Monitors for each Team Member & Space remaining for P&IDs

– Same Page Issue

– Quick Editing

– Comfortable

10/27/2009Keith V. Farrell

12

Page 13: Kv Farell Pha Study Enhancement

Tools: Equipment, cont.

•Document Camera to Project Drawings

– Use Basic Marked Drawings

– Lower Eye Strain

– Faster Information Recognition

– Visual Data preferred

10/27/2009Keith V. Farrell

13

Page 14: Kv Farell Pha Study Enhancement

EIS

Electronic Information Systems (EIS)

• What

• Where

• When

• How

Keith V. Farrell10/27/2009 14

Page 15: Kv Farell Pha Study Enhancement

EIS: Defined.

• Databases

• Information Availability

• Benefits

Keith V. Farrell10/27/2009 15

Page 16: Kv Farell Pha Study Enhancement

EIS: Databases

• PSI necessary for PHA

– PSI

– Alarms/ SIS

– SOLs

– PSV

– Process Control Points

– Process Information Points

– Procedures

Keith V. Farrell10/27/2009 16

Page 17: Kv Farell Pha Study Enhancement

EIS

• Proper Form of Database

– Accessibility

– User Friendly

– Updateable

– Protectable

Keith V. Farrell10/27/2009 17

Page 18: Kv Farell Pha Study Enhancement

WHAT FORM OF DATABASE?

• Software Needs Questions

– Stable

– Quick

– Ease of Use

– Expandable

– Software Life-span

Keith V. Farrell10/27/2009 18

Page 19: Kv Farell Pha Study Enhancement

Accessibility and User Friendly

• Questions to ask

– Who needs access

– What level of access

– Any training necessary

– Who will fix problems

– Who will maintain information

Keith V. Farrell10/27/2009 19

Page 20: Kv Farell Pha Study Enhancement

Expandable and Software Life-span

• What will be your PSI needs in the Future

• What software will be there at that time

Keith V. Farrell10/27/2009 20

Page 21: Kv Farell Pha Study Enhancement

Cost Analysis

• Equipment

• Software

• Training for Leaders

• Savings!!!!!!!

Keith V. Farrell10/27/2009 21

Page 22: Kv Farell Pha Study Enhancement

Equipment

• Seven Monitors @ $150 each

– Two – Operators

– Three– Engineers

– Two – Other Skill Sets

• One Document Camera @ $2000

• Other Minor Equipment @ $300

Keith V. Farrell10/27/2009 22

Page 23: Kv Farell Pha Study Enhancement

Software

• PHA Software (Current)

• Adobe Writer @$650

(Based on the assumption you have a computer and associated operational software)

Keith V. Farrell10/27/2009 23

Page 24: Kv Farell Pha Study Enhancement

Total Cost

• Equipment = $3350

• Software = $650

• Total = $3850

Keith V. Farrell10/27/2009 24

Page 25: Kv Farell Pha Study Enhancement

Training for Leaders

Necessary Training

•Basic Leader Development (In House?)

•Basic Instructor Development (In House?)

•Negotiating Development (In House?)

Items to consider

•Basic Interview Development

•Basic Speakers Development

Keith V. Farrell10/27/2009 25

Page 26: Kv Farell Pha Study Enhancement

Savings!!!!!!!

• Time for Initial Studies

– Normal; 5 to 8 weeks

– With Enhancements; 3 to 4 weeks

• Using one Operator & two Engineers; combined cost $270/hr

• Time Savings ~$11,300 per study

Keith V. Farrell10/27/2009 26

Page 27: Kv Farell Pha Study Enhancement

Savings, cont.

• Time for Revalidation Studies

– Normal; 2 to 4 weeks

– Enhanced; 1 to 8 study days

• Using one Operator & two Engineers; combined cost $270/hr

• Time Savings ~ $11,300 for each study

Keith V. Farrell10/27/2009 27

Page 28: Kv Farell Pha Study Enhancement

The Bottom Line

• Hardware and Software Total = $3350

• Savings per study = ~ $11,300

• Net Saving for the first Study = $7,450

Keith V. Farrell10/27/2009 28

Page 29: Kv Farell Pha Study Enhancement

Last Comment

Keith V. Farrell10/27/2009 29

DesiredDesiredResultsResults

PSIPSI

PH

AP

HA

Changes

Changes

Page 30: Kv Farell Pha Study Enhancement

THANKS

•Mary Kay O’Connor Process Safety Center

•Dr. M. Sam Mannan

•INVISTAKeith V. Farrell

10/27/2009 30

Page 31: Kv Farell Pha Study Enhancement

A Few Questions????