the essential guide to feasibility planning and construction procurement for junior mining companies...

Upload: tina-co

Post on 04-Jun-2018

221 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    1/38

    FINANCIAL INSTITUTIONS

    ENERGY

    INFRASTRUCTURE, MINING AND COMMODITIES

    TRANSPORT

    TECHNOLOGY AND INNOVATION

    PHARMACEUTICALS AND LIFE SCIENCES

    Part 2 Detailed engineeringand constructionAn essential guide to feasibility planning andconstruction procurement for junior mining

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    2/38

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    3/38

    A NORTON ROSE LLP GUIDE

    AUGUST 2011

    Part 2 Detailed engineeringand constructionAn essential guide to feasibility planning andconstruction procurement for junior mining

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    4/38

    Part 2 Detailed engineering and construction

    Norton Rose Group

    Norton Rose Group is a leading international legal practice. With more

    than 2600 lawyers, we oer a full business law service to many of the

    worlds pre-eminent nancial institutions and corporations from oces

    in Europe, Asia Pacic, Canada, Africa and the Middle East. We are strong

    in nancial institutions; energy; infrastructure, mining and commodities;

    transport; technology and innovation; and pharmaceuticals and life

    sciences. Norton Rose Group comprises Norton Rose LLP, Norton Rose

    Australia, Norton Rose OR LLP, Norton Rose South Africa (incorporated

    as Deneys Reitz Inc.), and their respective aliates.

    nortonrose.com

    The purpose of this publication is to provide information as to developments in the law. It does not contain a full

    analysis of the law nor does it constitute an opinion of Norton Rose LLP on the points of law discussed.

    No individual who is a member, partner, shareholder, director, employee or consultant of, in or to any constituent

    part of Norton Rose Group (whether or not such individual is described as a partner) accepts or assumes

    responsibility, or has any l iability, to any person in respect of this publication. Any reference to a partner or

    director is to a member, employee or consultant with equivalent standing and qualications of, as the case may

    be, Norton Rose LLP or Norton Rose Australia or Norton Rose OR LLP or Norton Rose South Africa (incorporated as

    Deneys Reitz Inc) or of one of their respective aliates.

    Norton Rose LLP NR11049 08/11 (UK)

    Extracts may be copied provided their source is acknowledged.

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    5/38

    Contents

    04 Summary

    05 Introduction

    07 EPC contracts

    20 EPCM contracts

    30 Appendix 1

    32 Contacts

    Contents

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    6/38

    Summary

    The importance of a robust strategy for the procurement of a mining

    project, from project inception through to construction implementation,

    can not be underestimated. Full consideration of the key procurement

    issues identied in this guide can often mean the dierence between

    achieving a bankable project with optimal returns for the mining

    company, and an expensive project failure.

    Part 2 Detailed engineering and construction

    04 Norton Rose LLPAugust 2011

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    7/38

    Introduction

    GeneralThis is the second part of a two part guide exploring the key steps and

    considerations to be made by junior mining companies (the Sponsors)

    to achieve a project structure that is both bankable and able to deliver

    optimal returns for the Sponsors.

    On the assumption that the Sponsors have determined through a full and

    proper feasibility process that the project is economically viable, they

    must then consider how the project is to be delivered. We have producedseveral brieng papers on issues to be considered when looking to

    secure nance for projects in the mining sector, but a key aspect of

    securing such nance will be convincing lenders (or any debt repayment

    guarantor in the context of a Chinese debt solution) that the structure for

    project delivery is robust.

    In this part two we will look at the key considerations to be made by

    Sponsors in terms of achieving a construction structure that is both

    bankable and economically viable.

    Whilst this guide is primarily written from a western perspective, the

    increasing signicance of Chinese debt solutions in this sector should

    also be taken into account. This guide will therefore, as appropriate, also

    oer some insight into the contrasting issues to be considered in the

    procurement of mining projects in the context of a Chinese debt solution.

    BankabilityWe have explained the meaning of bankable or bankability in partone to this guide. To recap, the terms are usually used to describe a

    lenders view on the robustness of the project structure in terms of its

    ability to secure full repayment of outstanding debt, either through

    project delivery in accordance with Sponsor requirements or, in a default

    scenario, through appropriate recourse against the contractor (or other

    stakeholders (as appropriate)) responsible for project delivery.

    Norton Rose LLPAugust 2011 05

    Introduction

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    8/38

    In the context of detailed engineering and construction delivery,

    lenders will typically look for one nancially robust party to accept fullresponsibility for the delivery of the works on time, on budget and to

    meet the required technical and performance specication. The key

    candidates in this regard are typically large internationally recognised

    engineering and construction contractors.

    The identity of the contractor can certainly have an impact on the lenders

    view on bankability.

    The importance of achieving this single point of responsibility relates to adesire by the lenders to see the party with the deepest pockets bearing

    the entire risk of project delivery. To the extent that more than one party

    is responsible for delivery of the works (in terms of direct liability to the

    Sponsors), lenders will be concerned that either:

    there may be gaps in liability cover; or

    that there may be interface issues when it comes to identifying the

    party responsible for a failure; or, perhaps worst of all

    that the party identied as being responsible for a failure can not be

    held to account either because its liability is limited in some way under

    the terms of its contract with either the Sponsors or the EPC contractor

    (as the case may be) or more generally because it does not have the

    balance sheet to meet the liabilities in question.

    Contract structuresThe preferred option for delivery of the single point responsibility solutiondescribed above will typically come in the form of a turn key engineering,

    procurement and construction (EPC) contract.

    Whilst it is recognised that there are several internationally recognised

    forms of EPC contract, each oering a balanced approach to contracting

    risk, the hardening of the lending market in recent years (and especially

    post global nancial crisis (GFC)) has seen a move away from use

    of these forms, in the context of a limited recourse project nancetransaction, without signicant amendment. When procuring an EPC

    Part 2 Detailed engineering and construction

    06 Norton Rose LLPAugust 2011

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    9/38

    contractor, it is essential that there is transparency regarding likely lender

    requirements from the outset. Raising these points post selection of thepreferred EPC contractor will place the Sponsors in a weak bargaining

    position if (and more likely, when), as a consequence, the EPC contractor

    proposes additional contingent risk pricing.

    We have discussed above how the development of detailed design

    at feasibility stage may undermine the Sponsors ability to achieve a

    single point of responsibility solution without being exposed to inated

    construction pricing, either because there is a lack of appetite in the

    market to take on 3rd party design risk or because those parties willingto take on such design risk will only do so with a signicant amount of

    contingent risk pricing.

    In circumstances where the single point responsibility position described

    above can not be achieved, the Sponsors may look for alternative

    structures. In this respect, we will consider below, in the context of

    bankability considerations, the fundamental dierences between the

    EPC and the alternative engineering, procurement and construction

    management (EPCM) contracting structures. In particular, we will

    identify the likely challenges when opting to use the EPCM structure in a

    hardening lending market.

    EPC contracts

    General

    Figure 1 below demonstrates a typical EPC contracting structure underwhich lenders and Sponsors will look for the EPC contractor to accept

    single point responsibility for all aspects of design and construction.

    Notwithstanding the fact that the Sponsors may be able to achieve this

    contractual structure, the bankability of the contracting structure will

    depend also on satisfaction of certain key lender requirements under

    the terms of the EPC contract. These key requirements will establish

    the obligations on the EPC contractor in terms of project delivery and

    importantly, the recourse available against the EPC contractor in a defaultscenario.

    Norton Rose LLPAugust 2011 07

    EPC contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    10/38

    Figure 1 typical EPC contracting structure

    In order to gain a better understanding of the approach being seen more

    recently by lenders in the mining sector, it would be helpful for us to set

    out what we see as being those key commercial terms that lenders will

    typically be looking for under the terms of an EPC contract.

    Key lender requirementsDesign risk

    As we have indicated earlier in part 2 of this guide, the lenders ideal

    position will be for the party delivering the works to be responsible for

    all aspects of the works, including design (whether or not produced

    by the party assuming responsibility for the works). This transfer of

    responsibility should even extend to mistakes in the Sponsors own

    stated initial design requirements. If this design risk transfer is not

    achieved, the risk to the Sponsors of cost overrun could be signicantsince there is likely to be increased exposure to claims for additional time

    and money resulting from the requirement to remediate errors identied

    in 3rd party design.

    Since the liability for cost overruns in the circumstances described above

    may be signicant, it is unlikely that this risk may be backed o fully with

    the party ultimately responsible for producing the design in question. It

    is more likely therefore that the residual cost overrun risk will rest with

    the Sponsors. Whilst in the rst instance, this is clearly a concern for theSponsors, lenders will also be concerned to see that the Sponsors are

    able to manage the potential nancial consequences.

    Mining company

    EPC contractor

    Sub-contractor BSub-contractor A Sub-contractor C

    EPC contract

    Part 2 Detailed engineering and construction

    08 Norton Rose LLPAugust 2011

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    11/38

    Whilst the intention of the parties may be for the EPC contractor to accept

    entire responsibility for the adequacy, accuracy and completeness ofdesign, the lenders will nonetheless want to assess fully the extent to

    which design risk may lter back to the Sponsors under the terms of the

    EPC contract. An example of where this may happen is in circumstances

    where the Sponsors accept the risk in certain sub-surface site conditions.

    For instance, the Sponsors may warrant the correctness of survey

    information relating to the site and accordingly the EPC Contractor will

    develop its detailed design and submit its tender price in accordance

    with the warranted information. However, if this information is incorrect,

    the risk in the design, and in particular the impact of the changes to thedesign required to reect actual sub surface conditions, will pass back to

    the Sponsors.

    In practice, the lenders technical adviser will review the risk prole

    proposed under the terms of the EPC Contract generally and will advise the

    lenders as to the Sponsors potential exposure to cost overrun risk arising

    from circumstances of the type described above. It will ultimately be for

    the Sponsors to either convince the lenders that any such risk identied

    may be managed by the Sponsors. Sponsors should be aware that lenders

    may seek additional mitigation through equity contributions, additional

    security or appropriate contractual mitigants. In the alternative, Sponsors

    and/or their lenders will seek to push the risk in question back to the EPC

    contractor, which may of course have pricing consequences.

    Time and cost

    Whilst we have discussed time and cost risk specically in relation to

    design above, as a general point of principle, lenders will want to limitto the fullest extent possible the EPC contractors ability to claim for

    additional time and/or money under the terms of the EPC contract. Again,

    lenders will be concerned about the ability of the Sponsors to manage the

    nancial consequences that will accompany these time and cost claims

    and more generally the extent to which exposure to such claims may

    impact on the delivery of the works in accordance with the requirements

    of the EPC contract.

    Many of the international forms of EPC contract contain scope for timeand money claims being made by the contractor. For instance, FIDIC

    Norton Rose LLPAugust 2011 09

    EPC contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    12/38

    Silver Book places time and cost risk for the occurrence of changes in

    law, compliance with certain employer instructions and the discoveryof objects of antiquity at the works site with the employer. Whilst on

    balance this may not appear unreasonable, the employers potential cost

    and loss of revenue exposure arising as a result of accepting these risks

    may be signicant. We have seen more recently lenders pushing back on

    the acceptance by Sponsors of these types of risk, allowing for contractor

    time and money claims only in very limited circumstances.

    The key point to recognise is that the acceptance by the Sponsors of any

    aspect of time and/or cost risk will undermine the xed price assumptionsought under the EPC structure. On the assumption that lenders can

    get comfortable with this type of risk being retained by the Sponsors,

    the Sponsors should themselves think very carefully before accepting

    such risks. The potential exposure to additional costs will need to be

    appraised fully by the Sponsors as will any potential impact on the

    nancial model for the project. The Sponsors should ideally seek board

    buy-in to any such proposals, and in particular to the commitment of

    additional equity as may be required at an early stage in the project.

    Parent company buy-in may also be necessary particularly where nance

    guarantees will be required. We would additionally expect the sponsors

    to formulate a strategy for managing any such risks. A lets wait and

    see approach is unlikely to be satisfactory, since it is likely that prompt

    and calculated action will be necessary on the occurrence of the risk in

    question if the Sponsors nancial exposure is to be mitigated to fullest

    extent possible.

    Delay damagesTo the extent that the works are completed on a date later than that xed

    under the terms of the EPC contract, the contract will typically include

    provision for payment of liquidated and ascertained damages (LADs).

    These LADs will typically be paid at a daily rate to cover anticipated lost

    revenue and costs (including debt service costs (as applicable)) during

    the period of delay. It would be unusual for the EPC contractor to accept

    unlimited exposure in this regard and any liability sub-cap agreed will

    typically be sized to the level of LADs payable up to the construction

    long stop date. Whether or not any such sub-cap will fall within thecontractors overall liability cap is likely to be an area of debate between

    10 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    13/38

    lenders and the EPC contractor. This issue will tend to be considered by

    lenders in the context of the EPC security package as a whole and we willdiscuss this point in further detail below.

    Performance liability

    Following completion of construction and the handover of the works, the

    Sponsors and the lenders will be keen to ensure that the plant is able

    to achieve certain performance guarantees. These are required in order

    to provide both parties with a degree of comfort that projected project

    revenues can be achieved by the completed plant over a sustained

    period. It is usual therefore for the EPC contract to also document therequirement for a post completion testing regime.

    To the extent that the required performance guarantees can not be

    achieved for a sustained period of operations, the EPC contractor will

    typically be liable for payment of performance liquidated damages up to

    an agreed liability cap. The damages will usually be sized according to

    the loss of revenue and/or prot occasioned by the performance shortfall

    for a nite period of time.

    It would be extremely unusual for the Sponsors to achieve a life of mine

    performance guarantee and, as such, it would be usual for the liability

    cap in relation to performance damages to be capped at the Sponsors

    loss of revenue and/or prot for a specically negotiated period. Whilst

    residual liability will be a Sponsor risk, it would be usual for Sponsors to

    manage this risk by building headroom into the nancial model for the

    project.

    The pre and post handover testing regime will be subject to scrutiny

    by the lenders technical adviser. If, for instance, it is apparent prior to

    handover of the works that the plant is not going to achieve the lenders

    base case performance/output requirements, the lenders would typically

    expect to see a right to reject the plant in its entirety with full recourse

    against the EPC contractor for debt outstanding. For obvious reasons, EPC

    contractors will tend to resist any such position. They may, for example,

    look for an extended period of additional testing in order to rene the

    plant and to achieve the required performance levels. If this is permitted,time and cost impact of this additional testing will tend to be at the EPC

    Norton Rose LLPAugust 2011 11

    EPC contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    14/38

    contractors risk and the lenders will typically seek to retain the right to

    reject at the conclusion of any such repeated testing, if a required level ofperformance is not demonstrated.

    Again, where detailed process design is not provided by the EPC contractor,

    it may be more dicult to require this party to accept performance risk in

    full, particularly in circumstances where the technology is more complex

    in nature. Carving out these types of risks from the EPC contractors

    liability under the terms of the EPC Contract is however likely to make

    potential lenders nervous for the reasons discussed above. Whilst

    lenders may accept the interface risk in this liability gap being lled bythe designer itself (whether under the terms of a design contract with the

    Sponsors or under the terms of a collateral warranty), it is often the case

    that the party providing the detailed process design is either unwilling or

    unable to accept the type and extent of liability for design failure that

    would usually rest with an EPC contractor under the terms of the EPC

    contract. If this is the case, lenders may require additional security from

    the Sponsors to bridge the liability gap.

    Limitations on liability

    As indicated above, a key consideration for lenders when considering

    lending into a mining project will be the extent to which they will have

    recourse against the EPC contractor for debt outstanding in an EPC

    contractor default scenario.

    There is, as may be expected, a tension between the lenders requirement

    for full coverage of debt outstanding from the EPC contractors security

    package and the legitimate requirement of a contractor to limit its liabilityexposure. It is not unusual however for lenders in the current market to

    look for an aggregate liability cap of up to 100 per cent of the contract

    price, especially where the works include an unproven technical solution.

    The lenders may however accept a lower liability cap of say 60-80 per

    cent of the contract sum in these circumstances on the basis that liability

    for certain key risks is excluded from the aggregate liability cap. It is not

    uncommon for instance for lenders to seek to exclude liabilities that are

    the subject of a sub-cap, such as delay or performance liquidated

    damages, from the aggregate liability cap.

    12 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    15/38

    The appropriate exclusions from the aggregate liability cap will be

    negotiated on a project specic basis by the lenders following adviserinput. The list of exclusions will typically include those liabilities that

    are not able to be limited at law (and this will require local law advice),

    those liabilities that are uninsurable and those liabilities that are not

    quantiable at the date of contracting.

    Security package

    As we have discussed above, to the extent that the EPC contractor fails

    to deliver the works, the lenders and, in the rst instance, the Sponsors,

    must have direct recourse against the EPC contractor to recovertheir losses. The lenders will ultimately control this process through

    restrictions placed on the Sponsors in the nance documentation. For

    instance, the lenders will not allow the Sponsors to use (and ultimately

    deplete) the EPC security package to replace a defaulting EPC contractor

    in circumstances where such replacement is unlikely, in itself, to secure

    delivery of the project. It is more likely in these circumstances that

    the lenders will look to call a default under the terms of the nance

    documentation, trigger its security over the project documentation and

    access the EPC security package to recover debt outstanding.

    The security provided by the EPC contractor in respect of its potential

    liabilities will typically be formed, in part, by a form or forms of liquid

    security.

    Liquid security and bonding

    When we talk of liquid security, we are talking about forms of security

    that should be as good as money in the bank for the Sponsors. TheSponsors should be able to claim any such monies by simply serving

    a demand on the party providing the security on behalf of the EPC

    contractor. Typical forms of liquid security are performance bonds,

    retention bonds and letters of credit, all usually provided by international

    banks with lender approved credit ratings.

    Leaving retention bonds to one side for the time being, the lenders in

    the current lending market will typically require the EPC contractor to

    procure performance security (ie, performance bonds and/or letters of

    Norton Rose LLPAugust 2011 13

    EPC contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    16/38

    credit) with a value no less than 15-20 per cent of the contract sum, but

    this may vary on a project specic basis. The lenders are however likelyto permit a step down in performance security coverage as the works

    progress to reect reduced risk in the project for the lenders. Typically,

    the level of performance security coverage may reduce by 50 per cent, for

    instance, following the completion of operational testing and will usually

    be discharged completely upon expiry of the defects liability period (ie,

    12-24 months post handover of the works).

    In the UK domestic market, there has been a shift in recent years in

    the surety market away from providing performance bonds of the typedescribed above. This is not to say that such bonds are not available,

    however procuring them can be prohibitively expensive. Instead the

    UK has increasingly seen use of conditional bonds under which the

    beneciary must rst establish the right to make a claim and the

    quantum of any claim before a call is made on the bond. Whilst a

    fraudulent claim under an unconditional bond of the type described

    above can be challenged, a conditional bond is more akin to a form of

    guarantee and for the reasons set below will be less attractive to both

    Sponsors and lenders.

    It is usual for lenders to also require that a xed amount of any payment

    being made to the EPC contractor is retained and held by the Sponsors

    as security for the remedying of defects subsequently discovered in the

    works. Unlike the performance security which secures more general

    performance by the EPC contractor under the terms of the EPC contract,

    retentions are held for a specic and dened purpose. However, in reality

    this is somewhat of a falsity as lenders generally view retentions as partof the wider security package available to the Sponsors, and ultimately

    the lenders, as security for non-performance by the EPC contractor.

    The level of retention required by lenders will vary but typically will be

    between 3-5 per cent of the contract sum. Instead of a cash retention

    being made on any payment to the EPC contractor, and to assist the

    EPC contractors cash ow, lenders will usually instead accept a form of

    retention bond as an alternative which will provide security for monies

    that would have otherwise been retained. Any such instrument should bein the same form as the performance bond discussed above, ie, provided

    14 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    17/38

    by an international bank with an approved credit rating and permitting

    claims for payment upon the presentation by the Sponsors of a demandfor payment. Again, any such bond should be as good as money in the

    bank for the Sponsors.

    To the extent that any advance payment is made to cover the cost of

    the ordering of plant and materials or mobilisation, lenders will expect

    the Sponsors to secure such payments by requiring the contractor to

    procure an advance payment bond. Again, any such bond should have

    the characteristics of the performance bond and the retention bond

    described above.

    Illiquid security and guarantees

    Outside of liquid forms of security, lenders will typically require a

    guarantee from the ultimate parent of the EPC contractor. The ultimate

    parent is usually a requirement as a shell holding company, for instance,

    with limited or no assets will not be acceptable to the lenders.

    In practice, lenders will carry out their own due diligence on the parent

    company proposed to ensure that it is suciently robust to meet its

    potential liabilities under the guarantee.

    Unlike the forms of liquid security described above, a guarantee of

    this kind will usually rst require the establishment by the Sponsors of

    liability against the EPC contractor, which the EPC contractor has failed

    to discharge. Furthermore, the Sponsors will run the risk that any claim

    made under the guarantee will be subject to challenge by the guarantor.

    Far from being akin to cash in the banks, the pursuit of a claim undera parent company guarantee can be a lengthily process which is why

    claims under the liquid forms of security will usually be the Sponsors

    rst port of call.

    Termination

    Lenders will tend to have certain minimum requirements in terms of the

    circumstances where they will expect the Sponsors to have the right

    to terminate the EPC contractor and access the EPC security package

    to either replace the defaulting EPC contractor and secure projectcontinuance or bring the project to an end. As we have indicated earlier,

    Norton Rose LLPAugust 2011 15

    EPC contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    18/38

    16 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    the lenders will control the actions of the Sponsors in this regard through

    the restrictions imposed on the Sponsors under the terms of the nancedocumentation.

    It would be usual for lenders to look for the EPC contract to contain a right

    to terminate the EPC contractor in circumstances where recourse against

    the EPC contractor may be limited in some way or where key requirements

    relating to performance are not achieved. Lenders will typically look for

    advance warning of any problems relating to the works so that armative

    action may be taken before the circumstances become critical.

    Lenders will be especially concerned to see that the losses recoverable

    on termination will (to the fullest extent possible) cover amounts

    outstanding under the terms of the nance documentation (ie, principal,

    interest and fees). The ability of lenders to recover these losses tends to

    be very dicult for the uninitiated to understand and accept this, but this

    is part and parcel of limited recourse project nancing where the lenders

    security is limited to the project and those responsible for delivering it.

    EPC contracts in a Chinese debt contextAs we discussed in part one of this guide, the focus of project scrutiny in

    the context of a Chinese debt solution will typically dier from that under

    a western project nance solution. The nature and extent of security

    typically required by Chinese lenders from the State of the Sponsor or its

    parent company (as the case may be) will tend to mean that the lenders

    themselves will be looking less closely at the project structure.

    Whilst the bankability requirements discussed above will not tend to bepressed by Chinese lenders, the Sponsors should themselves be looking

    to secure these positions and indeed this is likely to be a requirement of

    the relevant guarantor.

    In the context of a Chinese debt solution, Sponsors and guarantors must

    together take on an almost lender due diligence type approach towards

    the project structure and ensure that appropriate mechanisms are in

    place to secure completion of the works on time, on budget and to meet

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    19/38

    Norton Rose LLPAugust 2011 17

    a required performance and technical standards. Consideration of these

    issues in isolation and without lender support is often a new dynamic forsponsors.

    In the context of an Export Credit Agency (ECA) backed Chinese debt

    solution, we considered in part one to this guide the typical Chinese

    content requirement under the Sinosure policy. To recap, Sinosure is

    the ocial ECA for China and will provide lenders with political and

    commercial risk cover to support exports of Chinese goods and services.

    It will however be a condition of providing such cover that the export

    contract (for instance, an EPC contract with a Chinese contractor) has aChinese content of at least 60-70 per cent.

    It should be noted that whilst a breach of this requirement may

    have consequences for the Sponsors under the terms of the nance

    documentation, it would actually be unusual for Sponsors to ever have

    sight of the policy and hence be aware of the specic details of the

    Chinese content requirement. If the EPC contractor is a Chinese entity and

    has itself or through its agents procured the debt solution (as is often the

    case in this context), it is likely that the EPC contractor will have visibility

    on the specics of the Chinese content requirement and can therefore

    develop its design, procurement strategy and price accordingly. In these

    circumstances, any failure to meet the Chinese content requirement

    should be an EPC contractor risk under the terms of the EPC contract.

    There is a strong argument that the EPC contractor will be best placed to

    manage this risk in any event.

    We have set out above the key requirements that lenders are likely toseek under terms of the EPC contract in the context of a western debt

    solution, but it is recognised that these requirements may not always be

    achievable.

    Each project will see dierent positions that the EPC contractor will

    look to push back on, usually because it has not adequately priced for

    the risk in question. Whilst the obvious answer would be for the EPC

    contractor to price every risk, the real concern will be the extent to which

    EPC contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    20/38

    18 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    unknown risks can be priced sensibly without an unacceptable amount

    of contingent. Whilst the EPC contractor may be willing to oer a singlepoint of responsibility, the price on oer may not be acceptable to the

    Sponsors. In these circumstances, the Sponsors must consider how they

    will provide lenders with reassurance that the risk or risks in question can

    be managed by the Sponsors themselves.

    In the alternative, the Sponsors may wish to consider use of a dierent

    contracting structure, and we will consider this option in further detail

    below.

    Bribery Act new legislation for companies with UK linksWhilst not an issue that will directly aect the nancing of a mining

    project or more generally its economic viability, Sponsors incorporated

    in the UK or carrying out business or any part of their business in the

    UK should be considering very carefully the requirements of the

    Bribery Act 2010 (the Act).

    The Act will make it a criminal oence, for persons to whom the Act

    relates, to bribe another person or to be bribed, but perhaps most

    signicantly it also introduces a new criminal oence for corporates

    of failing to prevent bribery.

    Corporate entities can be guilty of this oence if an associated person,

    which given the scope of this denition is likely to include any EPC

    contractor or operator, carries out an act of bribery when acting on their

    behalf. It is important to recognise that the associated person does

    not need to be incorporated in the UK or indeed have any businessconnection with the UK.

    The only defence for an entity being prosecuted for failing to prevent

    bribery is to show that it had adequate procedures in place designed

    to prevent bribery being carried out on its behalf. Whilst the precise

    meaning of adequate measures is not clear, the UK Government

    has made available guidance as to the key principles to be followed.

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    21/38

    Norton Rose LLPAugust 2011 19

    Given the signicant scope and extraterritorial reach of the Bribery Act,

    it will be extremely important for Sponsors to rstly ensure that they haverobust internal policies in place to guard against bribery and secondly

    to ensure that its supply chain members have robust anti-corruption

    compliance programmes and are subject to appropriate due diligence

    and monitoring.

    Specic advice should be sought by Sponsors having any particular

    concerns about the scope and implications of the Act.

    EPC contracts key point summary In terms of delivery of the detailed engineering and construction

    phase of a project, Sponsors should, and lenders will, look for one

    nancially robust party to accept full responsibility for the delivery of

    all aspects of the works on time, on budget and to meet the required

    technical and performance specication. In achieving this single point

    of responsibility position there will be reduced risk that:

    there may be gaps in liability cover;

    there may be interface issues when it comes to identifying the party

    responsible for a failure; or

    the party identied as being responsible for a failure can not be held

    to account either because its liability is limited contractually or more

    generally because it does not have the balance sheet to meet the

    liabilities in question.

    If the single point of responsibility position can not be achieved,

    and on the assumption that lenders accept this, the Sponsors must

    consider how they will themselves manage the risk(s) in question

    and in particular the concerns identied above. The Sponsors should

    at an early stage plan for the management of the relevant risk(s) and

    obtain board approval to the provision of additional security (as may

    be necessary) and the nancial support that may be required upon

    materialisation of the risk(s) in question.

    EPC contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    22/38

    20 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    The lenders will have key requirements in terms of:

    the obligations on the EPC contract to deliver the works on time,

    on budget and to meet a required technical and performance

    specication; and

    the recourse available against the EPC contractor to the extent that it

    fails to discharge its obligations under the terms of the EPC contract.

    The preferred EPC contractor should be procured on the basis that these

    key requirements will be included in the form of EPC contract eventuallysigned. This will allow for certainty of EPC price at the conclusion of EPC

    procurement process and will mitigate the likelihood of price escalation

    following EPC contractor selection.

    EPCM contracts

    GeneralThe acronym EPCM is commonly mentioned in the same breath as the

    EPC structure described above. However, from both a structuring and risk

    allocation perspective, the two contracting solutions are fundamentally

    dierent. The confusion would appear to come from the shared use of the

    work construction in their titles. It is important however to recognise

    that an EPCM contract is (amongst other things) essentially a design and

    construction management contract and that no physical construction will

    actually be carried out by the EPCM contractor.

    The EPCM structure has been used extensively in the mining sector,

    especially in the years leading up to the global nancial crisis (GFC)

    where the lending market became more contractor friendly in terms of

    both risk allocation and pricing. However, post GFC the lending market

    has hardened and the liquidity gap has meant that lenders are now

    increasingly risk averse and far more selective about the projects they are

    willing to back.

    For the reasons set out below, the EPCM structure has tended to be lessattractive to lenders in the form typically employed in the mining sector

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    23/38

    Norton Rose LLPAugust 2011 21

    and so more challenging to achieve a project nancing. We will however

    consider below what the writers see as the likely requirements neededto bring an EPCM solution to market and importantly to attract project

    nance.

    The EPCM structureIn contrast with an EPC contract (and as mentioned above), the EPCM

    contractor does not undertake primary responsibility for delivery of the

    construction works. The EPCM contract is essentially a professional

    services contract under which the EPCM contractor will typically carry out

    the following services:

    Engineering services the EPCM contractor will typically be the party

    producing the basic design at feasibility stage or will be appointed

    post feasibility under the terms of the EPCM contract to complete the

    basic design developed by or on behalf of the Sponsors. The EPCM

    contractor will typically be responsible for overall co-ordination of

    design for the project to ensure that the completed works meet the

    required technical and performance specication (but note Appendix 1

    descibing the limited liability typically accepted by EPCM contractors in

    this regard).

    Procurement services the EPCM contractor will be responsible for the

    overall procurement strategy and will source contractors, consultants

    and the necessary plant and equipment in accordance with the

    Sponsors requirements and the assumptions established at feasibility

    stage. The EPCM will advise on the timing of the letting of the relevant

    packages and will advise the Sponsors on the terms available and willnegotiate the contract packages on the Sponsors behalf.

    Construction Management services the EPCM contractor will

    typically be responsible for overall management of the carrying out

    and completion of the works. This will include the co-ordination

    of the works and services being procured on the Sponsors behalf

    to achieve completion of the works in accordance with the project

    schedule, the project budget and to meet the required technical and

    EPCM contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    24/38

    22 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    performance specication (but again, note Appendix 1 and the limited

    liability typically accepted by EPCM contractors in this regard). Theconstruction management services will also typically include the

    management of health and safety at the site, the establishment of

    quality assurance systems and the management of the remedying of

    defective works and or services provided by other parties.

    Many mining clients are adopting a slight variant to the EPCM

    arrangement which is essentially a split EP & CM structure. Under this

    variant the Sponsors will appoint a rm generally with greater expertise

    in engineering design and, possibly procurement, as the EP Contractor.Sponsors then appoint a specialist construction management rm

    to appoint and manage the trade contractors and the rest of supply

    chain (including the engineering designer). This assists getting lenders

    comfortable that an appropriate party will be in place having expertise

    in procurement to ensure the best chance of success and avoiding cost

    overruns.

    Whilst the EPCM contractor will negotiate the terms of the contract

    packages, whether for delivery of works, services or the provision of plant

    and equipment, it is the Sponsors that will enter into direct contractual

    relations with the relevant third parties and assume the rights and

    obligations under the relevant contracts. For reference, we have set out

    below the typical EPCM structure.

    Mining company

    Contractor BCcontractor A Contractor C

    EPCM contractor

    EPCM contract

    Figure 2 typical EPCM contracting structure

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    25/38

    Norton Rose LLPAugust 2011 23

    It should be noted that we have structured arrangements for clients

    where the EPCM contractor actually enters into all of the trade contractoron behalf of the sponsors. The reasons being for particular project

    specic ECA coverage reasons. However, the EPCM contractor will, if well

    advised, insist on back to back protection for all liabilities under the

    trade contracts.

    As we have indicated above, the EPCM structure may be considered by

    Sponsors where the single point of responsibility EPC structure can not

    be achieved or is not attractive for one reason or another. This may be

    because:

    The securing of the single point of responsibility EPC solution may

    expose the Sponsors to inated pricing which may have an impact on

    project aordability and which may not be considered by the Sponsors

    to oer value for money;

    There may be a general lack of appetite in the market to take on the

    project in question on a turn key EPC basis;

    The Sponsors have a good track record in project delivery and have a

    large internal management resource and as a result prefer to adopt the

    EPCM structure to signicantly reduce overall outturn cost and increase

    equity returns.

    In the context of a mining project, the EPCM contractor will typically be

    the party developing the basic design at feasibility stage. This party will

    then be retained to develop the nal design and to provide the otherrelevant EPCM services for the construction phase of the project. This

    structure will obviously generate continuity in design responsibility

    throughout works planning and implementation and will typically allow

    for greater employer inuence in design evolution than would otherwise

    be available under the EPC structure.

    In considering the use of an alternative structure (and on the assumption

    that an EPC structure is otherwise achievable) the Sponsors will typically

    EPCM contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    26/38

    24 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    balance, amongst other things, the increased cost and reduced equity

    return that is likely to accompany use of the single point of responsibilityEPC solution against the corresponding key benets, namely, price

    certainty for project delivery and the increased likelihood of securing

    project nance. If the negatives of the EPC solution outweigh the

    positives, Sponsors may be inclined to consider use of an alternative

    contracting structure.

    EPCM and bankability

    The fundamental point for the Sponsors to consider will however be

    the extent to which the EPCM solution may be considered bankable bypotential lenders.

    A key dierence between the EPC and the EPCM solutions is that the

    EPCM solution does not oer a single point of responsibility for delivery

    of the works. There will be multiple interfaces which must be carefully

    managed by the EPCM contractor and the Sponsors and there will remain

    a risk that there may be gaps in liability or that a party identied as be

    liable for a failure will not, on its own or collectively with other culpable

    parties, be willing to accept the measure of liability typically recoverable

    by Sponsors when using the EPC structure.

    The provisions of the EPCM contract, in terms of both scope (as identied

    above) and liability for the services provided, will dier fundamentally

    from the terms seen in a typical EPC contract. To illustrate these

    dierences, we have provided at Appendix 1 to this guide a comparison

    between the key lender requirements under the EPC structure and the

    corresponding terms and risk allocation typically achieved in the contextof an EPCM structure.

    The reader should note that the summary at Appendix 1 provides only

    a high level overview for the purposes of comparing the risk allocation

    typically seen under the EPC and EPCM structures. There will of course

    be exceptions to these positions on a case by case basis. To provide a

    more detailed picture, we provide our clients with EPC and EPCM risk

    matrices that essentially show the positions taken on the key risk issues

    on recent projects closed in the mining sector. These invaluable tools

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    27/38

    Norton Rose LLPAugust 2011 25

    allow us to quickly identify the market position on any given risk and

    more particularly show how a particular risk allocation has been banked(if at all).

    From the high level summary at Appendix 1, it is apparent that the usual

    risk prole under the EPCM solution is far less favourable from the

    Sponsors (and ultimately the lenders) perspective when compared with

    the position typically secured by Sponsors under the EPC structure.

    It is easy to see why lenders prefer the certainty and security that comes

    with the EPC solution and also why many of the key principles underthat solution should gain support from the Sponsors. However, whilst

    risk allocation considerations are very important, Sponsors will also

    be looking at the commercial imperative of (a) bringing a project to

    market where, for instance, the EPC structure is not achievable and, (b)

    maximising equity returns from the project by securing a signicantly

    lower construction cost.

    EPCM key requirements

    We will consider below the more robust Sponsor approach to risk transfer

    typically adopted in other sectors, such as the petrochemicals sector,

    where the EPCM solution remains a popular contracting structure for

    project delivery (although not always on a project nance basis). On

    the face of it, there would seem no reason why a similar more Sponsor

    friendly approach to risk transfer should not be pursued in the mining

    sector.

    If the EPCM solution is to be considered, it will be important for theSponsors to rst satisfy themselves and ultimately the lenders that the

    proposed solution can oer a robust structure for project delivery. The

    following requirements will, in the writers view, be key to demonstrating

    a robust EPCM structure best equipped to secure project delivery:

    The selected EPCM contractor should be a robust experienced

    organisation with a strong track record of securing project delivery on

    an EPCM basis in the mining sector. The terms of the EPCM contract

    should reect an appropriate risk transfer to the EPCM contractor.

    EPCM contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    28/38

    26 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    In view of the more limited liability typically accepted by an EPCM

    contractor under the EPCM structure, the Sponsors should appointa full time experienced and well resourced internal team to monitor

    and manage the execution of the project in order to ensure that the

    Sponsors key requirements are being achieved and to permit early

    identication of issues that may impact on project delivery. There

    should be developed a clear internal strategy for the management and

    resolution of all risks retained in part or whole by the Sponsors.

    The contractors, service providers and equipment and plant suppliers

    should also be robust entities with experience and a track recordof project delivery in the mining sector. Where possible, these

    contracts should be nalised on a xed price basis with any limits on

    liability and security requirements being appropriately determined in

    accordance with the role assumed by the relevant party.

    The Sponsors should identify possible interface issues and put in

    place an appropriate mechanism to co-ordinate the completion of

    the works and to address the allocation of risks that may impact

    on delivery of the work. This mechanism should provide for prompt

    resolution of the relevant circumstances in a manner which does not

    detract in any material respect from project delivery.

    Whilst the points identied above will be important in developing

    robustness in the structure for project delivery, there is little doubt that

    potential lenders will seek from the Sponsors security for the residual

    risks that may be retained at Sponsor level under the EPCM solution. The

    nature and extent of this security will really depend on the lenders viewon the robustness of the project structure.

    Provided Sponsors are comfortable with the robustness an EPCM

    structure and the key requirements listed above can be achieved, the

    contracting freedom under a Chinese debt solution may make this

    nancing option more attractive, especially where security requirements

    for delivery of an EPCM and an EPC solution may not be substantially

    dierent.

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    29/38

    Norton Rose LLPAugust 2011 27

    A more robust view on EPCM risk transfer

    As Sponsors and contractors operating in the mining sector are usuallylarge sophisticated entities, it is perhaps surprising that the approach

    taken to risk transfer in the context of EPCM solutions has remained

    relatively simplistic in nature when compared to the approach taken in

    other sectors.

    Given that the role of an EPCM (or EP&CM) contractor will be

    fundamentally dierent to that adopted by an EPC contractor and given,

    as a consequence, the signicantly lower price paid for EPCM services

    when compared with that payable under a typical EPC contract, thewholesale transfer of risk from the Sponsors to the EPCM contractor will

    not be appropriate.

    However, use of more innovative ways to transfer risk to the contractor,

    without necessarily seeing a dollar for dollar pricing consequence,

    deserve more serious consideration in the mining context. Whilst use of

    these solutions will not, in themselves, secure a bankable position for

    the Sponsors, they will however create a more robust EPCM structure

    by ensuring that the EPCM contractor has skin in the game and is

    further motivated to secure project delivery in accordance with Sponsor

    requirements.

    Incentivisation

    The key aspect of the EPCM risk allocation in other sectors is the concept

    of incentivisation.

    Although sometimes seen in the mining sector, the nature and extentof its use is not of the order of that seen in other sectors. It is not really

    apparent why this is the case and the writers would simply put this down

    to Sponsors and contractors following approaches used previously. With

    no international standard form EPCM contract, there has previously been

    no real impetus to shift away from market practice. However, given the

    liquidity gap and the bankability issues discussed in this guide, it is

    perhaps clear that this approach requires a re-think.

    EPCM contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    30/38

    28 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    Incentivisation provisions will typically provide for EPCM contractors

    accepting nancial risk and reward in the achievement of key projectrequirements, including, completion of the works within the agreed

    project budget, completion of the works in accordance with the project

    programme and the nal works achieving key performance and other

    quality requirements. Again, we produce for clients risk allocation

    matrices demonstrating in more detail how key risks are allocated

    through incentivisation provisions under the EPCM structure in other

    sectors.

    Whilst these risks are not passed to the EPCM contractor in full, the EPCMcontractor will be accepting a degree of liability in the relevant risk, so

    will be more motivated to manage it. The key point to understand is that

    the EPCM contractor will be responsible for the nancial downside of the

    incentivisation provisions irrespective of whether it has used reasonable

    skill and care in managing the risk in question. There is therefore a clear

    imperative for the EPCM contractor taking ownership of the management

    of the risk in question from that date of contract to secure project delivery

    in accordance with the Sponsors requirements.

    There would ordinarily be concerns that the EPCM contractor will simply

    price the risk in question on a contingent basis, and this will of course

    not oer value for money for the Sponsors, particularly if the risk never

    materialises. These concerns however tend to be mitigated by the fact

    that the EPCM contractor s risk in the project will be limited to its agreed

    prot margin on which there should, in theory, be absolute transparency

    beyond the actual agreed cost for providing the EPCM services.

    Conversely, there will also typically be a bonus structure under which

    the EPCM contractor will receive additional payments for meeting and

    surpassing key project delivery requirements.

    EPCM key points summary An EPCM contract is essentially a professional services contract under

    which the contractor will accept no primary responsibility for the

    carrying out of the works.

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    31/38

    Norton Rose LLPAugust 2011 29

    The EPCM contractor will be responsible for:

    completion of detailed engineering;

    the procurement of contractors, service providers and plant and

    equipment suppliers on behalf of the Sponsors; and

    management of the carrying out and completion of the works on

    behalf of the Sponsors.

    The contracting structure under an EPCM solution is fundamentallydierent to that adopted under a typical EPC solution. Unlike the

    EPC solution, it will be the Sponsors, not the contractor (but see our

    comments above where this can be an option), that will enter into

    contractual relations with the contractors, service providers and plant

    and equipment suppliers responsible for delivery of the works.

    The risk prole under an EPCM solution is substantially more onerous

    from a Sponsor perspective when compared with the EPC structure. In

    order to attract project nance Sponsors will need to:

    demonstrate an allocation of risk between the Sponsors and the

    EPCM contractor appropriate in the post GFC lending market; and

    demonstrate to potential lenders how the risks retained by the

    Sponsors will be managed. It is likely, in any event, that Sponsors

    will be required by any potential lenders to provide additional

    security in respect of these risks.

    Given the level of risk retained by the Sponsors under the EPCM

    structure, it is likely that the level of security required by lenders from

    the Sponsors will be signicant. The level and nature of the security

    required from the Sponsors will be determined on a project specic

    basis and will depend on lenders view as to the robustness of the

    EPCM structure procured by the Sponsors.

    EPCM contracts

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    32/38

    30 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    Appendix 1

    Note: the reader should note that this summary provides only a high level

    overview for the purposes of comparing the risk allocation typically seen

    under the EPC and EPCM structures. There will of course be exceptions to

    these positions on a case by case basis. To provide a more detailed picture,

    we provide our clients with EPC and EPCM risk matrices that essentially

    show the positions taken on the key risk issues on recent projects closed

    in the mining sector. These invaluable tools allow us to quickly identify

    the market position on any given risk and more particularly show how a

    particular risk allocation has been banked (if at all).

    EPC riskallocation

    Typical EPCM position EPCM riskallocation

    Risk typicallytransferred tothe contractor

    EPC EPCM

    Contractor to beresponsible forcompleting the

    works on time.

    The EPCM contractor will not usuallyguarantee delivering the works on timeand will therefore not usually have

    responsibility for the payment of delayliquidated damages in this regard.

    Any damages recoverable from othercontractors, who are identified asbeing responsible for delayedcompletion of the works, will nottypically be of the order recoverableunder the EPC structure (eitherbecause of quantum or cappingarrangements agreed).

    Nominal delay liquidated damages maybe payable by the EPCM contractorto the extent that the design, or otherdeliverables for which the EPCMcontractor is responsible, are deliveredotherwise than in accordance withthe project programme.

    The EPCM contractor will be responsiblefor managing the overall worksprogramme and any failure to usereasonable skill and care in doing sowill give rise to liability. Any suchliability will usually be restricted to acontractual damages claim and willbe subject to the limitations onliability identified below.

    As the delaydamagesrecoverable

    from the EPCMcontractor,and any othercontractorsidentifiedas beingresponsiblefor delayedcompletionof the works,will not besufficient

    to cover theSponsorspotential lossin revenueand debtservice costsoccasionedby such delay,the financialrisk of delayedcompletionof the workswill ultimatelyrest with theSponsors.

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    33/38

    Norton Rose LLPAugust 2011 31

    EPC riskallocation

    Typical EPCM position EPCM riskallocation

    Risk typicallytransferred tothe contractor

    EPC EPCM

    Completionof works for alump sum fixedprice.

    The EPCM contractor will not usuallyguarantee the overall outturn cost ofthe works.

    The EPCM contract will provide forthe EPCM contractor setting thebudget and managing adherence tothe budget. Any failure by the EPCM

    contractor to use reasonable skilland care in doing so will give rise toliability. Given the limits on the EPCMcontractors liability typically agreedunder the terms of an EPCM contract(see below), it is unlikely thatliability for any significant costoverrun will be recoverable from theEPCM contractor.

    In procuring the works, servicesand plant and equipment supply

    packages on behalf of the Sponsors,the EPCM should attempt to procuresuch packages on a fixed pricebasis. However, this is not alwayspossible. Notwithstanding the factthat fixed price solutions may beachieved, the multiple interfaceswill however widen the scope fortime and money claims by the thirdparty contractors which will be aSponsor risk to the extent that theliability giving rise to any such claimcan not backed off fully with othercontractors.

    Payments to the EPCM contractorfor services performed are typicallymade on a monthly basis based onactually costs incurred at agreedrates. The parties will usually agreea target final contract price witha capped sharing mechanism forsavings and any cost overrun.

    The Sponsorswill ultimatelyaccept the riskof anymaterial costoverrun.

    Appendix 1

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    34/38

    32 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    EPC riskallocation

    Typical EPCM position EPCM riskallocation

    Risk typicallytransferred to

    the contractor

    EPC EPCM

    EPC contractorto provideperformanceguaranteesin respect ofthe completedplant.

    The EPCM contractor typicallyaccepts full responsibility for thefinal design and for it meeting therequired technical and performancerequirements and will typically beresponsible for coordinating thedesign produced by other parties.

    Establishing that a performance

    failure has resulted from the designproduced by the EPCM contractorand not from the implementationof such design by other contractorsmay not always be straight forward.

    The liability of the EPCM contractorfor design failure will however belimited as set out below.

    Due tointerfaceissues relatingto identifyingthe partyresponsibleforperformancefailure and themore limitedliabilitiesaccepted byparties underthe EPCMstructure,it is morelikely that themajority of theliability for anysubstantive

    performancefailure willretained bythe Sponsors.

    Any limit onliability toprovidesufficientcoverage forrecovery of

    amountsoutstandingunder the termsof the financedocumentation.Appropriatecarve outs to beagreed inrespect ofwhich the EPCcontractorsliability will be

    unlimited.

    The EPCM contractors liability willtypically be limited to anythingfrom 50-100% the EPCM contractprice (which will typically be US$5-10m) or, as is more common in themining sector, re-performance of the

    services.Carve outs from the liability cap areusually limited to those liabilitiesthan can not be limited at law.Sums recoverable from the othercontractors in the aggregate (onthe assumption that the partiesresponsible can be held to account)are unlikely to be of the order ofsums recoverable from an EPCcontractor under the EPC structure.

    The Sponsors(andultimatelythe lenders)recoursefor recovery

    of debtoutstandingand otherlosses in aproject defaultscenario willbe limited.The residualliability inthis regardwill ultimatelybe a Sponsor

    risk.

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    35/38

    Norton Rose LLPAugust 2011 33

    EPC riskallocation

    Typical EPCM position EPCM riskallocation

    Risk typicallytransferred tothe contractor

    EPC EPCM

    Securitypackage toinclude liquidperformancesecurity,retentionsand parentcompany

    guarantees.

    Whilst parent company guaranteestend to be procured, it would be lessusual for EPCM contractors in themining sector to provide other liquidforms of security.

    The EPCM position in this regardis symptomatic of the nature and

    extent of liability being accepted bythe EPCM contractor.

    The nature and extent of thesecurity package obtainable fromcontractors, services providers andplant and equipment suppliers willbe determined on a project specificbasis.

    Sponsorsaccept cashflow riskduring theperiod inwhich a claimis establishedagainst

    the EPCMcontractorand sumsfor whichthe EPCMcontractoris liable arerecovered.

    /

    Appendix 1

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    36/38

    34 Norton Rose LLPAugust 2011

    Part 2 Detailed engineering and construction

    Contacts

    For further information, please contact:

    Mark Berry

    PartnerNorton Rose LLP

    Tel +44 20 7444 [email protected]

    Matthew Hardwick

    Associate

    Norton Rose LLPTel +44 20 7444 [email protected]

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    37/38

  • 8/13/2019 The Essential Guide to Feasibility Planning and Construction Procurement for Junior Mining Companies Part 2 Detai

    38/38

    nortonrose.com

    Norton Rose LLP

    Norton Rose LLP is a member of Norton Rose Group a leading