the critical path method (antonio prensa pmp, mba 2002) diapositivas - puerto rico
TRANSCRIPT
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
1/19
The Critical Path MethodThe Critical Path Method
Presented byAntonio Prensa,MBA, PMP, CCP, CSTE for ProjectManagement Institute Puerto Rico
Chapter
June 20, 2002
San Juan, Puerto Rico
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
2/19
"I believe that this nation shouldcommit itself to achieving a goal, before
this decade is out, of landing a man on
the moon..." - John F. Kennedy,
May 27,1961
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
3/19
On July 20, 1969, just eight years after Kennedy's
speech, Apollo 11 landed two men on the moon.This achievement was possible only with careful
production planning that included the critical path
method.
NASA used the critical path method to help
determine an efficient schedule for the tasks thatled to the moon landing.
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
4/19
Discussion Topics
BackgroundSome questions about the project
What is the Critical Path Method(CPM)?
Why the CPM?
How to use the CPM ?Questions and Answers
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
5/19
Background
The critical path method (CPM) wasinvented by project managers in theearly 1950's.
The US Navy adapted and improved itto manage the Polaris missile project inthe late 1950's
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
6/19
Some questions about the
project
How long will the entire project take tocomplete?
Which activities determine total projecttime?
Which activity times should beshortened, if possible, or in otherwords, how many resources should beallocated to each activity?
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
7/19
What is the CPMCPM?
Critical Path Method (CPM), is a procedure for
using network analysis to identify those tasks whichare on the critical path: ie where any delay in thecompletion of these tasks will lengthen the projecttimescale, unless action is taken.
For all tasks off the critical path, a degree oftolerance is possible (eg. late start, late completion,early start, etc.).
Network charts and CPM analysis used to be carriedout by hand.
Software is now available which requires the useronly to enter the tasks, duration of each task anddependencies upon other tasks; a network chart andCPM is then automatically created.
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
8/19
Why the CPM?
The CPMCPM formally identifies tasks whichmust be completed on time for the wholeproject to be completed on time
Identifies which tasks can be delayed for awhile if resource needs to be reallocated tocatch up on missed tasks
It helps you to identify the minimum length of
time needed to complete a projectThe CPM determines both the early start and
the late start date for each activity in the
schedule.
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
9/19
How to use the CPM?
Project Network DiagramAny schematic display of the logical relationshipsAny schematic display of the logical relationships
of project activities.of project activities.
1
3
2
5 7
4 6
8
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
10/19
How to use the CPM?
List the activitiesAnd relationships
List the activitiesAnd relationships
Create a startnode
Create a startnode
Draw arrows fromStart node to the
First activitys node
Draw arrows fromStart node to the
First activitys node
Sequentially
Arrange allActivities fromStart
Sequentially
Arrange allActivities from
Start
Repeat process
from successorsfor all activities
Repeat process
from successorsfor all activities
Double check for
missedrelationships
Double check for
missedrelationships
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
11/19
How to use the CPM?
EarlyStart (ES)
Late
Start (LS)
Early Finish(EF)
Late
Finish (LF)
Task duration
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
12/19
How to use the CPM?
Task ID Duration Dependency
A 7
B 3
C 6 A
D 3 BE 3 D,F
F 2 B
G 3 C
H 2 E,G
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
13/19
How to use the CPM?
FS
A
B
C G
H
D
F
E
(7) (6) (3)
(3) (3)
(2)
(3)
(2)
0
0
77 13 16
16 18
3 3 6
3 5
6 9
13
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
14/19
How to use the CPM?
FS
A
B
C G
H
D
F
E
(7) (6) (3)
(3) (3)
(2)
(3)
(2)
0
0
77 13 16
16 18
3 3 6
3 5
6 9
1816
16
16
13
13
13
13
770
13
13
10
11
107
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
15/19
How to use the CPM?
FS
A
B
C G
H
D
F
E
(7) (6) (3)
(3) (3)
(2)
(3)
(2)
0
0
77 13 16
16 18
3 3 6
3 5
6 9
1816
16
16
13
13
13
13
770
13
13
10
11
107
000
0
77
8
7
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
16/19
Summary
Critical Path Analysis is an effective andpowerful method of assessing:
Tasks which must be carried out
Where parallel activity can be carried outThe shortest time in which a project can becompleted
Resources needed to achieve a projectThe sequence of activities, scheduling, andtimings involved
Task priorities
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
17/19
Do you need more
information?
Project Management:A systems approach toPlanning, Scheduling, and Controlling Harold Kerzner, Six edition.
Project Management: A Managerial Approach Jack R. Meredith, Samuel J. Mantel, FourthEdition.
Web Search Engine key word: The CriticalPath Method or The CPM.
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
18/19
Contact me at:
Antonio Prensa Email: [email protected] /
Phone: (787) 751-9800 ext. 3725
-
8/9/2019 The Critical Path Method (Antonio Prensa Pmp, Mba 2002) Diapositivas - Puerto Rico
19/19
The Critical Path MethodThe Critical Path Method
Presented byAntonio Prensa,MBA, PMP, CCP, CSTE forProject Management Institute
Puerto Rico Chapter
June 20, 2002
San Juan, Puerto Rico