Department of General Services Division of Engineering & Buildings The Capital Outlay Process in Virginia January 24, 2008

Upload: others

Post on 15-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

Department of General ServicesDivision of Engineering & Buildings

The Capital Outlay Process in Virginia

January 24, 2008

Page 2: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

Commonwealth of Virginia’s agencies and institutions design and construct facilities which are:

•LARGE•COMPLEX•EXPENSIVE

Examples:•Laboratories•Hospitals•Prisons•Technology-intensive classrooms•Stadiums and arenas

Page 3: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

• These projects are constructed under the “capital outlay process”

• On major projects, this process can span over several years

• The process begins when an agency submits a Capital Budget Request to DPB and ends when the building is occupied for its intended use

Page 4: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

The Process Begins

• Agencies submit their Six Year Plan to the Department of Planning and Budget (Dept of Planning and Budget is the Agency who is primarily responsible for the overall planning and programming for the Capital Outlay Process).

Page 5: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

~ ~

Agency(Owner)

Architect/Engineer

(A/E)

OtherConsultants

Contractor

Sub-contractors

Suppliers

Governor GeneralAssembly

DPB DGS SFMO DCRDHR DOHAARB

BuildingOccupants

DEQ

LocalityFederalGov’t

Sureties

Treas.BondingAuth.

~~

Many different participants are engaged in the process:

Page 6: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

BUDGET DESIGN PROCURE CONSTRUCT OCCUPY

CapitalBudgetRequest

Reviewand

Recommend

Governor’sProposed

Budget

AppropriationsAct

CBR BUD.REC.

GOV.BUD.BILL

APPRACT CO-2

The Capital Outlay Process

The Budget Development Phase

AuthorityTo Initiate

Project

Key Documents:

Key Activities:

Page 7: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

BUDGET DESIGN PROCURE CONSTRUCT OCCUPY

The Capital Outlay Process

Five Major Phases

Page 8: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

BUDGET DESIGN PROCURE CONSTRUCT OCCUPY

SelectArchitect /Engineer

SchematicDesign(15%)

PreliminaryDesign( 35% )

WorkingDrawings( 100 %)

CO-2 CO-3 CO-4 CO-5 CO-6

The Capital Outlay Process

The Design Phase

Page 9: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

BUDGET DESIGN PROCURE CONSTRUCT OCCUPY

The Capital Outlay Process

The Procurement Phase

PrepareBids

EvaluateBids

ApproveBonds

ObtainBuildingPermit

IssueNotice toProceed

Bid BidTab

Const.Contr.CO-9

BondsCO-10,

10.1

NTPCO-9.2

AwardContract

BldgPer.

CO-17

ObtainApprovalto Award

Appr.to AwdCO-8

Page 10: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

BUDGET DESIGN PROCURE CONSTRUCT OCCUPY

BeginConstruction

Process Change OrdersApprove Monthly Pay Requests Complete

Construction

NoticeTo Proceed

CO-9.2

ChangeOrders

CO-11

PayRequests

CO-12

Applicationfor

Certificate ofUse & Occupancy

CO-13.3a

The Capital Outlay Process

The Construction Phase

Construct Project

Page 11: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

BUDGET DESIGN PROCURE CONSTRUCT OCCUPY

IssueCertificate ofOccupancy

SubstantialCompletionInspections

SubmitProject

Closeout Docs.

A/ECertif.

CO-13.1

Contr’rCertif.

CO-13.2

Applicationfor

Certificate ofUse & Occupancy

CO-13.3a

The Capital Outlay Process

Occupancy

SubmitCompletion

Certifications

SFMOInspect’n

Report

Certificate ofUse & Occupancy

CO-13.3

ProjectCompletion

Report

CO-14

otherreports,

asneeded

Page 12: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

• Capital projects are complex, both from the technical & administrative perspectives

• Without experienced personnel, adequate systems, and sufficient oversight, projects can be delayed, and poorly managed, --- all of which result in increased costs to the Commonwealth

• Many small agencies do not have the expertise on staff to manage projects

Page 13: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

Methods of Procurement

• Agencies and their Project Management professionals must understand, select, and manage the most appropriate methods of procurement for their projects

• Methods include:

•Traditional ( Design–Bid–Build )

•Design–Build

•Construction Management (CM @ Risk)

•Construction Management Agency

Page 14: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

Methods of Procurement

Traditional( Design–Bid–Build )

Owner

Architect/Engineer

( A/E )Contractor

PROS•Well-defined scope puts all bidders on an even playing field•Owner has full control over quality of systems•Single set of plans and specifications expedites Building Official review process•Potential lowest cost

CONS•Delays start of construction until all design is complete•Award based on low price, although “pre-qualification” option can help assure suitable pool of bidders•Contractor has no input into design of systems•Multiple points of project liability•SWAM participation suffers

Page 15: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

Methods of Procurement

Design–Build PROS•May allow earlier award of construction contract•A single source of project responsibility/liability•RFP process allows consideration of factors other than price•Allows Contractor to use “initiative” in selecting systems•Has been used successfully for prototypical or simple bldgs•Total project time decreasesCONS•Owner loses control over quality of systems & details of construction•Change Orders can negate cost or schedule savings•Incorrectly defined scope & criteria can result in higher costs•Initial cost to contractors high•Partial/uncoordinated submittals to the Bldg Official can extend time to review & issue a permit

Owner

ContractorArchitect/Engineer

Page 16: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

Methods of Procurement

Construction Management

(CM @ Risk)

PROS•May allow earlier award of construction contract•RFP process allows consideration of factors other than price•Contractor has input into design of systems•Contractor has input to control costs•Better opportunities for SWAM subcontractors

CONS•The RFP process can make for an uneven playing field between proposers•Partial/uncoordinated submittals to the Bldg Official can extend review time •A/E’s fee for services will be higher•Requires more Owner time for project management and oversight

SiteworkContr.

ElectricalContr.

Mech.Contr.

SteelContr.

Owner

Architect/Engineer

( A/E )

Constr.Manager

( CM )

Page 17: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

Methods of ProcurementConstruction Management

(Agency CM)

PROS•May allow earlier award of construction contract•RFP process allows consideration of factors other than price•Contractor has input into design of systems•Contractor has input to control costs•SWAM business opportunitiesCONS•No risk for CM•Owner must administer multiple contracts•The RFP process and sketchy or ill-defined scope & criteria can make for an uneven playing field between proposers•Partial/uncoordinated submittals to the Bldg Official can extend review time•A/E’s fee for services will be higher•Requires more Owner time for project management and oversight

SiteworkContr.

ElectricalContr.

Mech.Contr.

SteelContr.

Owner

Architect/Engineer

( A/E )

Constr.Manager

( CM )

~~

Page 18: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

• Owners, including Commonwealth of Virginia agencies have seen inflation impact projects budgets

• Recent historical and forecast construction coat inflation rates as reported by industry sources who perform work in both public and private projects:

•2003 2 – 3% 3 – 5% •2004 12 – 15% 10 – 15% 12 - 15%•2005 10 – 13% 8 – 10% 10 -14%•2006 8 – 10% 10% 8 – 9%•2007 7 – 9% 5% 5 – 6%•2008 6 – 8% 3 – 4%•2009 3 – 4%

Cost Containment

Page 19: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

• Nongovernmental Building Costs:

•Office Buildings $165 - $195/sf

•Higher Ed Teaching Wet Labs $335 - $400/sf

•Health Care, Hospitals $285 - $345/sf

•Parking Garages $13,500 - $17,000/space

• Local Federal Courthouse Costs:(representative of high quality government buildings)

•Newport News $402.50/sf

•Richmond $432.50/sf

Cost Containment

Page 20: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

The Bureau of Capital Outlay Management (BCOM) currently provides the following key services:

•Building Code and ADA compliance reviews•Other project review services ( e.g., adherence to

procurement policies, ADA compliance, etc. )•Project inspections •Issuance of Building Permits & Certificates of Occupancy•Development and maintenance of the Commonwealth’s

Construction and Professional Services Manual (CPSM)•CPSM training•Virginia Construction Contracting Officer (VCCO) training,

testing, and certification•Technical assistance to agencies•Coordination of capital outlay forms, the Semi-Annual

Progress Report, and Annual Value Engineering (VE) Report•Assistance to DPB and Legislature’s money committees

Page 21: The Capital Outlay Process in Virginiahac.virginia.gov/subcommittee/2008_subcommittee/... · 1/24/2008  · •Office Buildings $165 - $195/sf •Higher Ed Teaching Wet Labs $335

Functions no longer performed by BCOM

Due to budget cuts, the following functions are no longer a function of BCOM:The Asbestos Section was disbandedThe Maintenance Section was disbandedThe Energy Section was disbanded. The Central Boiler Plant expertise was lost due to attrition.

Functions that BCOM lost support to enforce:Space Utilization in design. Facilities that exceed state guidelines and buildings efficiency criteria are now recommendations and not actively enforced.State owned building “Best Practices” in chapter 9 of the CPSM are typically identified for agency resolution but are not enforced nor do they hold up project approval.

Decentralization: Has led to multiple manuals for design guidelines.May fracture consistency within State procurement practices.

Internal Service Fund: Requiring Agencies to pay for services causes BCOM to not be as involved providing answers to technical questions or for interim inspections.