the basics of project management

Upload: taolawale

Post on 09-Apr-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 The Basics of Project Management

    1/77

    THE BASICS OF PROJECTMANAGEMENT

    By Akin Olawale, B.Sc., PGD(Tech. Mgt.), MBA

    +234-8033842162

    1

  • 8/8/2019 The Basics of Project Management

    2/77

    2

    For which of you, intending to build a tower sit not

    down first and count the cost, whether he has

    sufficient to finish it?, otherwise, after laying the

    foundation, and he is not able to complete it, all thatsee it would mock him

    - Luke 14: 28 - 29

  • 8/8/2019 The Basics of Project Management

    3/77

    Project Management Basics3

    CONTENT

    1. Project What is it?

    2. Project Management Defined

    3. Project Management Processes

    4. Project Management Knowledge Areas

    5. Success & Failure in Projects

    6. Useful information on Project Management

  • 8/8/2019 The Basics of Project Management

    4/77

    PART I - PROJECT4

    Projects can be as simple as winking and as complexas the weather.

    Project examples include:

    Attending project management course

    Attending World Cup Soccer Competition in SouthAfrica

    Building a house, road, port, bridge, etc.

    Starting a technology-driven business

    A nation waging war against another -----------(imagine many more)

  • 8/8/2019 The Basics of Project Management

    5/77

    PART I contd: Definition of Project

    5

    A process of bringing about a new product or

    service.

    A group of activities to bring about change orcreate a new product or service.

    A temporary endeavour undertaken toaccomplish a unique product or service.

  • 8/8/2019 The Basics of Project Management

    6/77

    PART I contd: Basic Building Blocks of Any

    Project6

    Quality

    CostTime

    1. Quality

    2. Time

    3. Cost (Budget)

    How can you measure a successful project?

    Only when

    1. You finished within agreed time with project sponsor(shortest time possible)

    2. You finished within agreed budget (minimum cost)

    3. You delivered the quality service/ product expected

    (high performance/best quality)

  • 8/8/2019 The Basics of Project Management

    7/77

    PART I contd: Attributes of a Project7

    One-off delivery

    Unique

    Time-bound i.e. has a start and end date Requires resources (financial, material, human &

    time)

    Uncertainties/Risk embedded

    Defined & Measurable Benefits

    Have a primary sponsor, target customer anddefined stakeholders.

  • 8/8/2019 The Basics of Project Management

    8/77

    PART I contd: How can a Project

    come about?8

    Through the generation of ideas individually or by

    brainstorming

    By providing solution to a problem

    By capitalizing on an emerging opportunity

    By reacting to change in the environment

    By obeying a given order or directive

    By obeying statutory requirements of goverment By technologizing taking advantage of innovation

    and technology

    ---------(wear your thinking cap & add more)

  • 8/8/2019 The Basics of Project Management

    9/77

    PART I contd:Project Environment

    9

    Internal Projects initiated within an entity for her development.

    Project team operates within functional units.

    PM acts independent outside functional duties.

    Project structure usually temporary.

    PM depends on people, who report to other functional heads.

    External External PM acts as agent on behalf of client.

    PM has direct control over project team members.

    No influence of functional structure over PM authority.

    Involves higher risk, strong risk management must be in place.

  • 8/8/2019 The Basics of Project Management

    10/77

    REVIEW 1 - PROJECT10

    1. In one sentence, what is your understanding of theterm Project.

    2. Give a classic example to buttress your

    understanding.3. Mention 3 major attributes of Project.

    4. Looking at your work environment, give an exampleeach of:

    - an internal project

    - an external project

  • 8/8/2019 The Basics of Project Management

    11/77

    PART II PROJECT MANAGEMENT11

    Project Management is:

    - The planning, coordination and control of activitiesand resources to meet a defined objective within agiven timescale, agreed quality and specifiedcost(budget).

    - Overseeing the development of a new

    product/service to the final stage of delivery.- The monitoring of the development of a goal from

    start to finish using effective methodology.

  • 8/8/2019 The Basics of Project Management

    12/77

    PART II contd

    Why Project Management?12

    Ensures timely delivery

    Ensures efficiency as well as effectiveness

    Ensures that all efforts are organised

    Ensures project delivers measurable & acceptablebenefits

    Ensures risks are managed with little or noconstraints

    Ensures required skills are available to provide bestsolutions.

  • 8/8/2019 The Basics of Project Management

    13/77

    PART II contd

    Comparison with Operations Management13

    Commonalities

    o Performed by people

    o Constrained by limited resources

    o Planned, executed & controlled

    Differences

    o Project is temporary and unique, while operations isongoing & repetitive

    o Project terminates after the achievement of a specificobjective, while operations takes on another objective,without end.

  • 8/8/2019 The Basics of Project Management

    14/77

    PART II contd

    Areas of Application14

    Public Works

    Private Works

    Complex Works All disciplines including IT, Construction, Finance,

    Administration, Marketing, Sports, Event Planning,

    etc.

    NOTE PM skill can help in everyday life and in everything you do. So

    take advantage.

  • 8/8/2019 The Basics of Project Management

    15/77

    PART II contd

    People Involved/Affected15

    Project Sponsor financial provider/idea originator

    Project Manager accountable for delivery

    Project Team deliver assigned work packages Project Consultants/Specialists technical

    involvement

    Users ultimate consumer of service/product

    Suppliers provides inputs in various forms

    Opponents of the Project interested in the failure of

    the project

  • 8/8/2019 The Basics of Project Management

    16/77

    PART II contdPROJECT MANAGEMENT OFFICE

    16

    Where the project manager operates from an

    office, the following complementary staff may be

    available or provided depending on the size of

    project and the organisational structure in place:

    Project Coordinator

    Project Accountant

    Project Auditor/ Quality Assurance Expert

    Project Secretary/Documentation Expert

  • 8/8/2019 The Basics of Project Management

    17/77

    PART II contdIMPORTANCE OF A PM

    17

    Accountable for project success

    Ensures project progresses and is delivered tospecification and within time and cost

    Reports major deviations to project sponsor for areview

    Manages project risk, issue and change

    Manages project finances & teams and ensurecommunication flow

    Keeps proper record at every stage of theproject

  • 8/8/2019 The Basics of Project Management

    18/77

    PART II contd

    Basic skills of a PM18

    Leadership Skills decision making, problem solving

    People Skills motivating others, building teams

    Communication Skills easily understood, strong

    negotiating ability

    Technical Skills general understanding of specific

    area of interest to the project Organisational Skills obtaining result using men,

    material, money and machine

  • 8/8/2019 The Basics of Project Management

    19/77

    PART II contd

    Profile of an effective PM19

    Enthusiastic - Handles ambiguity

    Good negotiator - Persistent Open - Responsive

    Flexible - Sense of humour

    Persuasive - Self Confident

    Innovative - Encouraging

    Sees potential problem before they arise, etc

  • 8/8/2019 The Basics of Project Management

    20/77

    20

    POINTON MARBLE

    A project manager isas good as

    his or her last project.-Anonymous

  • 8/8/2019 The Basics of Project Management

    21/77

    REVIEW 2 -21

    Answer YES/NO to questions 1-6 & provide short

    answers to 7-10:

    1. The management of project is sometimes on acontinuous basis

    2. Projects are managed through project teams

    3. A project manager must have full understanding ofthe project and must essentially be a technical

    person

  • 8/8/2019 The Basics of Project Management

    22/77

    22

    4. A project manager turns the sponsors dream into

    reality.

    5. Timescales get compromised due to poorcoordination by Project Accountant.

    6. Every of the project stakeholder is accountable for

    the successful delivery of projects.

    7. Who is a clever juggler of time, money and people

    to meet projects defined objectives

  • 8/8/2019 The Basics of Project Management

    23/77

    23

    8. Mention 3 of the several job functions of a Project

    Manager.

    9. What other singular word can you use to describethe role of a Project Auditor.

    10. Two qualities of the several expected of a Project

    Manager are ______ & ______ .

  • 8/8/2019 The Basics of Project Management

    24/77

    PART III: PROJECT MANAGEMENT PROCESSES -

    Using PMBOK from PMI(US)

    24

    - A series of actions directed toward a particular

    result. The processes are:

    - INITIATING

    - PLANNING

    - EXECUTING

    - MONITORING & CONTROLLING- CLOSING

  • 8/8/2019 The Basics of Project Management

    25/77

    Part III contd: What to expect?

    25

    For each of the process.

    What is the purpose?

    What are the inputs?

    What are the activities involved?

    What are the expected outputs or deliverables?

  • 8/8/2019 The Basics of Project Management

    26/77

    Part III contd:

    Level 0-Project Origination26

    Purpose:

    To provide a formal mechanism to recognise and

    evaluate potential projects, and reach consensus onprojects to be selected.

    Input:

    Business Need(s)

    Activities:

    Develop business proposal define goal, objectives,

    benefits and do a cost-benefit analysis.

  • 8/8/2019 The Basics of Project Management

    27/77

    27

    Evaluate project proposal

    Select project

    Outputs/Deliverables:

    Business Case

    Proposed Solution

  • 8/8/2019 The Basics of Project Management

    28/77

    Information to be included in the Business Case are:1. Introduction

    2. Business Objective

    3. Current Situation & Problem Opportunity Statement

    4. Critical Assumption & Constraints

    5. Analysis of Options & Recommendations

    6. Preliminary Project Requirements

    7. Budget Estimate & Financial Analysis8. Schedule Estimates

    9. Potential Risks

    10. Exhibits

    28

  • 8/8/2019 The Basics of Project Management

    29/77

    PROJECT SELECTION Involves looking at different alternatives with a view to determine their

    investment level and expected benefits/outcomes.

    The best way to arrive at the best project that will offer the greatestbenefit at the lowest cost is through empirical analysis using Cost-

    Benefit Analysis.

    Cost-Benefit Analysis include the following:

    Net Present Value

    Future Worth Methods Internal Rate of Return

    Payback Period

    Cost-benefit Analysis.

    29

  • 8/8/2019 The Basics of Project Management

    30/77

    Part III contd:

    Level 1-Project Initiation30

    Purpose:

    To verify assumptions made in Project Origination,define and authorize the project

    Input:

    Business Case

    Proposed Solution

    Activities:

    Assign Project Manager.

    Identify Stakeholders.

  • 8/8/2019 The Basics of Project Management

    31/77

    31

    Define Resources, Roles & Responsibilities

    Develop Project Charter to include scope, schedule,

    cost and quality

    Identify Risks

    Confirm Approval to Proceed

    Outputs/Deliverables: Project Charter

    Initial ProjectApproval

  • 8/8/2019 The Basics of Project Management

    32/77

    32

    Risk A potential event that may impact the

    project positively or negatively.

    Potential problems that can hinder or delay

    project success

    Issue Something that is preventing project

    progress.

    A risk that has manifest is an issue.Change Agreed alterations to project parameters

    scope, cost, schedule and quality due to

    resolution of issues or provision of solutions

    to risks.

  • 8/8/2019 The Basics of Project Management

    33/77

    33

    Risk Factors in Project Management

    Risk Factors obstacles that could prevent the meeting

    of project objectives

    How to assess risk

    Project Manager can use a checklist

    PM can hold brainstorming session with Project Team

    Stakeholders can be questioned or interviewed

    Check past project records.

  • 8/8/2019 The Basics of Project Management

    34/77

    Project Charters34

    After deciding what project to work on, it is

    important to formalize projects

    A project charter is a document that formally

    recognizes the existence of a project and providesdirection on the projects objectives and

    management

    Key project stakeholders should sign a projectcharter to acknowledge agreement on the need

    and intent of the project

  • 8/8/2019 The Basics of Project Management

    35/77

    35

    PROJECT CHARTER Information Reqd.

    Project Name

    Project Sponsor

    Project Manager

    Project Overview

    - Business Need/Opportunity

    - Product/Service Description

    - Objectives

    - Project Deliverables

    - Out of Scope

    - Known Risks

    Financial Benefits

    Project Stakeholders

    Human Resource Needs

    Roles & Responsibilities

    NOTE

    A PM must never

    sign a Project

    Charter that if he

    was not a party toevery of the

    agreement

    reached on the

    key project

    variables of

    COST, TIME,QUALITY,

    SCOPE & most

    importantly

    BENEFIT

    DERIVABLE.

  • 8/8/2019 The Basics of Project Management

    36/77

    JWDs Project Charter

    36

  • 8/8/2019 The Basics of Project Management

    37/77

    37

  • 8/8/2019 The Basics of Project Management

    38/77

    Part III contd:

    Level 2-Project Planning38

    Purpose:

    To define & refine objectives, & to establish a plan of

    action required to attain the objectives & scope of the

    project.

    Input:

    Project Charter

    Activities:

    Refine scope.

    Identify major tasks & deliverables.

  • 8/8/2019 The Basics of Project Management

    39/77

    39

    Develop Work Breakdown Structure-WBS*

    Develop Schedules

    Define specific skills & resource requirements

    Define Milestones/Review Points

    Develop complete Project Management Plan toinclude communication, personnel, risk, quality,

    procurement etc.

    Outputs/Deliverables: Project Management Plan

    Approval to continue

  • 8/8/2019 The Basics of Project Management

    40/77

    Basic Principles for Creating WBS

    1. A unit of work should appear at only one place in the WBS.

    2. The work content of a WBS item is the sum of the WBS items below it.

    3. A WBS item is the responsibility of only one individual, even though many

    people may be working on it.

    4. The WBS must be consistent with the way in which work is actually going to

    be performed; it should serve the project team first and other purposes

    only if practical.

    5. Project team members should be involved in developing the WBS to ensure

    consistency and buy-in.

    6. Each WBS item must be documented to ensure accurate understanding of

    the scope of work included and not included in that item.

    7. The WBS must be a flexible tool to accommodate inevitable changes while

    properly maintaining control of the work content in the project according to

    the scope statement.

    40

  • 8/8/2019 The Basics of Project Management

    41/77

    WORK BREAKDOWN STRUCTURE (WBS)

    41

    Dial-upAccess

    Requirements

    SurveyNeeds

    PrepareRequiredReport

    ReviewRequirement

    withStakeholder

    Procedures

    DevelopReqmt.

    Procedures

    Dev. SupportProcedures

    Dev. ProgramMeasurement

    ReviewProcedure

    Design

    Dev. High-level Design

    Dev.DetailedDesign

    ReviewDesign

    Build

    Config. ForWork Station

    Config. ForServer HW &

    SW

    Install ServerSW & HW

    Test ServerSystem

    InstallWorkstation HW

    & SW

    Performintegrated

    Test

    Implement

    Dev. User TrainingMatr.

    Dev. Oper.Support Doc.

    Train OperationalSupport Team

    Define PilotGroup

    Install Workstation SWfor Pilot Group

    Train Pilot Group

    Run Test with Pilot

    Group

    WBS is an organised view of project tasks and sub-tasks broken down

    into different categories that produces deliverables.

  • 8/8/2019 The Basics of Project Management

    42/77

    42

    WHATof Project ManagementTasks

    - Identify, sequence, estimate & flow chart

    WHO of Project ManagementResources- Identify, assign, estimate & identify constraints

    WHEN of Project ManagementSchedules*

    - The inter-twine of WHAT & WHO results in WHEN,

    which is the Project Schedule.

  • 8/8/2019 The Basics of Project Management

    43/77

    43

    PROJECT SCHEDULE

    - Objective is to estimate start & end dates of

    projects.

    - Know task duration

    - Know task dependencies/relationships

    - Know tools used for this purpose including Network

    Diagram, Critical Path Method, Gantt Chart.- Determine milestone with dates.

  • 8/8/2019 The Basics of Project Management

    44/77

    44

    A COMPLETE PROJECT PLAN GOES BEYOND JUST A SCHEDULE

    PROJECT MANAGEMENT PLAN

    Project Name

    Project Sponsor

    Project Manager

    Project Overview

    Project Scope In/Out

    DeliverablesProject Approach

    Cost/Time

    Milestones

    Assumptions

    Constraints

    Risks

    Communication Plan

    Change Management PlanResource Management Plan

    Risk Management PlanIssue Management Plan

    Quality Management Plan

    Project Close-Out Plan

  • 8/8/2019 The Basics of Project Management

    45/77

    45

    Baselinning your project plan

    Project Baseline is the version of your complete projectmanagement plan that was approved at PlanningStage (i.e. freezed project plan).

    Re-baselinning is officially adopting a new projectplan based on changes made to guide performancemanagement.

    Re-baselinning can be done severally within thelifespan of a project.

    Re-baselinning is a last resort when project work is notgoing according to plan as earlier agreed.

  • 8/8/2019 The Basics of Project Management

    46/77

    Part III contd:

    Level 3-Project Execution46

    Purpose:

    To develop/purchase product or service that the

    project was commissioned to deliver based on the

    Project Management Plan.

    Input:

    Approved Project Management Plan

    Approved Change Requests

    Approved Corrective/Preventive Actions

  • 8/8/2019 The Basics of Project Management

    47/77

  • 8/8/2019 The Basics of Project Management

    48/77

    48

    An important key to effective execution is

    - COMMUNICATIONStart off right:

    o communicate project goals & benefits

    o resolve questions from team at 1st project meeting

    o ensure everyone on the project understand their role

    Keep it up:

    o review checkpoint/milestones

    o follow communication plan

    P III d

  • 8/8/2019 The Basics of Project Management

    49/77

    Part III contd:

    Level 4-Project Monitoring & Control

    Purpose:

    To ensure that project objectives are met by

    monitoring and measuring progress & takingcorrective actions, when necessary.

    Input:

    Approved Project Management PlanWork Performance Information

    49

  • 8/8/2019 The Basics of Project Management

    50/77

    Activities:

    Measure progress based on scope, cost, schedule &

    quality

    Manage expectations, changes, issues and risk

    Resolve conflicts Meet with team regularly

    Report status writing

    Outputs/Deliverables:

    Project Plan & Financials Update

    Issue, Risk & Change Mgt. Log

    Meeting Documentation & Periodic Status Report

    50

  • 8/8/2019 The Basics of Project Management

    51/77

    How to track projects?

    Team member assigned task must provide actual

    time spent on task as well as remaining time to

    complete the task

    Project Manager to watch out for

    tasks exceeding planned period

    tasks not completed on schedule

    new, unplanned tasks to be incorporated

    51

  • 8/8/2019 The Basics of Project Management

    52/77

    Common causes of failed schedules

    Turnover on project team

    Poor time estimates for tasks

    Delay in receipt of supplies, materials or equipment

    Poor resource allocation Unexpected changes to plan

    Change Management/Control

    Changes are inevitable in every project Change unattended to can cause project to fail

    Goal of change management is not to suppress change,

    but to recognize the implications of it & deal with it

    promptly

    52

  • 8/8/2019 The Basics of Project Management

    53/77

    Steps to gain control of projects

    Meet with project sponsor Interview project team

    Clarify project scope & cost justification

    Revise funding requirements & seek approval

    Keep every stakeholder informed of progress & problems

    Recognise the need for change & add changes as required

    to project plan

    Trade off in Project ControlWhen issues occur in projects that require change,

    consideration is usually along this line

    SCOPE (reduce) RESOURCES (increase)

    SCHEDULE (increase) QUALITY (reduce)

    53

  • 8/8/2019 The Basics of Project Management

    54/77

    Purpose:

    To formalize acceptance of the project and bring it to

    an orderly end.

    Input:

    All previous inputs from the point of origination to

    control.

    Activities: Evaluate project outcomes & facilitate acceptance

    Document lessons learned

    Transfer responsibility to Operations/Maintenance

    54

    Part III contd:

    Level 5-Project Close

  • 8/8/2019 The Basics of Project Management

    55/77

    Outputs/Deliverables:

    ProjectEvaluation Report

    Deliverable Sign-off

    Post-implementation Review

    Project Close-out Report

    Project Responsibility Transfer

    55

  • 8/8/2019 The Basics of Project Management

    56/77

    56

    Knowledge areas describe the key competencies that

    project managers must develop

    4 core knowledge areas lead to specific project

    objectives (scope, time, cost, and quality) 4 facilitating knowledge areas are the means through

    which the project objectives are achieved (human

    resources, communication, risk, and procurement

    management) 1 knowledge area (project integration

    management) affects and is affected by all of the

    other knowledge areas

  • 8/8/2019 The Basics of Project Management

    57/77

    Project Management Framework57

  • 8/8/2019 The Basics of Project Management

    58/77

    PART IV: ACTIVITIES IN PROJECT

    MANAGEMENT KNOWLEDGE AREAS

    1. Integration Management

    Purpose

    Ensuring that the various elements of the project are coordinated.

    Activities oProject Charter Development (I)

    oPreliminary Scope Statement (I)

    oProject Plan Development (P)

    oProject Plan Execution (E)

    oChange Monitoring & Control (M&C)

    oIntegrated Change Management (M&C)

    oProject Close-out (C)

    58

  • 8/8/2019 The Basics of Project Management

    59/77

    Part IV PM Knowledge Areas & Activities

    2. Scope Management

    Purpose

    Ensuring the project include all and only the work required to

    complete the project successfully.

    Activities oScope Planning (P)

    oScope Definition (P)

    oWork Breakdown Structure -WBS (P)

    oScope Verification (M&C)

    oScope Change Control (M&C)

    59

  • 8/8/2019 The Basics of Project Management

    60/77

    Part IV PM Knowledge Areas & Activities

    3. Time Management

    Purpose

    Ensuring timely completion of project.

    Activities oActivity Definition (P)

    oActivity Sequencing (P)

    oActivity Resource Estimating (P)

    oActivity Duration Estimating (P)

    oSchedule Development (P)

    oSchedule Control (M&C)

    60

  • 8/8/2019 The Basics of Project Management

    61/77

    Part IV PM Knowledge Areas & Activities

    4. Cost Management

    Purpose

    Ensuring that the project is completed within approved budget.

    Activities

    oCost Estimating (P)

    o

    Cost Budgeting (P)oCost Control (M&C)

    61

  • 8/8/2019 The Basics of Project Management

    62/77

    Part IV PM Knowledge Areas & Activities

    5. Quality Management

    Purpose

    Ensuring that the project will satisfy the need for which it wasundertaken.

    Activities

    oQuality Planning (P)

    oQuality Assurance (E)

    oQuality Control (M&C)

    62

  • 8/8/2019 The Basics of Project Management

    63/77

  • 8/8/2019 The Basics of Project Management

    64/77

  • 8/8/2019 The Basics of Project Management

    65/77

    Part IV PM Knowledge Areas & Activities

    65

    8. Risk Management

    Purpose

    Ensuring appropriate identification, analysis & response to

    project risk.

    Activities oRisk Management Planning (P)

    oRisk Identification (P)

    oQualitative Risk Analysis (P)

    oQuantitative Risk Analysis (P)

    oRisk Response Development (P)

    oRisk Response Control (M&C)

  • 8/8/2019 The Basics of Project Management

    66/77

    Part IV PM Knowledge Areas & Activities

    9. Procurement Management

    Purpose

    Ensuring the required acquisition of goods & services from outside

    the performing organisation.

    Activities oProcurement Planning (P)

    oContract/Solicitation Planning (P)

    oRequest Contractor Response/Solicitation (E)

    oContractor Selection (E)

    oContract Administration (M&C)

    oContract Close-out (C)

    66

  • 8/8/2019 The Basics of Project Management

    67/77

    Part V SUCCESS & FAILURE IN PROJECTS

    Parameters for measuring project success:

    QUANTITATIVE

    Has it met the QUALITY defined in the Scope?

    Was it delivered within specified BUDGET/COST?

    Was it delivered within the agreed TIME FRAME?

    QUALITATIVE

    Was benefit delivered to the sponsor?

    Was benefit delivered to the stakeholders?

    67

    Part V (contd) Important Factors for

  • 8/8/2019 The Basics of Project Management

    68/77

    Part V (cont d) Important Factors for

    Project Success

    1. The Project Itself

    2. The Project Manager

    3. The Project Team

    4. Other Stakeholders, internal or external

    5. The environment political, social, economic, etc.

    68

  • 8/8/2019 The Basics of Project Management

    69/77

    Part V (contd) Why projects succeed?

    Clear Vision & Objective Business Case

    Sponsor/Executive Management Support

    Realistic Expectation deliverables indicated in the Scope

    Definition (Scope Statement)

    Well developed estimate of time and cost based on clearly

    articulated WBS

    Proper planning using appropriate tools

    Milestones at appropriate intervals

    Involvement of stakeholders

    Competent staff hardworking, intelligent and focused

    Good communication across board

    Good coordination skill by Project Manager

    69

    P V ( d) S C f F il i

  • 8/8/2019 The Basics of Project Management

    70/77

    Part V (contd) Some Causes of Failure in

    Projects

    Drawbacks in Initiating Projects

    Project plan not properly aligned with business plan

    Procedures for managing project not defined

    Priorities in project not communicated to stakeholdersNo shared vision among the players in the project

    Drawbacks in Planning Projects Project Plan without detailed WBS

    Use of cumbersome tools that implementers do not understand

    PM should elicit cooperation and lead team rather than being

    dictatorial, which can kill initiative

    Cost & Resource Estimates must be realistic

    70

  • 8/8/2019 The Basics of Project Management

    71/77

    71

    Drawbacks in Organising & Executing Projects

    Lack of cooperation of stakeholder to achieve commonobjective

    Lack of availability of resources when required

    Poor communication

    Roles & responsibilities of team members not clearlydefined

    PM not well grounded in other relevant skills apart from

    technical know-how

    Drawbacks in Monitoring & Control Projects PM failure to monitor progress, attend to issues & risks

    Review meeting not documented for appropriate follow-up

    PM having responsibilities but lacking authority

    P t VI USEFUL INFORMATION ON

  • 8/8/2019 The Basics of Project Management

    72/77

    Part VI USEFUL INFORMATION ON

    PROJECT MANAGEMENT

    1. Some Project Management Planning & Controlling Tools

    Work Breakdown Structure (WBS) SCOPE

    Project Logic Diagram SCOPE

    Gantt Chart TIME

    Critical Path Method (CPM) TIME

    Performance Evaluation & Review Technique (PERT) TIME

    Graphic Evaluation & Review Technique (GERT) TIME

    Earned Value Analysis COST

    Cost Breakdown Structure (CBS) COSTBrainstorming Sessions QUALITY CONTROL

    Pareto Analysis, SWOT Analysis QUALITY CONTROL

    Scatter Diagram, Control Charts QUALITY CONTROL

    Cause & Effect Analysis QUALITY CONTROL

    72

  • 8/8/2019 The Basics of Project Management

    73/77

    2. Commercial Project Planning & Control Software

    LARGEMULTI-PROJECTUSERS

    Power Project ProfessionalPrimavera Project Planner

    Artenus View 4

    Cobra

    Entreprise PM

    Micro Planner X-Pert

    MID-RANGE PRODUCTSUP TO ABOUT 2000 TASK

    Microsoft Project

    Micro-Planner Manager

    Primavera Suretrak

    LOWCOST PACKAGES

    Milestone Simplicity

    Project Vision

    Quick Gantt

    73

    Hi f P j M

  • 8/8/2019 The Basics of Project Management

    74/77

    3. History of Project Management 1900 Gantt chart introduced

    1944Atomic Bomb first really complex, high tech project need for new

    management approach identified 1950 First network diagrams, further development of Los Alamo principal into

    now called Project Management

    1957Dupont created Critical path method (CPM)

    1958US Navy launched program evaluation and review technique (PERT)

    1960 Computer technology provided improved capabilities

    1960 Association of Project Management (APM) in UK and ProjectManagement Institute (PMI) in US

    1967Graphical evaluation and review technique (GERT)

    1970 Planning and costing based on an earned value concept widespread

    1980 Project management software for PC

    1988Body of Knowledge for APM

    1996British standard BS6079

    1997European International standard ISO 10006

    74

  • 8/8/2019 The Basics of Project Management

    75/77

    4. Popular Project Management Methodologies

    A methodology is a set of methods /steps that is used or

    followed in delivering projects.

    Note that any existing method can be customized or you may

    create a method that will be peculiar to your establishmentonly.

    PMBOK Project Management Body of Knowledge by Project ManagementInstitute (PMI, US). www.pmi.org

    PRINCE2 Project in Controlled Environment by UK Office of Government

    Commerce (OGC). www.ogc.gov.uk/prince/ APMBOK Association of Project Management Body of Knowledge by

    Association of Project Management, UK (APM). www.apmgroup.co.uk

    75

  • 8/8/2019 The Basics of Project Management

    76/77

    CONCLUSION

    It is not what you know that matters but what you

    do with what you know, therefore go and affect

    your organisation with the knowledge of project

    management positively. Be an advocate of this new knowledge PROJECT

    MANAGEMENT.

    - Akin Olawale.

    76

  • 8/8/2019 The Basics of Project Management

    77/77