the asphalt lining of a large water reservoir near bengazi - schmid

Upload: mivos4

Post on 03-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 The Asphalt Lining of a Large Water Reservoir Near Bengazi - Schmid

    1/6

    409

    The Asphalt Lining of a Large Water Reservoir near Benghazi

    Die Asphaltdichtung eines groen Speicherbeckens bei Benghazi

    Reinhard Schmid

    Abstract

    The Great Man-Made River Project utilizes Libyas vast fossil groundwater reserves in the

    desert in order to supply fresh water to the populated and fertile Mediterranean coast. Pipelines

    are transferring the water to artificial reservoirs in the target areas. Near Benghazi, the largest

    reservoir with a capacity of twenty-four million cubic meters has recently been completed and

    sealed by an asphalt lining of more than one million square meters. Special equipment

    designed for hydraulic asphalt has been utilised to place the lining on the steep slopes and on

    the floor.

    Zusammenfassung

    Das Great Man-Made River Projekt nutzt die fossilen Wasservorrte in der libyschen Wste zur

    Versorgung der dicht besiedelten Kste im Norden des Landes. ber Betonpipelines wird das

    Wasser bis zu 1600 km in die in den Zielgebieten errichteten Reservoirs transportiert, von wo es

    zur Trinkwasserversorgung der Stdte oder zur Bewsserung landwirtschaftlicher Anbaugebiete

    verteilt wird. Das grte Speicherbecken, das Grand Omar Mukhtar Reservoir bei Benghazi,

    erhielt eine Asphaltdichtung, bestehend aus je einer Binder- und Dichtungslage. Hierzu wurdespeziell fr den Bschungseinbau entwickeltes Gert eingesetzt, das von fahrbaren Winden

    gehalten wird. Die Abdichtungsarbeiten wurden im Mrz 2007 abgeschlossen.

    1 Introduction

    The Great Man-Made River Project of Libya is one of the most ambitious engineering water

    projects worldwide: it started in 1983 and encompasses the large scale abstraction of fossil

    groundwater reserves in the desert and their long distance transfer via concrete pipelines to the

    coastal plains with their fertile soils, where the large majority of the Libyan population is located.

    Major phases of this project have been completed until now and water is permanentlydistributed to big Cities like Tripoli and agricultural lands in the coastal region (Figure 1).

    Engineering landmarks are the five major well fields with more than 1000 wells up to 800 m

    deep, the water conveying system of four meter diameter pre-stressed concrete pipes and

    numerous pump stations, as well as big storage reservoirs in the target areas. The largest of

    these reservoirs is the Grand Omar Mukhtar Reservoir, which was completed in March 2007.

  • 8/12/2019 The Asphalt Lining of a Large Water Reservoir Near Bengazi - Schmid

    2/6

    410

    THE GREAT MAN-MADE RIVER PROJECT

    Mediterranean Sea

    Benghazi

    Sirt

    Tripoli

    6004503001500

    Km

    Tazerbo

    Ajdabiya

    Sarir

    Wellfield

    Tazerbo

    Wellfield

    Sarir PCCPPlant

    NE Jebel Hasouna

    Wellfield

    E Jebel Hasouna

    Wellfield

    Tobruk

    Kufra

    Jaghbo ubGhadamesBrega PCCP Plant

    Egypt

    Egypt

    Algeria

    Algeria

    TunisiaTunisia

    Sudan

    Sudan

    Benghazi Plains

    Region

    Al-Ghar dabi ya Plains

    Region

    Jefara Plains

    RegionGrand Omar

    Mukhtar

    Reservoir

    Figure 1: Libya water grid with Grand Omar Mukhtar Reservoir near the coast

    2 The Grand Omar Mukhtar Reservoir

    The coastal city of Benghazi is already receiving more than 200 000 m3of water per day from

    well fields located 1900 km south. With the new Grand Omar Mukhtar Reservoir under

    operation, additional water will be provided to irrigate the large fertile plains in the Benghaziregion.

    There are many good reasons to choose asphaltic concrete as sealing material for a fill dam or

    water reservoir. High reliability, low maintenance costs and economic construction methods

    contribute to its long and very successful track record. In case of Grand Omar Mukhtar

    Reservoir, the asphalt lining covers an area of 800000 m2on the floor and 270000 m2 on the

    slope and it will retain an operational volume of 24 mill m3of valuable irrigation water. After

    commissioning, this reservoir will provide water for 18.000 hectares of agricultural land. Further

    extensions are envisaged in the near future.

    3 General Design Features

    The reservoir is surrounded by a 3600 m long ring embankment consisting of a crushed

    limestone fill and a vertical chimney drain of fine sand. The upstream slope is protected by

    coarse riprap whereas the downstream slope is overlaid by a drainage zone of crushed

    limestone material with specified drainage capacities and sufficient stability to allow safe

    operation of the asphalt paving equipment. The drainage zone was also designed to withstand

    rain water during construction time, a property which was tested successfully during occasional

    but very heavy rainfalls in winter. The drainage zone was placed in two layers of 15 cm eachwith the slope paving equipment, thus providing a very even and accurate formation for the

    binder asphalt layer.

  • 8/12/2019 The Asphalt Lining of a Large Water Reservoir Near Bengazi - Schmid

    3/6

    411

    The reservoir floor was milled five meter deep into the limestone underground by conventional

    road mining machines. On the accurately excavated bedrock formation a regulating layer of 20

    cm was sufficient to provide an even and stable base for the asphalt lining. The excavated

    material was used as fill material for the embankment thus minimising haulage expenditures for

    material from outside quarries.

    Filling of the reservoir is accomplished through a concrete intake structure where seven steel

    pipes allow for well regulated filling according to operational requirements. The outlet structure

    is situated on the opposite side of the reservoir to ensure a certain water circulation of the

    stored water. The draw-off is controlled by valves outside the reservoir.

    4 Design of the Asphalt Lining

    The lining consists of a binder layer of 8 cm thickness and a sealing layer of 6 cm thickness.

    Crucial for the good performance of the asphalt lining under water load are the connections to

    the concrete structures within the reservoir, in case of Grand Omar Mukhtar Reservoir, the inletand outlet structure on floor level. In both cases, special designs have been applied, taking into

    account the flexibility of the asphalt and the rigidity of the concrete. Possible differential

    deformations between asphalt lining and concrete structure require a special watertight joint

    construction design. A copper sheet which is clamped to the concrete and installed in loop

    profile will overbridge a possible opening of the joint between asphalt sealing and concrete wall

    and thus guarantee a watertight sealing system even in this critical area and under

    unfavourable load conditions.

    All construction material such as joint filler, copper sheet and clamping plate not only fulfilled the

    specified high quality standard but they have been successfully applied on numerous similar

    projects.

    At the dam crest the lining is connected to the wave wall. The joint is above the reservoir water

    level and therefore not exposed to a permanent static water pressure. Expensive joint

    construction is not required. The joint is filled with highly elastic joint filler which has good bond

    to both the concrete wave wall and the asphalt lining.

    5 Asphaltic Concrete Mix Design

    As a mixture of crushed coarse aggregates, sand, filler and bitumen, with a suitable mixcomposition and if professionally placed, asphaltic concrete can be manufactured in a way to be

    technically impermeable. The mix design had also to consider flexibility and stability

    characteristics under extreme temperature variations of more than 70K. This was established

    on the construction site laboratory with support of Strabags laboratory in Cologne, following the

    MS-2 Guidelines of the American Asphalt Institute which define in detail all required steps for

    the design evaluation. After verification of the specified quality on field tests outside and within

    the permanent works, full scale asphalt placing started in November 2005.

    6 Production of the Asphaltic Concrete

    In order to produce high quality hydraulic asphalt, a conventional asphalt mixing plant which

    was already on the construction site had to be technically modified and adapted to the specified

  • 8/12/2019 The Asphalt Lining of a Large Water Reservoir Near Bengazi - Schmid

    4/6

    412

    American Standard. This included mainly an electronically controlled mixing process with

    automatic recording of main mixing parameters such as weights, temperatures at various

    process steps and mixing times.

    The fully computerised plant was equipped with a precise weighting system that ensured a

    highly accurate and consistent mix composition, as for example a variation in the bitumencontent of less than 0,1 %. The production capacity of the mixing plant was at 140 tons per hour

    for binder asphalt and 120 tons per hour for dense asphalt, which allowed for a continuous

    asphalt placing process of one placing unit.

    For the entire asphalt lining covering an area of more than one mill m2, in total 370.000 tons of

    asphalt were produced between November 2005 and January 2007. All aggregates were taken

    from a limestone quarry situated 25 km from the construction site. Within the scope of the

    quality control, all components of the asphalt mix were tested regularly in the asphalt site labo-

    ratory.

    7 Placing of the asphalt lining

    On the embankment slope, the drainage zone and the asphalt lining were placed with special

    paving equipment. All machines working on the slope were held and moved by winch wagons

    which operated on the embankment crest (Figure 2). The paving machine equipped with a high

    compaction screed, worked in a vertical direction placing asphalt from bottom to top in a width of

    5,5 m each lane. In order to allow for a continuous paving process, a supply cart transported the

    asphalt from the crest to the paving machine. Final compaction of the asphalt was achieved by

    vibratory rollers which ran on separate winch wagons. On the floor a conventional road finisher

    with a high compaction screed was used (Figure 3).

    Figure 2: Asphalt placing on the reservoir slope

  • 8/12/2019 The Asphalt Lining of a Large Water Reservoir Near Bengazi - Schmid

    5/6

    413

    Figure 3: Reservoir lining under construction

    In this way the binder and dense asphalt layer were placed in two consecutive stages. After

    verifying the specified quality of the sealing by various tests, a hot mastic coating was spread on

    top of the lining at a thickness of 1,5 to 2 mm. The coating consists of approx. 30 % bitumen

    and 70 % of filler. Due to the high sun intensity in Libya, a stabilising agent was added to the

    bitumen. This final coating will protect the sealing against the ageing effects of the sun radiation,

    thus conserving the high quality characteristics of the sealing for decades.

    8 Sequence of Construct ion

    In order to shorten the overall construction period, placing of the drainage zone on the slope

    started when approximately 30 % of the embankment was still uncompleted and before the

    asphalt mixing plant was operational. After execution of successful field tests, asphalt placing

    started in one shift, and in spring 2006 a night shift was added for asphalt placing on thereservoir floor. Mainly for safety reasons, slope placing was restricted to the day shift.

    Whereas interruption of asphalt works by rain were limited to a few events during the winter

    season, dust and sand storms from the Sahara desert disturbed the placing works more

    frequently and more severely.

    In order to minimise interference between earth works and asphalt works and to avoid

    interruptions, careful work planning with permanent adjustment to the actual work progress was

    crucial for success. As a result of good co-operation the performance of the placing works met

    the schedule and only four months after hand over of the last dam section, which included

    almost 30 % of the entire slope section, the asphalt works were completed.

  • 8/12/2019 The Asphalt Lining of a Large Water Reservoir Near Bengazi - Schmid

    6/6

    414

    9 Monitor ing System

    In order to collect and monitor any seepage through the lining a ring drainage has been installed

    along the dam toe which is connected to the drainage layer of the slope. Seepage water from

    the reservoir slopes can be localised by fibre optical cable which has been installed at the toe of

    the drainage zone. In addition, the water tables below and around the reservoir are monitoredaccurately by piezometer boreholes which have been drilled from the dam crest and the

    surrounding area to a depth below the ground water table.

    10 Impounding

    Impounding of the reservoir will start in July 2007 after commissioning the pumping and

    conveying system that will feed the reservoir with water. According to the designers programme

    the filling procedure will be carried out in defined steps and will take approximately six months in

    total.

    Acknowledgement

    The author wishes to thank all Parties involved in the construction works namely the Owner of

    the reservoir, the Great Man-Made River Utilization Authority and their Consultant Brown and

    Root North Africa as well as the local Main Contractor General Company for Building and

    Construction and their Consultant LTCC from Benghazi.

    Author s Address and Affiliation

    Schmid, Reinhard, Dr.-Ing.

    Strabag International GmbH

    50679 Kln

    Germany

    [email protected]