Confidential Report
7.3 Robe Marina Straddle Carrier Jetty Tender
Report Title: Robe Marina Straddle Carrier Jetty Tender
Meeting Date: 8 August 2017
Author: Nick Brown
Author’s Title: Deputy Chief Executive Officer
Attachments: Robe Marina Straddle Carrier Jetty Tenders (3)
GHD John Ewers Tender Assessment
Purpose
To consider the Robe Marina Straddle Carrier Jetty tenders.
Recommendation
That the District Council of Robe having considered Report No. 7.3 “Robe Marina Straddle Carrier
Jetty Tender” approves the tender from Ecospec Pty. Ltd. for the construction of the Robe Marina
Straddle Carrier Jetty.
Background
Council issued a tender with the assistance of GHD (John Ewers) for the construction of the Robe
Marina Straddle Carrier Jetty.
Discussion
Council received three tenders and the tenders are summarised in the following table:
Tenderers ID Fabrication Ecospec P/L Engineered Water Systems
Tender price (excluding GST)
$790,950 $612,770 $699,034.54
GHD (John Ewers) has provided the attached documents and summary of the tenders:
Non-price tender comparison
Price tender comparison
EWS and Ecospec were shortlisted based on both price, and the quality of the initial tender
responses.
Supporting information was requested from EWS and Eco Spec. The non-price assessment
ranked Ecospec marginally higher than EWS.
GHD’s recommendation is that Ecospec is nominated as the preferred tenderer.
Policy Implication
Nil
9.24.1 District Council of Robe | Special Council Agenda 8 August 2017 - Confidential Item 7.3 1
Budget Implication
Council allocated funding of $800,000 in the 2017/18 budget for the completion of the
Fisherman’s Wharf upgrade and the construction of the Straddle Carrier Jetty. Taking into
account the tender amount for this project, the GHD costs and the amount outstanding for the
Fisherman’s Wharf, the budget allocation for 2017/18 will need to increase to $910,000.
Council is holding substantial funds from the 2016/17 financial year due to uncompleted capital
projects and there are sufficient funds to cover the budget increase of $110,000. The capital
budget will be adjusted at the first review of the 2017/18 budget.
Strategic Plan
Governance / Financial Sustainability
Provide leadership, good governance, and efficient, effective and responsive Council services.
Community Consultation
Nil
Risk Level
Low
9.24.1 District Council of Robe | Special Council Agenda 8 August 2017 - Confidential Item 7.3 2
A B http://www.engineeredwatersystems.com.au/ http://www.ecospecaus.com.au/
Assessment Description Assessment Criteria15.0 1 Organisation Experience Relevant Capability and experience demonstrating successful delivery of similar type or work (water load bearing
structure, marine environments, rehabilitation work) Referees include Department of Transport (WA) and City ofKwinana (WA)Referees - Pg 171 on RFT Form
Referees include Flinders Port (Carl Williamson), Brisbane CityCouncil and Redland City Council - pg 35 RFT Form
Recent project delivered and benefits delivered 3 examples Yes (pg 34 RFT) 3 Yes (pg 35 RFT) 3Demonstrated Relevance Yes 1 Yes 2.5
Details of at least one reference for similar work and information on the approximate date when work was completedand the approximate value of work undertaken. Referees Yes 3 Yes 3
11.67 14.1710.0 2 Organisational Structure Appropriateness of Project Organisational Structure
Organisational Chart No 2 Yes 2Roles and Responsibilities Yes 3 Yes 3Appropriateness of each Person Yes 3 Yes 3
8.89 8.8920.0 3 Key Personnel Experience Please supply/refine relevant qualifications and relevant experience of key personnel
(eg. CVs) nominated for the construction phase of the project, including designatedProject Manager, Site Supervisor and Safety Officer.
EWS\Post Tender Response\Key Personnel PM and Safety Manager
Project Manager, Site Supervisor and Safety Officer Detailed CV Yes 3 Yes 3Number of staff proposed to be used and their relevant qualifications and relevant experience Relevance of Experience Yes 3 Yes 2.5
Staff Roles Yes 3 Yes 3 Site Supervisor CV
20.00 18.8910.0 4 Subcontractors Provide details of all subcontractors to be used for the construction of the works. Subcontractors listed in RFI Response Eco Spec\Post Tender Response\Proposed Subcontractors -
Robe Straddle Carrier.pdf
Subcontractors Detail Yes 3 Yes 3Steel Fabrication Subcontractor http://www.haynesengineering.com.au/ 10.00 http://www.ottowayengineering.com.au/ 10.00
15.0 5 Detailed Construction Program Indicative Program (Gantt Chart)Award of Tender - 1st September 2017Access to Site - 1st November 2017
Construction Plan and MS Project Program - Incorrect StartDate
Completion Date - 14/12/17
MS Project Program Yes 3 Yes 3Critical Path activities Yes 3 Yes 3
15.00 15.0015.0 6 Task Appreciation Including Work Method Statements Comprehensive Work Methodology Provided pg 178 on RFT
Form Eco Spec\1. ROBE MARINA CONSTRUCTION METHOD.pdf
Understatnding Yes 2 Yes 3Complexities Yes 2 Yes 3
GHD assessment based on Methodologies Proposed Risks Yes 2 Yes 3
10.00 15.0015.0 7 Safety Plans and Management Provision of Safety and Management Plans Eco Spec\ECO-SF-001 PROJECT CONSTRUCTION SAFETY
PLAN.pdf
Safety Plans Provided Yes 1 Yes 2Work Method Statement Yes 1 Yes 3
Reliant on Fisherman's Wharf Documentation 5.00 10.00
100.0 81 (B) Eco Spec 92
(A) EWS
(A) EWS
(B) Eco Spec
NON PRICE TENDER COMPARISON FOR ROBE MARINA STRADDLE CARRIER JETTY REHABILIATATION
Total Tender Assessment Rating /100
Weighting
ScheduleTENDER ASSESSMENT
9.24.1 District Council of Robe | Special Council Agenda 8 August 2017 - Confidential Item 7.3 46
B C
Item No. Trade1 Establishment of Site2 Site Clean Up3 Project Management Plan (incorporating WHS,Quality System and Enviromental Plans)4 As Constructed Drawings5 Survey6 Project Management including Site Supervisor7 Other (Please Specify)
Total Firm Lump Sum 29,097.83$ 56,412.00$ Not Provided
Item No. Trade1 Construction Enviromental Management Plan2 Assessment of Existing Piles3 Disposal of Waste
Total Firm Lump Sum 49,217.39$ 48,019.00$ Not Provided
Item No. Trade1 Construction Enviromental Management Plan2 Assessment of Existing Piles3 Disposal of Waste
Total Firm Lump Sum 189,072.75$ 202,364.00$ Not Provided
Item No. Trade1 Site Signage2 Builders Signage3 Letter Boxes4 Optional Upgrades
Total Firm Lump Sum 263,743.75$ 252,341.00$ Not Provided
Item No. Trade1 Site Signage2 Builders Signage3 Letter Boxes4 Optional Upgrades
Total Firm Lump Sum 34,532.61$ 38,360.00$ Not Provided
Item No. TradeTotal Firm Lump Sum 133,370.21$ 15,274.00$ Not Provided
Total Excluding GST 699,034.54$ 612,770.00$ 790,950.00$
(A) EWSAmount (Excluding GST)
(B) Eco SpecAmount (Excluding GST)
(C) ID FabricationAmount (Excluding GST)
(A) EWSAmount (Excluding GST)
(B) Eco SpecAmount (Excluding GST)
(C) ID FabricationAmount (Excluding GST)
(A) EWSAmount (Excluding GST)
(B) Eco SpecAmount (Excluding GST)
(C) ID FabricationAmount (Excluding GST)
(C) ID FabricationAmount (Excluding GST)
(B) Eco SpecAmount (Excluding GST)
(A) EWSAmount (Excluding GST)
(B) Eco SpecAmount (Excluding GST)
(A) EWSAmount (Excluding GST)
(C) ID FabricationAmount (Excluding GST)
(A) EWSAmount (Excluding GST)
(B) Eco SpecAmount (Excluding GST)
(C) ID FabricationAmount (Excluding GST)
SEPARABLE PORTION 6 - Profit and Overheads
SEPARABLE PORTION 1 - Site Establishment
SEPARABLE PORTION 2 - Demolition
SEPARABLE PORTION 4 - Erection
SEPARABLE PORTION 3 - Fabrication
SEPARABLE PORTION 5 - Site - Civil Works
PRICE TENDER COMPARISON FOR ROBE MARINA STRADDLE CARRIER JETTY REHABILITATION
9.24.1 District Council of Robe | Special Council Agenda 8 August 2017 - Confidential Item 7.3 47
1
Nick Brown
From: John Ewers <[email protected]>
Sent: Thursday, 27 July 2017 3:07 PM
To: Nick Brown
Subject: EM201735611 - 7.81.4 - Robe Marina - Straddle Carrier Jetty Rehabilitation -
TENDER ASSESSMENT
Attachments: Non Price Tender Assessment for Robe Marina Straddle Carrier Jetty
Rehabilitation.pdf; Price Tender Assessment for Robe Marina Straddle Carrier Jetty
Rehabilitation.pdf
SynergySoft: EM201735611 - 7.81.4
Nick,
Please find attached the documentation we used in undertaking a price based and non-price based assessment of
the tender submissions.
Tenders were received from:
- EWS: $ 699,034.54
- Eco Spec: $ 612,770.00
- ID Fab $ 790,950.00
EWS and Eco Spec were shortlisted based on both price, and the quality of the initial tender responses.
Supporting information was requested from EWS and Eco Spec. The Non-price assessment ranked Eco Spec
marginally higher than EWS.
GHD’s recommendation is that Eco Spec is nominated as the preferred tenderer.
I will be in Robe on Monday morning, and we can discuss this in more detail.
Regards,
John Ewers
Project Director
Principal Civil Engineer
BE(Civil) FIEAust CPEng (NPER)
GHD
T: +61 8 81116643 | V: 336643 | M: +61 407 711 626 | F: +61 8 8111 6699 | [email protected]
Level 4 211 Victoria Square Adelaide SA 5000 Australia | http://www.ghd.com/
_____________________
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be
privileged. If you are not the intended recipient please notify the sender immediately, and please delete it;
you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its
affiliates reserve the right to monitor and modify all email communications through their networks.
_____________________
9.24.1 District Council of Robe | Special Council Agenda 8 August 2017 - Confidential Item 7.3 48