1 1. Advis e on pu blic/p rivat e coo pera tion for the a pplic ation of wa ste hea t outs ide the Tata Steel company 2. Estab lish t he work on En ergy Mana geme nt Syst em, i.e. de velo p a KPI tre e 3. Optimise p rodu ction and co nsump tion of wo rks arisi ng ga ses within s afety boundarie s (by means of simulation) 4. Advis e on th e opt imisation possi bilities o f elect ricity consu mptio n ov er time 5. Redevel op th e overall en ergy c onfi gura tion on site as an ideal situation 6. Advis e on ho w to move from e nerg y efficie ncy t o cont inuo us imp rovement on energy consumption 7. What hav e been the a ctual bene fits o f the Green Dea ls in N L. Why are th ey successful and would they have been successful without the Green Deal. Options for apprenticeships 2 1. Advise on public/private cooperation for the application of waste heat outside the Tata Steel company Info: As biggest energy consumer of the Netherlands, Tata Steel IJmuiden also has a tremendous quan tity of waste heat (flue gasses, water and material). As much as possible this is used internally. But there also remains much waste heat for which there are no projects yet with sufficient financial yield. Technically there are many options to apply the waste heat, like Organic Ranking Cycles, domestic heating. Such options don’t pass the financial yield criteria. Assigment: So the question is how to apply waste heat by means of cooperation with partners with lower financial thresholds for project selection? How should such a cooperation look like? What are the pro’s and con’s in financial and organisation point of view? Place to work: You will be working within the Energy Efficiency team of Tata Steel.

Upload: janfarsa9623

Post on 08-Aug-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

8/23/2019 Tat Steels

http://slidepdf.com/reader/full/tat-steels 1/4

1

1. Advise on public/private cooperation for the application of waste heat outside

the Tata Steel company

2. Establish the work on Energy Management System, i.e. develop a KPI tree

3. Optimise production and consumption of works arising gases within safetyboundaries (by means of simulation)

4. Advise on the optimisation possibilities of electricity consumption over time

5. Redevelop the overall energy configuration on site as an ideal situation

6. Advise on how to move from energy efficiency to continuous improvement onenergy consumption

7. What have been the actual benefits of the Green Deals in NL. Why are theysuccessful and would they have been successful without the Green Deal.

Options for apprenticeships

2

1. Advise on public/private cooperation for the application ofwaste heat outside the Tata Steel company

Info:As biggest energy consumer of the Netherlands, Tata Steel IJmuiden also has atremendous quantity of waste heat (flue gasses, water and material). As much aspossible this is used internally. But there also remains much waste heat for which thereare no projects yet with sufficient financial yield.Technically there are many options to apply the waste heat, like Organic RankingCycles, domestic heating. Such options don’t pass the financial yield criteria.

Assigment:So the question is how to apply waste heat by means of cooperation with partners with

lower financial thresholds for project selection?How should such a cooperation look like?What are the pro’s and con’s in financial and organisation point of view?

Place to work:You will be working within the Energy Efficiency team of Tata Steel.

8/23/2019 Tat Steels

http://slidepdf.com/reader/full/tat-steels 2/4

3

2. Establish the work on Energy Management System, i.e. developa KPI tree

Due to global warming and rising energy prices, energy efficient production is pushed tothe top of the agenda in production management. The Energy Efficiency team hasidentified and implemented several improvements with regard to energy efficiency. Butthe improvements should be maintained and secured in the production process.Therefore, it is important to embed the management of energy efficiency in theorganisation.

An energy management system (ISO 50.001 standard) facilitates the incorporation ofenergy efficiency management in the organisation. At this moment, Tata Steel is in thestart up phase for the implementation of an energy management system. Tata Steel isfacing challenges with regard to the following research directions:

How to establish an energy management system to control and maintain theimplemented improvements?• How to comply to the continuous improvement requirement of ISO 50001 and use the

existing Tata Tools for improvements.• Establish a KPI tree to identify and manage energy efficiency performance?• Design KPI’s for the shop floor for works which have a significant contribution to the

IJmuiden energy-efficiency KPI.

4

3. Optimise production and consumption of works arising gaseswithin safety boundaries (by means of simulation)

Tata Steel in IJmuiden produces 3 types of energy containing gasses. These are usedinside the works next to natural gas. Excess of these gasses are transported to a powerplant. To a little extend gasholder capacity is available. In emergency cases the gassesare flared.

Assigment:Develop a simulation tool for the site which should make it possible to study ways ofworking in order to maximise the result of the overall gas configuration taken intoaccount safety boundaries.

Assigment:Develop a simulation tool for the site which should make it possible to study ways ofworking in order to maximise the result of the overall gas configuration taken intoaccount safety boundaries.Work out options to extend the natural gas replacement program

8/23/2019 Tat Steels

http://slidepdf.com/reader/full/tat-steels 3/4

5

4. Advise on the optimisation possibilities of electricityconsumption over time

Price of electricity varies over time. What possibilities are there on the production site ofTata Steel in IJmuiden to optimise electricity cost? What should be the method tooptimise electricity cost?

Price of electricity varies over time. What possibilities are there on the production site ofTata Steel in IJmuiden to optimise electricity cost? What should be the method tooptimise electricity cost?Develop a tool to reduce electricity costs by making use of varying E market prices,which can be used in a 24/7 industry.

6

5. Redevelop the overall energy configuration on site as an idealsituation

The production site of Tata Steel IJmuiden developed over time. Given the productioninstallations as they are now, what would be the ideal energy configuration to supply thevarious works with energy. This developed set up should be useful for having a point onthe horizon for setting future directions.

The production site of Tata Steel IJmuiden developed over time. Given the productioninstallations as they are now, what will be the ideal energy configuration to supply thevarious works with energy. This developed set up should be useful for having a point onthe horizon for setting future directions. 10-20 years??

8/23/2019 Tat Steels

http://slidepdf.com/reader/full/tat-steels 4/4

7

6. Advise on how to move from energy efficiency to continuousimprovement on energy consumption

Due to global warming and rising energy prices, energy efficient production is pushed tothe top of the agenda in production management. By the use of a systematic andintensive analysis method of consumed energy, the Energy Efficiency program hasidentified and implemented several improvements with regard to energy efficiencyperformance. Furthermore, an energy management system will be implemented toembed energy efficiency in the organisation with as target to maintain and improvecontinuously in energy efficiency performance. In the ideal situation, the continuousimprovement in energy consumption will be realised by the employees at the lowesthierarchical levels in the organisation. Tata Steel is interested in the required activitiesto approach the ideal situation. In other words, how can we involve the productionworkers to improve continuously on energy efficiency.

hierarchical levels in the organisation. Tata Steel is interested in the required activities

to approach the ideal situation. In other words, how can we involve the productionworkers to improve continuously on energy efficiency.Is dit niet dubbel met de eerdere opdracht nr 2, of splitsten we 1 deel af?