target status report lara howlett university of sheffield
TRANSCRIPT
Target Status ReportTarget Status Report
Lara HowlettLara Howlett
University of SheffieldUniversity of Sheffield
Lara Howlett – University of Sheffield Frascati, June 2005
ContentsContents
A look at the specsA look at the specs Reminder of Prototype plansReminder of Prototype plans Meetings with ISIS engineersMeetings with ISIS engineers Testbeam plansTestbeam plans Status of electronics, readout and Status of electronics, readout and
radiation studiesradiation studies Plans / TimescalePlans / Timescale
Lara Howlett – University of Sheffield Frascati, June 2005
Updated SpecsUpdated Specs
Frequency 1-3 Hz. Higher may be Frequency 1-3 Hz. Higher may be possible but we may be limited by possible but we may be limited by heatingheating
Target will dip into the beam by 5-Target will dip into the beam by 5-10mm10mm
Only the intersection of the beam in Only the intersection of the beam in the last 1ms is usefulthe last 1ms is useful
We wish to intersect as little beam that We wish to intersect as little beam that is not useful as possibleis not useful as possible
Lara Howlett – University of Sheffield Frascati, June 2005
Updated SpecsUpdated SpecsHigher resolution
45
50
55
60
65
70
75
80
0 5 10 15 20 25 30
T(ms)
R (
mm
)
beam
target
4.4mm
2.05ms
Lara Howlett – University of Sheffield Frascati, June 2005
Updated SpecsUpdated Specs1000 g
40
45
50
55
60
65
70
75
80
85
0 5 10 15 20 25 30
T (ms)
R (
mm
)
beam
target
7.4mm
2.75ms
Lara Howlett – University of Sheffield Frascati, June 2005
Updated specsUpdated specs(3)
20
30
40
50
60
70
80
90
100
-15 -10 -5 0 5 10 15 20 25 30
T (ms)
R (
mm
)
beam
target
9.8mm
3.35ms
Lara Howlett – University of Sheffield Frascati, June 2005
Overview of PrototypeOverview of Prototype
The prototype is currently being The prototype is currently being built and is expected to be ready built and is expected to be ready by the end of the monthby the end of the month
The design consists of a a The design consists of a a magnetic shuttle to which the magnetic shuttle to which the target rod is attachedtarget rod is attached
This sits inside a series of coils This sits inside a series of coils which are driven in 3 phasewhich are driven in 3 phase
Lara Howlett – University of Sheffield Frascati, June 2005
PrototypePrototype
~8 cm
Lara Howlett – University of Sheffield Frascati, June 2005
Target MechanismTarget Mechanism
Lara Howlett – University of Sheffield Frascati, June 2005
Meetings with ISISMeetings with ISIS
Several very useful meetings have taken Several very useful meetings have taken place with engineers from ISISplace with engineers from ISIS
These have been very useful for These have been very useful for beginning to look atbeginning to look at– Safety issuesSafety issues– Vacuum issuesVacuum issues– How the target mechanism will be mountedHow the target mechanism will be mounted
A first set of engineering drawings have A first set of engineering drawings have also been produced by Stephanie Yangalso been produced by Stephanie Yang
Lara Howlett – University of Sheffield Frascati, June 2005
OutcomesOutcomes
The diaphragm springs will most likely be The diaphragm springs will most likely be replaced by ceramic bearingsreplaced by ceramic bearings
The target will be mounted on a replacement The target will be mounted on a replacement for the current A frame to reduce vibrations for the current A frame to reduce vibrations transmitted to the beam pipe by the targettransmitted to the beam pipe by the target
The possibility of replacing the inductive The possibility of replacing the inductive measurement system with an optical system measurement system with an optical system is under investigationis under investigation
The possibility of mounting the target using The possibility of mounting the target using nested bellows with a gate valve which would nested bellows with a gate valve which would allow the target to be completely removed allow the target to be completely removed from the beam in case of failure is being from the beam in case of failure is being investigatedinvestigated
Lara Howlett – University of Sheffield Frascati, June 2005
SchematicSchematic
Lara Howlett – University of Sheffield Frascati, June 2005
Status of ElectronicsStatus of Electronics
The electronics consists of two The electronics consists of two separate integrated circuitsseparate integrated circuits– Control logicControl logic– Current controllerCurrent controller
Lara Howlett – University of Sheffield Frascati, June 2005
Control LogicControl Logic
Position Decoder/Switching
Sequencer
Optical Isolators
Hex-Bridge Electronic 3 Phase Motor Switch (6
MOSFETS)Hall Switches
(Position Sensors)
ACTUATOR
Lara Howlett – University of Sheffield Frascati, June 2005
Current ControllerCurrent Controller
Hex-Bridge Electronic 3 Phase Motor Switch (6
MOSFETS)
Position Decoder/Switching
Sequencer
Active Current Control
PWM @ 19.5
kHz
Current Transducer
User Set Current (8-
Bit Resolution)
Lara Howlett – University of Sheffield Frascati, June 2005
Future PlansFuture Plans
To test this prototype circuitry with the actuator in order to ascertain its performance
Development of a quadrature position sensing system (to replace the hall switches) – This will allow greater control of the switching due to improved position information.
To develop an interface that will allow the electronics to be controlled via a PC
Lara Howlett – University of Sheffield Frascati, June 2005
Radiation StudiesRadiation Studies
Simulations of radiation levels Simulations of radiation levels have continued have continued
These now include the geometry These now include the geometry of the target mechanismof the target mechanism
Radiation levels in the magnet Radiation levels in the magnet are extremely highare extremely high
Lara Howlett – University of Sheffield Frascati, June 2005
Radiation studiesRadiation studies
Units :Grays/year/Unit Density
Lara Howlett – University of Sheffield Frascati, June 2005
Status of ReadoutStatus of Readout Problems with the readout board were Problems with the readout board were
experienced which caused jumps in experienced which caused jumps in the counts which were read outthe counts which were read out
After long correspondance with the After long correspondance with the company who provided the board, and company who provided the board, and returning the board for tests twice the returning the board for tests twice the problem has been resolvedproblem has been resolved
The readout system will therefore be The readout system will therefore be ready to be used with the new ready to be used with the new prototype when it arrivesprototype when it arrives
Sheffield will have a summer student Sheffield will have a summer student who will be working on this in the who will be working on this in the coming monthscoming months
Lara Howlett – University of Sheffield Frascati, June 2005
Test Beam PlansTest Beam Plans
There are plans to have the prototype There are plans to have the prototype ready for a test operation by Decemberready for a test operation by December
This would involve intersecting a few ISIS This would involve intersecting a few ISIS beam pulses when the machine starts up beam pulses when the machine starts up in Januaryin January
Measurements from the scintillators of Measurements from the scintillators of the Glasgow group will hopefully allow us the Glasgow group will hopefully allow us to gain a better understanding of how far to gain a better understanding of how far into the beam we need to go and how into the beam we need to go and how the beam profile changes with distancethe beam profile changes with distance
Lara Howlett – University of Sheffield Frascati, June 2005
Backup plansBackup plans
In parallel with the work In parallel with the work described two ‘backup’ plans are described two ‘backup’ plans are being investigated in the being investigated in the backgroundbackground– The use of a lever to move the The use of a lever to move the
actuator away from the targetactuator away from the target– The use of a cam to provide the The use of a cam to provide the
motionmotion
Lara Howlett – University of Sheffield Frascati, June 2005
LeverLever
Despite the hope that a lever would provide Despite the hope that a lever would provide a mechanical advantage discussions with an a mechanical advantage discussions with an engineer indicate that because of the low engineer indicate that because of the low mass of the shuttle this is not possiblemass of the shuttle this is not possible
However the use of a lever would give the However the use of a lever would give the advantage of moving the electronics and advantage of moving the electronics and magnets away from the radiation if this is magnets away from the radiation if this is necessarynecessary
The other advantage of this arrangement is The other advantage of this arrangement is that the target mechanism is isolated from that the target mechanism is isolated from the ISIS vacuum eliminating any possible the ISIS vacuum eliminating any possible problems of contaminationproblems of contamination
Lara Howlett – University of Sheffield Frascati, June 2005
CamCam
The idea of a cam has The idea of a cam has also been investigated also been investigated in the background so in the background so that in the instance that in the instance that the em design that the em design does not produce the does not produce the accelerations required accelerations required a backup plan is in a backup plan is in place. This would be place. This would be used in conjunction used in conjunction with a leverwith a lever
Lara Howlett – University of Sheffield Frascati, June 2005
PlansPlans
Upcoming milestones:Upcoming milestones:– Prototype should be assembled and Prototype should be assembled and
ready for tests to begin mid Julyready for tests to begin mid July– Prototype should be sufficiently Prototype should be sufficiently
tested to put in the beam by tested to put in the beam by ChristmasChristmas
– Data from beam tests should be Data from beam tests should be used as input for final designused as input for final design
Lara Howlett – University of Sheffield Frascati, June 2005
ConclusionsConclusions
Work towards the prototype is Work towards the prototype is progressing and we expect to start progressing and we expect to start tests in the coming weekstests in the coming weeks
Several successful meetings with ISIS Several successful meetings with ISIS engineers have taken place and these engineers have taken place and these have been extremely useful in have been extremely useful in progressing with the designprogressing with the design
Exactly how far we need to go into the Exactly how far we need to go into the beam has significant implications for beam has significant implications for the design, so we should pin this the design, so we should pin this number down as much as we cannumber down as much as we can