takreer - daewoo - civil works - quality plan
TRANSCRIPT
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 1/35
Contractor Transmittal No.
Document No.
BY DATE:
T-DH-5578-E4-5806
BY DATE:
COMPANY/PMC
EPC PACKAGE - 4 : TANKAGE AND ASSOCIATED INTERCONNECTING PIPING
Project Quality Plan for Civil Work
Rev. Date
Rev 0
21 Jul 2011
COMMENTS TO BE RETURNED TO:
DOCUMENT / DRAWING COMMENTS SHEET
FAX NO.:
COMMENTS:
25 Jul 2011Recd. Date
5578-E4-1041-QC-CC-304
PROJECT NO. 5578 / AGREEMENT NO. 09-5578-E-4
Document Title
ABU DHABI OIL REFINING COMPANY (TAKREER)
FAX NO.:
RUWAIS REFINERY EXPANSION (RRE) PROJECT
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 2/35
RUWAIS REFINERY
EXPANSION PROJECT
EPC-4 TANKAGE AND ASSOCIATED
INTERCONNECTING PIPING
AGREEMENT No. 09-5578-E-4
PROJECT No. 5578 Doc. No. 5578-E4-1041-QC-CC-304Rev.
0
Page
1 / 3
PROJECT QUALITY PLANfor Civil Work
AGREEMENT NO. : 09-5578-E-4
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 3/35
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 4/35
$
%
&
6HFDQG
6HF
)LUVWLVVXH
$GGHGFRGHDQGVWDQGDUGDQGSURMHFWVSHFLILFDWLRQ
$GGHG([KLELW%DSSOLFDEOHSURMHFWVSHFLILFDWLRQ
Rev Location of Change Brief Description of Change$ )LUVW,VVXH
% &RPPHQWZDVLQFRUSRUDWHG
,VVXHGIRU&RQVWUXFWLRQ
TAKREER
RUWAIS REFINERY EXPANSION PROJECT
EPC-4 TANKAGE AND ASSOCIATED
INTERCONNECTING PIPING
AGREEMENT No. 09-5578-E-4
DAEWOO E&C
PROJECT QUALITY PLANfor Civil Work
352-(&71R
'RF1R(4&&&
5HY
3DJH
REVISION INDEX DETAILS
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 5/35
DAEWOO E&C 'f QUALITY MANAGEMENT SYSTEMDoc. No.: TAK·PQP.S·GEN·0000·0001
H - b _ jT A K R E Page: 1 of30J . l J , . , & J ~ " ~ , . : A PROJECTQUALITY PLANW e ~ Rev.: 00
KETTANEH
ISO 9001 : 2008 Date: 18 April 2011
RUWAIS REFINERY EXPANSION PROJECT
EPC- 4 TANKAGE &ASSOCIATED
INTERCONNECTING PIPING
RUWAIS, U.A.E.
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 6/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 2 of 30
Rev. : 00
Date: 18 Apri l 2011
Amendment Form
SN Section / Item
Current Statement Amended Statement Rev. Date
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 7/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 3 of 30
Rev. : 00
Date: 18 Apri l 2011
Distribution Log
Controlled copies of this System Operating Procedure have been issued as follows:
Copy No. Issued to:
1 Project Management
2 Workshop
3 QA/QC Central Unit
4 QA/QC Site Unit
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 8/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 4 of 30
Rev. : 00
Date: 18 Apri l 2011
Table of Contents
KETTANEH STATEMENT OF QUALITY POLICY AND OBJECTIVE ..................................................................... 6
Project Quality Policy………………………………………………………………………………………………….......6
Project Quality Objective…………………………………………………………………………………………………..6
1. SCOPE ........................................................................................................................................................................ 7 2. APPLICABLE STANDARDS AND PROCEDURE .................................................................................................. 7 3. TERMS AND DEFINITIONS .................................................................................................................................... 7 4. PROJECT QUALITY MANAGEMENT SYSTEM................................................................................................... 7
4.1. GENERAL REQUIREMENTS ............................................................................................................................. 7 4.1.1 General......................................................................................................................................................... 7 4.1.2 Outsourcing processes ................................................................................................................................. 8
4.2 DOCUMENTATION ........................................................................................................................................... 8 4.2.1 Project Quality Management System Documents ....................................................................................... 8 4.2.2 Document and Data Control ........................................................................................................................ 8 4.2.3 Control of Quality Record ........................................................................................................................... 9
5. MANAGEMENT RESPONSIBILITY ....................................................................................................................... 9 5.1 GENERAL ........................................................................................................................................................... 9 5.2 ORGANIZATION ................................................................................................................................................ 9
5.2.1 Project Organization.................................................................................................................................... 9 5.2.2 Project Quality Organization ...................................................................................................................... 9 5.2.3 Function and Responsibility ........................................................................................................................ 9
6. RESOURCE MANAGEMENT ................................................................................................................................ 10 6.1 PROVISION OF RESOURCES .......................................................................................................................... 10 6.2 HUMAN RESOURCES ..................................................................................................................................... 10
6 2 1 G
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 9/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 5 of 30
Rev. : 00
Date: 18 Apri l 2011
7.3.2 Identification of Traceability ..................................................................................................................... 18 7.3.3 Client Supplied Material............................................................................................................................ 19 7.3.4 Handling, Receiving, Storing, Preservation and Delivery ......................................................................... 19
7.4 CONTROL OF INSPECTION, MEASUREMENT AND TEST EQUIPMENT ........................ ................. .......... 20 8. MEASUREMENT, ANALYSIS AND IMPROVEMENT ........................................................................................ 21
8.1 GENERAL ......................................................................................................................................................... 21 8.2 MONITORING AND MEASUREMENT ........................................................................................................... 21
8.2.1 Client’s Satisfaction ................................................................................................................................... 21 8.2.2 Internal Quality Audit ............................................................................................................................... 22 8.2.3 Monitoring and Measurement of Processes............................................................................................... 22 8.2.4 Monitoring & Measurement of Manufacturing Products & Construction Work .................................... 22
8.3 CONTROL OF NONCONFORMING PRODUCT ........................ ................ ........................ ....................... ....... 23 8.4 ANALYSIS OF DATA....................................................................................................................................... 24
8.4.1. Client Satisfaction ...................................................................................................................................... 24 8.4.2 Nonconformity to project requirements.................................................................................................... 24 8.4.3
Characteristics and trends of processes and products .............................................................................. 24
8.4.4 Subcontractors........................................................................................................................................... 24
8.5 IMPROVEMENT ............................................................................................................................................... 25 8.5.1 Continual Improvement ............................................................................................................................ 25 8.5.2 Corrective Action....................................................................................................................................... 25 8.5.3 Preventive Action...................................................................................................................................... 25
8.6 HANDOVER OF CIVIL WORKS ...................................................................................................................... 25 8.7 INSPECTION AND TEST ................................................................................................................................. 25
Appendix 1-1 Overall Organization Chart Rev. 01 .............................. .................... ................... ...................... ................ ... 26 Appendix 1-2 Field QA/QC Organization Rev. 01 ............................ .................. .................. ...................... ................. ....... 27 Attachment 1 : Project Quality Objective
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 10/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 6 of 30
Rev. : 00
Date: 18 Apri l 2011
KETTANEH STATEMENT OF QUALITY POLICY AND OBJECTIVE
Project Quality Policy
Kettaneh Construction Emirates (KCE) is committed to provide, in realizing the Ruwais Refinery EPC-
4 Project located at Ruwais Industrial City, services to the satisfaction of M/s. CB&I ANSTALT under DAEWOO E&C as per specifications and agreed conditions.
To meet its challenges KCE shall:
- Maintain a high level of technical capabilities through professional, experienced, skilled and
trained employees.- Use of relevant equipment and modern technologies.
- Respect and comply with all relevant national and international codes and standards.
- Continue the pursuit of improving the quality of services.
General Guidelines
In realizing this project with regard to the quality policy above, the Project Management states the
project goals hereunder:
KCE shall comply with the project quality plan in order to handover this project to the satisfaction of
the Client as for:
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 11/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 7 of 30
Rev. : 00
Date: 18 Apri l 2011
1. SCOPE
This “Project Quality Plan” identifies & describes the Quality Management System (QMS) processes
needed for the construction activities conducted by Kettaneh Construction Emirates for M/s CB&I
ANSTALT under DAEWOO E&C to realize the RUWAIS REFINERY EXPANSION EPC-4
PROJECT.
2. APPLICABLE STANDARDS AND PROCEDURE
The following Codes and Standards will be applied for this project:
ISO 9001:2008 : Quality Management Systems - Requirements
ISO 9000:2005 : Quality Management Systems – Fundamentals and vocabulary
BSI : British Standard Institution
ASTM : American Society for Testing and Materials
ACI : American Concrete Institute
Corporate Quality Manual: KCE-QM-101 Issue 01, 25 Nov 2010
3. TERMS AND DEFINITIONS
For the purposes of this Project Quality Plan, the terms and definitions given in the InternationalStandard, ISO 9001:2008 “Quality Management Systems – Fundamentals and Vocabulary” shall apply.
The following definitions will be applied in this document.
Company : TAKREER
Contractor : DAEWOO E&C
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 12/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 8 of 30
Rev. : 00
Date: 18 Apri l 2011
4. PROJECT QUALITY MANAGEMENT SYSTEM
4.1. GENERAL REQUIREMENTS
4.1.1 General
The Project Quality Plan is prepared in accordance with KCE “Quality Manual” based on
ISO 9001:2008, as well as the Client’s requirements specified in the Tender Documents.
4.1.2 Outsourcing processes
KCE will use Third Party Independent Testing Laboratory to conduct laboratory quality
tests, at site or off site, when and where applicable. The Project Management shall appoint
the Field QA/QC Manager to monitor the testing laboratory to ensure that their activities
and documentation are in line with the Project Requirement.
4.2 DOCUMENTATION
4.2.1 Project Quality Management System Documents
Project Specific procedures and method statements for all aspects of the Works will be
prepared based on the Project requirements and KCE’s Corporate Standard.
Applicable documents for the Project specific Quality Management System is listed inAppendix-3 “Applicable Document List”.
4 2 2 Document and Data Control
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 13/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 9 of 30
Rev. : 00
Date: 18 Apri l 2011
The applicable documents for this chapter are TAK-CQP-S-GEN-PDRC-0003 REV. 00
“Control Quality Procedure Drawing Control” and TAK-CQP-S-GEN-PDOC-0002 REV. 00
“Control Procedure for General Document Control”. All formats to be used shall be
approved under its respective Master Document (Attachment No.5)
4.2.3 Control of Quality Record
Project Management maintains quality records to provide evidence of conformity to
requirements and of the effective operation of the QMS. The “Control of Records
Procedure” defines the controls needed for identification, storage, protection, retrieval,
retention time and disposition of records.
The applicable document for this chapter is TAK-CQP-S-GEN-PCOR-0004 REV. 00 “Control
Quality Procedure for Control of Records”.
5. MANAGEMENT RESPONSIBILITY
5.1 GENERAL
The Project Management established the “Project Quality Objective” herewith attached
( Attachment No.1) and which shall be communicated by all concerned and will be instructed to
perform their duties strictly in accordance with this Project Quality Plan and thereby contribute tothe realization of the Project Quality Objective.
5 2 ORGANIZATION
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 14/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 10 of 30
Rev. : 00
Date: 18 Apri l 2011
5.2.3 Function and Responsibility
Please refer to Appendix 2 “ Job Description” for the Roles and Responsibilities of Key
Persons in this Project.
6. RESOURCE MANAGEMENT
6.1 PROVISION OF RESOURCES
The Project Management ensures the meeting of Client’s requirements by providing the resources
needed to implement and maintain the QMS and continually improve its effectiveness.
6.2 HUMAN RESOURCES
6.2.1 General
The General Manager assigned for this Project competent personnel, on the basis of
appropriate education, training, skills and experience, for the management and
implementation of the Works as well as their inspection including internal audits.
6.2.2 Competence, Training and Awareness
1) Qualification of Project Management Team Members
The General Manager ensures the qualifications of personnel for the ProjectManagement and Administration works Their appointment shall be based on the
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 15/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 11 of 30
Rev. : 00
Date: 18 Apri l 2011
The Project Management maintains records of training of project office personnel on
an individual basis, Attachment No. 6 “Training Record ”, which shall be kept
confidential at the Project Management disposition.
The applicable document for this chapter is TAK-CQP-S-GEN-PCTA-0008 REV. 00, “Control Quality
Procedure for Competence, Training & Awareness”6.3 INFRASTRUCTURE AND WORK INVIRONMENT
6.3.1 Infrastructure
Project Management provides the infrastructure needed in the project. Infrastructure
includes the following temporary items as follows:
1. project office and associated utilities, warehouse, stockyard, temporary car park,
2. materials, machine and process equipment (both hardware and software), and
3. supporting services such as transport, communication and/or information system
6.3.2 Work Environment
Project Management provides Work Environment to include the following temporary
items as follows:
1. temporary safe and healthful facilities,2. places of communication in the Project Site, and
3. safe work area and ambient working condition
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 16/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 12 of 30
Rev. : 00
Date: 18 Apri l 2011
The realization process in KCE is done in three stages:
• Pre-award Estimation Stage
• Award Stage
• Post-award Execution Stage
This PQP shall describe only the stages related specifically to this Project.
7.1.2.1 Post-Award Stage
1) Contract Budget and Cost Control
The contract quantities and budget are prepared for operational purposes
(procurement, accounting, cost control etc). Copy of the budget is checked by theETM and VP Business Development, Estimation & IT.
VP Business Development, Estimation & IT will forward the same to the General
Manager for his review, if the former finds it necessary. This is done prior todistribution to the Area Procurement Department for reference, Finance and Accounts
Unit (FAU) for control and PCSM for follow-up.
2) Contract Document Distribution
Copies of the contract document will be distributed to:
Area Managing Director (AMD)
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 17/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 13 of 30
Rev. : 00
Date: 18 Apri l 2011
Area Administrative & Commercial Manager (ACM)
The ACM will be basically involved in payment terms and the relevant cash flowincluding monthly expenses vs. income.
The ACM Shall be involved in procurement of site needs for various categories of
staff and labours and their accommodation, transportation and travel, visas, residencycards, work permits, etc.
Area Quality Assurance / Quality Control Manager (AQAQCM)
The Area QA/QC Manager will review the Contract and highlight all Quality related
issues. At a later stage, he will be responsible to define the processes and procedures
required by the Contract in order to implement them for this specific Project.
Contracts Manager (CM)
The CM will review the Contract and highlight all the specifically contractual rights
and duties of both KCE and the Client, in order to be able to follow them up at a later stage.
3) Transfer of Data
Upon signing the contract, the AMD shall invite all concerned to an internal kick off meeting, whereby the AMD will transfer the following basic elements/data tothe attendees for implementation:
a mobilization period
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 18/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 14 of 30
Rev. : 00
Date: 18 Apri l 2011
4) Construction Operations:
• Material Delivery
The Site Procurement Coordinator (SPC) in conjunction with the Site
Planning Engineer (SPE) will regularly review material delivery dates with
respect to construction activities and completion dates so as to meet theoverall project completion schedule date.
• Procurement
The Area Procurement Department (based in our Head Office, Abu Dhabi)
will review the contract schedule in relation to the material requirements
of the project:
- as to when the material is required on site, and- the relevant specification of that material
• Shop Drawings
The Technical Office (TO) reviews the contract requirement for shop
drawings envisaged to be prepared, in due course, for submittal to avoid
any delays in material procurement or project execution of the relevant
works.
• Project / Construction / Site Manager
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 19/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 15 of 30
Rev. : 00
Date: 18 Apri l 2011
7.1.2.2 Amendment of Contract
Variations to the Contract:
During the process of execution, should the Client introduce changes in
Specifications to certain items or changes in the scope of Work, the Technical
Office (TO) will evaluate with the assistance of the ESD, the price effect
resulting from these changes.
The TO will also evaluate any effect on the terms of the contract and in
particular, on the execution schedule of the project as a whole or part thereof
and also price effect of items related to the “indirect cost”. In case of any
amendment, the said amendment are resolved and properly documented and therelevant personnel and company departments concerned are made aware of the
changes for implementation.
Originals are added to the original Contract document retained by AMD.Contract review records are maintained with the Project Manager.
7.1.2.3 Communication with Client
The Project Management determines and implements effective arrangements for
communicating with Client in relation to:
1)
Product informationUpon request from Client, KCE shall submit relevant technical sheets, samples
etc. as applicable for Client’s information and records and/or review and
approval
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 20/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 16 of 30
Rev. : 00
Date: 18 Apri l 2011
7.2 PURCHASING
7.2.1 General
The Area Procurement / Procurement Manager based in the KCE Abu Dhabi head officehas overall responsibility for all purchasing activities to ensure purchasing will be
implemented in accordance with the Client’s requirements and Corporate Standard
Practices.
The applicable document for this chapter is TAK-CQP-S-GEN-PPUR-0007 REV. 00, “Control
Quality Procedure Purchasing”.
7.2.2 Sub-Vendor list
The Project Manager with the coordination of the Area Procurement / Procurement
Manager shall prepare and submit to the Client the Sub-vendor list for approval as per the
Contract requirements.
This list shall be prepared based on the return of experience from previous similar projects
and related activities which had materialized vide the periodical evaluation.
7.2.3 Assessment and Selection of Sub-vendors
Sub-vendor shall be selected from the Sub-vendor list unless vendors not listed are moreappropriate and suitable in technical aspect
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 21/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 17 of 30
Rev. : 00
Date: 18 Apri l 2011
- operation & maintenance manuals, and
- warranty
7.2.6 Verification of Purchased Product
1.) The Project Management established documented procedures for receiving,inspecting and testing of materials and equipment which are carried out, inside and
outside of the Project Site and verifies that such materials and equipments complies
with the relevant Specifications provided in the Contract. The documented
procedures established include the measures to prevent such materials and
equipment from being used by mistake prior to being inspected or tested.
2.) The Project Management determined and included in the documented procedures
the items, frequency and sampling rate of the receiving inspection and testing for
such materials and equipment considering the conditions described below.
a) The extent of quality of such material and equipments supplied by the
manufacturer are the quality records provided by the manufacturers’ and
suppliers. Where such information is not available or such information seems to
be unreliable, the sampling and testing frequency shall be as per Client
requirements, as well as applicable local and international Standards.
Subsequently, the increase or decrease of testing frequency, depending on the
results of such sampling testing.
b) If documented quality evidence of conformance is to be attached to deliveredmaterials and equipment and where it is attached its contents
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 22/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 18 of 30
Rev. : 00
Date: 18 Apri l 2011
7.2.7 Shipping and Custom Clearance
The shipping activities for equipment and materials for the Project will be performed in
accordance with Project shipping and packing instructions and applicable UAE law.
7.3 PRODUCTION AND SERVICE PROVISION
7.3.1 Control of Product and Service Provision
Project Management had clearly defined construction plan including construction
processes on the project schedule and/or work procedures as needed and shall carry out
construction under controlled conditions.
Controlled conditions shall include as applicable.
1) The availability of information that describes the characteristics of the product, such as
Design Drawings, Specifications, Design Instruction, etc.
(7.1.2 Review of Project requirements)
2) The availability of work instructions such as work procedures etc., as necessary and the
use of suitable equipment which are needed for the work;
(6.3.1: Infrastructure)
3) The availability and use of monitoring and measuring devices, as necessary;
(7.4: Control of Inspection, Measurement and Test Equipment)
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 23/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 19 of 30
Rev. : 00
Date: 18 Apri l 2011
3) Traceability for the state of inspection.
The applicable document for this chapter (Civil works) is TAK-CQP-S-GEN-PRET-0004
REV. 00 “Control Quality Procedure for Rebar Traceability” and approved concrete pour
card.
7.3.3 Client Supplied Material
Project Management performs regarding this section the following actions:
1) Where the Client’s property is to be incorporated in the Work as provided in the
Contract, the Project Management determined the process of handling these items and
verification on receipt, storage and release from storage until incorporation in the work
of such Client’s property, and
2) Where the Client’s property is found visually unacceptable or partly and/or entirely
missing, the Project Management shall report the fact to the Client and agrees with him
how to recover.
The applicable document for this chapter is TAK-CQP-S-GEN-PHRM-0005 REV. 00 “Control
Quality Procedure for Handling and Receiving Permanent Materials”
7.3.4 Handling, Receiving, Storing, Preservation and Delivery
The Project Management established and maintains documented procedures to handle,store protect and deliver materials and equipment as well as the completed portion of the
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 24/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 20 of 30
Rev. : 00
Date: 18 Apri l 2011
b) The Procedure shall be identified for the materials and equipment which could
easily deteriorate during storage and a matrix of inspection as applicable shall be
established with the frequency of inspection and assess the extent of any
deterioration and take necessary actions to prevent damage and/or deterioration,
and
c) Establish the materials “entry and release control procedure” including approvalof release.
3) Protection
The procedure for the protection methods for the completed portions of the Work,
identification for the items, which need rust-inhibiting treatment or sealing of
desiccant, and a practical method for prevention are included in the construction
procedure for the specific work items.
4) Delivery
The Project Management establishes documented procedures for the care of the
completed structure after in-house inspection and testing on completion and maintains
them until handing over to the Client in conformance with the procedures.
The applicable documents for this chapter is TAK-CQP-S-GEN-PHRM-0005 REV. 00
“Control Quality Procedure for Handling and Receiving Permanent Materials”
7.4 CONTROL OF INSPECTION, MEASUREMENT AND TEST EQUIPMENT
Where necessar to ens re alid res lt as the n merical al e b Client req irements
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 25/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 21 of 30
Rev. : 00
Date: 18 Apri l 2011
6) Pressure Gauges
7) Concrete Moisture Tester
8) Nuclear Density Gauge
9) Electrode Drying Oven
10) Welding Rectifier
11) Welding Generator Set12) Electrical Digital Multi Meter
13) Electrical Digital Clamp Meter
14) Cable Insulation Tester
In addition, Project Management shall assess & record the validity of the previous
measuring results when the equipment is found not conforms to the requirements. Project
Manager shall take appropriate action on the equipment & any product affected.
Records of the results of calibration & verification shall be maintained.
The applicable documents for this chapter are KCQ-QM-101-7.6.3 “Procedure for
Control of Inspection, Measurement and Test Equipment ”, of the Corporate Quality
Manual.
8. MEASUREMENT, ANALYSIS AND IMPROVEMENT
8.1 GENERAL
Top Management plans and implements the monitoring measurement analysis and improvement
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 26/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 22 of 30
Rev. : 00
Date: 18 Apri l 2011
2) Requests and complaints upon the completion of works;
- on the in-house final inspection and/or the handing over of the Project
3) Other information such as business development matters and Customer Survey Form
etc.
This information mentioned above shall be utilized for the Corrective and Preventiveaction, Management Review Meeting, and also spread within all the organization of KCE
as necessary.
8.2.2 Internal Quality Audit
The Area QA/QC Manager or his delegate shall conduct internal audits at planned
intervals; usually the first audit will be conducted when the project reaches a twenty
percent (20%) progress accomplishment, to determine whether the Project Quality Plan is
effectively implemented and maintained. Succeeding internal audits will be conducted at a
planned interval as practicable and applicable for a minimum of 2 audits per 12 months
project duration.
The General Manager will submit the relevant audit and/or surveillance reports, including
findings and observations, areas of concern and required corrective actions, if any, on
completion to the Client through the Project Management whenever requested by M/s.
DAEWOO E&C or to be shown as requested during an audit conducted by M/s.
DAEWOO E&C.
The applicable document for this chapter is TAK-CQP-S-GEN-PIQA-0008 REV. 00 “ControlQuality Procedure for Internal Audit”
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 27/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 23 of 30
Rev. : 00
Date: 18 Apri l 2011
1) Inspection during construction
Project Management establishes and implements the procedure for inspection and
testing of the work described in the relevant approved ITP including the measures to
prevent works from being progressed to the subsequent stage prior to inspection andtesting for conformance, except the process work which can be identified and tested
for conformance, from the subsequent work.
a) Information from the monthly reports which are provided by Project Management.
2) In-house inspection and testing and completion
Project Management carries out the in-house inspection and testing on completion in
order to verify that the Works conform to specified requirements and records the
results.
Project Management shall deliver the work to the Client after he confirms the
completion of the works complies with the Client requirements.
The applicable Document for this chapter is TAK-CQP-S-GEN-PPLP-0009 REV. 00
“Control Quality Procedure Punch List Procedure”
8.3 CONTROL OF NONCONFORMING PRODUCT
The Project Management ensures that product which does not conform to product requirements
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 28/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 24 of 30
Rev. : 00
Date: 18 Apri l 2011
The controls and related responsibilities and authorities for dealing with nonconforming
product shall be defined in TAK-CQP-S-GEN-PNCP-0010 REV. 00 “Control Quality
Procedure for Control of Nonconforming Product”.
8.4 ANALYSIS OF DATA
The Project Management with close coordination with the Corporate QA/QC Manager shall
collect and analyze appropriate data to demonstrate the suitability and effectiveness of the
QMS and to evaluate where continual improvement of the effectiveness of the QMS can be
made.
The analysis of data shall provide information relating to:
8.4.1. Client Satisfaction
Project Management analyses claims and requests from Client through their regular
meetings during construction as well as the “customer satisfaction survey”, and
then takes measures against them. Where necessary, Project Management
discusses the matter with the Corporate QA/QC Manager.
The Corporate QA/QC Manager shall then report to Top Management vide the VP
Projects Control, Safety & Quality and utilize the data to ensure Client satisfaction
through Continual Improvement of QMS, and such information shall also be
included as one of the inputs during Management Review Meeting.
8.4.2 Nonconformity to project requirements
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 29/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 25 of 30
Rev. : 00
Date: 18 Apri l 2011
8.5 IMPROVEMENT
8.5.1 Continual Improvement
KCE continually improves the effectiveness of the Quality Management System
through the use of the Quality Policy, Quality Objectives, Audit Results, Analysis
of Data, Corrective and Preventive actions and Management Review.
8.5.2 Corrective Action
Project Management takes action to eliminate the cause of nonconformities in order
to prevent reoccurrence. Corrective action shall be appropriate to the effects of the
nonconformities encountered. A documented procedure has been established to
define the requirements as mentioned below;
a. evaluating the need for action to ensure that non-conformities do not reoccur,
b. reviewing nonconformities (including Client complaints),
c. determining the root causes of nonconformities,
d. determining and implementing action needed,
e. correction of the nonconformity,f. records of the results of action taken, and
g. reviewing corrective action and analyze the effectiveness of action taken
8.5.3 Preventive Action
Project Management determines action to eliminate the causes of potential
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 30/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 26 of 30
Rev. : 00
Date: 18 Apri l 2011
8.6 HANDOVER OF CIVIL WORKS
8.6.1 The handover of CIVIL WORK will be in accordance with a DAEWOO procedure to beagreed with COMPANY.
8.6.2 KCE shall be totally responsible for handover of all its WORK related to the construction
of the PLANT as per Scope of Work. KCE procedure will typically include the followinghandover steps:
-Discipline Acceptance
-Systems Acceptance
-Unit Acceptance
-CIVIL COMPLETION
8.6.3 Each of these handover steps will be a “Hold Point‟, i.e., progress from one step to thenext requires written approval from DAEWOO E&C.
8.7 INSPECTION AND TEST
KCE will inspect and test not only as per COMPANY approved field Inspection &
Test Plan but also as per Contract Requirements.
Appendix 1-1 Overall Organization Chart Rev. 01
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 31/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 27 of 30
Rev. : 00
Date: 18 Apri l 2011
Appendix 1-2 Field QA/QC Organization Rev. 0
CORPORATE QA/QC
MANAGER
Toni Hamouche
KETTANEH CONSTRUCTION EMIRATES OFF SITE ORGANIZATION
SITE ORGANIZATION
PROJECT
MANAGEMENT
Field QA/QC MANAGER TBA
CB&I QA/QC
MANAGER
TBA
Coordination
Communication
SECRETARY &
DOCUMENT CONTROLLER
TANK 2 TANK 3TANK 1
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 32/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 28 of 30
Rev. : 00
Date: 18 Apri l 2011
Appendix 2: “Job Description”
1) Project Manager
a. Having full charge of all operations and full authority to represent the project and to control
the Safety, Quality, Schedule and Cost.
b. Has the overall responsibility for the Project HSE and Quality Plans functioning within the
Company & Client policies. This responsibility and authority shall be delegated to
responsible project personnel with instructions to maintain and verify compliance to the
system throughout the duration of the project.
c. Approving the Project Plan and appraising the performance of the project WORKS and
submit monthly progress reports to the Client and highlighting any adverse trend with
counter measures to be taken.
d. Implementing the Project Safety / Quality Plan for procurement, construction /
commissioning work etc.
e. Detecting non-conformities / incidents and initiating and/or approving corrective actions,
intervening as to resolve outstanding safety & Quality issues and ensuring documenting of
all changes to project specification.
f. Fulfilling Contractor’s requirements specified in the Contract.
g Attend project review meeting
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 33/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 29 of 30
Rev. : 00
Date: 18 Apri l 2011
3) Section Engineer
a. Responsible for the general progress of the section construction work
b. Controlling work schedule, Quality, Work packages subcontract works and construction.
c. Implement method statements / work procedure.d. Reporting to the Site / Construction Manager
4) Technical Office Manager
a. Responsible for the preparation, review of method statement and shop drawings, technical
queries, etc.
b. Responsible for the preparation of monthly progress reportsc. Responsible for the schedule control
d. Review contracts and change orders with coordination of the Contract Manager
e. Attend project review meeting
f. Reporting to the Site Manager
5) Field QA/QC Manager
a. Preparing, maintaining and implementing of the Project Quality Plan
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 34/35
QUALITY MANAGEMENT SYSTEM
PROJECT QUALITY PLAN
ISO 9001: 2008
Doc. No.: TAK-PQP-S-GEN-0000-0001
Page: 30 of 30
Rev. : 00
Date: 18 Apri l 2011
e. Major administrative issues reported to Area Administrative and Commercial Manager.
Appendix 3: “Applicable Document List”
Doc. No. Title
1 TAK-CQP-S-GEN-PCOW-0001 REV. 00 Control Quality Procedure for Concrete Works
2 TAK -CQP-S-GEN-PGDC-0002 REV. 00Control Quality Procedure for General DocumentControl
3 TAK -CQP-S-GEN-PDRC-0003 REV. 00 Control Quality Procedure for Drawing Control
4 TAK -CQP-S-GEN-PCOR-0004 REV. 00 Control Quality Procedure for Control of Records
5 TAK -CQP-S-GEN-PRET-0005 REV. 00 Control Quality Procedure for Rebar Traceability
6 TAK -CQP-S-GEN-PHRM-0006 REV. 00 Control Quality Procedure for Handling andReceiving Permanent Materials
7 TAK -CQP-S-GEN-PPUR-0007 REV. 00 Control Quality Procedure Purchasing
8 TAK -CQP-S-GEN-PCTA-0008 REV. 00 Control Quality Procedure for Competence, Training
& Awareness
9 TAK -CQP-S-GEN-PIQA-0009 REV. 00 Control Quality Procedure for Internal Quality Audit
7/27/2019 Takreer - Daewoo - Civil Works - Quality Plan.
http://slidepdf.com/reader/full/takreer-daewoo-civil-works-quality-plan 35/35
RUWAIS REFINERY EXPANSION PROJECT, EPC-4 Tankage and Associated Inter connecting Piping Page 1 of 1
Reply sh eet to Company’s Review and Comments Transmittal Number: T-DH-5578-E4-5536
Return Code: 3 Document No 5578-E4-1041-QC-CC-304 Rev. B Document Title: Project Quality Plan for Civil Work Date: 9 July 2011
No. COMPANY’S COMMENT CONTRACTOR’S REPLY 1 None. --
------------- End -------------