tack coat: a “must have” in pavement placement presenations 2015/utah...•application rate...

61
Tack Coat: A “Must Have” in Pavement Placement Robert Horan, PE Regional Engineer Asphalt Institute Mechanicsville VA

Upload: dinhkhanh

Post on 29-Apr-2018

227 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Tack Coat:A “Must Have” in

Pavement PlacementRobert Horan, PERegional EngineerAsphalt InstituteMechanicsville VA

Page 2: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Purpose of Tack Coats

• Terminology

• Consequences of Poor Bond

• Relative Cost for Tack Coat

• Tack Coat Field Operations

• Manuals of Practice

• Best Practices

• Surface Preparation

• Truck Setup

• Research on Bond Strength Testing

Our Visit Today

Page 3: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Materials

• Traditional

• New Materials

• Selection

• Tack Coat Challenges

• Contractor

• Agency

• Spray Pavers

• Review and Summary

• Common Tack Coat Questions

• Areas of Known Agreement

Tack Coat Best Practices Outline

Page 4: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• To promote the bond between pavement layers.

• Prevent slippage/ shoving failures• Full bond is vital for structural performance of

the pavement. • When bonded, all layers working together.• Critical that tack materials are applied

uniformly at appropriate application rate

• Apply tack coat on all surfaces including vertical surfaces.

Purpose of Tack Coats

4

Page 5: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Far Too Frequent Poor Practices

Page 6: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Condition of Existing Pavement

• Tack Coat Application Rate

• Residual Binder Content

• Proper Distributor Operation

• Emulsion Break and Set Times

Key Factors for Tack Coat Success

6

Page 7: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Terminology

• Tack Coat—sprayed application of liquid asphalt upon an existing asphalt or Portland cement concrete pavement which may or may not have been milled before an overlay, or between layers of fresh asphalt concrete.

• Original Emulsion (emulsified asphalt)—an undiluted emulsion which consists of a mixture of paving grade binder, water, and an emulsifying agent.

• Diluted Emulsion—an emulsion that has been diluted with additional water.

• Critical to control

• 1:1 typical (original emulsion: added water)

Page 8: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Residual Asphalt—the remaining asphalt after an emulsion has set typically 57-70 percent.

• Tack Coat Break—the moment when water separates enough from the asphalt showing a color change from brown to black.

• Tack Coat Set (cure)—when all the water has evaporated, leaving only the residual asphalt. Some refer to this as completely broken.

Terminology

Page 9: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Emulsions are asphalt droplets suspended in water • Breaking

• Contact with surface changes pH; reducing charge• Setting

• Evaporation leads to coalescence• Original asphalt characteristics return

Emulsion Breaking & Setting

Page 10: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Consequences of Poor Bonding

• Poor pavement performance

• Slippage cracks

• Shoving

• Early fatigue cracking

• Bottom up

• Top down

• Costly pavement repairs

• Repair of isolated area relatively inexpensive

• Removal and replacement of a portion or the entire pavement structure is very expensive

• Shorter than expected pavement life can be devastating for agency budgets

Page 11: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Layer independence• Reduced fatigue life

• Increased rutting

• Slippage

• Shoving

• Compaction difficulty

Consequences of Poor Bonding

Direction of traffic?

Page 12: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Courtesy of Rich May

Tension

Stress Distribution

Soil Subgrade

Aggregate Base

Shear Transfer?

Pavement Behavior

Compression

Load Distributed by Tire

Page 13: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

½” Deflection,

60# Load¼” Deflection,

160# Load

Fully BondedUnbonded

Bonding Demonstration

Page 14: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• 5 unbonded layers deflected 4x more than 5 bonded with the same loading.

• 2 bonded layers had less deflection than 5 unbonded with the same loading.

• 5 bonded layers with over 2½x the load deflected half as much as 5 unbonded.

Bonding Demonstration Highlights

14

Page 15: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• May and King:• 10% bond loss = 50% less fatigue life

• Roffe and Chaignon• No bond = 60% loss of life

• Brown and Brunton• No Bond = 75% loss of life

• 30% bond loss = 70% loss of life

Loss of Fatigue Life Research

Page 16: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

8 – 10 years (est.) Interstate Pavement

Courtesy of MODOT

Page 17: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Cores Showing Debonding

Bonding Failures

Courtesy of MODOT

Page 18: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Cost of Tack Coat• New or Reconstruction

• About 0.1-0.2% of Project Total• About 1.0-1.5% of Pavement Total Cost

• Mill and Overlay• About 1.0-2.0% of Project Total• About 1.0-2.5% of Pavement Total Cost

What Does It Cost?

Page 19: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Assume no inflation for materials

• Estimated traffic control

• Used project plans for thicknesses

• Used bid tabs for:• Milling

• Material costs

• Replaced pavement markings

Estimated Cost of Bond Failure in Only the Top Lift

30-100% of OriginalPavement Costs

Page 20: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Emulsified Asphalt• Most common option

• SS-1, SS-1H

• CSS-1, CSS-1H

• RS-1, RS-1H, RS-2

• CRS-1, CRS-2

• PMAE

• PG Graded Binders• Neat Binders

• PG 58-28

• PG 64-22

• PG 67-22

• Polymer Modified

• Reduced or Non-tracking Emulsions

Common Tack Coat Materials

Page 21: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

States - Reduced Tracking Tack Mat’ls

CA

AZ

CO

NM

TX

OKAR

LA

MO KY

AL GA

FL

VA

OH

MI

VTAK

MT

NV

ME

WA

OR

UT

KS

ID

WY

ND

SD

MN

NE

WI

IA

IL IN

MS

TN

SC

NC

WV

PA

NY

CT

NJ

DE

MD

DC

MA

NH

RI

HI

PR

21

Page 22: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Dilution• Verify if it is allowed.

• If allowed, where?• Supplier only?

• Contractor?

• Control amount of water added. • 1:1 typical (Original Emulsion: Added Water)

• Use acceptable/approved water.

• Terminal added or field diluted.

• Always add water to emulsion.

Handling of Emulsions

22

Page 23: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Tack Coat Field Operations

Page 24: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Asphalt Institute• MS-4 The Asphalt Manual, 7th Edition (2007)

• MS-16 Asphalt Pavement Preservation and Maintenance, 4th Edition (2009)

• MS-19 Basic Asphalt Emulsion Manual, 4th Edition (2008)

• MS-22 Construction of Hot Mix Asphalt Pavements, 2nd

Edition

• Comments• AI has a long history of promoting the proper use of tack

coats.

Manuals of Practice

Page 25: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• QIP-128,Tack Coat Best Practices, NAPA (2013)

• Hot-Mix Asphalt Paving, US Army Corp of Engineers (2000)

• Airfield Asphalt Pavement Construction Best Practice Manual, NCAT (2008)

• Tack Coat Guidelines, Caltrans (2009)

• Tack Coats: How and what to apply! Colorado Asphalt Pavement Association (CAPA) (2011)

• Guide for Using Prime and Tack Coats, CFLHD (2005)

• Best Practices for Applying Undiluted Emulsified Asphalt Tack Coats, CAPA (2013)

Manuals of Practice

Page 26: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Tack Coat Application

Page 27: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Contractor• Variable application rates• Consistency of application• Tack coat pick-up or tracking by construction

vehicles• Breaking/setting time prior to paving

• Agency• Acceptance (method or performance)• Bond quality testing• Dilution?• Visual inspection• Application rate measurement

Tack Coat Challenges

Page 28: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Example of Tack Pick-Up

Photo courtesy of Road Science

Page 29: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Surfaces need to be clean and dry.

• Uniform application.

• All surfaces are tacked.

• Tack should not be tracked off the road.

Best Practices

Page 30: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Match application to conditions.

• Materials

• Residual rate

• Verify application rate.

• Resist tacking too far ahead of paver.

Best Practices

Page 31: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Distributor Truck Setup

Page 32: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Liquid temperature

• Monitor and match to material

• Calibrate distributor truck

• Spray bar height

• Spray bar pressure

• Nozzle selection

• Nozzle angle

• Thermometers

• Volumeter

• Application rate

Distributor Truck Setup

Page 33: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Method A—Weighing Pads• Pre-weigh pads

• Secure pads to surface

• Apply tack coat

• Reweigh pads

• Calculate application rate

Direct Measurement using ASTM D2995

Page 34: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads
Page 35: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Field Measurement of Application Rate• Longitudinally

• Transversely

• Units of Gallons/Yard2 (Liters/Meter2)

Direct Measurement using ASTM D2995

Photos courtesy of Dr. Louay Mohamad

Page 36: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Photo courtesy of Ergon Asphalt

Page 37: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Nozzle Selection

Page 38: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Consult with distributor truck manufacturer to match the material to the nozzle.

• ONE SIZE DOES NOT FIT ALL

38

Nozzle Selection

Page 39: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Effect of Nozzle Orientation

Proper nozzle angle of 15-30% assures proper overlap between nozzles without interference of tack streams.

Page 40: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Spray Bar/Nozzles

Page 41: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Nozzles are clogged, buttriple overlap covering the gap.

Note: not a tack coat, but principle applies.

Page 42: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Critical when changing from one product to another

• Significant safety hazard can occur

• Product quality can be affected

• Best Practice is to empty the tank and clean if necessary.

Cleaning Distributor Tank

42

Page 43: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Check truck setup.• Spray bar height (~12”)

• Appropriate nozzles

• Nozzle orientation (15-30°)

• Check application rate gauge in truck

• Check application temperature

• Collect samples.

• Know the desired application and residual rates.

• Visually inspect application

• Verify application. • Volume

• Mass

• ASTM D2995

Key Items for Inspectors

43

Page 44: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

44

Page 45: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Materials

• Emulsion

• Paving grade asphalt

• Field/Laboratory Bond Testing

• Shear Testing

• Torsion Testing

• Pull-Off Testing (tension)nsion)

• Cyclic

Testing Methods

Page 46: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Shear Testing• Lab test• Quick • Repeatable• Most widely promoted• Uses common lab

equipment• Cleanly ranks materials

• Torsional Testing• Lab or field test• Quick• Poorer repeatability

(manually ran)

• Tension Testing• Lab or field test• Quick• Repeatable• Cleanly ranks materials• Used in Texas and Kansas

• Cyclic Testing• Lab test• More time consuming• Repeatable• Cleanly ranks materials

Comments on Testing Options

Page 47: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• What Type of Bond Testing?

• Shear

• Torsion

• Pull off

• Cyclic

• All have advantages and disadvantages

• Further research and acceptance will likely lead to a generally preferred method.

Common Tack Coat Questions

Page 48: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Review and Summary

Page 49: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Experts commonly disagree

• “Do I still need to tack…”

• Milled Surface

• “Fresh” Pavement

• Late season/cooler days

• Asphalt Institute recommends tacking all surfaces

Common Tack Coat Questions

Page 50: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• “When can I pave on the emulsion?”

• Has emulsion broken?

• Does it need to be set?

• Asphalt Institute recommends paving begin after the emulsion has broken.

• “How can I prevent tack pull-up/tracking?”• Make sure tack coat is broken

• Use emulsions with hard base asphalt (CSS-1h)

• Use a proprietary reduced-tracking emulsion

• Use a spray paver

Common Tack Coat Questions

Page 51: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Spray Pavers

• Spray pavers are an engineered system that consists of a paver with built-in emulsion application systems that applies tack just prior to asphalt laydown.

• Emulsions used in spray pavers are designed to perform without break/set.

• No tack coat tracking or pull-up

Page 52: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Roadtec SP 200 Spray Paver

Courtesy of Roadtec

Page 53: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Vögele: Spray Jet

Courtesy of Road Science

Page 54: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• No tracking of the tack

• Better bonding of overlays • Increased Overlay life

• Reduce Rutting

• Reduce Cracking

• Improved bond = easier compaction

Purported Spray Paver Benefits

Page 55: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• What is the optimal aplication rate?• Surface type

• Surface condition

• Asphalt Institute recommended ranges

Common Tack Coat Questions

Surface Type Residual Application Rate (gsy)

New Asphalt 0.020 – 0.045

Existing Asphalt 0.040 - 0.070

Milled Surface 0.040 – 0.080

Portland Cement Concrete 0.030 – 0.050

Page 56: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• When to Re-Tack?

• Tracking

• Contamination

Re-Tack when in doubt.

• Is Dilution okay?

• Follow state specs

• Verify dilution amount

• Can not be used to

“stretch” tack as residual

value is key.

Limit dilution to supplier.

Common Tack Coat Questions

Page 57: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Layer Bonding is Vital

• Surface Preparation • Clean • Dry

• Millings Improves Field Performance• Shear• Cleaning

Areas of Known Agreement

Page 58: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Application Quality Vital

• Proper Rate

• Consistency

• Distributor Truck

• Setup

• Calibration/Verification

• Maintenance

• Tacking of Longitudinal Joints

• Bonding

• Confinement

• Excessive Tack is Bad

Areas of Known Agreement

Page 59: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

• Tack Coat Rate Depends on Surface Condition

• Fresh

• Weathered

• Raveled

• Milled

• Treat Tack as Separate Pay Item vs. Incidental Item

• Need for Research

• Field Performance

• Field Testing

• Bond strength

• Application amount

Areas of Known Agreement

Page 60: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Successful Tack Coat

The Ultimate Goal:

Uniform tack coat coverage

Page 61: Tack Coat: A “Must Have” in Pavement Placement Presenations 2015/Utah...•Application rate Distributor Truck Setup •Method A—Weighing Pads •Pre-weigh pads •Secure pads

Thank You!

Free webinar: http://www.asphaltinstitute.org/public/asphalt_academy/webinars/tack-coat-best-practices-webinar-recording.dot

Free 4-hour workshop requested through FHWA

divisional offices