table of contents - indiaenvironmentportal common_eia... · coastal tamil nadu power ltd. common...

72
Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 1 Table of Contents INTRODUCTION................................................................................................................................................... 3 1.1 BACKGROUND ......................................................................................................................................................... 3 1.2 SITE SELECTION........................................................................................................................................................ 4 1.3 LAND REQUIREMENTS AND AVAILABILITY ...................................................................................................................... 6 1.4 EIA NOTIFICATION &STUDY ...................................................................................................................................... 7 TERMS OF REFERENCE FOR EIA STUDIES .............................................................................................................. 9 2.1 INTRODUCTION ........................................................................................................................................................ 9 2.2 TERMS OF REFERENCE (TOR) FOR MAIN PLANT ............................................................................................................ 9 2.3 TERMS OF REFERENCE (TOR) FOR CAPTIVE PORT ......................................................................................................... 12 PROJECT DESCRIPTION ...................................................................................................................................... 14 3.1 INTRODUCTION ...................................................................................................................................................... 14 3.2 LAND REQUIREMENT.............................................................................................................................................. 14 3.3 SITE CHARACTERISTICS OF THE PROJECT ..................................................................................................................... 14 Main Plant .......................................................................................................................................................... 14 Captive Port ....................................................................................................................................................... 15 Main Plant Layout ............................................................................................................................................. 15 Captive Port Layout ............................................................................................................................................ 17 3.4 Coal Transportation from Port to Power Plant............................................................................................. 20 METHODOLOGY OF EIA STUDY .......................................................................................................................... 22 4.1 General ......................................................................................................................................................... 22 4.2 Study Area .................................................................................................................................................... 22 4.3 Scoping Matrix ............................................................................................................................................. 22 4.4 Data Collection ............................................................................................................................................. 22 4.5 Impact Prediction ......................................................................................................................................... 22 4.6 Environmental Management Plan (EMP) .................................................................................................... 23 4.7 Risk Analysis and Disaster Management Plan ............................................................................................. 23 4.8 Resettlement and Rehabilitation (R&R) Plan ............................................................................................. 23 4.9 Environmental Monitoring Programme (EMP) ............................................................................................ 23 ENVIRONMENTAL BASELINE STUDY DATA ......................................................................................................... 25 5.1 INTRODUCTION ...................................................................................................................................................... 25 5.2 MAIN PLANT AREA................................................................................................................................................. 25 5.2.1 Project Area District .................................................................................................................................. 25 5.2.2 Topography ............................................................................................................................................... 26 5.2.3 Physiography ............................................................................................................................................. 26 5.2.4 Geology ..................................................................................................................................................... 26 5.2.5 Soils ........................................................................................................................................................... 26 5.2.6 Meteorology .............................................................................................................................................. 27 5.2.7 Ambient Air Quality ................................................................................................................................... 27 5.2.8 Ambient Noise Level .................................................................................................................................. 29 5.2.9 Water Resources ...................................................................................................................................... 30 5.2.10 Water Quality .......................................................................................................................................... 30 5.2.11 Land Use Pattern ..................................................................................................................................... 31 5.2.12 Vegetation............................................................................................................................................... 31 5.2.13 Wildlife .................................................................................................................................................... 31

Upload: nguyenthuy

Post on 10-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 1 

Table of Contents

INTRODUCTION................................................................................................................................................... 3 

1.1 BACKGROUND ......................................................................................................................................................... 3 1.2 SITE SELECTION ........................................................................................................................................................ 4 1.3 LAND REQUIREMENTS AND AVAILABILITY ...................................................................................................................... 6 1.4 EIA NOTIFICATION & STUDY ...................................................................................................................................... 7 

TERMS OF REFERENCE FOR EIA STUDIES .............................................................................................................. 9 

2.1 INTRODUCTION ........................................................................................................................................................ 9 2.2 TERMS OF REFERENCE (TOR) FOR MAIN PLANT  ............................................................................................................ 9 2.3 TERMS OF REFERENCE (TOR) FOR CAPTIVE PORT  ......................................................................................................... 12 

PROJECT DESCRIPTION ...................................................................................................................................... 14 

3.1 INTRODUCTION ...................................................................................................................................................... 14  3.2 LAND REQUIREMENT .............................................................................................................................................. 14 3.3 SITE CHARACTERISTICS OF THE PROJECT ..................................................................................................................... 14 

Main Plant .......................................................................................................................................................... 14 Captive Port  ....................................................................................................................................................... 15 Main Plant Layout  ............................................................................................................................................. 15 Captive Port Layout ............................................................................................................................................ 17 3.4 Coal Transportation from Port to Power Plant ............................................................................................. 20 

METHODOLOGY OF EIA STUDY .......................................................................................................................... 22 

4.1 General ......................................................................................................................................................... 22 4.2 Study Area .................................................................................................................................................... 22 4.3 Scoping Matrix ............................................................................................................................................. 22 4.4 Data Collection ............................................................................................................................................. 22 4.5 Impact Prediction ......................................................................................................................................... 22 4.6 Environmental Management Plan (EMP)  .................................................................................................... 23 4.7 Risk Analysis and Disaster Management Plan  ............................................................................................. 23  4.8 Resettlement and Rehabilitation (R&R) Plan   ............................................................................................. 23 4.9 Environmental Monitoring Programme (EMP) ............................................................................................ 23 

ENVIRONMENTAL BASELINE STUDY DATA ......................................................................................................... 25 

5.1 INTRODUCTION ...................................................................................................................................................... 25 5.2 MAIN PLANT AREA ................................................................................................................................................. 25 

5.2.1 Project Area District .................................................................................................................................. 25 5.2.2 Topography ............................................................................................................................................... 26 5.2.3 Physiography ............................................................................................................................................. 26 5.2.4 Geology ..................................................................................................................................................... 26 5.2.5 Soils ........................................................................................................................................................... 26 5.2.6 Meteorology .............................................................................................................................................. 27 5.2.7 Ambient Air Quality ................................................................................................................................... 27 5.2.8 Ambient Noise Level .................................................................................................................................. 29 5.2.9 Water Resources  ...................................................................................................................................... 30 5.2.10 Water Quality .......................................................................................................................................... 30 5.2.11 Land Use Pattern ..................................................................................................................................... 31 5.2.12 Vegetation ............................................................................................................................................... 31 5.2.13 Wildlife .................................................................................................................................................... 31 

Page 2: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 2 

5.2.14 Avifauna  ................................................................................................................................................. 32 5.2.15 Fisheries ................................................................................................................................................... 32 

5.3 CAPTIVE PORT AREA ............................................................................................................................................... 32 5.3.1 Water quality ............................................................................................................................................ 33 

ASSESSMENT OF IMPACTS ................................................................................................................................. 40 

6.1 ASSESSMENT OF IMPACTS ........................................................................................................................................ 40 6.2 MAIN PLANT ......................................................................................................................................................... 40 

6.2.1 Impact on Land Environment .................................................................................................................... 40 6.2.2 Impact on Water Environment .................................................................................................................. 41 6.2.3 Impact on Noise Level ............................................................................................................................... 42 6.2.4 Impact on Air Environment ....................................................................................................................... 42 6.2.5 Impact Due to Coal Handling .................................................................................................................... 43 6.2.6 Impact on Ecology ..................................................................................................................................... 43 6.2.7 Impact on Socio‐Economic Environment ................................................................................................... 43 Impact on Infrastructure Facilities ..................................................................................................................... 44 Impact Due to Immigrant Population And Labour Camps ................................................................................. 44 Impact on Cultural/ Religious/ Historical Monuments ....................................................................................... 44 Impacts on Salt Pans .......................................................................................................................................... 45 6.2.8 Summary of Impacts ................................................................................................................................. 45 

6.3 CAPTIVE PORT  ...................................................................................................................................................... 48 6.3.1 Scoping Outcome ...................................................................................................................................... 48 6.3.2 Estimation of Impacts – Design ................................................................................................................. 49 6.4 Prediction of Impacts ................................................................................................................................... 50 

ENVIRONMENT MANAGEMENT PLAN ................................................................................................................ 57 

7.1 MAIN PLANT AREA ................................................................................................................................................. 57 7.1.1 EMP for Construction Phase ...................................................................................................................... 57 7.1.2 Environmental Management during Operation Phase ............................................................................. 59 Air Pollution Control ........................................................................................................................................... 60 Compensatory Afforestation .............................................................................................................................. 61 Rain Water Harvesting ....................................................................................................................................... 61 Greenbelt Development ..................................................................................................................................... 62 Socio‐economic Environment ............................................................................................................................. 62 Fire Protection System........................................................................................................................................ 62 Bird Conservation Plan  ...................................................................................................................................... 63 

7.2 CAPTIVE PORT   ...................................................................................................................................................... 63 7.2.1 Mitigation Measures ................................................................................................................................. 63 7.2.2 Tsunami Early Warning System ................................................................................................................. 63 7.2.3 Operational Criteria For Port Craft (Tugboats And Mooring Boats) ......................................................... 64 7.2.4 Fire Fighting System for Coal Conveyor ..................................................................................................... 64 

PUBLIC HEARINGS AND PROCEEDINGS .............................................................................................................. 65 

8.1  MAIN PLANT AND ASH DYKE AREA ........................................................................................................................... 65 8.2 CAPTIVE JETTY AND COAL CONVEYOR OFF PANAIYUR CHINNAKUPPAM ............................................................................. 65 

RISK ASSESSMENT AND DISSASTER MANAGEMENT PLAN .................................................................................. 66 

9.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN ................................................................................................. 66 

RESETTLEMENT AND REHABILITATION PLAN & CORPORATE SOCIAL RESPONSIBILITY ......................................... 67 

10.1 RESETTLEMENT & REHABILITATION PLAN  ................................................................................................................. 67 10.2 CORPORATE SOCIAL RESPONSIBILITY ACTIVITIES ......................................................................................................... 67

Page 3: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 3 

 

Page 4: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 4 

CHAPTER ONE

INTRODUCTION 

1.1  Background 

Electricity  is  one  of  the  key  infrastructure  elements  for  the  economic  growth  of  a country.  The  infrastructure  needs  the  availability  of  assured  and  quality  power  at affordable  price.  In  order  to  augment  the  availability  of  Electricity,  an  initiative  for Environment  friendly  Thermal  capacity  development  of  100,000 MW was  proposed with the aim to provide “Power to All” by 2012. However, this objective is not likely to be  achieved due  to  huge deficits  in  achieving  the  capacity  additions  of  10th  and  11th plans. The 12th plan (2012‐17) also envisages about 75,000 MW of fresh additions along with 11th plan spillovers.   To  achieve  the  objective  of  fast  capacity  addition,  power  planners  in  India  had contemplated  building  of  large Coal  fired  Power  Plants  either  at Coal  Pit‐heads  for using indigenous Coal without stressing much on Rail Transport System or as Coastal Thermal Power Station near the Sea Ports for using  imported Coal. With this aim in for overall  development, Ministry  of  Power,  Govt.  of  India  has  initiated  a  scheme  for development  of  Ultra  Mega  Power  Projects  (UMPPs)  in  India.  As  on  date,  fifteen UMPPs have been envisaged, out of which four UMPPs have been awarded to selected developer.  UMPPs Awarded: 

Sasan Power Limited, Sasan UMPP, Madhya Pradesh  Coastal Gujarat Power Limited, Mundra UMPP, Gujarat  Coastal Andhra Power Ltd., Krishnapatnam UMPP, Andhra Pradesh  Jharkhand Integrated Power Ltd., Tilaiya UMPP, Jharkhand 

   UMPPs in Pipeline: 

Chhattisgarh Surguja Power Ltd., Chhattisgarh UMPP  Orissa Integrated Power Ltd., Sundargarh UMPP, Orissa  Coastal Tamil Nadu Power Ltd., Cheyyur UMPP, Tamil Nadu  Tatiya Andhra Mega Power Ltd., Andhra Pradesh 2nd UMPP  Sakhigopal Integrated Power Co. Ltd., Orissa Additional UMPP 1  Ghogarpalli Integrated Power Co. Ltd., Orissa Additional UMPP 2  Coastal Maharashtra Power Ltd. Maharashtra UMPP 

Page 5: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 5 

Coastal Karnataka Power Ltd., Karnataka UMPP  Tamil Nadu 2nd UMPP  Gujarat 2nd UMPP  Jharkhand 2nd UMPP 

 Each  project would  be  of  4000 MW  capacity  and would  be  based  on  super  critical technology. Thus, they would have the advantage of economies of scale on account of large  capacity  at  single  location,  reduction  in  emissions  on  account  of  super  critical technology  and  competitive  tariff.    The  power  from  such  projects  is  allocated  by Ministry of Power (MoP), Govt. of India to various States of the Country in view of their requirements.  Central  Electricity Authority  (CEA), GoI  is  the  Technical  partner  and Power Finance Corporation Limited (PFCL) has been identified as the nodal agency for the development of UMPPs.    The  objective  is  to  develop  large  capacity  projects  in  India  and  attract  potential investors including private participants for developing such Projects from a stage where these Projects are already having major clearances and Power selling tie‐ups etc.  The UMPPs are developed  in accordance with  ‘Case 2’ scenario of the “Guidelines for Determination of Tariff by Bidding Process  for Procurement of Power by Distribution Licensees”  issued  by MoP.  As  per  the  Guidelines multi‐procurer  projects  have  the option to conduct the bid process through an authorized representative. The authorized representative  may  be  one  of  the  procurers  or  a  special  purpose  vehicle  (SPV) incorporated  for such purpose. PFC, as  the nodal agency,  incorporates a SPV  for each UMPP.   The SPVs tie up necessary inputs and clearances such as provision of site, fuel through captive mining blocks, water and  in principle  environment and  forest  clearances and also works as  the authorized  representative of  the procurers of power  for conducting the bid process to select the developer. On completion of the bidding process the SPVs along with the various clearances, tie ups etc. are transferred to the successful bidder for implementation of the projects at the agreed tariff and within the agreed timeframe.    One of such UMPPs is envisaged in Cheyyur in Kancheepuram District of Tamil Nadu. The project would be based on  imported coal. A captive  jetty for the  import of coal  is also  a  part  of  the  project.  For  development  of Cheyyur UMPP, Coastal  Tamil Nadu Power Limited (CTNPL) has been incorporated as a wholly owned subsidiary of PFCL.  The capacity of Cheyyur UMPP shall be 4000 MW and  the contracted output shall be 

Page 6: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 6 

3500 to 3800 MW at the above Power Plant Switchyard bus. The Units shall use Super‐critical Technology.  1.2  Site SelectionThe key elements for selection of site for a Thermal Power Station (TPS) include:  

The availability of suitable and adequate land with least R & R issues  Fuel availability and its transportation from the source of availability  Water availability within a reasonable distance  Road and Railway access  Acceptability from the Environmental consideration  Availability of infrastructural facilities  Rehabilitation and Resettlement issues (R&R)  Proximity to Grid for Evacuation of Power 

 For development of Ultra Mega Thermal Power Project, a Site Selection Committee of CEA, PFCL and Govt. of Tamil Nadu authorities in October, 2006 visited two potential area namely Cheyyur and Nagapattinam . The objective of the joint visit was to identify potential coal based sites for setting up of new UMPP in the State of Tamil Nadu. Four (4)  alternative  sites,  viz  Nagapattinam,  Cheyyur,  Kilakarai  and  Vembar  site  were considered. Based on these alternatives, Cheyyur was considered the most suitable site due to following reasons: 

Minimum Agricultural land  No habitation in the proposed Site   Religious places  including Mahabalipuram are well away  from Site  (30‐60 km) and no Ecological sensitive locations 

Project  Site  is  located  at  a  distance  more  than  the  minimum  specified  from Railway lines, National Highways and High Tide Level. 

Availability of Sea Water nearby    No ground filling is required  Encouraging response from local Public.   

 The site is located near Cheyyur village in Cheyyur Block of Kancheepuram district in Tamil Nadu Coastal area. The Main Plant is located in a cluster of four Villages namely Cheyyur  B  Block,  Gangadevankuppam,  Chitharkadu  and  Vedal.  The  ash  pond  is located in a cluster of two villages namely, Vilangadu and Kokkaranthangal.   As  it  is  proposed  to  import  coal  through  a  marine  coal  handling  facility,    a  Joint inspection  of  Panaiyur  area was  undertaken  by  officials  from CEA, GoTN’s  various departments namely Revenue Department; Department of Environment; Tamil Nadu 

Page 7: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 7 

Pollution  Control  Board;  Tamil  Nadu Maritime  Board;  Archaeological  Department, Tourism Department  and  PFCC  for  setting  up  of  the Captive  Port.  The  site  for  the Captive Port was selected in the village Panaiyur, District Kancheepuram, Tamil Nadu. Based on  the  joint site  inspection report, GoTN  in October 2009 advised  to  ʹgo‐aheadʹ with the Port site at Panaiyur.   The Main Plant area  is  located at a distance of approximately 5 km  to  the west of  the proposed Captive Port  location. The  total coal  import  is estimated at 12  to 14 Million Metric Tons per annum and the estimated consumption is 40,000 to 45,000 MT per day.   1.3  Land Requirements and Availability 

The  land  initially  for  the project  as per  the Administrative  Sanction  accorded by  the GoTN  in December 2010 was  about  1,627  acres. However,  the  land  requirement was revised based on Guidelines issued by CEA and is reduced to about 1,111 acres.   In addition,  the  land of about 258 acres has been  identified  for  corridor  for Ash Pipe line, Railway Siding, Service/ approach Road and conveyor alignment. The Corridor for cooling Water Pipelines and Discharge Pipelines shall be aligned below the corridor for conveyor  belt  from Captive  Port  to Main  Plant. As  such,  no  additional  corridor  for cooling  water  pipeline  and  discharge  pipeline  is  required.  The  proposed  conveyor corridor  is  free  from  any  major  encumbrances  and  it  does  not  pass  through  any habitation & reserve forest areas.  The  location of  the Main Plant, Ash Dyke and Captive Port area are  indicated  in  the following map.   

Page 8: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 8 

  1.4  EIA Notification & Study 

As per EIA notification issued by Ministry of Environment and Forests in September 14, 2006, the proposed thermal power project comes under category `A’. For such projects, it  is mandatory for the project proponent to get approval for Terms of Reference from Ministry of Environment and Forests, (MOEF), Government of India.   For  Captive  Port,  it  is  required  to  conduct  EIA  studies  for  the  Port  development proposals  as  per  the  requirements  of  the  Environmental  Impact  Assessment  (EIA) Notification (dated 14th September 2006) and the CRZ Notification dated 19th February 1991 and January 6, 2011 of the Ministry of Environmental and Forests (MoEF).   For the Main Plant, MOEF has issued the Terms of Reference (ToR) for the Environment Impact  Assessment  (EIA)  Studies  on  March  19,  2009  and  for  the  Captive  Port  on February 1, 2010.  The  EIA  study  for  the  proposed  thermal  power  project  has  been  conducted  by M/s WAPCOS  Limited,  a  Government  of  India  Undertaking  in  the  Ministry  of  Water 

Page 9: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 9 

Resources  (MOWR)  and  for  the  Captive  Port,  M/s  National  Institute  of  Ocean Technology (NIOT) was appointed for conducting the EIA studies.   As per  the MOEF notification dated December  24,  2010,  for  an  integrated  and  inter‐linked projects having multi sectoral components shall prepare a common EIA  report covering  impact of each of the component in a comprehensive manner after obtaining ToRs from each of the respective sectoral Expert Appraisal Committee (EACs). Further, it  has  also  been  prescribed  that  after  the  EIA  report  has  been  prepared  and  public hearing has been held,  the proposals  for environmental clearance  in  respect of all  the sectoral components of the project shall be submitted simultaneously.  The Public hearing  for  the Main Plant was held on  June 10, 2010 and  for  the Captive Port & Coal conveyor was held on December 28, 2011.  In  accordance with  the  above MOEF  guidelines,  this Common  EIA  report  has  been prepared  for  consideration  of  the  project  by  EAC  (Thermal  Power  and  Coal Mine Projects) as well as by EAC (Coastal Regulation Zone, Infrastructure Development and Miscellaneous projects).  

Page 10: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 10 

CHAPTER TWO

TERMS OF REFERENCE FOR EIA STUDIES 

 2.1  Introduction 

For the Main Plant, MOEF has issued the Terms of Reference (ToR) for the Environment Impact  Assessment  (EIA)  Studies  on  March  19,  2009  and  for  the  Captive  Port  on February 1, 2010. 2.2  Terms of Reference (ToR) for Main Plant  

The  Expert  Appraisal  Committee  (EAC)  of  MoEF  for  environmental  appraisal  of Thermal  Power  and  Coal  mine  projects  considered  the  proposal  for  setting  up  of 4,000MW  UMPP  during  its meeting  held  on  February  10‐11,  2009.  Based  upon  the considerations  of  the  documents  submitted  and  the  presentation  made  by  the proponent,  the Committee prescribed  the  following Terms of Reference  (ToR)  for  the Main Plant and Colony area:  

1. Comparison  of  alternate  sites  considered  and  the  reasons  for  selecting  the proposed site. Conformity of the site with the prescribed guidelines  in terms of distance of 500 m from HFL of  the river, highways, railway  line should also be shown. 

2. All the coordinates of the plant site as well as ash pond with toposheet. 3. Examine  the  adoption  of  super  critical  technology.  Reasons  for  selecting  the 

proposed technology should be given.  4. The study area should cover an area of 10 km radius around the proposed site. 5. Land use of the study area as well as the project area shall be given. 6. Location  of  any National  Park,  Sanctuary,  Elephant/Tiger Reserve  (existing  as 

well as proposed), migratory routes, if any, within 10 km of the project site shall be  specified and marked on  the map duly authenticated by  the Chief Wildlife Warden. 

7. Land  requirement  for  the project  to be optimized.  Item wise break up of  land requirement and  its availability  to be  furnished. The norms prescribed by CEA should be kept in view. It should also include land to be acquired, if any, for coal transportation  system as well as  for  laying of pipeline  including ROW.  It may clearly be  confirmed  that  the  land  including ROW  is  free of all encumbrances. The  issues  relating  to  land acquisition and R&R should be clearly discussed  in the EIA report. 

Page 11: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 11 

8. Identification  of  CRZ  area:  A  CRZ  map  duly  authenticated  by  one  of  the authorised agencies demarcating LTL, HTL, CRZ area, location of the project and associated  facilities w.r.t. CRZ,  coastal  features  such as mangroves,  if any. The route of the pipeline, conveyor system etc. passing through CRZ, if any, should also  be  demarcated.  The  recommendations  of  the  State  Coastal Management Authority for the activities to be taken up in the CRZ should also be provided. 

9. Impact of the activities to be taken up in the CRZ area including jetty etc. should be  integrated  into  the  EIA  report,  however,  action  should  be  taken  to  obtain separate  clearance  from  the  competent  authority  as may be  applicable  to  such activities.  

10. Location of  intake and outfall points  (with coordinates) should be given. These locations should be selected based on modeling studies. Details of modeling and the results obtained there from should be furnished. It may be kept in view that the  intake  and outfall points  are  away  from  the mangroves. Marine  impact of such activities should be clearly brought out in the EIA report.  

11. Details of desalination plant and disposal of sludge. 12. Marine  ecology  and  terrestrial  ecology  and  the  impact  thereon  should  also  be 

covered in the EIA report. 13. Topography  of  the  area  should  be  given  clearly  indicating  whether  the  site 

requires any  filling.  If so, details of  filling, quantity of  fill material required,  its source, transportation etc. should be given.  

14. Impact on drainage of  the area and  the surroundings. A detailed area drainage study should be carried out and report furnished. 

15. Contour map of the area should also be provided. 16. Information  regarding  surface hydrology  and water  regime  and  impact  of  the 

same, if any due to the project.  17. One season site‐specific meteorological data shall be provided. 18. One  complete  season  Air  Quality  (AAQ)  data  (except monsoon)  to  be  given 

along with  the dates of monitoring. The parameters  to be covered shall  include SPM,  RSPM,  S02,  NOx,  Hg  and  Ozone  (ground  level).  The  location  of  the monitoring stations should be so decided so as to take into consideration the pre‐dominant  downwind  direction,  population  zone  and  sensitive  receptors including reserved forests. There should be at least one monitoring station in the upwind  direction.  There  should  be  at  least  one monitoring  station  in  the  pre dominant  downwind  direction  at  a  location  where  maximum  ground  level concentration is likely to occur.  

19. Impact of the project on the AAQ of the area. Details of the model used and the input data used for modeling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation 

Page 12: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 12 

nearby, sensitive receptors, if any. The wind roses should also be shown on this map. 

20. Fuel analysis  to be provided  (sulphur, ash content and heavy metals  including Pb, Cr, As and Hg). Details of auxiliary fuel, if any including its quantity, quality, storage etc. should also be given. 

21. Quantity of fuel required its source and transportation. A confirmed fuel linkage should be provided. 

22. Source  of  water  and  its  availability.  Commitment  regarding  availability  of requisite quantity of water from the competent authority. 

23. Details of rainwater harvesting and how it will be used in the plant. 24. Examine the feasibility of zero discharge. In case of any proposed discharge, its 

quantity,  quality  and  point  of  discharge,  users  downstream  etc.  should  be provided. 

25. Optimization  of  COC  for  water  conservation.  Other  water  conservation measuresʹ  proposed  in  the  project  should  also  be  given.  Quantity  of  water requirement for the project should be optimized. 

26. Details of water balance taking into account reuse and re‐circulation of effluents. 27. Details of greenbelt i.e. land with not less than 1500 trees per ha giving details of 

species, width of plantation, planning schedule etc. 28. Detailed plan of ash utilization/ management.  29. Details of evacuation of ash 30. Details  regarding  ash  pond  impermeability  including  soil  analysis  report  and 

whether it would be lined, if so details of the lining 31. Detailed R&R plan/compensation package in consonance with the National/State 

R&R  Policy  for  the  project  affected  people  including  that  due  to  fuel transportation system/pipeline and  their ROW,  if any, shall be prepared  taking into  account  the  socio  economic  status  of  the  area,  homestead  oustees,  land oustees, landless laboureres.  

32. Details of flora and fauna duly authenticated should be provided. In case of any scheduled fauna, conservation plan should be provided. 

33. Details  regarding  infrastructure  facilities  such  as  sanitation,  fuel,  restroom, medical  facilities,  safety  during  construction  phase  etc.  to  be  provided  to  the labour force during construction as well as to the casual workers including truck drivers during operation phase.  

34. Public hearing points  raised  and  commitment  of  the project proponent  on  the same. An action plan to address the issues raised during public hearing and the necessary allocation of funds for the same should be provided. 

Page 13: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 13 

35. Measures  of  socio  economic  influence  to  the  local  community  proposed  to  be provided by project proponent. As far as possible, quantitative dimension to be given. 

36. Impact of the project on local infrastructure of the area such as road network and whether  any  additional  infrastructure would  need  to  be  constructed  and  the agency responsible for the same with time frame.  

37. Environment Management Plan  (EMP)  to mitigate  the  adverse  impacts due  to the project along with item wise cost of its implementation. 

38. Risk  assessment  including  fire  and  explosion  issues due  to  storage  and use of fuel should be carried out. It should take into account the maximum inventory of storage at site at any point  in  time. The  risk contours should be plotted on  the plant  layout map  clearly  showing which  of  the  proposed  activities would  be affected  in  case  of  an  accident  taking  place.  Based  on  the  same,  proposed safeguard measures should be provided. Measures to guard against fire hazards should also be provided.  

39. Any litigation pending against the project and/or any direction/order passed by any Court of Law against the project, if so, details thereof. 

 2.3  Terms of Reference (ToR) for Captive Port  

The  proposal  of  site  at  Panaiyur  village was  considered  in  the  83rd  EAC meeting  of MoEF  held  on  21st‐23rd  Dec,  2009.  The  details  presented  by  the  proponent  were discussed and  the  following “Terms of Reference  (ToR)” was  finalised  to be  suitably added to those furnished earlier.  

1. Examine  and  submit  the  details  of  the  impact  of  coal  conveyor  belt which  is passing  through  some  habitations,  crossing  the  Buckingham  Canal,  Tourism Corridor, and East Coast Road. 

2. Examine and submit the details of impacts on nearby water bodies and other eco‐sensitive areas in the vicinity and impact due the project 

3. Examine and submit  the  impact of  the project on  the mouth of water bodies at southern side and sea line. 

4. Examine and submit the details on impact to the fishing activities. 5. Submit the status of the approval of power plant project. 6. Examine and submit the details of land use alongside the corridor and also of the 

site. 7. Coconut trees are also falling in the alignment. 8. Examine the no. of trees to be cut, and also submit a re‐plantation plan. 9. Submit a copy of recommendations of TNSCZMA. 

Page 14: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 14 

10. The  air  quality monitoring  should  be  carried  out  as  per  the  new  notification issued on 16th November, 2009. 

11. Examine and submit details of Risk Analysis and Disaster Management Plan. 12. Examine the details of what will be CO2, NOx and SO2 emissions per year with 

respect to the plant life. 13. A comprehensive Environmental  Impact Assessment based on a minimum of 3 

seasons  data  and  environment  impact  assessment  report  should  be  prepared based on actual field measurements, appropriate modeling studies etc. 

14. Examine  and  submit  Comprehensive  EIA,  Risk  Analysis  and  Disaster Management. 

15. Examine and submit the details of R&R.  2.4  Agencies involved in various studies 

As per the requirement of Tamil Nadu Pollution Control Board the following consulting organisations  were  appointed  by  CTNPL  for  conducting  various  studies  for  the Cheyyur UMPP:  

WAPCOS  Limited:  For  Rapid  Environmental  Impact  Assessment  and  other technical studies.  

Institute of Remote Sensing (IRS): For topography study for the project site  National  Institute  of  Ocean  Technology  (NIOT):  For  Comprehensive Environmental  Impact  Assessment  of  proposed  Captive  Marine  Terminal  of Panaiyur Chinnakuppam f or Cheyyur UMPP. 

RITES Limited: For Feasibility Study for Transportation of Coal & POL  Institute for Ocean Management (IOM): For Coastal morphology study  Indian Maritime University: For pre‐feasibility study for port site selection  

  

Page 15: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 15 

CHAPTER THREE

PROJECT DESCRIPTION 

 3.1  Introduction 

The proposed 4000 MW Cheyyur Ultra Mega Power Project site is located near Cheyyur village  in Cheyyur Block of Kancheepuram District  in Tamil Nadu Coastal area. The power plant would be based on imported coal for which a Captive Port is proposed as a part of the Project.   The location of the Main Plant is in a cluster of four Villages namely Cheyyur B Block, Gangadevankuppam, Chitharkadu  and Vedal.  The  location  of  the Ash  Pond  is  in  a cluster of one village namely Vilangadu of Kancheepuram District.  The Captive Port is at Panaiyur, District Kancheepuram.  The nearest  railway station  is Melmaruvathur  (21 km)/ Maduranthakam  (22 km). The railway  stations are well  connected  to Chennai  through broad gauge  railway  system. The nearest airport is at Chennai, located about 96 km from the site. The site needs to be connected with State Highway (East Coast Road)/National Highway (NH‐45).   3.2  Land Requirement 

The  total  land required  for  the Main Plant, Ash Dyke and Captive Port  is about 1,111 acres. In addition, land of about 258 acres has been identified for corridor for Ash Pipe line, Railway Siding, Service/ approach Road and conveyor alignment. The Corridor for cooling Water Pipelines and Discharge Pipelines shall be aligned below the corridor for conveyor  belt  from Captive  Port  to Main  Plant. As  such,  no  additional  corridor  for cooling  water  pipeline  and  discharge  pipeline  is  required.  The  proposed  conveyor corridor  is  free  from  any  major  encumbrances  and  it  does  not  pass  through  any habitation & reserve forest areas.  3.3  Site Characteristics of The Project 

Main Plant The Main Plant site  is about 4.0km on  the Western side of  the East Coast  in Cheyyur Village topography of the plot of land is gently sloping downwards from North West to South‐East direction and  there are no major structures present on  the site. The Project site and adjoining area is essentially a gently sloping land.  There is a level difference of 

Page 16: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 16 

about 2.0m to 15m  in the Main Plant & Colony area and 21m to 32m  in the Ash Pond Area.   The proposed site of 1028.63 acres is bounded by East Coast Road (ECR) & Sea on the East, National Highway NH‐45 & Chennai  ‐ Kanyakumari Railway  line on  the West and plain lands on both North and South. The land for Ash Pond is approx 3.5 km away towards North West of the Power Plant site.  The Site grade level would be kept at 5 m elevation above MSL for the Main Plant. As the Elevation varies from 2.0 m to 15 m,  lot of  leveling work  is required and no Earth shall  be  spare  for  dumping. As  such  no  dumping  sites  are  envisaged  at  this  stage. Similarly, Site grade level would be kept below 25.0 m for the Ash Pond in which case lot of excavation  is  required. Earth  so excavated  shall be used  in construction of Ash Dyke  all  around  the  Ash  Pond. However,  actual  aspects  shall  be  examined  during Engineering Design  and  the Developer  shall  ensure  the needful depending upon  the actual Earth work both in Main Plant and Ash Pond.   Captive Port  The  site  for  the Captive Port  lies  in Panaiyur village. The  total  land area  is about 83 acres  and  lies  in  between  Panaiyur  Chinnakuppam  and  Panaiyur  Periakuppam hamlets. There is a metal road connecting ECR and Panaiyur Periyakuppam.  A kutcha road branches off from the metal road to connect Panaiyur Chinnakuppam.  The water front is about 650m long.  The water front is completely free from any activity.  The land area identified is abutting the water front and is predominantly vacant land with some coconut  plantations  of  recent  origin  and  some  fenced  private  houses  also  of  recent construction.  There  is  no  inhabitation  in  the  water  front  and  back  up  area.  The identified project land area has no sand dunes and is fairly flat. There are no religious or archaeological structures within this area. Two fishing hamlets are located to the north and south of the proposed site and are connected to the road on the landward side by a kutcha road.   Main Plant Layout  The Nominal Capacity of the Power Plant would be 4000 MW. Number of units could vary  depending  upon  the  plant  configuration  chosen  by  the  selected  developer.  However, all calculations are based assuming Unit size of 660 MW. However, Unit sizes of 5x800 & 4x1000 are also possible. Supercritical Steam cycle would be adopted for the Ultra Mega Power Project.  

Page 17: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 17 

 The layout of the Power Plant has been planned considering the space requirements for the equipment, systems, building and structures, Coal handing, Coal storage area and Ash Sea water is proposed for Condenser Cooling in a Recirculation System. Necessary Plant drainage system would be provided at the proposed Power Plant site.  Rain water harvesting  is  proposed  to  be  included  as  a  Project  component  to  conserve  naturally available water source. The layout of main plant is enclosed as Figure‐3.1.  The Coal shall be normally transported to Main Plant stockyard and under emergency conditions;  the  same  shall be  stored  at Captive Port  stockyard  for  transit  storage  for further transportation to the Main Plant at the earliest available opportunity. The Coal received  at  the  Plant  Site would  be  stacked  by  three  Stacker  Reclaimers  for  further conveying  either  to  the Plant Bunkers  or  to  the Plant  Stock‐yard  through  a  series  of Conveyors. Provision  is made to keep 30 days stocks at the Main Plant Stockyard & a maximum of Two (2) Shiploads Capacity stockpile at the Port site.  The source of water for the Plant is Sea‐water drawn from Bay of Bengal which is at a distance  of  about  4  to  5  km  from  the  proposed  Plant.  Sea water  shall  be  used  for Condenser Cooling and also for other miscellaneous requirements such as Desalination Plant  /  RO  System, DM  Plant,  Coal Handling  Plant, Ash Handling  system,  Potable water for Plant / Colony, Air Conditioning system and Plant Service water etc.  The area identified for Ash Disposal is about 220 Acres which can accommodate around Ash  (Both Bottom & even Fly Ash  if  required) over a period of 25 years as per CEA norms for Coastal Thermal Power Stations. As regards Fly Ash, 100% utilization of the same has  to be ensured. The Fly Ash Management plan shall be drawn by  the Power Project Developer so that the Fly Ash in dry form is utilized fully for gainful purposes. The Power Developer would look for prospective buyers for 100% utilization of the Fly Ash and part utilization of Bottom Ash produced. Tree Plant Nursery and trial planting area would be set up near  the Ash Disposal area  for effective growth of vegetation  in and around the Ash Disposal area in order to prevent wind carrying away the exposed Ash.  The  type  of  vegetation  should  be  tolerant  to  the  Bottom Ash  characteristics  to achieve growth on Ash.  

Page 18: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 18 

                                 

Page 19: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 19 

Captive Port Layout It  is proposed to  import coal through a marine coal handling facility.   The Main Plant shall  be  located  shoreward  at  a  distance  of  approximately  5  km  to  the west  of  the proposed  captive  jetty  location. The  total  coal  import  is estimated at 12  to 14 Million Metric Tons per annum and the estimated daily consumption is 40,000 to 45,000 MT.  A coal handling  jetty at a distance of 1000  to 1200 m offshore  in 12‐13m water depths  is proposed. There shall be two berths of approximately 600m length.  An approach trestle shall be constructed  to connect  the  jetty and port  land. The Proposed breakwater and jetty layout is shown in Figure 3.2. The Cross section of proposed Breakwater, jetty and approach  trestle  are  shown  in  Figures  3.3  to  3.5  respectively.  The  berths  will  be provided with  grab  unloaders  of  suitable  capacity  for  unloading  coal  from  the  coal carriers. It is proposed to have four ship unloaders for handling two vessels at a time. There will be two streams of conveyors running parallel. The coal berth will be located within breakwaters so that tranquil conditions exist for year round operations. 

 Fig 3.2: Proposed breakwater and jetty layout 

 

Page 20: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 20 

Page 21: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 21 

Fig 3.3: Cross Section of Proposed Breakwater   

 Fig 3.4: Cross Section of Proposed Jetty

 Fig 3.5: Cross Section of Proposed Approach Trestle 

Page 22: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 22 

 It  is  proposed  to  have  an  emergency  stockyard  at  the  foreshore  to  stock  the  coal unloaded  from  the  ship  in  case  of  breakdown  of  the  downstream  conveyor  system.  This stockyard will not be regularly used and will be empty most of the time.  In case of emergency only  this will be  stocked with  coal which will be  removed as  soon as  the system  is restored.   This will be designed to store two parcels of capesize vessels. The Figure 3.6 shows the proposed Emergency Stackyard Arrangement.  

 Fig 3.6: Proposed Emergency Stackyard Arrangement 

 The stackyard will be surrounded on all the sides with a 50 m wide greenbelt to prevent coal dust  from moving over  to  the adjoining areas. A suitable water sprinkler system will also be provided to arrest generation of coal dust.  A proper drainage system with a settling pond will be provided to take care of rain and sprinkled water  

Page 23: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 23 

3.4  Coal Transportation from Port to Power Plant The coal unloaded at the terminal  is proposed to be transported directly to the power plant stockpile. However, for meeting any exigency, an emergency stockpile in the Port area has been planned with a  storage  capacity of about 300,000 T  equivalents  to  two ship  loads  of  cape  size  vessel.  From  the  transfer  point  in  the  backup  area  of  port terminal, transfer point of the power plant stockpile it is proposed to install two streams of belt conveyors of matching capacity i. e. 4,000 TPH each.  Based on reconnaissance survey of the proposed Port & Power Plant sites as well as the adjoining  areas  in  the vicinity of  the  sites,  a  conveyor  alignment  connecting  the port stockpile and the plant has been proposed. A pipe conveyor system is recommended for transportation of coal from the marine terminal to the proposed UMPP at Cheyyur. The advantages of pipe conveyor include elimination of multiple transfer points as well as of multiple  drive  units. No  enroute  spillage  or  dust  generation.  Significantly  lower power requirements and lower space requirement for installation. Lesser degradation of material and lower structural and foundation cost. 

Page 24: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 24 

CHAPTER FOUR  

METHODOLOGY OF EIA STUDY 

4.1  General Standard methodologies of Environment  Impact Assessment  (EIA) were  followed  for conducting  the CEIA  study  for  the proposed 4000 MW Ultra Mega Power Project. A brief account of the methodologies for the identification, collection and organization of environmental  impact  data  is  mentioned  below  and  the  information  analysed  is presented in detail in the respective CEIA Reports for Main Plant and Captive Port.   4.2  Study Area The area covered as a part of the CEIA study is: 

Land to be acquired for various project appurtenances including Main Plant, Ash disposal area and Captive Port 

Area within 10 km periphery of  the boundary of  the  land  to be acquired both Power Plant and Captive Port. 

 4.3  Scoping Matrix The  scoping  exercise  was  conducted  selecting  various  types  of  impacts  which  can accrue due  to  the proposed  thermal power project. Based on  the project  features,  site conditions, various parameters to be covered as a part of the EIA study were selected. The  scoping  matrix  included  various  aspects  during  Construction  and  Operational Phase  like  land environment, water quality, aquatic ecology,  terrestrial ecology, socio‐economics, air pollution, noise pollution, public health etc. The details of scoping matrix for  activities undertaken  are presented  in  section  3.3  of CEIA  of  the Main Plant  and section 3.8.1 of CEIA for the Captive Port.  4.4  Data Collection  Primary  surveys  for  the  CEIA  started  in  January  2009  to  collect  data  on  land  use pattern,  soil  quality, water  quality,  ambient  air  quality  ambient  noise  level,  geology flora, fauna, fisheries forest types etc. During these surveys, data and information was collected on physio‐chemical, biological and socio‐economic aspects of  the study area. In addition, detailed  surveys and  studies were also  conducted  for understanding  the environmental setting of the area. The study was conducted for the period March 2009 to February 2010 and also from March 2012 to June 2012. (Details are in sections 4.9 to 4.14 of CEIA of Main Plant and Chapters 4 & 5 of Captive Port.) 

Page 25: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 25 

 4.5  Impact Prediction  Impact  of  project  activities  as  per MoEF  criteria  during  construction  and  operation phase  has  been  predicted  using mathematical models  and  overlay  technique  (super‐imposition of activity on environmental parameter). For intangible impacts, qualitative assessment has been done.   The details are given  in section 3.5 of CEIA of Main Plant and section 4.0 of CEIA report Captive Port.  4.6  Environmental Management Plan (EMP)   Based on the environmental baseline conditions and project inputs, the adverse impacts were  identified. A  set  of measures  have  been  suggested  as  a  part  of  Environmental Management Plan (EMP) for amelioration of adverse  impacts during construction and operation phase.   4.7  Risk Analysis and Disaster Management Plan   A detailed risk analysis study comprising of the following has been conducted: 

Identification of potential accidents.  Consequence analysis for identified failures.   Assessment of what the calculated risk levels portray.  

 The above aspects have been studied using Standard Models and based on the findings of the modeling exercise. A Disaster Management Plan too has been formulated.   4.8  Resettlement and Rehabilitation (R&R) Plan    The demographic and socio‐economic characteristics of  the project area as well as  the study area were studied  through primary as well secondary sources. As a part of  the CEIA study, a socio‐economic survey of project affected  families was conducted. As a part  of  the  survey,  information  on  family  profile,  occupational  profile,  income,  land holding,  crop  grown,  assets  owned,  etc. was  collected.  Based  on  the  findings  of  the survey and the norms outlined in R&R Scheme for Project Affected Families (PAFs) of Cheyyur UMPP,  a  (R&R) Plan has  been  formulated  based  on  the norms  of National Resettlement  and Rehabilitation  Policy‐2007. A  detailed CSR  has  also  been  prepared separately for the benefit of Study Area villages.   

Page 26: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 26 

4.9  Environmental Monitoring Programme (EMP) It  is necessary  to continue monitoring of certain parameters  to verify  the adequacy of various measures outlined  in  the EMP and  to assess  the  implementation of mitigative measures. An  environmental monitoring programme  for  critical parameters has been suggested for implementation during project operation phase.    

Page 27: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 27 

CHAPTER FIVE  

ENVIRONMENTAL BASELINE STUDY DATA 

5.1  Introduction 

Baseline  data  defines  the  present  quality  of  the  environment  at  the  site without  the project. The baseline study requirements are based on screening of possible impacts of the  project  and  the  existing  activities  in  the  proposed  project  vicinity.  The  brief description  of  the data  collection  and  baseline  status  of  the  study  area  is  as  follows: (Details are in Chapter 4 of CEIA of Main Plant and Chapter 5.0 of Captive Port).  5.2  Main Plant Area 

Relevant  environmental  impacts  out  of  the  entire  gamut  of  issues  outlined  in  the Scoping Matrix are identified. For these impacts or aspects, environmental baseline data has been  collected  from  secondary  as well  as primary data  sources. The  area  for  the CEIA  study has been  taken  as  the  area within  10 km  radius of  the proposed project plant and ash pond site. Baseline status has been ascertained for the following aspects:  

Topography   Physiography  Geology  Soils  Meteorology  Ambient air quality  Ambient noise level  Water Resources  Water Quality  Landuse pattern  Vegetation  Wildlife  Fisheries 

 5.2.1  Project Area District The proposed project  is  located  in Cheyyur  taluk of Kancheepuram a  coastal district, lying adjacent to the city of Chennai. The district has an area of about 4,447 sq.km. and has  1252 villages. The district  lies within  coordinates  from  12º,  10’  and  13º  15’ north latitude and 79º 15’ and 80º. 2’ east longitude. It is bounded on the North by Thiruvallur district, on  the  east by Chennai  city  and Bay of Bengal, on  the  south by Villupuram district and on the west by Vellore district. Near the coast, the district is mostly flat but 

Page 28: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 28 

in  the  hinterland  it  is  undulating  and  even  hilly.  The  south  eastern  taluks  of Chengalpattu,  Kancheepuram  and  Maduranthakam  have  undulating  plains interspersed with hillocks.  5.2.2  Topography The project  area district  comprises mainly of peneplain with  residual hills  extending parallel to  the coast (N.20‐300E) ranging  in elevation between 16 and 230 metres. This forms  the  zonal  of  pediments  and  buried  pediments  with  maximum  number  of surface/storage  tanks. The  coastal  track  is marked by  three beach  terraces  ranging  in elevation between 4 and 12 metres with broad inter terrace depressions.  5.2.3  Physiography The project area lies in the south eastern part of the district comprising Maduranthakam and Cheyyur taluks. These talukas have undulating plains traversed by several ridges of low hills stretching parallel with the coast for about 32 km, at a distance of 12 or 14 km  inland.  They  are  ridged  or  conical  or  ellipsoidal  hills  rarely  exceeding  200 m  in height.   5.2.4  Geology The Archaeans represented by charudeite are exposed in the study area. The Archaean is represented by Chnockites, migmatites, granites, gneisses, dolerites. The Archaean is overlain unconformably  by  the Talchir  formation, which  are  overlain  by Continental upper Gondwana sediments. Along the coastal track, soil and alluvium, are observed. The Upper Gondwana sediments and marine sediments are observed  in the project as well as the study area.   5.2.5  Soils The major soil  types  found  in district Kancheepuram  in order of predominance are as follows: Brown soil         53.70 % Red loam         14.31 % Mixed soils         13.27 % Black soil         13.09 % Sandy coastal alluvium      5.63 %  In  the  project  area  and  the  study  area  sandy  coastal  alluvium  type  soil  is  mainly observed. The soil pH ranged from 6.78 to 7.72  in pre‐monsoon season, 6.70 to 7.65  in monsoon  season and 6.95  to 7.7  in post‐monsoon  season. The Electrical Conductivity 

Page 29: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 29 

(EC) ranged from 32.4 to 184.4 μs/cm. The CEC ranged from 12.30 to 23.36 meq/100 gm. The organic matter was observed in the range of 0.18 to 1.51% in pre‐monsoon season, 0.16  to  1.5%  in monsoon  season  and  0.16  to  1.50%  in post‐monsoon  season. The  soil texture was mainly  sandy  loam. At  some  stations,  soil  texture was  sandy.  The  bulk density ranged from 1.17 to 1.29 gm/cc.          5.2.6  Meteorology 

Climate The  project  area  has  a  moderate  climate  with  high  humidity.  Extreme  climatic conditions are not prevalent in the project area. Both the monsoons, i.e. south‐west and north‐east  monsoons  influence  the  rainfall  pattern  in  the  project  area.  In  summer months, heat  is  considerably mitigated  in  the  by  the  sea  breeze.   The project  area  is characterized by an oppressive summer and good seasonal rainfall.  

Temperature  In project area district, large‐scale variations in temperature in various seasons are not observed.  The months  between April  and  June  are  generally  hot with  temperatures going up to a maximum of 40º C. Generally, May is the hottest month of the year with mean daily maximum temperature of 37.6 ºC. The month of December and January are the coolest months of the year with a mean daily minimum temperature of 20 ºC.  

Winds In the project area, the predominant wind direction is mostly from W and SW direction during the rainy season from June to September at 8.30 hrs and 17.30 hrs. In the post‐monsoon months and up to the month of December, the pre‐dominant wind direction is from SW and NW at 8.30 hrs and from SE and NE at 17.30 hrs. During the months from January to March, winds from NW and NE direction predominate at 8.30hrs and from N and W at 17.30 hrs. During monsoon months, predominant direction  is  from S and SW.

Rainfall The average annual rainfall  in the district  is around 1,055 mm. Majority of the rainfall (about  two‐third)  is  received under  the  influence  of north‐east monsoons, months  of October, November and December. On an average, the project area has about 53 rainy days per year.   

Page 30: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 30 

Humidity Humidity is generally high throughout the year in the project area. During south‐west monsoon months i.e. June to September, humidity ranges from 66% to 78% and during the north‐east monsoon month i.e. October to December, humidity ranges from 80% to 84%. The average humidity observed over the year is about 70%.   5.2.7  Ambient Air Quality As  a  part  of  the  study,  six  (6)  locations  were  covered  for  Ambient  Air  Quality Monitoring  viz.  Cheyyur  Model  School,  Vedal,  Gangadevankuppan,  Chitharkadu, Panaiyur and Kadukallur. The baseline data of ambient air environment was generated for the following parameters: 

Suspended Particulate Matter (SPM)  Respirable Particulate Matter (RPM)  Sulphur dioxide (SO2)  Oxides of Nitrogen (NOx)  Ozone (O3)  Mercury (Hg)  

The average SPM level ranged from 115.6 to 121.2 μg/m3, 40.4 to 46.6 μg/m3 and 39.1 to 44.3  μg/m3  in  pre‐monsoon,  post‐monsoon  and  winter  seasons  respectively.  The maximum SPM  level of 139 μg/m3 was observed at station  located at Cheyyur  in pre‐monsoon season.  The average RPM levels ranged from 41.56 to 51.54 μg/m3 in pre‐monsoon season. The average RPM level in post‐monsoon and north‐east monsoon seasons ranged from 38.9 to 41.8 μg/m3 and 38.7  to 37.4 μg/m3 respectively. The highest RPM value of 59 μg/m3 was  recorded  in  pre‐monsoon  season  at  sampling  stations  located  at  Panaiyur  and Kadukallur.  The values of RPM monitored during the field survey were well within the permissible limit of 100 µg/m3 specified for industrial, residential, rural and other areas.  The highest SO2 value observed was 9.8 µg/m3 in post‐monsoon. The SO2 level observed at various  sampling  stations was much  lower  than  the permissible  limit  of  80 µg/m3 specified for industrial, residential, rural and other areas.  The highest NOx values of   13.6 µg/m3 were observed at stations  located   at Cheyyur.  The  NOx  level  observed  at  various  sampling  stations  was  much  lower  than  the permissible limit of 80 µg/m3 specified for industrial, residential, rural and other areas.   

Page 31: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 31 

The ozone  level was much  lower  than  the permissible  limit of 100 µg/m3 specified  for industrial,  residential,  rural  and  other  areas.  The  mercury  level  was  below  the detectable limits in ambient air at various sampling stations monitored.  The ambient air quality was monitored for a period twelve weeks from March to June 2012 as well. The  frequency of  sampling at each  station was  twice a week  for  twelve consecutive weeks. The baseline data of ambient air environment was generated for the following parameters: 

Particulate Matter less than 10 microns (PM10)  Particulate Matter less than  2.5microns (PM2.5)  Sulphur dioxide (SO2)  Nitrogen oxide (NO2) 

 The average PM10 level at various monitoring stations ranged from 43.2 to 45.2 μg/m3. The  highest  PM10  value  of  53  μg/m3 was  recorded  at  sampling  stations  located  at Gangadevankuppam  and  Panaiyur.  The  values  of  PM10 monitored  during  the  field survey were well within  the  permissible  limit  of  100  µg/m3  specified  for  industrial, residential, rural and other areas.  The average PM2.5 levels as observed at various stations in the study area ranged from 19.2  to  20.3  μg/m3.  The  highest  PM2.5  value  of  26  μg/m3 was  recorded  at  sampling stations  located  at Panaiyur. The values  of PM2.5 monitored during  the  field  survey were well within  the permissible  limit of 80 µg/m3 specified  for  residential,  rural and other areas.   The average SO2  levels as observed at various stations  in  the study area  ranged  from 8.65 to 9.0 μg/m3. The highest SO2 value of 9.8 μg/m3 was recorded at sampling station located at Chittarikkadu. The SO2 level observed at various sampling stations was much lower  than  the permissible  limit of 80 µg/m3 specified  for  industrial,  residential,  rural and other areas.  The average NO2  levels as observed at various stations  in  the study area ranged  from 12.1  to12.4  μg/m3.  The  highest NO2  value  of  14.2  μg/m3 was  recorded  at  sampling station  located at Chittarikkadu. The NO2  level observed at various sampling stations was well below  the permissible  limit of  80 µg/m3  specified  for  industrial,  residential, rural and other areas.  Ambient air quality results and observations are detailed in Chapter 4 the CEIA report of M/s WAPCOS.

Page 32: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 32 

5.2.8  Ambient Noise Level The noise levels were monitored continuously for a period of 24 hours at each location and  hourly  equivalent  noise  level  was  measured.  Sound  Pressure  Level  (SPL) measurement in the ambient environment was made using sound pressure level meter.  The noise level at various sampling stations ranged from 32 to 48 dB(A). The day time equivalent  noise  levels  in  pre‐monsoon, monsoon  and  post‐monsoon  seasons  ranges from 39.9  to 43.6 dB(A), 40.4  to 40.5 dB(A) and 40.1 dB(A)  to 43.2 dB(A)  respectively. The day time equivalent noise levels were well below the permissible limits of 55 dB(A). The  night  time  equivalent  noise  levels  in  pre‐monsoon, monsoon  and post‐monsoon seasons ranges from 33.3 to 35.5 dB(A), 34.1 to 37.7 dB(A) and 33.3 dB(A) to 35.2 dB(A) respectively. The night  time  equivalent noise  levels were well below  the permissible limits of 45 dB(A).  The hourly equivalent noise  level at various  sampling  locations  in  the  study area  for three seasons is given in Table‐4.15 to 4.18 of the main CEIA report of M/s WAPCOS.  5.2.9  Water Resources  In the project area district, the only river that flows is the river Palar, originating from Nandhi Durg in Karnataka. In Tamil Nadu it runs for about 295 km. The river enters the project area district about a  few kilometers  to  the west of Kancheepuram. The annual average  rainfall  of  Palar  river  basin  is  of  the  order  of  1036 mm. The  annual  surface water and ground water potential  is 1,758 Mm3 and 3013 Mm3 respectively. No major dams and reservoirs have been constructed on river Palar. Palar is essentially a seasonal river  and  flow  is  observed  only  for  a  few months during  north‐east  and  south‐west monsoon period. The Kancheepuram district has many tanks that serve as storage areas for rain water. No system tanks fed by reservoirs or anicuts exist.   5.2.10 Water Quality As  a  part  of  the  CEIA  study,  surface  and  ground  water  quality  monitoring  was conducted at various locations in the study area.   The pH  in groundwater  samples  ranged  from 6.5  to 7.12  in pre‐monsoon  season and monsoon and post‐monsoon season ranged  from 6.6  to 7.0 and 6.3  to 7.0 respectively. The pH level indicates neutral nature of the water, and are within the permissible limit specified for meeting drinking water requirements.  The Electrical Conductivity (EC) ranged from 90 to 750 μs/cm, 85 to 720 μs/cm and 88 to 728 μs/cm in pre‐monsoon, monsoon and post‐monsoon seasons respectively.   

Page 33: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 33 

The TDS  level  ranged  from  64  to  548 mg/l  in pre‐monsoon  season. The TDS  level  in monsoon  and post‐monsoon  seasons  ranged  from  62  to  526 mg/l  and  64  to  531 mg/l respectively.  The  TDS  level  in  various  ground water  samples  in  some  of  the water samples  was  below  the  permissible  limit  of  500  mg/l  specified  for  drinking  water purposes. However, TDS  level was much  below  the  cause  for  rejection  limit  of  1500 mg/l.  The  BOD  values  are  well  within  the  permissible  limits,  which  indicates  the absence of organic pollution loading. This is mainly due to absence of industries in the area. The low COD values also indicate the absence of chemical pollution loading in the area.   The concentration of various heavy metals e.g. Copper, Cadmium, Zinc, Chromium and Lead was observed to be below the detectable limits. The concentration level of various heavy metals and toxic compounds indicates the absence of chemical pollution sources in the area. Fluorosis is not reported in the study area villages. This was also confirmed by  the  Government  Hospital  at  Cheyyur.  The  details  of  analysis  results  for  three seasons covered as a part of the CEIA study are given in Tables‐4.20 to 4.22 respectively of the main CEIA report of M/s WAPCOS.  5.2.11  Land Use Pattern The land use pattern of the study area, i.e. area within 10 km radius was studied using satellite data. The  raw digital  satellite data has been procured  from National Remote Sensing Agency (NRSA), Hyderabad. The data was processed with the use of GIS and ERDAS  IMAGINE.  Ground  truth  studies  were  conducted  at  site  for  the  physical verification of signals of satellite imagery.   It  is observed  that  as per  satellite data,  the major portion  in  the  study  area  is under agriculture  land  as  it  accounts  for  about  48.58%  of  the  total  study  area.  The  next dominant  landuse category  is water body of 19.30%, area under vegetation of 13.48%. Salt pans account  for about 8.19% of  the study area. Area under barren  land accounts for about 10.27%.  5.2.12  Vegetation As per Champion and Seth Classification, the following forest types are observed in the Study Area are listed as below: 

• Tropical dry evergreen (Group 7G)     : Climatic Climax forests • Tropical dry evergreen scrub (Group7‐ds1)  : Degraded forests • Southern Tropical Thorn forests       : (Group 6 AC1) 

 

Page 34: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 34 

The  land to be acquired for the proposed project have a few area under reserve forest land.  This  reserve  forest  land  comprises mainly  of  Eucalyptus  plantation  for which Hon’ble Supreme Court order had been obtained to remove naturally grown trees. The details  of  above  referred  forest  categories  are  given  in  section  4.16  of  the WAPCOS CEIA Report.  5.2.13 Wildlife In the project area, dense forests are generally absent. The major landuse in study area is agriculture land interspersed with settlements villages. The faunal species reported in the study area  include.  Jackal, hare, common mongoose amongst mammals. Amongst birds,  species  reported  are  Shrew, Pangolin, Kite, Partridge, Koel,  etc.  are  commonly observed. Amongst  reptiles,  commonly  reported  species  are Rat  snake, Cobra, Green Whip snake, etc. The list of faunal species as Authenticated by DFO, Kancheepuram is enclosed at Annexure‐IX in CEIA report.  5.2.14  Avifauna  The  avi‐fauna  study was  conducted  as  a  four month period  from  June  to September 2009.  During  the  survey period,  112  species  of  birds were  observed.  In  all  these  observed birds, includes 33 species of water dependent birds and 79 Species of land birds. Most of  the Aquatic  birds were  observed  in  the  Reservoir  in  Cheyyur  called  Periya  yari, Yekyari  and  Odapari.  In  the  Cheyyur  area  and  its  immediate  surroundings  24 migratory  Species  that  include  8  aquatic  and  16  semi  aquatic  /  terrestrial  birds were observed. As per the investigations, aquatic birds used the lakes and saltpans for only feeding.   The  fever  number  of  aquatic migrants  in  the  study  area  is due  to  the  non availability of habitats. Communal roosting and colonial nesting places were not found within  the  study  area. The  list  of bird  species  reported  in  the  study  area  is given  in Table‐4.16 of CEIA  report of main plant. The  list of bird  species as Authenticated by DFO,  Kancheepuram  is  enclosed  as  Annexure‐IX  of  the  main  CEIA  report  of M/s WAPCOS.  5.2.15  Fisheries The project area district has a coastline of 87.2 km. The inland fresh water area spreads over  about  75,006  ha  and  estuaries  and  brackish  water  area  are  14,841  ha.  In Kancheepuram  district,  there  are  44  fishing  villages  and  39  Fish  landing  centres  of which only 2 are major fish landing centers. In project area, there are no fishing villages. In study area following fishing villages are observed: Kuppam    :  No. of boats ‐  52 and 500 fishermen  

Page 35: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 35 

Chinakuppam  :  No. of boats ‐ 30 and 150 fishermen  The major edible marine fishes reported in the area are given in the Table ‐ 4.27 of the main CEIA report of M/s WAPCOS.  5.3  Captive Port Area 

NIOT collected primary data, by undertaking field visits and surveys to collect samples for three seasons and conduct physio‐chemical and biological analyses. Current metres were deployed at three locations. Water quality was analysed at 10 locations along with sediment quality and biological characteristics.  Standard  procedures  were  used  for  analysis  and  quality  control.  Sampling  was conducted  in  season  representing  premonsoon  during  the  month  of  June  (2010), October  2010  (Monsoon  season)  and  February  2011  (Post  monsoon).  The  monsoon season  is critical because of the possible discharges  into the coastal waters comprising runoff from the upland through various creeks / water bodies  5.3.1  Water quality The southern boundary of  the study area was  fixed at a distance of 13.0 km north of Marakkanam  coast  for  near  shore  station  and  14  Kms  for  offshore  station  and  the Northern boundary was fixed at 33 km south of Mamallapuram coast. The marine water  quality parameters measured were pH,  temperature,  salinity, DO, BOD, TSS, Nutrients, Chlorophyll a, faecal coliforms etc. Ten stations were selected for water quality  sampling based on possible discharge  locations, dredge dump  location, hydrodynamic  characteristics  in  the  study  area  etc.  Locations  of  the  water  quality sampling  sites  and  summary of water quality parameters  are provided  in Table  5.22 and Table 5.23 of CEIA Report.  

Temperature Samples did not show any variation in temperature with tide and distance from shore. It varied between 27.6  and 29.9oC with the average of 29.5oC during  the  three seasons of measurement. The low value of 27.6oC was recorded during post monsoon season. In general  surface  temperatures  showed  minor  variations  with  time  of  the  day  and seasonal changes. 

Salinity Salinity  value  ranges  between  29.2  and  36.0  ppt.  during  the  3‐seasons  and  showed negligible variations with tide off the Panaiyur coast. The ambient salinity values are in conformance with normal marine waters without any anthropogenic inputs.

Page 36: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 36 

pH The variation of observed pH  in  the samples  ranged between 8.15 and 8.22 along  the study area during the three seasons. The pH is within the ranges specified.

Total Suspended Solids (TSS) The variation of observed suspended solids  is 4.73 to 36.94 mg/l during pre‐monsoon; 8.32  to 18.3 mg/l during monsoon season and 8.00  to 20.5 mg/l during post‐monsoon. Maximum value of 36.94 mg/l was recorded at a location near shore station during pre‐monsoon. The range of values indicates negligible anthropogenic/ organic inputs. It also indicates  that  the ambient water quality has negligible  turbidity during  the period of measurement during monsoon

Dissolved Oxygen (DO) The observed dissolved oxygen  ranged between 5.01  to 6.97 mg/l. DO  concentrations did  not  show  any  significant  fluctuation  and  an  average  value  of  5.94  mg/l  was recorded during the pre‐monsoon season. The monsoon season DO ranged from 5.98 to 6.93 mg/l with maximum concentration recorded near shore station PFCWQ3. During post‐monsoon,  it varied between 5.86 and 6.63mg/l.   The DO  is also within the ranges specified.

Biological Oxygen Demand Observation during  the premonsoon  survey  indicated BOD  ranges between  1.10  and 2.10 mg/L. During monsoon season, BOD ranged between 1.20 and 2.10 mg/l. Among the post‐monsoon samples, BOD varied between 1.50 and 2.40 mg/l. BOD values in the study area complies with the prescribed limits.

Nutrients In  general,  nutrient  concentrations  in  the  seawater  are  very  low, minor  increases  or decreases can alter primary productivity. The concentration ranges of nutrients are as follows:

Ammonia Nitrogen The variations  in Ammonia values were negligible with  a  range of  0.43  to  0.58  μg/L recorded during pre‐monsoon survey. During monsoon season,  it varied between 0.40 and 0.55μg/L with maximum value recorded at near shore station PFCWQ5. The post‐monsoon  values  ranged  between  0.38  and  0.53μg/L.  Values  indicate  negligible anthropogenic  inputs/  pollution  from  other  sources.  The  values  measured  are  not significant from an environmental impact perspective.

 

Page 37: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 37 

Nitrate Nitrogen  In  general,  Nitrate  values  varied  between  0.43  and  2.63  μg/L  during  pre‐monsoon season.  During  monsoon,  it  varied  between  0.90  and  2.17μg/L.  The  post‐monsoon survey recorded the maximum of 2.18μg/L and minimum of 0.90 μg/L. However these values are not significant from an environmental perspective.

Nitrite Nitrogen The transitional Nitrogen product Nitrite varied between 0.02 (PFCWQ‐3) and 0.13μg/L during  the pre‐monsoon  season. During monsoon  season,  it varied between 0.03 and 0.05μg/L. The post‐monsoon season recorded variation of 0.02 to 0.05μg/L. 

Inorganic Reactive Phosphorous (IRP)  In general, the IRP concentrations variations are minimal and amongst the ten stations, it  varied  between  0.09  and  0.55  μg/L  during  pre‐monsoon  and  0.13  and  0.43  μg/L during monsoon. In post‐monsoon samples, it varied between 0.13 and 0.43 μg/L.

Petroleum hydro carbon (PHC) Petroleum  hydrocarbon  residue  in water  varied  between  0.56  and  1.29  μg/L  during premonsoon  season  survey.  It  varied  between  0.52  and  0.92  μg/L  during monsoon survey. During postmonsoon season,  it varied between 0.47 and 0.72 μg/L. In general, near  shore  stations  recorded maximum  values  indicating  negligible  discharges  from boats operating in the area.  

Oil & Grease Oil &  grease  residue  in  the  coastal waters  sampled  off  Panaiyur  showed  negligible values (<0.5mg/l) which are below detectable limits.

Chlorophyll‐a  In the marine environment, Phytoplankton are the primary producers. In the study area coastal waters the chlorophyll concentration variations during the pre‐monsoon survey ranged from 0.57 to 2.06 mg/m3. Coastal waters off Kalpakkam recorded Chlorophyll‐a values  of  20.0 mg/m3  during  blooming  of  phytoplankton  Trichodesmium  sp.  about 27kms north of Cheyyur  coast as  cited  in other  studies.   However,  the present water quality locations did not record such values indicating negligible anthropogenic inputs.  During monsoon season chlorophyll‐a varied between 0.34 and 1.09 mg/m3. The post‐monsoon season recorded minimum of 0.56 mg/m3 and maximum of 1.76 mg/m3. The increase in maximum concentration of chlorophyll a of monsoon during post‐monsoon may be attributed to the increase in sunlight penetration.

Page 38: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 38 

Microbiology in water In general,  levels of  fecal coliforms provide a warning of possible contamination  from pathogens.  When  levels  are  high,  there  may  be  an  elevated  risk  of  waterborne gastroenteritis. The water analysis for microbiology showed variations between 130 and 180 CFU/100ml  for  fecal  coliforms  and  20  to  70 CFU/100ml  for  Streptococcus  fecalis during premonsoon season. During monsoon  it varied between 135 to 170 CFU/100ml for Fecal coliform and 20 to 60 CFU/100ml for Streptococcus fecalis. The post‐monsoon season recorded the maximum of 180 CFU/100ml and minimum of 130 CFU/100ml fecal coliform.  The  Streptococcus  fecalis  varied  between  30  to  75  CFU/100ml  during  this season. All the Fecal coliform counts were within the ranges specified.

Heavy metals in water During  the  sampling off Panaiyur  coast  it was observed  that  in general, heavy metal concentrations  in  the water were  found  to  be  low.    The monsoon  season  recorded higher  zinc  concentrations  than  other metals  concentrations.  Post‐monsoon  samples recorded maximum value (2.65μg/L) of zinc when compared to all the other metals. It also  reflects  the  background  concentration  of  metal  rather  than  human  impact.  In general, the sediment content also recorded maximum concentration of zinc, compared to all the metals estimated.  In general, heavy metal concentrations in the sediments recorded low values. Maximum concentration of Cu  (2.98μg/g) was observed which may be  inherent  to  the system  in the absence of any discharges. In general, the maximum concentration of Zn (17mg/g) was observed station during pre‐monsoon and during monsoon peak value of Zn (0.22 mg/g) was recorded. The post‐monsoon survey recorded maximum value (0.21 mg/g) of zinc.

Biological sampling Phytoplankton,  zooplankton  and  macro  benthos  were  measured  for  analysing  the biological characteristics. A  total number of 10 stations were selected  for sampling  for biological parameters based on location of proposed dredge dump, breakwater location and coolant water discharge location etc. 

Phytoplanktons Analysis of phytoplankton samples are summarized as follows: 

Pre‐monsoon  season  samples  indicated  presence  of  35  species  phytoplankton and  the  cell  counts  ranging  from  16,563 Nos./L  to  24,471 Nos./L.  The  diatom species Biddulphia sinensis showed significant presence  in  the  total population of phytoplankton.  

Page 39: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 39 

During Monsoon season phytoplankton was  represented by 25 species and  the density varied between 10,053 and 15,977 Nos/L. The diatom species Biddulphia sinensis and Asterionella japonica were found to be major contributer to the total population of phytoplankton during monsoon. 

During  post‐monsoon  season,  population  density  of  phytoplankton  varied between 16,179 Nos./L and 20,672 Nos./L and dominated by Biddulphia sinensi as well  as Leptocylindrus danicus. These  species  belong  to  rapid proliferating type in general oceanic conditions.

Zooplanktons Analysis of samples for zooplankton indicates the following: 

Density of the population varied from 302 to 1693 Nos./m3 during pre‐monsoon period  A  total  number  of  18  species  were  recorded  in  the  coastal  waters. Calanoid, Appendicularians, Zoea larvae and fish eggs were the dominant forms of zooplankton recorded during pre‐monsoon  

Calanoids,  Cyclopoids,  fish  eggs  were  the  dominant  forms  recorded  during survey. 

The post‐monsoon  recorded  a  total  of  17  species  and dominated  by Calanoid, Cyclopoids, Evadne sp. were the dominant form. The population density varied from 590 to 1464 Nos./ m3 during post‐monsoon season.

Benthos The sub  tidal benthic organisms  recorded moderate  fluctuation of standing stock and diversity. 

During  pre‐monsoon  survey  benthic  population  varied  between  325‐6125 Nos./m2 .  

During monsoon season the variation was from 328 to 717 Nos./m2.   Post‐monsoon season recorded population density between 455‐ 6350 Nos./m2 

5.3.2  Flora and fauna The  coastal  stretch  along  the  project  site  is  characterized  by  sandy  beaches  with sporadic distribution of spiny vegetations like Spinifex littoreus, and Ipomoea sp. Some Casuarina plantations (Casuarina equisetifolia) were also sighted. Mammals like jackals (Canis aureus) and domestic dogs (Canis familiaris) are found in this area.  While  the port area  is not a notified  turtle nesting area by  the wildlife conservator of Tamil Nadu, it is reported that sandy stretches between Pondicherry to Mamallapuram coast have  recorded sporadic  turtle movement during  the nestling season  (January  to March)  every  year.  NIOT  survey  team  visited  the  port  area  during  the months  of 

Page 40: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 40 

February‐March  to  assess  the port  area.   No  eggs  or  turtles were  located during  the survey period. 

5.3.3  Fisheries Potential Fisheries  data  of  the  Kancheepuram  district  was  collected  from  the  Directorate  of Fisheries,  Tamil  Nadu  Fisheries  Deptt.  The  catch  composition  indicated  dwindling percentage  of  crabs,  cephalopods  and  prawns  between  2007‐2008  along  the Kancheepuram district  coast  and not particularly  in  this  area  (Detail  in Appendix A Table 5 & 6 & Appendix B Figs. 1 to 5 of NIOT CEIA report). 

5.3.4  Ambient Air Quality The ambient air quality was monitored for three seasons.  

The  average  PM2.5  levels  as  observed  at  various  stations  in  the  study  area ranged  from  15.4  to 27μg/m3. The values of PM2.5 monitored during  the  field survey were well below the permissible limit of 80 µg/m3 specified for industrial, residential, rural and other areas. 

The average PM10 levels as observed at various stations in the study area ranged from  32.0  to  55μg/m3  during  the  survey  conducted  for  various  seasons.  The values  of  PM10  monitored  during  the  field  survey  were  well  below  the permissible limit of 80 µg/m3 specified for industrial, residential, rural and other areas. 

The average SO2 levels as observed at various stations in the study area ranged from 5.1 to 11μg/m3. The SO2 levels monitored during the field survey were well below the permissible limit of 80 µg/m3 specified for industrial, residential, rural and  other  areas.  The NO2  level monitored  at  various  stations was  below  the detectable limit.

5.3.5  Noise Quality The day time and night time equivalent noise level at various sampling stations ranged from 34.9 to 37.9 dB(A), and 29.5 to 32.5 dB(A) respectively. The equivalent noise level of all the stations were well below the permissible limits specified for residential area of 55 dB(A) for day time and 45 dB(A) for night time.

5.3.6  Vegetation in the Port Area The port area is about 83 acres in area, out of which about 78 acres is patta dry land and 5 acres  is poramboke  land.   Some coconut plantations of recent origin are observed  in the proposed port area.

Page 41: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 41 

5.3.7  Coal Conveyor Corridor Alignment The proposed coal conveyor corridor shall be 30m wide and approximately 6.2km long. There  lie 115 palm  trees, 294 Coconut  trees, 108 Cashew nut  trees, 35 Mango  trees, 78 Safeda trees & 400 other small trees & bushes in the proposed conveyor corridor

5.3.8  Wildlife Wildlife  recorded  in  the  study  area  comprises  common  species  like  jackals,  hares, mongoose  and  common  birds  and  do  not  comprise  fauna  that  are  endangered  or endemic.

5.3.9  Sediment Quality Grab samples were collected in the proposed project location and over an area of 11 km x 20 km.   Soil samples  indicate predominant presence of  fine sand with some silt and negligible clays.  Sub‐seabed profile shows that the area is devoid of hard / rocky strata.

5.4  Summary of Baseline Environmental Status  Data on water and sediment quality and biology was measured by collecting data  for three  seasons  viz.,  pre‐monsoon, monsoon  and  post‐monsoon  to  detect  any  possible seasonal variations.  Analysis of the comprehensive field data reveals the following: 

The near shore coastal belt shows negligible variation  in water quality. Beyond foreshore areas data reflects background concentrations.  The area represents an environment free from anthropogenic inputs. 

Analysis  of  heavy  metals  in  the  water  column  and  sediments  indicate background concentrations free from anthropogenic inputs 

Biological  characteristics  of  the  site  indicate  significant  plankton  and  benthic population with good diversity representing a healthy environment. 

During  the  site  visits  it  was  observed  that  the  fishing  villages  abutting  the proposed port  area had  about  60  small  boats  each  for  fishing  operations.   No trawlers were observed.   These boats were  landed on  the beach across each of these villages. 

Site visit to the proposed project location during March 2011 indicated presence of some empty pits. No eggs or turtles were located during the survey.  

The ambient air quality for SPM (2.5 and 10 �g/m3) and SO2 and NOx are within the  permissible  levels  for  rural/residential  area  and  represent  the  ambient conditions in the absence of any air pollution source 

There are negligible sources of noise generation and  therefore  the noise quality data  represent  ambient  conditions.    These  are  well  within  the  limits  for  a residential area as per NAAQS. 

Page 42: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 42 

Landuse  in  the  study  area  indicates major  portion  under water  body  (51.6%), followed by area under vegetation (22%) and area under agriculture (21.8%). 

Vegetation  in  the  study  area  indicates  some  portions  of  land  falling  under ‘reserve forest’ comprising mainly of eucalyptus plantation and land area within 10 km  radius  comprises  tropical dry  evergreen  forests, Tropical dry  evergreen scrub and Southern Tropical Thorn forests 

Wildlife recorded in the study area comprises common species like jackals, hares, mongoose and common birds and do not comprise fauna that are endangered or endemic. 

Soil  samples  indicate  predominant  presence  of  fine  sand with  some  silt  and negligible clays.  Sub‐seabed profile shows that the area is devoid of hard / rocky strata. 

 

Page 43: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 43 

CHAPTER SIX  

ASSESSMENT OF IMPACTS 

6.1  Assessment of Impacts 

Based on the project details and the baseline environmental status, the aim is to predict/ forecast  impacts  of  the  activities  and  provide  an  estimate  of  the  difference  in environmental  quality  after  the  project  is  initiated.  The  Environmental  Impact Assessment for quite a few disciplines is subjective in nature and cannot be quantified. Wherever possible, the impacts have been quantified. However, for intangible impacts, a qualitative assessment has been done. The basis for determining the change in future environmental quality  is  the current baseline data obtained  from  site survey.  Impacts have been assessed  for  the Construction and Operation phases of  the project and  the effects  on  the  environmental  quality  evaluated  by  comparing  the  results  with  the national standards where possible and background levels in other cases.   6.2  Main Plant 

6.2.1  Impact on Land Environment 

Construction Phase 

Impact due to land acquisition The preparatory activities like the use of existing of access roads, construction of storage sheds,  staff  quarters,  etc.  being  spread  over  a  large  area would  have  no  significant impact, except that as soon as the land is acquired, its use changes and the land ceases to be a productive unit. The land to be diverted for the proposed thermal power project is about 1,029 acres. To this an area of 10% is added as the edge effect, which brings the total area to about 460 ha, out of a total study area of about 31,416 ha. The area likely to be affected  is around 1.5% of  the  study area. The power  station would  require  lot of ancillary developments like shops, restaurant, workshops, etc.  The site preparation activities  like clearing, stripping,  levelling, construction of bunds, for  protection  from  flooding  and  impounding  of  ash  dump,  altering  slopes  for transmission  towers  each  filling  and  excavation  for  foundation, will  result  in  loss  of local plants and other biota and change of existing land use pattern. Since, only a small portion  of  the  area  is  affected  and  no  rare,  endangered  or  threatened  species  is observed. Hence, no major impact is envisaged as a result of acquisition of land for the proposed thermal power plant.  

Page 44: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 44 

Impact due to extraction of construction material The proposed Cheyyur Ultra Mega Thermal power station would require construction material. Construction material, e.g. sand, coarse aggregates, bricks, stone metal, would be  required  from  various  sources.  Construction  materials  such  as  sand,  coarse aggregates,  bricks,  stone,  etc.  required  for  construction  of  the proposed power plant would be procured  from nearby sources. Use of environmental  friendly  fly ash bricks would be explored for use in the proposed power plant.  

b) Operation phase 

Impact due to Coal Handling The annual coal requirement would be of  the order 12‐14 million  tonnes. As a part of the project, a coal stockyard for stacking of coal for a minimum period of 30 days at the Power  Project  shall  be  provided. Coal would  be  received  at  plant  site  through  pipe conveyor system.  The coal  received by conveyor belts  from  the port, would be stored  in  the stock‐yard near  the  power  plant.  The  in‐plant  crushing,  stacking,  reclaiming,  conveying  and bunker  feeding system of required capacity shall be  installed by  the power developer depending upon the quality, quantity and size of coal proposed to be imported. In the proposed project the coal bunker would be covered with bunker sealing belt  to avoid  dust  nuisance.  The  bunker would  be  adequately  ventilated  so  as  to  keep  the bunkers  free  from accumulation of volatile gases,  thereby eliminating  fire hazard and also  avoiding  dust  nuisance  on  the  tipper  floor.  Adequate  measures  will  be implemented  to  prevent  air  pollution  due  to  entrainment  of  coal  dust  during  coal handling operations.  6.2.2  Impact on Water Environment 

Construction Phase 

Impact due to Effluents  During  construction phase, about 10,000 persons are  likely  to be employed. The  total increase  in  population  shall  be  18,000.  A  labour  colony  shall  be  constructed  for providing  accommodation  to  the  labour  and  technical  staff  involved  in  construction activities.  The  facilities  for  meeting  water  requirement  and  sewage  disposal  and treatment  shall  be provided. The details  are  outlined  in Environmental Management Plan (EMP) of the CEIA Report.  

Page 45: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 45 

b) Operation Phase The following types of liquid wastes are expected in the project operation phase: 

cooling water and boiler blow down   effluent from water treatment plant  sewage generation.  runoff from coal stack sites 

 Sea  water  shall  be  used  for  meeting  condenser  cooling  water  requirements.  The temperature  of  cooling water  discharged  into  sea water  shall  not  be  5oC more  than above  the  receiving water  temperature. Boiler blow down water would be  led  to  the guard pond for storage prior to further utilization.  Rejected Water from Desalination Plants and Desalination Plant’s Rejected Water,  DM Plant combined with  filter backwash would be  led  to a separate Neutralizing Pit and would be discharged  to  Sea  through  an  independent Plant Effluent Drainage  system which shall not be mixed with Storm water Drainage system.   The water  requirement  for domestic use  includes  requirement  for drinking,  cleaning, etc.  in  the project area. The sewage generated  from domestic sources  in  the proposed thermal power station shall be treated before disposal. The effluent generated from coal stack  pile  area  containing  high  suspended  solids  and mildly  acidic  shall  be  treated before disposal.  6.2.3  Impact on Noise Level 

(a)    Construction phase The major sources of noise during construction phase are due  to operation of various construction  equipment.  The  increase  in  noise  level  at  a  distance  of  1  km  from  the construction  site will  be  only  1  dB(A). No  adverse  impacts  are  anticipated  on  noise levels in the construction phase of the proposed project.

b)   Operation phase The  noise  generated  by  various machineries  is  of  a  broad  based  variety with  strong component in low frequency range. The increase in noise level a distance of 500 m from the site due  to various  rotating and moving equipment at power plant will be only 1 dB(A). There are no residential areas within 500 m of proposed project site. Hence, no adverse impacts are anticipated on noise levels in the due to operation of the proposed project.  

Page 46: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 46 

6.2.4  Impact on Air Environment 

(a)   Construction phase The major pollutant  in  the  construction phase  is SPM being air‐borne due  to various construction activities. The vehicular movement generates pollutants such as NOx, CO and HC. But, the vehicular pollution is not expected to lead to any major impacts. The fugitive emissions due  to vehicular movement will be 8  to 12 kg/km  travelled by  the vehicle.   The  short‐term  increase  in  concentration  has  been  predicted  using  Gaussian  plume dispersion model.  The maximum  short‐term  increase  in  SO2  is  observed  as  0.00119 µg/m3, which  is at a distance of 200 m  from  the emission source. The maximum SPM concentration was 1.15 µg/m3 which is at a distance of 400 m from the emission source. The  incremental  concentration  is  so  low  that  it  does  not  need  any  specific  control measure. Thus,  the operation of  construction  equipment  is not  expected  to have  any major impact on the ambient air quality as a result of the project.

b)        Operation phase  On  the basis of process emission characteristics coal analysis and  theoretical estimates from fuel being used in boilers or furnaces, the emission characteristics were calculated. The predicted  incremental  ground  level  concentration  for PM10 was predicted  in  the range of 0.47 to 1.18 µg/m3; SO2 in the range of 17.64 to 44.19 µg/m3 and NOx levels in the range of 11.07 to 27.73 µg/m3.   6.2.5  Impact Due to Coal Handling The coal stock pile would be regularly sprayed with water to prevent the entrainment of fugitive dust from the stock pile.   6.2.6  Impact on Ecology The  direct  impact  of  construction  activity  for  any  project  is  generally  limited  in  the vicinity of  the construction sites only. The construction sites  include berthing, storage and  infrastructure  facilities. The  total  land requirement  for  this project  is about 416.45 ha. About 24.29 acre (9.83ha)   of forest land is proposed to be acquired for the project. The forest land to be acquired has mainly plantations of consuarina, and dense forest is not observed. No endemic, rare or threatened species are  observed on the forest land to be acquired for the project.  As a part of the project, greenbelt will be developed, which will improve the vegetal cover in the area. The critical concentration levels of SO2 and SPM are not likely to be attained in the vicinity of Cheyyur Ultra Mega Power Plant as adequate control measures are proposed to mitigate pollution due to flue gas emissions.  

Page 47: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 47 

 6.2.7  Impact on Socio‐Economic Environment 

a) Construction phase 

Economic Impacts  The construction of the proposed project would create a number of direct employment opportunities. However,  indirect  employment opportunities would also be generated which would provide great impetus to the economy of the local area. The construction and  operation  of  the  project  will  provide  an  impetus  to  the  industrialization  and urbanization in the area. Many of the agricultural lands or barren lands are likely to be put  to  non‐agricultural  use.  The  power  station  would  require  lot  of  ancillary developments  like  shops,  restaurant,  workshops,  etc.  which  will  have  a  significant impact on the existing land use of the area.  Besides,  a  variety  of  suppliers,  traders,  transporters,  service  providers,  etc.,  are  also likely to concentrate and likely to benefit immensely, as demand for almost all types of goods  and  services will  increase  significantly.  The  business  community  as  a whole would be benefited. The  locals would  also  avail  these opportunities  arising  from  the project and increase their income levels.   Job  opportunities  will  drastically  improve  in  this  area.  At  present  most  of  the population sustains on agriculture and allied activities. There are no major industries or other avenues of occupation in the area. The project will open a large number of jobs to the local population during project construction phase.   Impact on Infrastructure Facilities The  facilities  such  as  adequate water  supply,  sewage  treatment,  housing,  health  and education etc. shall be ensured before hand and adequate measures shall be  taken so that these infrastructure facilities do not pose problems during the construction phase.   Impact Due to Immigrant Population And Labour Camps During construction phase about 10,000 labour and technical staff is likely to migrate in the area. The total increase in population shall be about 18,000. A labour camp or colony shall  be  developed  for  providing  accommodation  to  the  technical  staff  and  labour population  involved  in  construction  activities.  Facilities  for  potable  water,  sewage treatment facilities etc. shall be provided at the labour camp and at the construction site. The  garbage  comprising  of  waste  materials,  e.g.  packaging,  polythene  or  plastic 

Page 48: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 48 

materials are likely to be generated during project construction and operation phase at the power station shall be properly collected and disposed at designated sites.  Impact on Cultural/ Religious/ Historical Monuments Monuments of cultural/ religious/ historical/ archaeological importance are not reported in the project area. Thus, no impact on such structures is envisaged.  Impacts on Salt Pans There is one salt pan in the study area located Cheyyur Village, Kancheepuram District (Rev. Survey no.‐506).  The salt pan is located about 3.5 km from the project area. As per the  local  enquires,  most  of  the  salt  produced  is  consumed  by  tanneries  located  at Ranipet and Vellore in the state of Tamil Nadu. The salt is used without any treatment or processing  in  tanneries  for peeling off  the skin of animals. Thus, no  impact on salt pans due to the proposed thermal power project is anticipated.  6.2.8  Summary of Impacts The  summary  of  impacts  likely  to  accrue  during  project  construction  and  operation phases is outlined in Tables 6.1 and 6.2 respectively. 

Table‐6.1: Summary of Impacts likely to accrue during construction phase of main plant S. No. 

Aspect  Impact  Duration Reversibility Significance 

1.  Land Environment 

Disturbance  at  site  due to  various  site preparatory activities 

Short‐term  Reversible  Moderately  significant, as  the  area  to  be acquired is quite small. 

Increased  soil  erosion from quarry sites 

Short‐term  Reversible  Not  significant  as  this impact can be managed by  appropriate management measures 

2.  Water Environment 

Degradation  of  water quality  due  to  disposal of  untreated  effluents from labour camps 

Short‐term  Reversible  Not  significant,  as quantity  of  effluent  is quite small 

Impacts  on  water quality  due  to  runoff carrying  high suspended  solids  from construction sites 

Short‐term  Reversible  Not  significant,  as quantity  of  effluent  is quite small 

Page 49: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 49 

S. No. 

Aspect  Impact  Duration Reversibility Significance 

3.  Noise Environment 

Noise  generation  by operation  of  various construction equipments 

Short‐term  Reversible  No  major  impact  is envisaged,  as habitations  are  at  a distance  for  the  project site. 

Increase  in  noise  level due  to  increased vehicular movement 

Short‐term  Reversible  Significant  increase  in noise  level  is  not expected 

4.  Air Environment 

Impacts  on  ambient  air quality due to emissions generated  as  a  result  of fuel  combustion operation  of  various construction equipment 

Short‐term  Reversible  Insignificant  increase  in SPM & SO2 levels. 

Fugitive  emissions  from storage  sites  of construction material 

Short‐term  Reversible  Insignificant  impacts  as no  human  population resides in the area likely to be affected. 

5.  Ecology  Impacts on  ecology due to  increased  human interferences 

Short‐term  Reversible  No  impact  is anticipated  as  all workers  will  be provided with alternate fuel 

6.  Socio‐economic Environment 

Increased  stress  on existing  infrastructure due  to  immigration  of labour population 

Short‐term  Reversible  Impacts  to be mitigated to  a  large  extent  by providing  sanitation, sewage and solid waste management  facilities 

Improvement  in employment  potential as  a  result  of  project construction  activities and  mushrooming  of allied activities 

Short‐term  Reversible  Positive  impacts  as marginal  improvement in employment scenario are expected. 

 

 

 

 

Page 50: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 50 

Table‐6.2: Summary of Impacts likely to accrue during project operation phase of main plant S.No.  Aspect  Impact  Duration Reversibility Significance1.  Land 

Environment Acquisition  of  private land 

Long‐term 

Irreversible  Significant  impact,  but compensation  to  be given  as  per  the norms/  guidelines outlined  in  National Resettlement  & Rehabilitation  Policy (2007) 

Change  in  land  use pattern 

Long‐term 

Irreversible  Marginal  impact,  as the  area  likely  to  be affected is quite small 

Generation  of  solid waste/  coal  dust  ash during  coal  and  ash handling  and  other project related activities 

Long‐term 

Irreversible  Significant  impact which  is  to  mitigated by  implementing appropriate management measures. 

2.  Water Environment 

Impacts in water quality due  to  disposal  of various  types  of  liquid wastes 

Long‐term 

Irreversible  Significant  impacts, which  are  to  be managed  by appropriate  treatment of  various  types  of effluents.  The  related effluents  to  be  reused to the extent possible. 

3.  Noise Environment 

Noise generation due  to operation  of  various equipments  / machineries  in  the thermal power station 

Long‐term 

Irreversible  Impacts  on  workers operating  in  high noise,  which  is  to  be mitigated  by  adopting appropriate management measures 

Impacts  on  workers operating  in  high  noise areas 

Long‐term 

Irreversible  Impacts  on  workers operating  in  high noise,  which  is  to  be mitigated  by  adopting appropriate management measures 

4.  Air Environment 

Impacts  on  ambient  air quality due  to  stack gas emissions 

Long‐term 

Irreversible  Emissions  to  be controlled  by commissioning  ESP and providing stack of adequate height.  

Page 51: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 51 

S.No.  Aspect  Impact  Duration Reversibility Significance5.  Ecology  Impacts  on  vegetation 

due  to  SPM  and  SO2 emissions 

Long‐term 

Irreversible  Emissions  to  be controlled  by commissioning  ESP and providing stack of adequate height. 

Impacts  due  to acquisition of 9.83 ha of  forest land 

Long‐term 

Irreversible  Compensation  to  be paid  as  per  the  norms outlined  in  Forest Conservation  Act (1980). 

6.  Socio‐economic Environment 

Impacts  due  to  private land acquisition 

Long‐term 

Irreversible  Significant  impact,  but compensation  to  be given  as  per  the  norms/  guidelines outlined  in  National Policy for Resettlement & Rehabilitation (2007) 

Mushrooming  of  allied activities  in  and  around the project area 

Long‐term 

Irreversible  Significant  positive impact 

 6.3  Captive Port  

The evaluation of the project  location was done as per MoEF siting criteria and  it was concluded  that  the project  is NOT  sited  in  an  ecologically  sensitive  area. The project operations  are  carried  out within  the  Port  area.  The  coal  containers  proposed  to  be handled  is  not  hazardous  or  toxic  and  therefore  there  is NO  RISK  involved  in  the Construction or Operation stages of the project.   6.3.1  Scoping Outcome The proposed marine facilities are exclusively for handling coal the UMPP at Cheyyur.  

There are no mangroves, coral reefs or critical habitats in the area or its vicinity.  Capital  dredging  and  dumping  activities  are  likely  to  cause  impacts  on water/sediment quality, benthic ecology, bathymetry and shoreline;  

Impacts on hydrodynamics and  littoral  transport  from breakwater construction are expected 

The proposed outfall is located in the offshore areas at about 14m water depths and shall be taken along the corridor prepared for the coal conveyor.  Impacts of higher temperature and salinity at discharge are expected to be negligible.   The land  acquisition  /  resettlement  issue  associated  with  the  coal  conveyor  is addressed in the terrestrial EIA report.  

Page 52: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 52 

As  cooling  towers  are  provided,  the  discharge  waters  are  expected  to  have temperature increase of up to 5oC above ambient. Location of the marine outfall for disposal of reject water needs to focus on impact from increased temperature and salinity concentrations than ambient.  

Handling  of  coal  are  likely  to  cause  air  quality  impacts  from  dispersion  of particulate matter 

Construction  activities  causing  air  quality  impacts  are  temporary,  intermittent and reversible; 

Impacts on noise quality from piling and dredging operations shall be temporary and limited to the project site  

 6.3.2  Estimation of Impacts – Design Given the knowledge of the project setting, present environmental conditions, baseline status  of  the  study  area  through  previous  investigations,  the  following  assessments have been considered significant and are required to be assessed 

Prediction of impacts on water quality from dredge dump disposal and impacts on benthic ecology at disposal site 

Accretion  /  erosion  impacts  on  the  coastline due  to  change  in  hydrodynamics from breakwater construction. 

Design of an appropriate location for locating the marine outfall for discharge of reject waters and withdrawal of makeup water using MIKE21 

Design of diffuser configuration to ensure well mixed conditions and dilution in the vicinity (mixing zone) of the outfall using CORMIX.  

Ecological impacts due to disposal of brine and high temperature water through the outfall 

Assessment  of  air  quality  impacts  from  dispersion  of  particulate matter  from stockpiles and conveyors during loading operations  

Impacts on air & noise quality due to construction activities shall be short‐term and cease to exist after construction is completed. While these can be considered insignificant,  following  assessments  are  required  to  be  done  to  obtain  a quantitative estimate. 

Air  quality  impacts  due  to  transportation  of  construction  materials  during construction  phase  and  vehicular  emissions  and  ship  emissions  during  the operations phase. 

Noise  levels  at  receptor  during  piling  and  dredging  operations  (during construction phase). 

 

Page 53: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 53 

6.4  Prediction of Impacts 

6.4.1  Air Quality Impacts Impacts on ambient air quality are possible due to the following activities 

Construction material handling/ transportation of materials/ quarrying  Construction activities including fabrication, welding, pre‐casting  Dispersion of particulate matter during coal handling operations and emergency storage 

Ship operations  The  impacts on air quality during  the construction phase are expected  to be minimal and the ambient air quality shall remain within the permissible limits. In addition, the impacts are temporary, existing only for the period of the activity. Also, the impacts can be mitigated with simple, low cost EMPs, such as, covering trucks, checking vehicular emission compliance and masks for workers.

6.4.2  Impacts of Dredging The primary water quality issue to be addressed is related to dredging. The quantity of capital dredging involved is 7.8 million m3.  A preliminary assessment of a dredge spoil impact was assessed by simulating the discharge of a single dredge load using MIKE21, a two dimensional hydrodynamic, sediment transport.    From  the model  results an area of 4km x 4km area  is  identified near 30m depths  for dumping the dredged material. Dredging shall be carried out for over sixteen months in the channel and basin.  This will result in removal of native benthic species within the dredge  area.    This  would  result  in  a  medium‐short‐term‐reversible  impact  but  its environmental significance would be low because: 

Common benthic groups  like  copepods, nematods, polychaetes, gastropods etc are present in this location. These communities have widespread distribution not only  in  the proposed  channel but  also  in  all  locations  sampled.   While during capital  dredging  these  will  be  smothered,  it  is  highly  likely  that  these communities  shall  move  into  the  rejuvenated  channel  and  flourish;  Typical example  is the Ennore navigational channel and harbour area where significant increase in numbers were recorded after capital dredging was carried out. 

The channel and basin is devoid of threatened / endangered / endemic species;  The location is not a spawning or breeding ground for fisheries was not observed in and around the project area; 

Sensitive phytoplankton like sea grasses or aquatic fauna are not present in this location; 

Page 54: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 54 

The area is not a significant fishing ground or feeding ground for fisheries. The fisheries in this area is confined to artesenal fishing with trawlers already having moved to offshore areas from the coast off Panaiyur 

At  the  dredging  site,  the  initial  disturbances  to  benthic  organisms  result  in smothering/death. Communities  are  expected  to  regenerate  in  a period of  two years.  The  sediment  analysis  indicates  low  to  average  values  for  toxic  heavy metals  and  shall  not  result  in  high  water  column  concentrations  due  to  the disturbance.  The  toxic  metal  concentrations  are  well  within  background concentrations and can be safely disposed as dredged material or as a landfill.

6.4.3  Impacts on fishing activities It  is expected  that  there will be  improvement  in breeding and spawning areas due  to tranquil conditions provided by the breakwater. This has been observed in all harbours with  breakwaters,  e.g.  Ennore.  Eventually  these  fish  will  move  out  and  would  be available in the local areas for catch.  Restriction  to  fish  boat  movement  during  harbour  construction  is  expected.    Also during port operations  there  shall be  interruption/  restrictions  to movement of boats due  to  vessel  navigation.    However  this  may  be  restricted  to  the  time  period  of approximately half  to one hour when  the vessels  are  in movement  in  the navigation channel. Since only  small boats  and not  trawlers/  fishing vessels operate  in  the  area, manoeuvring is not an issue. It is possible to manage and implement these restrictions locally. In order to improve the effort/ catch, fishermen can be provided with additional infrastructure  like  better  fish drying  areas,  ice plants  and  ice  boxes  for preservation.  Fish processing units can be setup.  The port operator can link the fishing villages with the consumer market and provide better market facilities for the fish catch.

6.4.4  Morphological changes to coastline due to breakwater  The  results  of  the  shoreline  evolution were  carried  out  using  LITPACK module  of MIKE21.  Results  of modeling with  detached  breakwaters  indicates  about  20  to  30m erosion at a distance of 350 m to the north of the breakwater and less than 20 m erosion at a distance of 600 m to the south of the breakwaters with some deposition in between the breakwaters. Though, the annual net sediment transport is northerly in the order 0.19 x 106 m3/year, without placing any structure also, the coast is observed to be eroding (50‐60 m after 1 year) in the north. This also corroborates with the IOM studies for shoreline to the north and south of Panaiyur.  

Page 55: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 55 

6.4.5  Dispersion studies for cooling water discharge The modeling  illustrates  that  the  offshore  location  has  the  capacity  for  handling  the withdrawal and discharge of water for cooling waters. The temperature and salinity increase within 500m from the outfall is estimated to rise by approximately 0.1oC and 0.5 ppt  respectively during non monsoon period and by 0.15oC and 0.9 ppt respectively during monsoon period.

6.4.6 Summary of estimate of impacts The summary of impacts for captive port is given in Table‐6.3.  

Table‐6.3: Summary of impacts due to Captive port Issues considered  Results of prediction Level  of  significance  with 

EMP Air Quality Impacts Generation  of  SPM due to  construction material handling 

Estimated  24‐hour  average  SPM concentrations  are  within NAAQS standards of 60�g/m3 

Low  and  will  cease  to contribute  pollution  and construction is complete 

Vehicular  emissions during transportation of construction  materials for  800  numbers/day  of  vehicles 

The  increase  in  the concentration of NOx, CO and HC at a distance of  500m  is  negligible  and  the overall concentrations conform to NAAQS 

Regular  emission  checks  on vehicles must be mandatory as the  location  is  new  and pristine. 

Construction  activities like  precasting, fabrication, welding  

‐  Low;  It  shall  be  ensured  that construction  debris  shall  be cleared  by  contractor  after completion of construction 

Emissions  from vehicular  traffic  during cargo    handling  for additional  number  of 2200 vehicles/day 

The  increase  in  the concentration of NOx, CO and HC at a distance of  500m  is  negligible  and  the overall concentrations conform to NAAQS 

Low 

Generation of SPM from coal stackyard 

24‐hour  average  SPM concentrations  are  estimated  as 

Low  impact  as  the  coal unloading  will  be  within 

Page 56: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 56 

Issues considered  Results of prediction Level  of  significance  with EMP 

Generation  of  SPM during Loading/unloading  of coal 

0.72 μg/m3 for D‐stability class  hoppers  thereby  minimizing fugitive  dust.    Also  the  coal will be in wet condition during handling.    The  emergency stackyard  will  also  have  wet coal  only.    There  will  be sprinklers for keeping the coal in  a  wet  condition.    An  all‐round  green  belt  of  50m  is proposed as a buffer zone. 

Generation  of  SPM during  coal  transport using conveyors 

Closed conveyors with negligible SPM generation as  in  the case of Ennore shall be used. 

Low  impact  as  the  conveyors are  closed  /  pipe without  any contact with the atmosphere 

Emissions  and  SPM from  ships  berthed  at the jetty 

The  increase  in  the concentration of  SPM,  SO2, NOx, CO  and HC within  the  jetty area  is negligible and  the  overall  concentrations conform to NAAQS 

Low

Noise Quality Impacts Capital dredging  Noise  levels  are  reduced  to 

background  levels  within  100m from  the source and conforms  to NAAQS.  No  noise  sensitive receptors within 500m 

Low 

Piling operations  Noise  levels  are  reduced  to background  levels  within  50m from  the source and conforms  to NAAQS.  No  noise  sensitive receptors within 500m 

Low 

Construction  vehicle transport 

Noise levels are 70 dB(A) at 200m distance  from  the  road  and  the increase  is  found  to negligible at 500m 

Low

Water Quality Impacts Water  for  construction and  turbid  runoff  from construction site 

Negligible,  groundwater  shall not  be  tapped. No  turbid  runoff due to scanty rainfall 

No impact 

Water  usage  by  labour force  and  generation  of wastewater 

Negligible  No impact 

Page 57: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 57 

Issues considered  Results of prediction Level  of  significance  with EMP 

Sediment  resuspension, release  of  toxic substances  and nutrients  from sediments  during capital dredging 

Sediment  suspension  is negligible,  since  concentrations return  to  background  levels within  12  hours  of  dredging. Sediments are not toxic 

Low,  Dredging  shall  be stopped  during  spawning periods  

Hydrodynamics / shoreline changes  Impact  of  detached breakwater construction  

Accretion  /  erosion  is  negligible.  Some  deposition  within  the breakwater  along  shoreline observed.   Generally  stable coast as  interpreted  from  satellite imageries over 40 years 

Low  as  breakwater  is  located beyond  6m  contours  up  to which  littoral  transport  is predominant. EMP  requires  dredging  and bypassing  of  sediments deposited  within  the  harbour area  to  avoid  any  shore connection in the long term   

Biology/Benthic Ecology Loss of benthos/biomass due to capital dredging 

The site appears to be productive.  Recolonization is expected within 2‐3 months of dredging. 

No impact 

Impacts of breakwater  It  is  expected  that  the breakwaters will provide tranquil conditions  for  breeding  and spawning of fishes as observed in other existing breakwaters.  

Positive  impact  in  the  long term 

Landuse / Aesthetics Quarrying  for breakwater construction material 

Removal  of  boulders  thereby changing  landforms  and topography 

Low  when  material  is procured  from  approved quarries.

Socio‐economics Capital dredging  Temporary  removal  of  benthos, 

however  rejuvenation  expected in 3‐4 months 

Temporary  /  Low  negative impact. Low when dredging is not carried during  fishery ban period. 

Vehicular traffic  Large  numbers  of  vehicles phying  in  the  area  for transporting  materials    over  a period of 3‐4 years 

High  impact  limited  to construction  period.    Impacts include  accidents,  air  and noise  pollution.    Check  posts and speed limits required 

Page 58: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 58 

Issues considered  Results of prediction Level  of  significance  with EMP 

Employment  Temporary  employment  during construction  and  several employment  opportunities  and allied  industries  during operations 

Positive impact 

Fisheries   Improvement  in  breeding  and spawning  areas  due  to  tranquil conditions  provided  by  the breakwater.    Eventually  these fish will move out and would be available to the local for catch 

Positive impact 

Fishermen population  Restriction to fish boat movement during  harbour  construction.  Interruptions  to  movement  of boats  during  operations  due  to vessel navigation.   

Medium  impact  since  the fishermen  operate  small  boats and  have  beach  landing  only, the restrictions it is possible to manage  locally.  These restrictions  would  be applicable  only  during  vessel movement  in  the navigational channel.  Additional infrastructure  like  better  fish drying areas, ice plants and ice boxes  can  be  provided  for preservation.    Fish  processing units can be setup.   

Cooling water discharge – water quality & Ecological impacts Pipeline Laying  Removal  of  negligible  quantities 

of benthic flora/fauna The  impacts  are  short‐term  and cease  after  construction  is complete. Pipelines  shall  not  be  routed through coral formations 

Low  (limited  to  construction phase only) 

Page 59: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 59 

Issues considered  Results of prediction Level  of  significance  with EMP 

Discharge  of  reject water from the outfall 

Low  when  discharged  at  10  to 14m water depths with multiport diffusers at locations specified by NIOT  

Low  at  a  distance  of  500m from  the  source  where temperature  and  salinity excesses  fall within  the  range of ambient natural variations. Since  the  temperature  and salinity  variations  return  to ambient  conditions  within 500m,  impacts  on  aquatic ecology is LOW. 

Environmental  Costs of Project 

Low  because  breakwaters  are detached  and  is  likely  to  result  in negligible  accretion  /  erosion;  Cooling  water  discharges  have localized impacts.  Impacts of project limited to construction phase

Benefits   Benefits to country and state are large scale power generation and employment

NET IMPACT  Net benefits to the region

 

Page 60: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 60 

CHAPTER SEVEN  

ENVIRONMENT MANAGEMENT PLAN 

7.1  Main Plant Area 

The Environmental Management Plan (EMP) integrates the baseline conditions, impacts likely  to  occur,  and  the  measures  for  amelioration  of  adverse  impacts.  during implementation of the project in Construction and Operation phases.  7.1.1  EMP for Construction Phase 

Water Quality The major source of water pollution during construction phase is the sewage generated by  the  workers  and  employees  congregating  at  the  construction  site.  During construction phase about 10,000 workers and technical staff are  likely to congregate at the project site. The total increase in population is expected to be about 18,000. A labour camp or colony is proposed to be constructed for providing accommodation to technical staff  and  labour  involved  in  construction  activities.  It  is  proposed  to  construct  900 community  toilets within  the  labour  camps  and  close  to  construction  sites  itself. The sewage can be treated in sewage treatment plant prior to disposal. 

Solid Waste Management  Adequate  facilities  for  collection,  conveyance  and  disposal  of  solid  waste  shall  be developed. The solid waste will be disposed at the designated landfill sites. The landfill site shall be finalized in consultation with the district administration. The landfill shall have is impervious clay as the bottom most layer. The second layer shall be impervious liner (Geo‐membrane), third layer is sand, after that well compacted solid waste is to be put over the sand, then again a layer of clay, finally a layer of soil. Some vegetation can be done at the top most layer for aesthetic view of landfill.

Provision of Free Fuel The project proponent  in association with  the State Government shall make necessary arrangements for distribution of LPG to families of labour and technical staff involved in construction activities. 

Restoration and landscaping of project site The construction of the proposed project would lead to minor disturbance the existing topography and physiography. No major alteration of the area is expected, as the layout has  been  so  conceived  that  no major  impacts  on  this  account  are  anticipated.  It  is 

Page 61: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 61 

proposed to landscape the area so that it integrates with the natural surroundings. It is proposed  to  clear  construction  waste material  from  entire  area.  It  should  be made mandatory  for  the  contractor  involved  in  construction  activities  to  remove  all  the construction waste and restore the original topography of the area. 

Health Facilities During Construction Phase To cater  to diseases such as  insect bites,  fever, diarrhoea, work exhaustion etc during construction phase or from injuries caused by accidents at the work site, a first‐aid post is proposed at the construction site for providing  immediate health care with facilities like  First  ‐aid  box with  essential medicines  using ORS  packets,  First‐aid  appliances, splints  and  dressing materials,  Stretcher, wheel  chair,  etc.    For  serious  injuries,  the patient will be immediately reached to the nearby hospital for which a van will be kept at the construction site. 

Air pollution Control Measures 

a)  Control of Emissions To minimize  air quality  impacts by  emissions  from  construction vehicles,  equipment and DG  sets  and  emissions  from  transportation  traffic,  the measures  recommended include   proper maintenance of construction equipment to minimize exhaust; to avoid unnecessary  idling  of  construction  vehicles;  effective  traffic  management  to  avoid delays in and around the project area; to promptly attend road damage caused by sub‐project activities. 

b)  Dust Control The  project  authorities  will  work  closely  with  representatives  from  the  community living  in  the vicinity of project area  to  identify areas of concern and  to mitigate dust‐related impacts. 

Noise Control Measures The  ambient  noise  levels would  have marginal  increase  up  to  about  1  km  from  the major construction site and will not have any significant adverse impact. Efforts will be made  to  bring  down  the  noise  levels  due  to  the DG  sets within  the  ambient  noise requirements by proper sitting and control measures. 

Disposal of Runoff From Construction Sites  Fencing  will  be  provided  around  stockpiles.  Construction materials  containing  fine particles will be stored  in an enclosure such that sediment‐laden water does not drain into nearby watercourses. All discharge standards promulgated under Environmental Protection Act, 1986, will be adhered to. 

Page 62: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 62 

Prevention of Soil Contamination Vehicle/  machinery  and  equipment  operation,  maintenance  and  refuelling  will  be carried out in such a fashion that spillage of fuels and lubricants does not contaminate the  ground. Oil  interceptors will  be  provided  for  vehicle  parking, wash  down  and refuelling areas within  the construction camps. Fuel storage will be  in proper bunded areas. All  spills  and  collected petroleum products will be disposed off  in  accordance with MoEF and SPCB guidelines. Fuel storage and refilling areas will be located at least 1000 m from rivers and other water bodies or as directed by the Site Engineer. In all fuel storage  and  refuelling  areas,  if  located  on  agricultural  land  or  areas  supporting vegetation, the top soil will be stripped, stockpiled and returned after cessation of such storage and refuelling activities.

Safety Practices During Construction The Contractor is required to comply with all the precautions as required for the safety of the workers as per the International Labour Organisation (ILO) Convention No. 62 as far  as  those  are  applicable  to  this  contract.  The  contractor will  supply  all  necessary safety appliances such as safety goggles, helmets, masks, etc., to the workers and staff. The  contractor  shall  to  comply  with  all  regulation  regarding,  working  platforms, excavations,  trenches  and  safe  means  of  entry  and  egress.  In  order  to  guarantee construction  safety, efficient  lighting and  safety  signs  shall be  installed on  temporary roads  during  construction  and  adequate  traffic  regulations  shall  be  adopted  and implemented for temporary roads.  7.1.2  Environmental Management during Operation Phase 

Water Environment  

All Plant  process drains &, Plant surface drains (except Rain water) shall be first treated for Oil removal and thereafter routed to Effluent  Treatment (Neutralizing  Pond) from where  the  treated  water  shall  be  utilized  for  Horticulture  &  Dust  Suppression  in Coal/Ash Handling areas. Only CT Blowdown and Desalination Process rejects shall be sent back to Sea.  The mitigatory measures for source of water pollution are as follows:  Cooling water The  total cooling water discharge shall be stored  in a guard pond  for storage prior  to disposal. As per the norms specified for disposal of effluents, the temperature shall not exceed 5oC above the temperature of the receiving water temperature.  

Page 63: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 63 

Plant wash down water and Miscellaneous drains Plant  Process Drains  after  oil water  separator  shall  also  be  sent  to  the  above Guard Pond. The water so stored in the Guard Pond shall be used for Horticulture/Gardening   Rain (Storm) Water Drainage The  rain  (storm) water  removed  from  the  building  roofs  and  yard  area  grade  level surfaces would be directed through the open ditches and culverts to the storm drainage piping. Grade level would be contoured such that storm water run off is directed on the ground, to well defined drainage paths leading to the storage pditches.    Effluent from Water Treatment Plant Rejected  Water  from  Desalination  Plants  may  contain  high  Salt  concentrations  & Chemicals used for Pre‐treatment. Desalination Plant’s Rejected Water would be led to a Common Monitoring Basin and Guard Pond and would be discharged to Sea through the outfall system pumps & pipes, which shall not be mixed with Storm water Drainage system.   Effluent from coal stock yard The  coal  and  clinker  stock  yard  shall  be  cleaned  immediately  once  a  phase  of  coal handling operations  is completed. The water can be channeled from various area, and can then be settled in a settling tank. It is likely that considerable quantity of coal slurry settles within the drain, before reaching the settling pond. Thus, at regular intervals of drain length sumps can be installed adjacent to the drain to allow the bulk of the solids to settle in these sumps with overflow water being channeled to the settling pond. The solids which settle out  in  the sumps can be cleaned out by a  front end  loader or back hoe and the material can be returned to the respective stock pile area.  Effluent from ash disposal area The ash settles in the ash pond and the slurry water accumulates in the low lying area and reaches the ash recovery system. This effluent is likely to contain suspended solids which can be removed in a clarifier.    Sewage from Various Buildings in the Plant Sewage  from various buildings  in  the power plant  area would be  conveyed  through separate drains and treated in a sewage treatment plant (STP). The treated effluent shall be reused or recycled depending on the quality..  

Page 64: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 64 

Air Pollution Control 

Dust control during coal handling The conveyors would be provided with completely enclosed galleries with GI sheeting on  sides.  Seal  plates will  be  provided  on  the  bottom  run  off  these  galleries  at  road crossing, plant  area  to prevent  coal  for  from  falling down  the  conveyor  gallery. The crusher house and  junction  towers would be provided with dry  type dust  extraction system with bag  filters. Water will be  sprayed  around  the  stockpile  and  the  transfer point hoppers  to suppress  the dust generated and  to  reduce  the dust nuisance. Wind shields / screens are presently available for prevention of entrainment of fugitive dust. 

Dust control during fly ash handling To reduce the dust nuisance while loading the ash into the trucks from fly ash silos, the fly  ash  is  conditioned with water  spray.  It  is proposed  to  cover  the  ash  in  the  open trucks  with  tarpaulin  to  prevent  flying  of  fine  ash  during  transportation.  The  ash disposal area would be  lined with  impervious  lining  to prevent seepage of rain water from the disposal area in to the ground and pollute ground water.

Dust Particulate From Fly Ash in Flue Gas As  per  the  Pollution  Control  Board  norms,  the  standard  for  particulate  emission applicable to this project is 50 mg / Nm3. The electrostatic precipitators (ESP) proposed for this project would be designed to limit the emission level of the particulate matter to 50 mg  / Nm3.  Dust  extraction  system  of  coal  crusher  and  other  equipment will  be provided with a Bag Filter.  The outlet will be designed to meet particulate emission of less than 50 mg/Nm3.

Sulphur Di‐Oxide (SO2) in Flue Gas As per  the norms of minimum stack height  for 500 MW unit would be 275 metres. A single multi  flue  stack of 275 m would meet  the norms  for  the power plant has been proposed for effective dispersal of sulphur dioxide. 

Nitrogen Oxides (NOx) in Flue Gas To  reduce  NOx  emissions,  over‐fire  air  system  equipment  with  airports  would  be installed for the furnace. Further, the steam generators would be fitted with advanced low NOx burners.   Compensatory Afforestation The  total  forest  loss  in  the  land acquired  for  the project  is 24.29 ha.  It  is proposed  to afforest double the amount of forest land being acquired for the project. Thus, a total of 

Page 65: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 65 

49 ha  of  land needs  to be  afforested. The  afforestation work  is  to be done by Forest Department.   Rain Water Harvesting In the proposed project, storage of rainwater on surface for future use is envisaged. The total paved surface area  is 254082 m2.   The annual average rainfall  in  the area  is 1055 mm  (1.055 m). Thus, volume of water available at  roof  top  is 268057 m3. The Runoff Coefficient  has  been  taken  as  0.80.  Thus,  volume  of  water  that  can  be  used  for storage/recharge is estimated as 214445 m3 or about 214 million  litres per annum. This water is proposed to be used for meeting irrigation or dust suppression requirements.  For harvesting the rain water the paved surface would be maintained clean and should be  free  from dumps  and unwanted or unused material. The dust  and other material would be removed periodically, so that the water harvested as far as possible free from suspended particles.   Greenbelt Development It  is proposed  to develop greenbelt around various project appurtenances  to mitigate pollution  levels  in  the  area. Depending  upon  the  topo‐climatological  conditions  and regional ecological status, selection of the appropriate plant species shall be made. The greenbelt  development  plan  proposed  would  have  the  plantation  at  appropriate spacing.    The width  of  the  greenbelt will  be  50m. About  1,600  trees  per  hectare  are proposed to be planted. The maintenance of the plantation area will also be done by the project proponents.   Socio‐economic Environment The construction and commissioning of the power plant would lead to mushrooming of various  allied  activities,  where  largely  local  population  would  be  involved.  The development  of  various  activities  would  provide  an  impetus  to  improvement  in infrastructure at the local level. During project operation phase, local population would be given priority for employment for unskilled posts.   Fire Protection System An elaborate  fire protection  system  covering all  the buildings of  the proposed power plant including coal stockyard would be provided. The water would be drawn from the desalinated  water  storage  tank  in  which  reserve  capacity  of  2000  cu.m  would  be provided.    

Page 66: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 66 

The following fire protection systems are proposed:  Hydrant system for plant area and foam system for HFO & LDO tanks.   Automatic  High  velocity  water  spray  (HVWS)  system  for  the  protection  of transformer and manual HVWS system for the protection of turbine oil tanks. 

Automatic deluge  (Medium velocity water  spray)  system  for  the protection  of cable vaults and coal conveyors. 

Clean gas agents for the protection of control rooms.   Portable fire extinguishers for different areas.  The system would be designed to conform to the Rules and Regulations of Fire Safety standards as per TAC. 

 Bird Conservation Plan  The following measures are recommended for conservation of birds: 

Level and the quality of water needs to be properly maintained for meeting the requirements of birds. 

No further encroachment of the water area needs to be made.  Vegetal  cover  of  the  area needs  to  be  improved  by plantation  of  local  species preferably  plants  with  prolific  branching  to  provide  sufficient  roosting  and nesting sites for the birds.  

As the area is covered by the tidal wetland and with thick vegetation, it should be  considered  as  the  core  of  the  protected  area  hence  the  silt  removal  and desalting  in  select  areas  during  the  appropriate  seasons  may  be  helpful  in improving the system.  

Dumping of  solid wastes  should be avoided within a distance of 500 m  in  the catchment area of wetland.  

 7.2  Captive Port   

The  nodal  agency  of  Project  Developer  will  co‐ordinate  with  the  contractors  for implementation of EMPs during the construction phase.  Environmental monitoring in the Port area shall be undertaken by Project Developer. Annual monitoring of air, water and sediment quality shall be carried out routinely for the Port area.  7.2.1  Mitigation Measures The  impacts  of  the  various  activities  of  the  proposed  development  and  the  specific measures that are needed during the design, construction and operation phases of the project  shall  form  part  of  the  implementation.    Best  housekeeping  practices  shall  be incorporated in the design, construction and operation phases of the project. Green Belt 

Page 67: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 67 

area 50m wide  in  four  tiers  is suggested  for attentutation of  fugitive dust.   The  list of trees native to the port area includes Casurina, Euclaptus, Coconut, Casurina etc.  Also wind barriers using HDPE screens are presently used for prevention of particulate matter dispersion.  It  can be  seen  that  they are  significantly  tall  to prevent particulate matter  from  being  blow  off  by wind.    These  screens  are  used  in  some  of  the  ports handling  and  storing  coal.  The  same  types  of  screens with  bubble  top  covering  are suggested at  the emergency stackyard at  the port site of Panaiyur  for minimization of particulate emissions.  7.2.2  Tsunami Early Warning System This site was not affected by the devastating tsunami of 2004. However, the port shall have a link with the National Disaster Management Agency for early tsunami warning to plan for evacuation and thereby minimize the damage especially to life.  This would be  useful  in  evacuating  the  vessels  inside  the  breakwater  to  offshore  locations. Occasional drills for tsunami warning and mitigation shall be practised.    7.2.3  Operational Criteria For Port Craft (Tugboats And Mooring Boats) The tug boats will have operational constraints due to wind generated or short period waves.  The  limiting  criteria  for  ordinary  tugboats  would  be  Hs<1.0‐1.5  m  and approximately 1.5 m  for  tractor  tug boats. Modern mooring  launches can operate at a wind speed of up to 30 knots and with a Hs< 1.0‐1.3 m. Beyond the above mentioned limits the boats will face difficulty in delivering the lines from the ship to the mooring points. It is recommended that the Pilots, Tugboat Masters and crew are provided with adequate  training and  familiarisation prior  to  the commencement of operations at  the proposed port facility. It  is recommended that the key personnel are familiarised with the emergency procedures to deal with emergencies like engine and steering failure.  7.2.4  Fire Fighting System for Coal Conveyor The  system  shall be designed  to give  suitable  fire protection  for  the  facility based on Indian  Standards  or  equivalent  and  shall  conform  to  the  provisions  of  the  Tariff Advisory Committee’s Fire Protection Manual.    The Fire hydrant system shall be designed to ensure that adequate quantity of water is available at all times, at all areas of the facility where a potential fire hazard exists. Each hydrant  connection  shall  be  provided with  suitable  length  of  hoses  and  nozzles  to permit effective operation.  

Page 68: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 68 

The hydrant service shall cover  the entire  facility, and shall have pumps,  located  in a common pump house. Adequate  arrangement with  jockey pumps, pressure  switches etc.  shall  be  provided  to maintain  the  required  pressure  in  the  hydrant  system. The operations of the Pumps provided for the system shall be automatic.  

Page 69: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 69 

CHAPTER EIGHT  

PUBLIC HEARINGS AND PROCEEDINGS 

8.1   Main Plant and Ash Dyke Area 

The public hearing  for  the Main Plant and Ash Dyke area was held on 10.06.2010 at 11.00AM  in  the  presence  of  District  collector,  Kancheepuram  District  and  District Environmental Engineer, TNPCB, Maraimalai Nagar and various concerns of the public have been addressed.   The  proceedings  of  the  public  hearing  have  been  duly  authenticated  by  the District collector District and District Environmental Engineer.  8.2  Captive Jetty and Coal Conveyor Off Panaiyur Chinnakuppam 

The public hearing for the captive jetty and coal conveyor off Panaiyur Chinnakuppam was held on 28.12.2011 at 11.00AM in the presence of District collector, Kancheepuram District and District Environmental Engineer, Tamil Nadu Pollution Control Board and various concerns of the public have been addressed suitably.   The  proceedings  of  the  public  hearing  have  been  duly  authenticated  by  the District collector District and District Environmental Engineer.   

Page 70: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 70 

CHAPTER NINE  

RISK ASSESSMENT AND DISSASTER MANAGEMENT PLAN 

9.1  Risk Assessment and Disaster Management Plan 

A thermal power plant contains various equipment and storages operating under high temperature  and  high  pressure.  The  scale  of  possible  fire  and  release  from  chlorine tonners  has  grown  and  so  as  the  area,  which  might  be  affected  by  such  events, especially  outside  the plant  boundary.   As per Ministry  of Environment  and  Forests (MoEF), Government of India risk assessment is a mandatory requirement for thermal power stations. In order to minimize damages in case of accident or likely failure cases, a risk analysis study has been carried out to quantify zone of influence of various failure cases  and  a  disaster management  plan  has  been  prepared  to  control  the  spread  of incident effectively.  The details of Disaster Management Plan to be implemented are described in Chapter 7 and Chapter 8 of CEIA Report of WAPCOS and NIOT respectively.     

Page 71: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 71 

CHAPTER TEN  

RESETTLEMENT AND REHABILITATION PLAN & CORPORATE SOCIAL RESPONSIBILITY 

10.1  Resettlement & Rehabilitation Plan  

The R&R Plan  for  the project affected  families of  the proposed  thermal power project has been  formulated as per  the provisions and/or guidelines as given  in  the National Rehabilitation and Resettlement Policy, 2007  (NRRP–2007),  formulated by Ministry of Rural  Development,  Department  of  Land  Resources,  Government  of  India  and  the Rehabilitation and Resettlement Policy Framework submitted to Government of Tamil Nadu.  The  details  of  Resettlement  and  Rehabilitation  (R&R)  Plan  for  the  Project  Affected Families (PAFs) has been separately covered in Chapter 7 of each of the Socio‐economic Study for Main Plant and Captive Port.   10.2  Corporate Social Responsibility Activities 

Corporate Social Responsibility (CSR) of Cheyyur UMPP is broadly framed to empower the  project  affected  families  in  particular  and  the  population  in  the  study  area  in general, in every possible way and to improve their overall quality of life and standard of  living.  The  assessment was  conducted  in  50  villages  in  the  Cheyyur  Taluka  and Maduranthakam  Taluka  in  district Kancheepuram.  The  villages  are  located within  a radius  of  10  km  of  the  proposed  Cheyyur  Ultra Mega  Power  Project. Most  of  the information  that was  required  for  preparation  of  CSR Activities was  gathered  from secondary  as  well  as  primary  sources.  Both  qualitative  as  well  as  quantitative information was collected and used. The following aspects have been covered under the CSR activities: 

Protection of Environment o Afforestation and green belt development  

Upgradation of Educational Facilities o Establishment  of  new  schools  and  colleges  and  upgradation  of 

infrastructure  facilities  such  as  furniture,  equipments,  computers, playgrounds etc. in the existing ones. 

o Scholarships for Students  Improvement in Public Health Facilities 

o Appointment of additional doctors (surgeons, gyanecologist, etc.) o Establishment of additional primary health centres  

Page 72: Table of Contents - indiaenvironmentportal Common_EIA... · Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP Page | 4 CHAPTER ONE ... Jharkhand Integrated Power Ltd

Coastal Tamil Nadu Power Ltd. Common EIA Report for Cheyyur UMPP

Page | 72 

o Provision of new equipments such as ventilator, ambulance etc., o Poison Treatment Centre  o Increase in no. of beds in hospitals, etc.  

Development of an Industrial Training Institute   Infrastructure Facilities in Fishing Villages 

o Boat making and repair yard o Ice plant for preservation of fish o Auction Hall for auctioning of fish catch o Net mending sheds and net drying yards o Endowment Fund for welfare of fishermen and other groups o Construction/ upgradation of Bus Stands o Widening and metaling of existing internal roads 

Improvement in Quality of Life o Construction  of  low  cost  sanitation  facilities  (lavatories)  for  those 

households which do not have the same. o Construction of Old Age homes and Orphanage. 

Funds for CSR Activities o Around Rs. 80 Crore (One Time) 

Scholarships to student      Rs. 20 Crore   Public Health         Rs. 17.5 Crore   Schools          Rs. 16.5 Crore   Improvement in Quality of Life    Rs. 11 Crore   Endowment Fund        Rs. 10 Crore   Facilities for Fishing Village     Rs. 2 Crore   Industrial Training Institute     Rs. 1.5 Crore  

o Around Rs. 3 Crore (Recurring)  Rs. 2 Crore for Environment Protection  Rs. 1 Crore for other expenses like salaries etc. 

 The  Area  Development  and  Corporate  Social  Responsibility  Activities  have  been elucidated separately in the CSR Report.