system safety program (ssp-task 100) establishing the foundation of a systematic process

60
System Safety Program System Safety Program (SSP-Task 100) (SSP-Task 100) Establishing the Establishing the foundation of a foundation of a systematic process systematic process

Upload: francis-flynn

Post on 23-Dec-2015

217 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

System Safety ProgramSystem Safety Program(SSP-Task 100) (SSP-Task 100)

Establishing the foundation of a Establishing the foundation of a systematic process systematic process

Page 2: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Managements ResponsibilityManagements Responsibility

Plan, Organize, and Implement an effective System Plan, Organize, and Implement an effective System Safety Program Safety Program Integrate System Safety into all phases of the life cycleIntegrate System Safety into all phases of the life cycle Planned approach to task accomplishmentPlanned approach to task accomplishment

Responsibilities and Functions clearly definedResponsibilities and Functions clearly defined Establish a safety organization and provide qualified safety Establish a safety organization and provide qualified safety

personnelpersonnel Assurances (Accountability) that safety recommendations Assurances (Accountability) that safety recommendations

will be reconciledwill be reconciled Compliance insured by a System Safety Program Plan Compliance insured by a System Safety Program Plan

(SSPP) – A contractual requirement (SSPP) – A contractual requirement

Page 3: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

System Safety Program PlanSystem Safety Program Plan(SSPP – Task 101)(SSPP – Task 101)

““Fail to plan and you plan to fail”Fail to plan and you plan to fail”

Page 4: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

SSPP ObjectivesSSPP Objectives

Brief description of the proposed systemBrief description of the proposed system May be speculative during initial program plan May be speculative during initial program plan

preparationpreparation Defines systematic approach that will insure:Defines systematic approach that will insure:

Safe design consistent with system requirementsSafe design consistent with system requirements Timely deliveryTimely delivery Cost-effective mannerCost-effective manner

Page 5: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

SSPP Objective (cont)SSPP Objective (cont)

Hazards are identified, evaluated, eliminated or Hazards are identified, evaluated, eliminated or controlled to an acceptable level throughout LCcontrolled to an acceptable level throughout LC

Minimum risk is involved in design, testing, Minimum risk is involved in design, testing, productionproduction

Supporting safety data from other systems are Supporting safety data from other systems are consideredconsidered

Retrofit/Change to improve safety minimizedRetrofit/Change to improve safety minimized Operational safety and maintainability Operational safety and maintainability

demonstrateddemonstrated System termination established with clear methods System termination established with clear methods

and procedures and procedures

Page 6: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

System Safety Working GroupSystem Safety Working Group(SSWG – Task 104)(SSWG – Task 104)

Multi-disciplinary teamMulti-disciplinary team Normally comprised of:Normally comprised of:

Project ManagersProject Managers Design EngineersDesign Engineers Safety EngineersSafety Engineers End Users (customer)End Users (customer)

Project Management provides overall direction and Project Management provides overall direction and decision-making authoritydecision-making authority

Project Manager is chairman of the SSWG and Project Manager is chairman of the SSWG and provides liaison with higher levels of managementprovides liaison with higher levels of management

Page 7: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Excellent Example of SSPPExcellent Example of SSPP

MIL-STD 882DMIL-STD 882D

Page 8: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hazard Tracking and Risk Hazard Tracking and Risk Resolution (Task 105)Resolution (Task 105)

Establish and maintain a single closed-loop Establish and maintain a single closed-loop tracking systemtracking system

Define methods to identify, document , and Define methods to identify, document , and track hazards – establish an audit trailtrack hazards – establish an audit trail

Deliver a “Hazard Log” as part of Deliver a “Hazard Log” as part of engineering reportsengineering reports

Page 9: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hazard IdentificationHazard Identification

Page 10: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Systematic ProcessesSystematic Processes

1. HazardIdentification

2. RiskAssessment

3. Analyze Risk Control

Measures

4. Risk Controls

5. ImplementRisk Controls

6. Follow Through &

Review

1. HazardIdentification

2. RiskAssessment

3. Analyze Risk Control

Measures

4. Risk Controls

5. ImplementRisk Controls

6. Follow Through &

Review

Page 11: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

What Constitutes a Hazard?What Constitutes a Hazard?

A real or potential condition that, when A real or potential condition that, when activated, can transform into a series of activated, can transform into a series of

interrelated events that result in damage to interrelated events that result in damage to equipment or property and or injury to equipment or property and or injury to

people. people.

Page 12: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Find the HazardsFind the Hazards

Page 13: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Safety Managers ViewSafety Managers View HazardHazard

An implied threat or danger, a potential An implied threat or danger, a potential condition waiting to become a losscondition waiting to become a loss

StimulusStimulus Required to initiate action from potential to Required to initiate action from potential to

kinetickinetic May be a:May be a:

Component out of toleranceComponent out of tolerance Maintenance failureMaintenance failure Operator failureOperator failure Any combination of other events and conditionsAny combination of other events and conditions

Page 14: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

When Do We Look for When Do We Look for Hazards?Hazards?

The 5 Common Phases of a Systems Life The 5 Common Phases of a Systems Life CycleCycle Conceptual - ResearchConceptual - Research Design (Validation & Verification)Design (Validation & Verification) Development (Full-scale engineering & Development (Full-scale engineering &

production)production) Operational DeploymentOperational Deployment Termination & DisposalTermination & Disposal

Page 15: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Primary ObjectivePrimary Objective

The first major undertakings of a systematic The first major undertakings of a systematic safety effort must be to identify, analyze and safety effort must be to identify, analyze and control hazardscontrol hazards

Review operational goals, objectives & constraints Review operational goals, objectives & constraints – “Before the fact” process– “Before the fact” process Resources (people, time & money) must be consideredResources (people, time & money) must be considered

Preliminary Hazard List (PHL) developed by Preliminary Hazard List (PHL) developed by experts from multiple areas of expertise experts from multiple areas of expertise

Page 16: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

PHL PurposePHL Purpose

The SSPP will seek this inputThe SSPP will seek this input List of hazards prepared and analyzed List of hazards prepared and analyzed

during the concept/definition phase (PHA)during the concept/definition phase (PHA) Handoff to System Safety Hazard Analysis Handoff to System Safety Hazard Analysis

(SSHA) effort(SSHA) effort Update list as the system matures and Update list as the system matures and

changeschanges

Page 17: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

PHA PurposePHA Purpose

Identify and evaluate hazardsIdentify and evaluate hazards EliminateEliminate MitigateMitigate

Identify need to control those which can’t Identify need to control those which can’t be eliminatedbe eliminated Determine & Establish severityDetermine & Establish severity

System Safety personnel should be prepared System Safety personnel should be prepared to compete with other prioritiesto compete with other priorities Cost, Performance, Schedule, etc.Cost, Performance, Schedule, etc.

Page 18: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hazard SeverityHazard Severity

A key factor in establishing a common A key factor in establishing a common understanding of a safety programs goalunderstanding of a safety programs goal

MIL-STD 882 suggests four categoriesMIL-STD 882 suggests four categories Cat 1: CatastrophicCat 1: Catastrophic Cat 2: CriticalCat 2: Critical Cat 3: MarginalCat 3: Marginal Cat 4: Negligible Cat 4: Negligible

Page 19: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Category DefinitionsCategory Definitions

CatastrophicCatastrophic Death or total system lossDeath or total system loss

CriticalCritical Severe injury, illness or major system damageSevere injury, illness or major system damage

MarginalMarginal Minor Injury or system damageMinor Injury or system damage

NegligibleNegligible Less than minor injury or system damageLess than minor injury or system damage

Page 20: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Analysis of the System TaskingAnalysis of the System Tasking

SSWG efforts would focus on the most SSWG efforts would focus on the most critical components of the mission critical components of the mission

Expert review of:Expert review of: Mission statementMission statement Previous accident/incident reportsPrevious accident/incident reports Operator reportsOperator reports All available historical dataAll available historical data

Page 21: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

3 Basic Sources of Historical 3 Basic Sources of Historical Information Information

Expert Opinion (published & peer Expert Opinion (published & peer reviewed) reviewed)

Traditional Techniques (Inspections, Traditional Techniques (Inspections, Mishap Reports, Interviews, Audits)Mishap Reports, Interviews, Audits)

Previously developed Hazard Analysis Previously developed Hazard Analysis Tools (PHL’s and PHA’s)Tools (PHL’s and PHA’s)

Page 22: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Other Available SourcesOther Available Sources

Operational “Front Line” personnelOperational “Front Line” personnel An existing data base of “lessons learned”An existing data base of “lessons learned” An accident/incident (mishap) report fileAn accident/incident (mishap) report file An outside agency reviewAn outside agency review A previous self critical safety reviewA previous self critical safety review OSHA reportsOSHA reports EPA (HAZMAT) reportsEPA (HAZMAT) reports

Page 23: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

List the HazardsList the Hazards

PHL reviewed & developedPHL reviewed & developed Preliminary Hazard Analysis (PHA) is the Preliminary Hazard Analysis (PHA) is the

initial look at the entire system initial look at the entire system PHA may be used in lieu of a PHLPHA may be used in lieu of a PHL As systems and sub-systems are developed As systems and sub-systems are developed

a more detailed Systems Hazard Analysis a more detailed Systems Hazard Analysis (SHA or SSHA) will provide more detailed (SHA or SSHA) will provide more detailed risk assessment informationrisk assessment information

Page 24: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hazard Analysis MethodsHazard Analysis Methods

Failure Modes & Effects Analysis (FMEA)Failure Modes & Effects Analysis (FMEA) Systematic look at hardware piece by pieceSystematic look at hardware piece by piece Review of how each component could failReview of how each component could fail Considers how a failure effects other Considers how a failure effects other

components, sub-systems and systems as a components, sub-systems and systems as a whole whole

Risk assessment accomplished (severity & Risk assessment accomplished (severity & probability)probability)

Risk Assessment Code (RAC) assigned Risk Assessment Code (RAC) assigned

Page 25: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hazard Analysis Methods Hazard Analysis Methods

Fault Tree Analysis (FTA)Fault Tree Analysis (FTA) Detailed review of a specific undesirable eventDetailed review of a specific undesirable event Deductive in natureDeductive in nature Top-down effortTop-down effort Normally reserved for critical failures or Normally reserved for critical failures or

mishapsmishaps

May be qualitative or quantitativeMay be qualitative or quantitative

Page 26: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Risk Assessment Code’sRisk Assessment Code’s The effort in System Safety is to provide The effort in System Safety is to provide

accurate, meaningful analysis of hazardsaccurate, meaningful analysis of hazards Objective review of useful data should promote Objective review of useful data should promote

enlightened choices by decision makers enlightened choices by decision makers Data – Information – KnowledgeData – Information – Knowledge

The RAC is used to prioritize hazards and The RAC is used to prioritize hazards and determine acceptabilitydetermine acceptability

The quality of the RAC determines the The quality of the RAC determines the credibility of the system safety effortcredibility of the system safety effort

Page 27: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

MIL-STD 882 Risk MIL-STD 882 Risk Acceptance CriteriaAcceptance Criteria

RAC –1 UnacceptableRAC –1 Unacceptable RAC - 2 UndesirableRAC - 2 Undesirable RAC – 3 Acceptable with controlsRAC – 3 Acceptable with controls RAC – 4 AcceptableRAC – 4 Acceptable

Page 28: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hazard Analysis MethodsHazard Analysis Methods

Operating Hazard Analysis (OHA)Operating Hazard Analysis (OHA) Also known as Operating & Support Hazard Analysis Also known as Operating & Support Hazard Analysis

(O&SHA)(O&SHA) ““What if” tool brings user into the loop What if” tool brings user into the loop

Integrates people and procedures into the systemIntegrates people and procedures into the system Diagrams the flow or sequence of eventsDiagrams the flow or sequence of events

Project Evaluation Tree (PET) may be used for Project Evaluation Tree (PET) may be used for OHA accomplishmentOHA accomplishment Systematic evaluation of man, machine, & proceduresSystematic evaluation of man, machine, & procedures

Page 29: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hazard Analysis LogicHazard Analysis Logic

Inductive ReasoningInductive Reasoning Bottom Up Review --Asks “What if?”Bottom Up Review --Asks “What if?” PHA, SSHA, FMEAPHA, SSHA, FMEA

Deductive ReasoningDeductive Reasoning Top Down Review Asks “How can?”Top Down Review Asks “How can?” SHA, FTASHA, FTA

Intuitive-ExperientialIntuitive-Experiential Based on historical experience Based on historical experience Lessons Learned and/or Change Analysis Lessons Learned and/or Change Analysis

Composite Composite Combination of all (systems approach)Combination of all (systems approach)

Page 30: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

The Tool BoxThe Tool Box

Preliminary Hazard Analysis (PHA)Preliminary Hazard Analysis (PHA) Concept PhaseConcept Phase

Sub-System Hazard Analysis (SHA)Sub-System Hazard Analysis (SHA) Design and Development Phase Design and Development Phase

System Hazard Analysis (SSHA)System Hazard Analysis (SSHA) Design, Development and early Operations PhaseDesign, Development and early Operations Phase

Operating & Support Hazard Analysis Operating & Support Hazard Analysis (O&SHA)(O&SHA) Operations and DisposalOperations and Disposal

Page 31: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

More Hazard Identification More Hazard Identification ToolsTools

The 5 M model helps the SSWG to The 5 M model helps the SSWG to systematically review the interrelationships systematically review the interrelationships of the various composites in a system and of the various composites in a system and their interacting mishap causal factorstheir interacting mishap causal factors

Brainstorming or “what if” session with Brainstorming or “what if” session with operational personnel provides valuable operational personnel provides valuable insight and lessons learned that may or may insight and lessons learned that may or may not be part of the historical datanot be part of the historical data

Page 32: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

MachineMachine MediumMedium

ManMan

MissionMission

ManagementManagement

5 M model5 M model

Page 33: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Man Man

Page 34: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Man as a Root CauseMan as a Root Cause

Generally accepted to be causal in 70-80% Generally accepted to be causal in 70-80% of mishapsof mishaps Incident review should question: “Is he Incident review should question: “Is he

involved or did he induce?”involved or did he induce?”

Areas to considerAreas to consider Selection: Is he capable?Selection: Is he capable? Training: Does he understand?Training: Does he understand? Motivation: Does he care?Motivation: Does he care?

Page 35: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

HFAC’s HFAC’s

Efforts to integrate human factors into Efforts to integrate human factors into safety designs focus on 4 specific areas:safety designs focus on 4 specific areas: Behavioral StereotypesBehavioral Stereotypes Human EngineeringHuman Engineering Man-Machine Interface (& Tradeoffs)Man-Machine Interface (& Tradeoffs) Misuse AnalysisMisuse Analysis

Page 36: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Behavioral StereotypesBehavioral Stereotypes

Habit patterns compel us to act in a Habit patterns compel us to act in a predictable mannerpredictable manner

Learned behavior varies by groupsLearned behavior varies by groups Law of PrimacyLaw of Primacy Designs that do not consider the users Designs that do not consider the users

behavior patterns may be behavior patterns may be ERROR-ERROR-INDUCINGINDUCING

Page 37: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Error-Inducing ExemplarError-Inducing Exemplar(Have you driven a Ford lately?)(Have you driven a Ford lately?)

First vehicle you drove most likely had the First vehicle you drove most likely had the horn activated by pushing in the middle of horn activated by pushing in the middle of the steering wheelthe steering wheel

Ford Motor Company design co-located Ford Motor Company design co-located horn switch on the turn signal leverhorn switch on the turn signal lever

In a time compressed situation most In a time compressed situation most operators push the center of the wheel operators push the center of the wheel looking for a horn if neededlooking for a horn if needed

Page 38: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

QUESTION ???QUESTION ???

Would an accident that occurred as a result of Would an accident that occurred as a result of a GM owner/driver failing to alert someone a GM owner/driver failing to alert someone

to an upcoming conflict because they to an upcoming conflict because they fumbled unsuccessfully to activate a horn on fumbled unsuccessfully to activate a horn on

a Ford they were using be an operator a Ford they were using be an operator involvedinvolved or or inducedinduced error? error?

Page 39: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Human EngineeringHuman Engineering

Ergonomics are the most developed human Ergonomics are the most developed human performance disciplineperformance discipline

Range and motion of equipment designed Range and motion of equipment designed for “average man”for “average man” A compromise for majority of operators A compromise for majority of operators

MIL-STD-1472DMIL-STD-1472D Basic human design criteria standardsBasic human design criteria standards

Page 40: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Man-Machine InterfaceMan-Machine Interface

Not to be confused with physical interfaceNot to be confused with physical interface Functional control – “whose got it?”Functional control – “whose got it?”

Human (manual) control with automated Human (manual) control with automated response should certain conditions be presentresponse should certain conditions be present

Automated controls with human monitors Automated controls with human monitors

Optimizing the system to do what each does Optimizing the system to do what each does best is the challenge in designbest is the challenge in design

Page 41: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Who Does What Best ???Who Does What Best ???

Page 42: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Misuse Analysis:Misuse Analysis:AKA Corollaries to Murphy’s LawAKA Corollaries to Murphy’s Law

““What can be used will be misused”What can be used will be misused” Future Darwin Award winners epitaphFuture Darwin Award winners epitaph

““New systems generate new problems” New systems generate new problems” SSWG should systematically review “what-why” SSWG should systematically review “what-why”

relationships to ID potential hazardsrelationships to ID potential hazards

Proper analysis of information and Proper analysis of information and implementation of controls demonstrate implementation of controls demonstrate Due DiligenceDue Diligence on behalf of managementon behalf of management

Page 43: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Are Humans a Hazard?Are Humans a Hazard? Human life support requirements are fairly Human life support requirements are fairly

intolerant of variation: intolerant of variation: Environmental factors must be maintained within a Environmental factors must be maintained within a

fairly narrow set of parametersfairly narrow set of parameters Lack of a temperate climate, light, soundproofing and Lack of a temperate climate, light, soundproofing and

other “creature comforts”can induce psychological and other “creature comforts”can induce psychological and physiological stress thus causing errorsphysiological stress thus causing errors

Human capabilities are relatively static compared Human capabilities are relatively static compared to machinesto machines

Machine capabilities continue to expand at high Machine capabilities continue to expand at high ratesrates

Page 44: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Compensating for Human ErrorCompensating for Human Error

Error-TolerantError-Tolerant designs are necessary to designs are necessary to mitigate known human deficienciesmitigate known human deficiencies Frequency of errors generally known by Frequency of errors generally known by

situationsituation Consider how your design comparesConsider how your design compares

Rates expressed in events per number of Rates expressed in events per number of exposures or task accomplishmentsexposures or task accomplishments

Upper limit of unaided human performance is Upper limit of unaided human performance is one error for every 100,000 attemptsone error for every 100,000 attempts

Page 45: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

MachinesMachines

Page 46: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Machine as a Root CauseMachine as a Root Cause

System safety process analyzes each System safety process analyzes each component and operational procedure for it’s component and operational procedure for it’s hazard contributionhazard contribution Poor designPoor design Inadequate operating proceduresInadequate operating procedures Ill defined limitationsIll defined limitations Improper MaintenanceImproper Maintenance

Known component hazards as well as Design-Known component hazards as well as Design-Induced maintenance and personnel errors are Induced maintenance and personnel errors are part of the hazard identification processpart of the hazard identification process

Page 47: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hierarchy of Hardware Terms Hierarchy of Hardware Terms SystemSystem

Sub-SystemSub-System AssembliesAssemblies Sub-assembliesSub-assemblies ComponentComponent

Interconnected to perform a specific Interconnected to perform a specific functionfunction

Interaction creates a series of logical and Interaction creates a series of logical and sequential outputssequential outputs

Page 48: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

MediumMedium

Page 49: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Medium as a Root causeMedium as a Root cause System safety processes should analyze each System safety processes should analyze each

component and their intended or potential component and their intended or potential interrelation with their operating environment for interrelation with their operating environment for hazardshazards

Natural “acts of God” -- A phenomena?Natural “acts of God” -- A phenomena? Temperature variationsTemperature variations Earth QuakeEarth Quake VolcanoVolcano HurricaneHurricane

Known environmental hazards as well as Design-Known environmental hazards as well as Design-Induced limitations should be part of the Hazard Induced limitations should be part of the Hazard ID processID process

Page 50: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Even with properly identified hazards someone Even with properly identified hazards someone may chose to operation outside design may chose to operation outside design limitations – That is a limitations – That is a gamblegamble at best at best

Page 51: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Managing Threats Managing Threats

Page 52: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Management as a Root CauseManagement as a Root Cause

Lack of genuine commitment to safetyLack of genuine commitment to safety Example: Failure to adequately resource a SSPExample: Failure to adequately resource a SSP

Failure to act on safety recommendationsFailure to act on safety recommendations Severity & Probability quibbling or gambling – Severity & Probability quibbling or gambling –

“Playing the Numbers game” “Playing the Numbers game” Inadequate SOP’sInadequate SOP’s

Poorly developed PHA through O&SHAPoorly developed PHA through O&SHA Poor standards and controlsPoor standards and controls

Inadequate design “wished” into operationInadequate design “wished” into operation

Page 53: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Murphy’s Law for Murphy’s Law for Management Management

Technology is dominated by Technology is dominated by those who manage what they those who manage what they

don’t understanddon’t understand

Page 54: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

The lowest temperature the system had previously experienced The lowest temperature the system had previously experienced was 53 degrees F and both the primary and secondary was 53 degrees F and both the primary and secondary

component had failed to function as designed. The predicted component had failed to function as designed. The predicted temperature for operation was approximately 26 degrees F. “…temperature for operation was approximately 26 degrees F. “…

data below 53 degree’s F was not available and [my] data below 53 degree’s F was not available and [my]

department could not prove it was unsafe to launch.”department could not prove it was unsafe to launch.”

Morton-Thiokol VP of Morton-Thiokol VP of Engineering, STS-51L Accident Engineering, STS-51L Accident

InvestigationInvestigation

1986 1986

Page 55: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

MissionMission

Page 56: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Mission as a Root CauseMission as a Root Cause Some missions are higher in riskSome missions are higher in risk

Combat RescueCombat Rescue Poorly developed or ill-conceived Poorly developed or ill-conceived

Operation Eagle ClawOperation Eagle Claw IncompatibilitiesIncompatibilities

Unfamiliar organizations combined to operate Unfamiliar organizations combined to operate in new and complex role with erroneous in new and complex role with erroneous assumptionsassumptions

Poorly defined Poorly defined Desert One (Now what?)Desert One (Now what?)

Page 57: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Predictable & Preventable Predictable & Preventable Mission ResultsMission Results

Page 58: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Senate TestimonySenate Testimony

The Commander of the operation blamed the helicopter The Commander of the operation blamed the helicopter pilots immediately after the mission. However, in his pilots immediately after the mission. However, in his

critique to the Senate Armed Services Committee, he later critique to the Senate Armed Services Committee, he later attributed the failure to Murphy's Law and the use of an ad attributed the failure to Murphy's Law and the use of an ad

hoc organization for such a difficult mission. hoc organization for such a difficult mission.

“We went out and found bits and pieces, people and We went out and found bits and pieces, people and equipment, brought them together occasionally, and equipment, brought them together occasionally, and

then asked them to perform a highly complex then asked them to perform a highly complex mission," he said. "The parts all performed, but mission," he said. "The parts all performed, but

they didn't necessarily perform as a teamthey didn't necessarily perform as a team."

Page 59: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Hazard ID -- First, Last and Always! Hazard ID -- First, Last and Always! (Because what you don’t know can hurt you)(Because what you don’t know can hurt you)

1. HazardIdentification

2. RiskAssessment

3. Analyze Risk Control

Measures

4. Risk Controls

5. ImplementRisk Controls

6. Follow Through &

Review

Page 60: System Safety Program (SSP-Task 100) Establishing the foundation of a systematic process

Pitts’ Premise (PP) #1 Pitts’ Premise (PP) #1 “No matter how good it might look -- Sometimes it “No matter how good it might look -- Sometimes it just doesn’t pay to be on the ground floor of a new just doesn’t pay to be on the ground floor of a new

design”design”

Murphy’s New & Murphy’s New & Improved Two Story Improved Two Story

OuthouseOuthouse