system 360™ total fluids management™...
TRANSCRIPT
![Page 1: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/1.jpg)
Introduction:
Minera Hampton Peru SAC (a wholly owned subsidiary of METMINCO Limited) is currently undertaking a resource definition drilling program on its Los Calatos Cu-Mo Project located in
the Department of Moquegua, 70 km southeast of the regional city of Arequipa in southern
Peru. In 2009, Minera Hampton continued their coring programs on the project and in late
2011, AK Drilling International, SA received a coring contract with the specific goals of reduc-
ing industrial water consumption and disposal of fluids on the project. Los Calatos is located
in an area defined as being subtropical montane perarid desert at altitudes ranging from
2500 to 3000 meters above sea level, which presents challenges in supplying adequate in-
dustrial water to the exploration drills working at the site. Water must be transported by truck
from the city of Moquegua, located approximately 65 km from the project. All but 10 km of
the road is a rough gravel road. Round trip time for each load of water hauled by a truck is
approximately 4 hours.
Project Scope:
AK Drilling International approached Baroid IDP with the idea of using the SYSTEM 360™
unit with an engineered fluid to address the water consumption and disposal issues and opti-
mize the drilling operations.
Before using the SYSTEM 360™ unit, rigs at Los Calatos had been consuming
an average of 13,000 gallons of water per rig, per day. Several water trucks were
needed to supply the program. With the drill program expanding, water supply
and mud disposal became important issues.
Each water truck must make a round trip of 130 km to supply 6000 gallons of wa-
ter to the drill sites. There are restrictions on nighttime driving, so each truck can
only make two (4 hour) round trips per day.
Because of rapid incorporation of fine pyritic drilled solids in the drilling fluids, ad-
ditives were needed to treat high solids in muds, thereby, increasing costs. Used
fluids were disposed of in large settling ponds for evaporation. Large volume mud
systems were accepted as normal and fluid disposal rates were high.
Water costs were in excess of $50.00 USD per drilled meter. Water supply logis-
tics, road maintenance, drilling fluid disposal and sump construction all contribut-
ed to high drilling program costs.
SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEM
Total Solution Baroid Industrial Drilling Products
![Page 2: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/2.jpg)
HOW THE SYSTEM 360™ UNIT WORKS
The SYSTEM 360™ Total Fluid Management™ system consists of a highly efficient mud mix-
ing system coupled with a patent-pending flocculent additive process which concentrates and
removes the solids from spent drilling fluid on a core rig. Removal of these fine solids allows
for the re-use of a fluid that would normally be discarded. The SYSTEM 360 unit removes the
solids from the drilling fluid with hydrocyclones and mixes SYSTEM FLOC-360® flocculent with
the solids concentrated slurry from the bottom of the cones. This mixing chamber is where
flocculation occurs. This flocculation creates cross-linked structures in the fluid containing the
solids which can be quickly separated from the water phase in the filter bags mounted on the
unit. (Figure 1)
Cleaned drilling fluid is directed back to the active circulating system when the mud weight is
reduced to less than 8.6 lbs/gallon, while the flocculated mixture containing the drilled solids is
discharged into a filter bag rack where water and flocs are separated. Water generated in this
final filtration step can be returned to the mixing tank to mix new drilling fluid. (Figure 2)
IDP Solution
Flocs discharged from mixing box on the SYSTEM 360™ unit. Water is breaking out of the flocs.
Figure 1
Total Solution Baroid Industrial Drilling Products
![Page 3: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/3.jpg)
WHAT IS SYSTEM FLOC-360® flocculent?
SYSTEM FLOC-360® aqueous polymeric flocculent causes rapid flocculation of the drilled
solids that have been exposed to PHPA polymer in the drilling fluid during the drilling pro-
cess. The mixing of SYSTEM FLOC-360® flocculent with the fluid occurs within the
SYSTEM 360™ solids separation unit. Once the flocculation of drilled solids and PHPA pol-
ymer occurs, flocs are produced, which are separated from the liquid phase in the filter
bags. The flocs are easily disposed of in a semi-solid form using the bagging feature on the
SYSTEM 360 unit.
IDP Solution
Solids handling unit. Mixing/pumping unit
Figure 2
Total Solution Baroid Industrial Drilling Products
![Page 4: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/4.jpg)
HOW SYSTEM 360™ SOLIDS SEPARATION UNIT WAS USED FOR THE PROJECT
Usage is very simple:
1. Pump approximately 900 liters (240 gallons) of dirty mud into the mixing tank of the
SYSTEM 360™ unit. With a mud balance, determine the fluid density of the fluid to be
cleaned. (Figure 3)
2. If not already present in the drilling fluid, add EZ-MUD® GOLD polymer to the fluid to be
treated at a concentration of approximately 1 kilo/ 900 liters of drilling fluid (~2 lbs/240 gal-
lons) using the mixer of the SYSTEM 360 unit.
3. Fill the flocculent additive barrel on the SYSTEM 360 unit to the “Full” mark with fresh water
and add 1 liter of SYSTEM FLOC-360® mixture to each full drum of water.
4. Start the injector pump for the SYSTEM FLOC-360® mixture and set the discharge pressure
at 8-10 PSI. Direct the main pump flow from the mixing tank to the hydrocyclones. The drill-
ing fluid must enter the hydrocyclones with a pressure of 32-40 PSI. Verify this by checking
the pressure gauge mounted on the hydrocyclones.(Figure 4)
IDP Solution
System 360 solids control unit
Figure 3
Hydrocyclones discharging concentrated solids
Figure 4
Total Solution Baroid Industrial Drilling Products
![Page 5: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/5.jpg)
DESCRIPTION OF THE WORK PERFORMED
The SYSTEM 360 unit was run from the surface to the total depth (TD) on a particular drill
hole. The SYSTEM 360 unit was used to mix all mud on the site. Coring began at the sur-
face, and the hole was drilled HQ mm in diameter from the surface to 1137.55 m where the
hole reached TD.
The drill rigs were equipped with volumetric water flow meters to quantify the
amount of water used.
Los Calatos project comprises a multi-phase porphyry system, brecciated and cut by vertical
dikes. There are hard compact sections with some fracturing accompanied by high amounts
of pyrite in some sections. Other sections are altered (potassic, quartz sericite, propyllitic and
argillic alteration) with brecciated clasts with rock flour and clays as matrix. (Figure 5). The
characteristics of the drilling fluid were designed to match the type of ground conditions en-
countered at the site. The mud mixture consisted of engineered ratios of QUIK-GEL® GOLD,
QUIK-TROL® GOLD LV, EZ-MUD® GOLD and EZ-MUD® DP additives. The make-up water
that was being delivered to the site had a very high hardness level (magnesium ~800 ppm), so
before any additives were mixed, it was necessary to treat the water by adding a diluted caus-
tic soda solution. The solution precipitated divalent ions present in the water to reduce total
hardness to less than 150 ppm.
IDP Solution Continued:
Examples of competent sections of drill core on Los Calatos Project
Figure 5
Total Solution Baroid Industrial Drilling Products
![Page 6: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/6.jpg)
The newly mixed drilling fluid was weighed with a FANN® mud balance and had an average
density of 8.45 lbs / gal. Returns from the hole were also weighed using the mud balance.
When the mud density reached 8.7 lbs / gallon, the SYSTEM 360 unit was used to treat
batches of the drilling fluid in order to remove solids and lower the mud weight to approxi-
mately 8.6 lbs/gallon. (Figure 6)
To treat each batch, approximately 900 liters of spent drilling fluid was pumped into the
SYSTEM 360 mixing tank. To this tank, 1 kilogram of EZ-MUD® GOLD polymer was added.
Then, the fluid was diverted to the hydrocyclones. Slurry from the bottom of the hydrocy-
clones was sent to the mixing box where the flocculent was introduced. Flocs were formed
immediately, and discharged along with the water phase into the filter bags. Clean water
drained from the filter bags into the tank located at the bottom of the SYSTEM 360 unit.
IDP Solution Continued
Mixing tank with dirty mud being processed using the SYSTEM 360 unit.
Figure 6
Total Solution Baroid Industrial Drilling Products
![Page 7: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/7.jpg)
Filter bag rack and bag press on the SYSTEM 360 unit. The
press is used to squeeze water from the filter bags.
Figure 7
Solids separated using the SYSTEM 360 unit during the
drilling of the hole at the Los Calatos Cu-Mo Project.
Figure 8
During the process of removing the drilled solids, the density of the drilling fluid being cycled
through the unit was monitored in the processing/mixing tank using a FANN® mud balance.
When the density was reduced to 8.6 lbs/gallon, a diverter valve on the SYSTEM 360 unit
was opened and the cleaned drilling fluid was pumped to the suction tank of the active circu-
lating system.
Once the water had drained from the filter bags, the solids were dumped on site to be
cleaned up later, which allowed the bags to be re-used several times.
IDP Solution Continued
Total Solution Baroid Industrial Drilling Products
![Page 8: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/8.jpg)
Of the 900 liters of drilling fluid used, approximately 400 liters of clean water was generated; the
remainder of the fluid (cleaned mud with a density less than 8.6 lbs / gallon) was discharged to
the suction tank in the active circulating system. (Figure 9)
During the drilling of the hole, the drill rig used approximately 8000 liters of water per shift (an
average of 22 meters of drilling per shift), with a recovery of approximately 3600 liters of clean
water (45%) and approximately 2650 liters of cleaned drilling fluid returned to the system, per
shift (33%). (Chart 1 and 2)
The following data was generated during the drilling of the specific hole:
Results
Water filtering into lower tank. Solids being dumped from bag.
Figure 9
Fluid Treated
(Ltrs.)
Water Recovered
(Ltrs.)
Fluid improved returned to system for drill
(Ltrs.)
416,000 187,200 137,800
Chart 1: Drilled from surface to 1,137 m. (52 shifts worked)
Total Solution Baroid Industrial Drilling Products
![Page 9: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/9.jpg)
Chart 2:
A total of 72,514 gallons of water were used during the 26 days of drilling the hole, an
average of 2,789 gallons per day.
Total water consumption was reduced by 78.5 %.
Total water savings on this hole was approximately 265,486 gallons. With each water truck hav-
ing a capacity of 6000 gallons, this equates to avoiding 44 water truck trips during the drilling of
this hole.
Drilling fluid additive usage was reduced and the drilling was completed ahead of schedule.
Training the AK Drilling International crews was accomplished in one week by Baroid IDP person-
nel.
While drilling the hole, heavy rainstorms washed out 14 kilometers of the access road to Los Ca-
latos project, which prevented any water trucks from traveling to the project for 10 days. During
that time, AK Drilling International personnel pumped spent drilling fluids out of sumps on previous
drill sites at Los Calatos and used the SYSTEM 360 unit to separate solids from the fluids and re-
covered make-up water and usable drilling fluids. This allowed drilling to proceed without inter-
ruption even though there was no fresh water available on site for drilling. Another drilling contrac-
tor had to shut their drills down during this time.
Results Continued
Water consumption prior to
using SYSTEM 360 solids
control unit, per rig.
(Gallons/Day)
Water used when running
the SYSTEM 360 solids
control unit.
(Gallons/Day)
Total saving of water using
SYSTEM 360 unit.
(Gallons/Day)
13,000 2,789 10,211
Total Solution Baroid Industrial Drilling Products
![Page 10: SYSTEM 360™ TOTAL FLUIDS MANAGEMENT™ SYSTEMfiles.ctctcdn.com/5661b393201/2d8b4a5e-9ad6-4566-96a1-cc5a4502753c.pdf2. If not already present in the drilling fluid, add EZ-MUD® GOLD](https://reader034.vdocuments.us/reader034/viewer/2022042017/5e756326be844a460746d92f/html5/thumbnails/10.jpg)
Use of the SYSTEM 360 unit reduced water usage by almost 80%.
Safety was enhanced by the substantial reduction of water hauls and truck time.
Drill sump size was reduced by 90%. (Figure 10)
No stuck tubes or broken wire lines have occurred at Los Calatos since the SYSTEM 360 unit
has been in use. This indicates a cleaner fluid with less solids to centrifuge inside the rods and
tube heads.
Water separated by the SYSTEM 360 unit can be re-used for the preparation of new drilling fluid.
Because the SYSTEM 360 unit effectively removes fine clays from a drilling fluid, the amount of
additives necessary to maintain a mud system is greatly reduced.
Drill crews were easily trained to use the system.
Economic Value Created
A drill pad at Los Calatos on an 1100
meter hole before implementation of the
SYSTEM 360 unit.
Sump size on a 1900 meter hole using the
SYSTEM 360 unit to remove solids. Approxi-
mately 4 meters by 5 meters.
Figure 10: Sump size comparison
© 2012 Halliburton. All rights reserved. Sales of Halliburton products and services will be in accord solely with the terms and conditions contained in
the contract between Halliburton and the customer that is applicable to the sale.
Total Solution Baroid Industrial Drilling Products