symposium 2016 : conf. 401 jonathan shriqui evm: go beyond the numbers

51
1 EVM: Go Beyond the Numbers Jonathan Shriqui, PMP

Upload: pmi-montreal

Post on 17-Jan-2017

199 views

Category:

Data & Analytics


0 download

TRANSCRIPT

Page 1: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

1

EVM: Go Beyond the Numbers

Jonathan Shriqui, PMP

Page 2: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

2

Page 3: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

3

WHAT IS THE PURPOSE OF EVM?

To establish a common standard of project performance measurement & stakeholder

management, regardless of program size or industry.

To provide early warning signs of deviation from plan.

Page 4: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

4

WHAT IS EVM?

Not a single processGrouping of 32 guidelines (EIA-748-C)Management technique:• Establish a time phased budget of the SOW• Captures the progression of work• Provide reliable & timely information for

project management analysis & actions

Page 5: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

5

3 Key components to EVMPMI Talent Triangle:

LeadershipStrategic and Business

Management Technical Project

Management

Page 6: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

6

Role of Leadership with EVM

Leadership is the foundation of EVM:Set the organizational toneFosters a culture of EVMTailors business process to support EVMUtilizes EVM info to support leadership

decisions

Page 7: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

7

EVM Challenges to Leadership

Leadership must accept that EVM:May be lengthy to implementRequires tools & trainingMay be process heavyRequires a business rhythm Acceptance that EVM requires TIME.

Page 8: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

8

EVM Benefits to Leadership

Leadership should receive the following benefits:Provide early warning signs of potential

project issuesIntegration of scope, schedule & costCredibility of program controlStakeholder CommunicationEnhanced Risk Management

Page 9: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

9

Strategic and Business Management

Business MaturityBusiness OperationsCustomer Relationship

Page 10: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

10

Strategic & Business Management

Business Maturity • Capability Maturity Model Integration• CMMI Rating from 1 to 5

The CMMI principal is that “the quality of a system or product is highly influenced by the

process used to develop and maintain it”*

Page 11: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

11

Business Maturity

EVMS will most likely be effective

in a org. that reflects a CMMI rating of 3 or

above

Page 12: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

12

Strategic & Business ManagementBusiness Operations

- Reporting- Cash Flow Forecasting- Resource Forecasting- Risk Management

Page 13: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

13

Strategic & Business Management

Business Operations / Reporting• EVM Culture• EVM lingo & metrics in review meeting• EVM understood/used by senior management• EVM data should remain constant throughout the

various level of reporting

Page 14: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

14

Strategic & Business Management• Business Operation

- Cash Profiling- Resource Reqs.

Your ETC is yourForecast.

USE INPUT FROM YOUR CAMs.

Page 15: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

15

Strategic & Business Management• Business Operations / EVM &Risk Management

– Both work cohesively, not in silos

Mgmt Reserve > Risk Register + VACIf not, engage in stakeholder awareness

Page 16: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

16

Customer / Stakeholder Relationship

The outputs of EVM process (variance reporting) should be the source of data for stakeholder mgmtThe project is:

Over/under cost because…Late/ahead of schedule because…The key risks are…Our mitigation/enhancement plan is…

Program Control InstillsStakeholder Confidence

Page 17: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

17

Technical Project Management

EVM BasicsSmall Project

Page 18: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

18

Business world: “Cash Is King”

EVM world: “Schedule Is King”

A realistic, achievable & logical schedule is key with EVM

WHO IS KING?

Page 19: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

EVM 101

Time

Budget versus Actual

2D Project (Business) Management

$’s

Budget

Actual

Time Now

Under spent ?

BehindSchedule ?

$’s

3D Project Management

Time

Plan

Costs

Time Now

Budget versus Actual

Earned

Schedule

Cost

Page 20: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

7. Reporting- CAM reports (e.g. one page reports,

SWOT, SOFT)- Variance Reports (by exception)- Recovery Plans

2. Schedule- Work & Planning packages- Resource- Time-phased budget

1.Scope- Contract / SOW- WBS, OBS, RAM &

WBS Dictionary- Control Accounts

5. Costs- Booking / charge numbers- Actual costs / bookings

6. Analysis- Trend analysis- Variance analysis- TCPI, IEAC- Other PM analysis (e.g.

Critical Path Analysis)

8. Risk & Opportunity- Exposure (financial, schedule & performance)- Costed Mitigation / Realisation actions

9. Change- Change Requests- Change Log- Baseline

maintenance- Re-planning- Formal control of

scope & budget changes

4. Status Data (Progress) & Forecasts- Achievements (earned value)- Estimates to complete

3. EV “Engine”- PMB- Performance data- EVM reports (CPR1-5,

trends & SPA graph)

Page 21: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

21

Bathroom Renovation

Page 22: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

22

Our Budget - BACItem BAC

Flooring $1,600Vanity $1,900Shower $2,000Bathtub $1,500Total $7,000

Page 23: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

23

BCWSBudgeted Cost of Work Scheduled

23

The BCWS is your time phased BAC∑BCWS = BAC = YOUR DOLLARIZED PLAN

Week 1 Week 2 Week 3 BAC

Flooring $1,600 $1,600

Vanity $1,000 $900 $1,900

Shower $1,000 $1,000 $2,000

Bathtub $1,000 $500 $1,500

Period Total $2,600 $2,000 $2,400 $7,000

Page 24: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

24

BCWSBudgeted Cost of Work Scheduled – Week 1

Our PLAN is to perform $2,600 of defined scope in week 1.• Old Floor Removal = 6hrs @ 50$/h = $300• Purchase materials (tiles, grout, etc) = $500• Tile Installation = 16hrs @ 50$/h = $800• Purchase & delivery of bathtub = $1,000

$2,600 BCWS Week1

Page 25: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

25

ACWPActual Cost of Work Performed

ACTUAL cost of the EARNED scope.BAC:• Planned Direct Cost• Planned Indirect Cost• Planned Material Cost

No expenditures to unplanned scope

ACWP:• Actual Direct Cost• Actual Indirect Cost• Actual Materials Cost

Page 26: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

26

Our Cost – ACWP – Week 1BCWS W1 ACWP W1

Removal $300 VS $100

Material $500 VS $500

Installation $800 VS $700

Bathtub $1,000 VS $1,000

Period Total $2,600 VS $2,300

But what did we accomplish?

Page 27: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

27

BCWPBudgeted Cost of Work Performed

What did we “earn” in relation to our plan?What did we accomplish?What did we start/finish?

What is the status of the scope?

Page 28: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

28

What was accomplished in week 1?

Earned / Planned– Removal 100% completed – we earned $300/$300– Purchased 100% of materials – we earned $500/$500– Installed 25% of the tile – we earned $200/$800– Purchased & installed bathtub - we earned $1,500/ $1,000

$2,500/$2,600

BCWPBudgeted Cost of Work Performed – Week 1

Page 29: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

29

The key to good EV is proper “statusing”A realistic and achievable schedule Selecting appropriate EV Technique:• LOE, % complete, 50/50, Milestone, units complete,

apportioned (0-100, 50-50, 20-80, etc)

Be honest and objective!

BCWPBudgeted Cost of Work Performed

Page 30: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

30

SVP - S

SPIP / S

CVP - A

CPIP / A

$0 1.0 +$200 3.0

$0 1.0 $0 1.0

($600) 0.25 ($500) 0.28

+$500 1.5 +$500 1.5

($100) 0.96 +$200 1.09

BCWS W1

BCWP W1

ACWP W1

Removal $300 $300 $100

Material $500 $500 $500

Installation $800 $200 $700

Bathtub $1,000 $1,500 $1000

Period Total $2,600 $2,500 $2,300

EV Metrics – Week 1

SV = BCWP – BCWS SPI = BCWP/BCWSCV = BCWP – ACWP CPI = BCWP/ACWP

Page 31: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

Time Now

BCWS 100 100 100 100 100 100 100 100 BCWS 400

BCWP 0 400 0 0 0 0 0 0 BCWP 400SPI 1.0

BCWS 100 100 100 100 100 100 100 100 BCWS 400

BCWP 0 200 0 200 0 0 0 0 BCWP 400SPI 1.0

BCWS 100 100 100 100 100 100 100 100 BCWS 400

BCWP 100 100 100 100 0 0 0 0 BCWP 400SPI 1.0

“My SPI is 1.0, but my project is late!?”

Page 32: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

32

SPI, CPI, EAC, TCPI, iEAC, BEI, VAC, BAC, BCWR,

UB, MR, PMB, etc. So What? I need

information, not data!

Page 33: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

33

BCWS W1

BCWP W1

ACWP W1

Installation $800 $200 $700

SVP - S

SPIP / S

CVP - A

CPIP / A

($600) 0.25 ($500) 0.28

Why SV? Inspection determined that the grading of the existing subfloor was out of tolerance. Leveling of the subfloor

was required for proper tile installation. Why CV? Due to the unleveled subfloor, the purchase of self-leveling cement and extra labour was required to level subfloor.

Variance Analysis

Why SV?

Why CV?

Contracts Management

Page 34: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

34

BCWS W1

BCWP W1

ACWP W1

Installation $800 $200 $700

Impact AnalysisSV

P - SSPI

P / SCV

P - ACPI

P / A($600) 0.25 ($500) 0.28

Schedule Impact: Delays due to releveling the subfloor may affect the start date of the vanity installation. Tile installation is

now on the critical path.Cost Impact: Extra material and extra labour effort will

increase the estimate at complete (EAC). Will incur storage costs for the vanity (offsite) if floor is not finished on time.

Schedule Management

Supply Chain Management

Risk Management

Page 35: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

35

BCWS W1

BCWP W1

ACWP W1

Installation $800 $200 $700

SVP - S

SPIP / S

CVP - A

CPIP / A

($600) 0.25 ($500) 0.28

Schedule : Consider diverting resources to minimize schedule delays and getting off the critical path.

Cost: Recommend absorbing the cost of additional resources to avoid paying storage and transportation costs

Schedule Management

Cost Growth

Mitigation Plan

Page 36: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

36

Importance of CAM trainingCAM training & experience will affect the quality of: • Performance Assessment • Variance Analysis• Impact Analysis• Mitigation plans• Ultimately the data used influence the outcome.

Page 37: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

37

Lets go 15 years into the future…

Page 38: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

38

Vertical EV

38

$’000 BCWS BCWP ACWP Foundation $300 $300 $100

Framing $500 $500 $800

Electrical $800 $200 $700

Plumbing $1,000 $1,500 $1000

Period Total $2,600 $2,500 $2,600

SV SPI CV CPI$0 1.0 +$200 3.0

$0 1.0 $(300) 0.6

($600) 0.25 $(500) 0.28

+$500 1.5 +$500 1.5

($100) 0.96 $(100) 0.96

Labour $800 $400 $600

Material $600 $500 $400

Subcontract $1,200 $1,600 $1,600

Period Total $2,600 $2,500 $2,600

$(400) 0.5 $(200) 0.7

($100) 0.8 +$100 1.25

+$400 1.3 $0 1.0

($100) 0.96 $(100) 0.96

But my schedule is late!

Page 39: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

39

3939

Resources BCWS BCWP ACWP

Labour $800 $400 $600

Material $600 $500 $400

Subcontract $1,200 $1,600 $1,600

Period Total $2,600 $2,500 $2,600

SV SPI CV CPI

$(400) 0.5 $(200) 0.7

($100) 0.8 +$100 1.25

+$400 1.3 $0 1.0

($100) 0.96 $(100) 0.96

Vertical EV

LOE $400 $400 $500

Discrete $400 $0 $100

Period Total $800 $400 $600

$0 1.0 $(100) 0.7

($400) 0.0 $(100) 0.0

($100) 0.5 $(200) 0.7

Page 40: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

40

Horizontal EV

Date SPI

CUR - SPI 0.90

CUM - SPI 0.94

3 Month 0.856 Month 0.869 Month 0.89

• Trends without graph• Shifts in program momentum• Labour vs Material• Discrete Labour Only

𝟗𝒎𝒐𝒏𝒕𝒉𝑺𝑷𝑰= 𝑩𝑪𝑾𝑺𝒄𝒖𝒎−𝑩𝑪𝑾𝑺𝒄𝒖𝒎𝟗𝒎𝒐𝒏𝒕𝒉𝒔 𝒂𝒈𝒐

𝑩𝑪𝑾 𝑷𝒄𝒖𝒎−𝑩𝑪𝑾 𝑷𝒄𝒖𝒎𝟗𝒎𝒐𝒏𝒕𝒉𝒔𝒂𝒈𝒐

Page 41: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

41

Integrate them with:• Risk Management Strategy• Business’ Internal Processes• Forecasting Processes•Schedule/Baseline Management

EVM Outputs

Program Control

Earned Value Management System

Data EVMS Information

• Quantitative Data • SPI, CPI

• Qualitative Information• We were late because…• We spent more because…• Our mitigation plan is…

Page 42: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

42

EVM is NOT a quality tool!You must PLAN for quality WITHIN your project.

Page 43: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

43

Another 15 years later…

Page 44: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

44

EVMS: Contractual Requirement Customer

Contractor

Expectation of Program ControlCommon Knowledge & Lingo

Page 45: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

45

• Customer:• Ability to understand & assess

EVM data• Ability to conduct audit• Define your reporting reqs

(CDRL/SDRL)

EVMS: Contractual Requirement• Contractor:

– Ability to produce EVM data (CDRL/SDRL)

– Ready to be audited– Adhere to an EVM

culture / processes

Page 46: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

46

EVM SOWAn improper or too vague EVM SOW may result in an EVMS that is:- Contractually compliant- But has little or zero value added- May cause more “pain” than gain

Page 47: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

47

Refine your EVM SOW• EVMS that complies with a standard (EIA 748-C)

• % of LOE labour shall not be greater then X%• EVM as a SDRL to subcontractors• A task shall not have a duration longer then X days• Reporting shall be at the X level of the WBS or CA.• Expectation EVM analysis and recovery.

Page 48: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

48

Always remember…

Good decisions are based on knowledge and not on numbers.

- Plato

Page 49: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

49

For more information…

• Thank you for your participation today!

• For more information on the contents of this presentation, please feel free to contact me as follows:

o Jonathan Shriqui, PMPo [email protected] 613-255-6520o www.fleetech.com

Page 50: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

50

Time Permitting…

Page 51: Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers

EVM Practical Uses