![Page 1: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/1.jpg)
© Minewater BV 2012
Minewater 3.0
Sustainability Vision
Minewater Corporation Heerlen
The Netherlands
27 February 2013 Louis Hiddes ([email protected])
Director Mijnwater BV
![Page 2: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/2.jpg)
2
Minewater 3.0 Pilot project: Minewater 1.0
February 2014
HLN2
HLN1
HLN3
HH1
HH2
CBS
HHC
![Page 3: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/3.jpg)
3
HLN2
HLN1 HLN3
HH1
HH2
Minewater 3.0 Final situation
February 2014
Return well HLN3 out of order
Hot to Hot (HH2) Cold to Cold (HLN2)
Thot supply 28˚C Tcold supply 16˚C Thot return 28˚C Tcold return 16˚C
![Page 4: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/4.jpg)
4
HLN2
HLN1 HLN3
HH1
HH2
Minewater 3.0 Final situation
February 2014
All wells bidirectional
![Page 5: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/5.jpg)
5
HLN2
HLN1 HLN3
HH1
HH2
Minewater 3.0 Final situation
February 2014
CLUSTER B CBS-
Maankwartier
CLUSTER D Componenta-Otterveurdt
CLUSTER A Arcus-APG
CLUSTER C Weller HHC
Cluster grids
![Page 6: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/6.jpg)
6
HLN2
HLN1 HLN3
HH1
HH2
Minewater 3.0 Minewater 2.0: situation 2013
February 2014
CLUSTER A Arcus-APG
CBS
HHC
Arcus
APG
![Page 7: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/7.jpg)
7
HLN2
HLN1 HLN3
HH1
HH2
Minewater 3.0 Minewater 2.0: situation 2013
February 2014
CLUSTER A Arcus-APG
CBS
HHC
Arcus
APG
![Page 8: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/8.jpg)
8
HLN2
HLN1 HLN3
HH1
HH2
Minewater 3.0 Minewater 2.0: situation 2013
February 2014
CLUSTER A Arcus-APG
CBS
HHC
Arcus
APG
![Page 9: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/9.jpg)
9
HLN2
HLN1 HLN3
HH1
HH2
Minewater 3.0 Minewater 2.0: situation 2013
February 2014
CLUSTER A Arcus-APG
CBS
HHC
Arcus
APG
![Page 10: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/10.jpg)
10 February 2014
Artist impression Minewater 2.0
Minewater 3.0 Smart grid: Minewater 2.0
MI-HLN1
MI-HLN2
MI-HH1
MI-HH2 MI-Cluster
MI-Building
![Page 11: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/11.jpg)
11 February 2014
Minewater 3.0
Comfort
Health
Well being
Entertainment
Mobility
Affordability
Conventional living
![Page 12: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/12.jpg)
12 February 2014
Minewater 3.0
Comfort
Health
Well being
Entertainment
Mobility
Affordability
Sustainable living
Time & Intelligence
![Page 13: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/13.jpg)
13 February 2014
• Prepare for energy neutral future by choosing all-electric solutions now
• Shift Trias Energetica nessesary for energy neutral future • Eliminate fossil use and ad reuse /exchange energy
Reduce energy demand Reduce energy demand
Minewater 3.0 Shift Trias Energetica
![Page 14: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/14.jpg)
14 February 2014
Minewater 3.0 Sustainability creates space
![Page 15: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/15.jpg)
15
-600
-400
-200
0
200
400
600
800
1000
1200
0 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000
W-piek
W-basis
W-Verlies
W-TW
K
February 2014
Minewater 3.0 Low-Ex and energy storage
Peak load 200 – 400 hours (10–20 days): Additional generation + storage at clusterlevel
Feed temperature 38 – 45 ˚C
Base load 3600 hours (5 months): Generation + storage at buildinglevel + storage at clusterlevel
Feed temperature 30 – 38 ˚C
Hot water demand 8760 hours: Heatloss HT-network 25% total heat generation;
LT-network + booster HP < 5%
![Page 16: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/16.jpg)
16 February 2014
Minewater 3.0 Low-Ex, storage and exchange
Periods with extreme change in demand => though storage at
building and cluster level instand (passive) exchange of heat and cold
Peak load 200 – 400 hours (10–20 days): Additional generation + storage at clusterlevel
Feed temperature 38 – 45 ˚C
Base load 3600 hours (5 months): Generation + storage at buildinglevel + storage at clusterlevel
Feed temperature 30 – 38 ˚C
![Page 17: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/17.jpg)
17 February 2014
Conventional energy supply = 100% fossil + 100% loss of energy
Minewater 3.0 Conventional energy supply
![Page 18: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/18.jpg)
18
Minewater 3.0 District heating with CHP
February 2014
![Page 19: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/19.jpg)
19 February 2014
Heat pump
Energy exchange + storage = energy re-use = reduction energy loss and CO2-emission up to 100% in combination with renewable sources
Minewater 3.0 Sustainable energy supply: MW 2.0
![Page 20: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/20.jpg)
20 February 2014
Heat pump
Energy exchange + storage = energy re-use = reduction energy loss and CO2-emission up to 100% in combination with renewable sources
Minewater 3.0 Sustainable energy supply: MW 2.0
![Page 21: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/21.jpg)
21
Minewater 3.0 Creating a brave new area
February 2014
Sustainable energy - Minewater and OU Campus Cluster APG – Arcus:
• 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor area • Reduction of circa 20 billion m3 natural gas, 35.000 ton
CO2 for heating and 6.500 ton CO2 for cooling Casus Experience Parkstad important contribution for location O.U., Zuyd University, Arcus en Datacentre. First calculations show a surplus of heat in combination with other locations.
How to use this surplus of heat for customers with a heat demand besides a cold demand?
![Page 22: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/22.jpg)
22
Minewater 3.0 Creating a brave new area
February 2014
Zero-energy greenhouse OU Campus • Typical example of a “Sustaining living” project • 10.000 m2 in combination with a bio CHP and mine water to
provide sustainable heating, cooling and electricity to the buildings on the campus and greenhouse.
• Utilized for various purposes, such as a 'living lab', production of sustainable and healthy food, hydroponic cultivation, various health aspects, research quality indoor climate
• Function as ‘hot spot’ for students on campus, but also for Heerlen’s inhabitants.
• The recently signed EU climate agreement certainly offers good perspectives for this project in Heerlen.
• Offers development chances for entrepreneurs and centers of expertise and employment opportunities for the local and regional population.
![Page 23: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/23.jpg)
23
Minewater 3.0 Cluster Educationcampus
CLUSTER A
February 2014
APG
Zuyd
Arcus OU
LD IKEA
Rabo
MAB Tobias
Atrium
KAS
Data center
BMC
![Page 24: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/24.jpg)
24
Minewater 3.0 Creating a brave new area
February 2014
Multifunctional Energy Greenhouse in Heerlen
![Page 25: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/25.jpg)
25
Minewater 3.0 Creating a brave new area
February 2014
Summery of functions
ENERGY
FOOD
APPLIED
RESEARCH
HEALTH
EDUCATION
CATERING
MEETINGS
CULTURE
RELAXATION
![Page 26: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/26.jpg)
26
Minewater 3.0 Creating a brave new area
February 2014
Villa Flora (Floriade Venlo NL)
![Page 27: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/27.jpg)
27
Minewater 3.0 Creating a brave new area
February 2014
Impressions ‘other’ Greenhouses
Geenhouse on roof terrace InHolland
Greenhouse kiosk with pizza buffet
Multifunctional Geenhouse City border Rotterdam
![Page 28: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/28.jpg)
28
Minewater 3.0 Creating a brave new area
February 2014
Geenhouse Hortus Botanicus Leiden
![Page 29: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/29.jpg)
29
Minewater 3.0 Creating a brave new area
February 2014
Closed geenhouse
![Page 30: Sustainability Vision Minewater Corporation Heerlen The …€¦ · solutions now • Shift Trias ... • 25 potential buildings to attach till medio 2017 • Total 1.000.000 m2 floor](https://reader034.vdocuments.us/reader034/viewer/2022043013/5faef11d5c56547cb973842f/html5/thumbnails/30.jpg)
30
Minewater 3.0
February 2014
Thank your for your attention